You are on page 1of 2

ACTIVITY 2

CLEARING AND GRUBBING 13 X 6 = 78 sq.m.


BATTERBOARD INSTALLATION 13 (2) + 6 (2) = 38 cu.m.
SOIL POISONING 13 X 6 = 78 sq.m.

DIMENSION

DESCRIPTION
EXCAVATION DEPTH W D AREA
FOUNDATION
F1 1.5 1 1 1
F2 1.5 1 1 1
F3 1.5 0.8 0.8 0.64

WALL
FOOTING
WF-1 0.6 0.58 0.3 0.1752
0.6 0.3 0.3 0.09

FOOTING

CEMENT (bags) = 0.96 x 12 say 12 bags


SAND (cu.m.) = 0.96 x 0.5 say 1 cu.m.
GRAVEL (cu.m.) = 0.96 x 1 say 1 cu.m.

WALL FOOTING

CEMENT (bags) 0.66 x 12 say 8 bags


SAND (cu.m.) 0.66 x 0.5 say 1 cu.m.
GRAVEL (cu.m) 0.66 x 1 say 1 cu.m.
TOTAL
LENGTH CONC VOLUME VOLUME VOLUME
THICKNESS VOLUME OF CEMENT QTY VOLUME EXCAVATED BACKFILLED DISPOSAL

0.25 0.1923076923 12 3 18 17.7 0.3


0.25 0.1923076923 2 0.5 3 2.5 0.5
0.25 0.1 1 0.16 1.2 1.04 0.16

0.25 0.0197 1 0.0435 0.10512


0.25 0.005192307692 1 0.0225 0.054

say 12 bags
say 1 cu.m.
say 1 cu.m.

say 8 bags
say 1 cu.m.
say 1 cu.m.