Professional Documents
Culture Documents
Appendix D - Agri Eco Analysis and Estimate Tupa
Appendix D - Agri Eco Analysis and Estimate Tupa
Appendix D - Agri Eco Analysis and Estimate Tupa
Abstract of Cost
NCA(in ha) 3.4
S.no. Description Amount Remarks
A DWRI Part (With 13% VAT and 15% Overhead) Rs.3,123,882.4
B General Items
a. Third party insurance as per condition of the contract (0.15% of A) Rs.4,685.82
b Insurance of the work as per condition of the contract (0.15% of A) Rs.4,685.82
Insurance against accident to work men as per condition of the contract
c. (0.15% of A) Rs.4,685.82
d. Preparation of as built drawing (0.05% of A) Rs.1,561.94
e Commission for Performance bond (0.05% of A) Rs.1,561.94
Sub Total (B) Rs.17,181.35
C. Miscellaneous Items
a. Environmental Protection Rs.10,000.00
b. Institutional Development and Training Works Rs.10,000.00
c. Commissioning work Rs.10,000.00
Sub Total (C) Rs.30,000.00
d. Physical Contingency @ 3% of (A) Rs.93,716.47
E. Work Charge @ 1.5% of (A) Rs.46,858.24
G.Total (A+B+C+D+E) Rs.3,311,639.00
Per Ha cost (3.4 Ha) Rs.974,011.47
Name of Project : Tungapal Irrigation Project
Location : Tupatara, Kaike Rural Municipality-4
District : Dolpa
Total Rs Rs.2,764,497.72
DWRI Part
Amount through Contract = 2,764,497.72
Amount with VAT (13%) 3,123,882.42
S.N Description No. Length Breadth Height Quantity Unit Rate Amount
3
2 Stone Masonry in 1:4 1 3.5 0.65 1.7 3.87 m 25,238.66 97,673.61
B=(0.2+1.1)/2=0.65
3
3 Gravel filling 1 2.5 1 0.5 1.25 m 5,608.64 7,010.80
3
6 Gabion Box (3 m*1 m*1 m size) 1 3 1 1 3.00 m 5,540.28 16,620.84
3
7 Gabion Mattress (3 m*1.7 m*0.3 m size) 1 3 1.7 0.3 1.53 m 6,162.89 9,429.22
3
Boulder Packing and Filling in Gabion Box 1 3 1 1 3.00 m
3
1 3 1.7 0.3 1.53 m 6,162.89 9,429.22
3
8 Boulder Pitching 1 2.5 1 0.3 0.75 m 8,215.20 6,161.40
S.no. Description of work No. Length Breadth Height Quantity Unit Rate Amount
E/W excavation in Foundation in
1
GBM soil
Levelling ground 1 3.95 3.95 0.50 7.80
RT (80% Excavation) 1 3.95 3.95 1.20 3.79
Sub Total 3
11.59 m 1114.02 12913.74
2 Earth Work in back filling with
ordinary soil in 15 cm layers and
hand compaction (10m lead ) 1 20% of E/W in excavation 2.31 m3 467.80 1080.61
7 Form work
wall Exterior 2 3.90 3.9 1.60 24.96
wall Interior 2 3.50 3.5 1.25 17.50
Sub Total 42.46 m2 486.75 20667.57
8 12.5 mm thick1:4 C/S plaster
bed 1 3.5 3.50 12.25
Wall 2 3.5 3.50 1.25 17.50
Sub Total 29.75 m2 716.15 21305.46
9 3mm thick Cement punning
bed 1 3.5 3.50 12.25
Wall 2 3.5 3.50 1.25 17.50
Sub Total 29.75 m2 565.63 16827.49
S.no. Description of work No. Length Breadth Height Quantity Unit Rate Amount Remarks
E/W excavation in Foundation in
1
GBM soil
Valve chamber 1 1 1 0.500 0.50 assuming
Sub Total 0.50 m3 1114.02 557.01 75% hard &
25% ordinary
2 Boulder filling work soil
bed 1 1 1.00 0.10 0.10
3
Sub Total 0.10 m 8215.20 821.51
3 PCC ( 1:3:6)
bed 1 0.8 0.80 0.10 0.06
Sub Total 0.06 m3 27447.66 1756.65
4 RCC ( 1:2:4)
Cover 1 0.67 0.67 0.08 0.04
Sub Total 3
0.04 m 33726.85 1211.19
5 Tor steel @1% of item no, 4 2.64 Kg
Say, 2.64 Kg 193.11 509.81
6 Form work
Cover slab base 1 0.67 0.67 - 0.45
sides 4 0.7 - 0.10 0.27
Sub Total 0.72 m2 486.75 348.95
7 R.R.Masonry in 1:4 C/S mortar
Centreline method 1 2.68 0.23 0.40 0.25
Sub Total 0.25 m3 25238.66 6222.84
8 GI fittings +Gate Valve supplying & fitting work LS LS 50000.00
Total Rs.368,567.76
Procurement of Pipes
Name of Project : Tungapal Irrigation Project
Unit Total
S.No. Pipe size and series Unit Quantity weight weight Rate Amount
(kg/m) (kg)
1 HDPE pipes
Transmission line:
32 mmØ 10 kg/cm² m 199.1 0.235 46.79 336.33 15 736.32
32 mmØ 16 kg/cm² m 510.4 0.338 172.52 336.33 58 021.82
Distribution line:
32 mmØ 10 kg/cm² m 788.70 0.235 185.34 336.33 62 336.68
32 mmØ 16 kg/cm² m 504.90 0.338 170.66 336.33 57 396.58
40 mmØ 10 kg/cm² m 182.60 0.36 65.74 336.33 22 108.91
Total 2185.7 421.74 Rs. 2 15 600.31
Value added Tax @ 13.00 % 28 028.04
Total cost of HDPE pipes Rs. 2 43 628.35
Name of Project : Tungapal Irrigation Project
Location : Tupatara, Kaike Rural Municipality-4
District : Dolpa
S.no. Description of work No. Length Breadth Height Quantity Unit Rate Amount Remarks
1 E/w Excavation in GBM soil in pipe
trench
3
Transmission Main 1 709.5 0.5 0.9 319.27 m 1114.02 Rs.355,673.88 75% hard & 25%
3 ordinary Soil
Distribution pipeline 1 1,476.20 0.5 0.9 664.29 m 1114.02 Rs.740,033.84
Sub total 1095707.72
3
2 Ew in back filling 1 70 % of excavated soil 688.49 m 467.80 Rs.322,074.49 Rs.322,074.49
II) Transportation
Transportation mode Rate in Rs. For
Unit per
a) By Vehicle Easy Goods Difficult Goods
~ Metalled Road Per Kg. per Km.
~ Earthen Road 1.920 2.75 Per Kg. per Km.
~ Load unload Per quintal
b) By Porter 2.750 3.63 Per Kg per Kosh
Note: These materials rates are based on approved District Rate of Dolpa for F.Y. 077/78
(b) BRICK LOCAL CHIMNEY (Wt. of Brick 2.8Kg /1no =Density of brick/560=1570/560)=2.8 kg PER no.
(g) MS ROD OF DIFFERENT SIZES Difficult goods 1Mt= 1000.00 Kg. PER MT
2 Excavation of hard soils incl.disposal upto 10m. And lift 1.5m. Per Cu.m.
Source Level/Types Quantity Unit Rate per unit Amount Total
Labours Unskilled Labours 1.25 Mds. 792.00 990.00 990.00
Tools and Plants 3% 29.70
Actual Rate 1019.70
15% Overhead 152.96
Rate Per Cu.m. = Rs.1,172.65 Total Rate 1172.66
Excavation of Boulder and gravel mixed soil stones(upto 30cm.) incl.disposal upto 10 m.
3 And lift 1.5m.
Per Cu.m.
Source Level/Types Quantity Unit Rate per unit Amount Total
Labours Unskilled Labours 1.59 Mds. 792.00 1259.28 1259.28
Tools and Plants 3% 37.78
Actual Rate 1297.06
15% Overhead 194.56
Rate Per Cu.m. = Rs.1,491.61 Total Rate 1491.62
Earthwork in excavation with 10m lead and 1.5 m lift in pipeline trench in ordinary soils.
4
Per Cu.m.
Source Level/Types Quantity Unit Rate per unit Amount Total
Labours Unskilled Labours 1 Mds. 792.00 792.00 792.00
Tools and Plants 3% 23.76
Actual Rate 815.76
15% Overhead 122.36
Rate Per Cu.m. = Rs.938.12 Total Rate 938.12
7 Rubble masonary work in CM 1:4 incl. Supply of materials and haulage upto 10m.
Per Cu.m.
Source Level/Types Quantity Unit Rate per unit Amount Total
a) Skilled Labours 1.50 Mds. 1078.00 1617.00
Labours
b) Unskilled Labours 5.00 Mds. 792.00 3960.00 5577.00
Cement 0.159 M.T. 57304.50 9111.42
Materials River bed Sand 0.45 Cu.m. 3997.56 1798.90
Block and Bond Stone 1.10 Cu.m. 4963.04 5459.34 16369.66
Actual Rate 21946.66
15% Overhead 3292.00
Rate Per Cu.m. = Rs.25,238.66 Total Rate 25238.66
8 Dry Rubble masonary work incl. Supply of materials and haulage upto 30m.
Per Cu.m.
Source Level/Types Quantity Unit Rate per unit Amount Total
a) Skilled Labours 1.00 Mds. 1078.00 1078.00
Labours
b) Unskilled Labours 2.00 Mds. 792.00 1584.00 2662.00
Block Stone 1.000 Cu.m. 4963.04 4963.04
Materials
Bond Stone 0.10 Cu.m. 4963.04 496.30 5459.34
Actual Rate 8121.34
15% Overhead 1218.20
Rate Per Cu.m. = Rs.9,339.54 Total Rate 9339.55
Concreting of foundation, vert.faces, walls & abutments in 1:3:6 incl. Supply of materials and haulage
9 distance of 30 m.
Per Cu.m.
Source Level/Types Quantity Unit Rate per unit Amount Total
a) Skilled Labours 1.00 Mds. 1078.00 1078.00
Labours
b) Unskilled Labours 4.00 Mds. 792.00 3168.00 4246.00
Cement 0.220 M.T. 57304.50 12606.99
River bed Sand 0.47 Cu.m. 3997.56 1878.85
Materials
Aggregate crushed 40mm 0.65 Cu.m. 5608.64 3645.62
Aggregate crushed 20mm 0.24 Cu.m. 6208.64 1490.07 19621.53
Actual Rate 23867.53
15% Overhead 3580.13
Rate Per Cu.m. = Rs.27,447.66 Total Rate 27447.66
Concreting of foundation, vert.faces, walls & abutments in 1:2:4 incl. Supply of materials and haulage
10 distance of 30 m.
Per Cu.m.
Source Level/Types Quantity Unit Rate per unit Amount Total
a) Skilled Labours 1.00 Mds. 1078.00 1078.00
Labours
b) Unskilled Labours 4.00 Mds. 792.00 3168.00 4246.00
Cement 0.320 M.T. 57304.50 18337.44
River bed Sand 0.445 Cu.m. 3997.56 1778.91
Materials
Aggregate crushed 40mm 0.52 Cu.m. 5608.64 2916.49
Aggregate crushed 10-20mm 0.33 Cu.m. 6208.64 2048.85 25081.70
Actual Rate 29327.70
15% Overhead 4399.15
Rate Per Cu.m. = Rs.33,726.85 Total Rate 33726.85
Concreting of foundation, vert.faces, walls & abutments in 1:1.5:3 incl. Supply of materials and haulage
11 distance of 30 m.
Per Cu.m.
Source Level/Types Quantity Unit Rate per unit Amount Total
a) Skilled Labours 0.80 Mds. 1078.00 862.40
Labours
b) Unskilled Labours 7.00 Mds. 792.00 5544.00 6406.40
Cement 0.400 M.T. 57304.50 22921.80
Materials River bed Sand 0.425 Cu.m. 3997.56 1698.96
Aggregate crushed 10-20mm 0.86 Cu.m. 6208.64 5339.43 29960.19
Actual Rate 36366.59
15% Overhead 5454.99
Rate Per Cu.m. = Rs.41,821.58 Total Rate 41821.58
Cutting,bending, placing in position as shown in drawing & binding by G.I wire of reinforcement steel bars
for RCC works included haulage distance of 30m. MT
12
Source Level/Types Quantity Unit Rate per unit Amount Total
a) Skilled Labours 12.00 Mds. 1078.00 12936.00
Labours
b) Unskilled Labours 12.00 Mds. 792.00 9504.00 22440.00
M.S.Bar 1.05 M.T. 137.07 143923.50 145484.29
Materials
GI Binding Wire 10.000 Kg. 156.08 1560.79
Actual Rate 167924.29
15% Overhead 25188.64
Rate Per M.T. = Rs.193.11 Total Rate 193112.93
Making wooden forms including supply & selection of mat., fixing, nailing according to drawings, placing
13 seperators, dismantling forms & hauling up to 30m distance.
Per 10Sq.m.
Source Level/Types Quantity Unit Rate per unit Amount Total
a) Skilled Labours 1.44 Mds. 1078.00 1552.32
Labours
b) Unskilled Labours 2.10 Mds. 792.00 1663.20 3215.52
3
Materials Woods 0.526 m 32174.99 2115.51
Nail 2.500 Kg. 125.00 312.50 2428.01
Deducting rate of 25% selvage value and 6 times reuse in wood Actual Rate 423.26
15% Overhead 63.49
Rate Per M2= Rs.267.26 Total Rate 486.75
14 Dry stone laying or soling . Per Cu.m.
Source Per m2 Level/Types Quantity Unit Rate per unit Amount Total
a) Skilled Labours 0.00 Mds. 1078.00 0.00
Labours
b) Unskilled Labours 1.50 Mds. 792.00 1188.00 1188.00
Sand 0.00 Cu.m. 3997.56 0.00
Rubble stone 1.200 Cu.m. 4963.04 5955.65 5955.65
Actual Rate 7143.65
15% Overhead 1071.55
Rate Per Cu.m. = Rs.8,215.19 Total Rate 8215.20
Making gabion box (2mx1mx1m) with two way knot incl. wire cutting, netting etc. complete. (Mesh size 80 x
18 100mm. ,Salvege wire - 8 SWG mesh wire 11 SWG.)
Per no.
Source Level/Types Quantity Unit Rate per unit Amount Total
a) Skilled Labours 0.50 Mds. 1078.00 539.00
Labours
b) Unskilled Labours 0.20 Mds. 792.00 158.40 697.40
GI Wire 10 SWG 28.40 Kg. 145.08 4120.24
Materials
4120.24
Actual Rate 4817.64
15% Overhead 722.65
Rate Per box no. = Rs.5,540.28 Total Rate 5540.28
Income analysis
SN Cropping pattern Area (Ha) Yield (kg per Ha)Yield kg Price per kg (Nrs)
Income (Nrs)
1 Potatoes 0.85 3000 2550 80 204,000.00
2 Spring Vegetables 0.51 1100 561 20.00 11,220.00
3 Summer veg 0.68 1000 680 20.00 13,600.00
228,820.00
Cost Analysis
SN Items Cost per Ha Cultivated area (Ha)
Amount (Nrs)
Agriculturing cost
1 potatoes 130000.00 0.85 110,500.00
2 Spring vegetables 82250 0.51 41,947.50
3 Summer Veg 82250.00 0.68 55,930.00
Sum of A 208,377.50
Economic Analysis :
Page 20 of 25
Name of Project : Tungapal Irrigation Project
Location : Tupatara, Kaike Rural Municipality-4
District : Dolpa
Sensitivity Analysis
Case I: Cost Increased by 20%
Discount Present Value (PV), Cost at Benefit at
Year Construction cost O & M cost Cost Benefit Cash Flow
10% 12% 10% 12% at 10% 12%
1 4807536.87 0.00 4807536.87 0.000 0.909 0.893 4370488.062 4292443.63 0.00 0.00 -4807536.87
2 0.00 1171337.73 1171337.73 1723375.000 0.826 0.797 968047.710 933783.27 1424276.86 1373864.00 552037.27
3 0.00 1171337.73 1171337.73 1723375.000 0.751 0.712 880043.373 833735.06 1294797.15 1226664.28 552037.27
4 0.00 1171337.73 1171337.73 1723375.000 0.683 0.636 800039.430 744406.30 1177088.31 1095235.97 552037.27
5 0.00 1171337.73 1171337.73 1723375.000 0.621 0.567 727308.573 664648.48 1070080.29 977889.26 552037.27
6 0.00 1171337.73 1171337.73 1723375.000 0.751 0.712 880043.373 833735.06 1294797.15 1226664.28 552037.27
7 0.00 1171337.73 1171337.73 1723375.000 0.683 0.636 800039.430 744406.30 1177088.31 1095235.97 552037.27
8 0.00 1171337.73 1171337.73 1723375.000 0.621 0.567 727308.573 664648.48 1070080.29 977889.26 552037.27
9 0.00 1171337.73 1171337.73 1723375.000 0.564 0.507 661189.611 593436.15 972800.26 873115.41 552037.27
10 0.00 1171337.73 1171337.73 1723375.000 0.513 0.452 601081.465 529853.70 884363.87 779567.33 552037.27
11 0.00 1171337.73 1171337.73 1723375.000 0.467 0.404 546437.695 473083.66 803967.16 696042.26 552037.27
12 0.00 1171337.73 1171337.73 1723375.000 0.424 0.361 496761.541 422396.13 730879.23 621466.30 552037.27
13 0.00 1171337.73 1171337.73 1723375.000 0.386 0.322 451601.401 377139.40 664435.67 554880.63 552037.27
14 0.00 1171337.73 1171337.73 1723375.000 0.350 0.287 410546.728 336731.61 604032.42 495429.13 552037.27
15 0.00 1171337.73 1171337.73 1723375.000 0.319 0.257 373224.298 300653.22 549120.39 442347.44 552037.27
16 0.00 1171337.73 1171337.73 1723375.000 0.290 0.229 339294.817 268440.38 499200.35 394953.07 552037.27
17 0.00 1171337.73 1171337.73 1723375.000 0.263 0.205 308449.833 239678.91 453818.50 352636.67 552037.27
18 0.00 1171337.73 1171337.73 1723375.000 0.239 0.183 280408.939 213999.02 412562.27 314854.17 552037.27
19 0.00 1171337.73 1171337.73 1723375.000 0.218 0.163 254917.218 191070.56 375056.61 281119.79 552037.27
20 0.00 1171337.73 1171337.73 1723375.000 0.198 0.146 231742.925 170598.71 340960.56 250999.82 552037.27
15108975 13828888 15799406 14030855
B/C Ratio at 10.00% 1.05 EIRR 9.40%
B/C Ratio at 12.00% 1.01
Page 21 of 25