SHUT DOWN PLAN FOR BOP

Sr. No. Work Descripation Responsible 27-Dec-21 28-Dec-21 29-Dec-21 30-Dec-21 31-Dec-21 1-Jan-22 2-Jan-22

1 To be put stickers on master samples for validation Dharmender

To be done White paint in BOP Master Samples, Almira &


2 Inspection Tables Nehru/Parmanand

Supplier audit and Parts correction be done (cvpil,san


auto, AP tool ,Intergal & Pragati )
CEIL Bawal
63412/812-62S00
3.A 58234/35-72S00 Pradeep Yadav
AP tool ,Faridabad
63451/851-55R00
3 62313-62S00
3.B 63816-62S00 Pradeep Kumar
Hyline Auto ,Shona
62212-62S00
61132-69R00
3.C 61213-68P00 Pradeep Kumar
61221-68P00
Metal Dyne , Bawal
3.D 61218-55R00 Pradeep Yadav
63237/637-62S00
RAKESH/MAHENDER /RAVI/BHAGWAT /HIMANSHU