PROJECT: PROPOSED CREEK RETAININIG WALL AND STAFFHOUSE

SUBJECT: DEDUCTIONS TO DONOR BUILDERS CIVIL WORKS CONTRACT DUE TO CHANGED ORIGINAL PLAN
LABOR AND
LABOR COST
ITEM SCOPE OF WORKS QTY UNIT CONSUMABLES
DEDUCTIONS
UNIT PRICE
1. EARTHWORKS
STRUCTURAL EXCAVATION CU.M. 30.28 350.00 10,598.00
GRAVEL BEDDING SQ.M. 78.87 25.00 1,971.75
2. CONCRETE WORKS
FOUNDATION CU.M. 3.84 1,000.00 3,840.00
PEDESTAL CU.M. 3.94 1,000.00 3,940.00
BEAMS CU.M. 4.68 1,000.00 4,680.00
SETBACK CONCRETING CU.M. 20.55 1,000.00 20,550.00
3. REBARS
FOUNDATION KGS. 307.20 6.50 1,996.80
PEDESTAL KGS. 315.20 6.50 2,048.80
BEAMS KGS. 374.40 6.50 2,433.60
SETBACK CONCRETING KGS. 1,438.50 6.50 9,350.25
4. FORMWORKS
FOUNDATION SQ.M. 9.60 536.00 5,145.60
PEDESTAL SQ.M. 28.80 536.00 15,436.80
BEAMS SQ.M. 42.90 536.00 22,994.40
5. ROOFING WORKS
ROOF SHEET AND INSULATION SQ.M. 143.30 200 28,660.00
6. MASONRY WORKS
CHB LAYING SQ.M. 136.80 300 41,040.00
PLASTERING SQ.M. 273.60 300 82,080.00
7. PAINTING WORKS
INT/EXT WALL SQ.M. 273.60 100 27,360.00
284,126.00