Leachate Volume Computation
Leachate Volume Computation
Where,
Q: Leachate Volume/Leachate Flow = 81.6 cu.m/day
I: Monthly average daily rainfull = 12 mm/day Leachate Coefficient,C
C1 : Complete leachate coefficient = 1 C1
C2 : Un-complete leachate coefficient = 0.6 C2
A1 : Completed sectioned landfill area = 2000 sq.m
A2 : Un-completed sectioned landfill area = 8000 sq.m
E: Evaporation = 0 mm
V = QT
Q = 81.6 cu.m/day
T= 7 days
V= 571.2 cu.m
LEACHATE VOLUME , Q
by Rational Equation Method
Q = (1/1000) X I X (C1 X A1 +C2 X A2)
Where,
Q: Leachate Volume/Leachate Flow = 24 cu.m/day
I: Monthly average daily rainfull = 12 mm/day Leachate Coefficient,C
C1 : Complete leachate coefficient = 1 C1
C2 : Un-complete leachate coefficient = 0.6 C2
A1 : Completed sectioned landfill area = 2000 sq.m
E: Evaporation = 0 mm
V = QT
Q = 24 cu.m/day
T= 7 days
V= 168 cu.m
Coefficient,C
: 1
: 0.6