Chainage Span LHS/RHS Fabrication Supply Assembly Torquing Launching Bracing Lowering

309 43 mtr LHS Done Done 04-Mar-22 06-Mar-22 07-Mar-22 10-Mar-22 12-Mar-22
309 43 mtr RHS Done Done 07-Mar-22 09-Mar-22 10-Mar-22 13-Mar-22 15-Mar-22
293 30 mtr LHS Done 07-Mar-22 09-Mar-22 11-Mar-22 13-Mar-22 15-Mar-22 17-Mar-22
293 30 mtr LHS Done 07-Mar-22 10-Mar-22 12-Mar-22 15-Mar-22 17-Mar-22 19-Mar-22
293 43 mtr LHS 12-Mar-22 17-Mar-22 21-Mar-22 24-Mar-22 26-Mar-22 29-Mar-22 31-Mar-22
293 30 mtr RHS 08-Mar-22 11-Mar-22 13-Mar-22 15-Mar-22 17-Mar-22 19-Mar-22 21-Mar-22
293 30 mtr RHS 08-Mar-22 11-Mar-22 13-Mar-22 15-Mar-22 17-Mar-22 19-Mar-22 21-Mar-22
293 43 mtr RHS 20-Mar-22 25-Mar-22 27-Mar-22 31-Mar-22 03-Apr-22 05-Apr-22 07-Apr-22