PROJECT Phnom Penh Cambodia Temple PROJECT NO. 5244.009 REV NO. 00
ITP DESCRIPTION Site Clearance & Land Leveling PREPARED BY Kaim Sithaung DATE Click here
to enter a
date.
ITP NO * 001 DISCIPLINE: Civil/Structure REVIEWED BY Justin Landis DATE Click here
Works to enter a
date.
Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A
1. Document Preparation/Permit/Approvals
2. Unsuitable Soils
COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 1 of 4
INSPECTION & TEST PLAN
Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A
2.1 UXO Investigation Unexploded After removal Investigation until Certificate of R S I/R
Ordnance topsoil -200mm 1.0m-1.5m Handover
None Detected
2.2 Remove Unsuitable Soil Organic Site Clearance Organic matter As per R S -
Materials content Approved
≤ 10% Method
Swelling Index ≤ 3%
Liquid Limit ≤ 45%
Plastic Index ≤ 27%
3. Backfilling
3.1 Selection of Fill Material Particle Prior to start Organic matter As per R - I/R Test Certificate
(Sample) Size/Distribut of work content Approved
ion ≤ 10% Method
Swelling Index ≤ 3% ASTM D1557
Liquid Limit ≤ 45%
Plastic Index ≤ 27%
CBR @ 0.95
3.2 Sand Cone Test Density and Each Layer Compaction K 95% As per R S I/R
Unit Weight Approved
Compaction Method
Characteristic ASTM D 1556
s
3.3 Plate Load Field Test Bearing Founding Design Load As per R S I/R
Capacity Level/Subgrade 250KN/sq.m Approved
Method
COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 2 of 4
INSPECTION & TEST PLAN
Verifying Inspection /
Item Parameter to be Verification
Activity / Description Stage /Frequency Acceptance Criteria Document / DWG Remark
No. Verified
Number C E A
3.4 Leveling of Layer Survey Level Each Layer Tolerance at top As per I/R S -
layer surface with Approved
target level Method
+11.00m : ± 100 mm Structural
dwg/Specificat
ion
3.5 Compaction of Backfill Density Level < 11m k ≥ 95%, Structural I/R S -
Each 0.8W0≤W≤1.2W0 dwg/Specificat
Unconsolidated ion
200mm Layer up
to Foundation
Level
3.6 Anti-Termite Treatment Application Backfilling Top Approved M/S & Structural I/R W -
Layer Approved Supplier / dwg/Specificat
Applicator ion
COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 3 of 4
INSPECTION & TEST PLAN
COVA Thinking (Cambodia) Co. Ltd Inspection & Test Plan (F302 30) • Revision 14 • 30
Registration Number: 00036945 July 2021
covagroup.com Project: 5244.009
Page 4 of 4