Calculation Precommisioning CBIII
Calculation Precommisioning CBIII
Pipe Volume (Vair) = 23312.49 meter cubic Pipe Volume (Vair) = 32699.59 meter cubic
Velocity Pig
Velocity (Vpig) = 0.50 meter per second Velocity (Vpig) = 0.36 meter per second
= 30.14 meter per minute = 21.49 meter per minute
= 1808.35 meter per hour = 1289.23 meter per hour
FLOODING, CEANING, GAUGING CALCULATION
Nitrogen Volume need (Vn) achieved dew point and O2 content 31767.96 meter³
(assumed; 7 x pipe volume)