You are on page 1of 1

DATA BASE PEKERJAAN

MEN
POWE DURASI
NO PEKERJAAN VOLUME SAT KET
R (HARI)
1 TOWER FONDATION
Cut and Bending 3 5 1,183.00 m
2 Bor Pile
Cut and Bending 2 2 950 m include Mob to site
Rakit Besi 3 2 950 m
Drilling Work 3 9 Titik Diameter 40 cm
3 Bongkar Isi Kontainer 4 1 2 Tower Include Buruh