PROJECT NAME : CLP PROJECT

SCOPE OF WORK : TEMPORARY REPAIR STEEL STRUCTURE BUILDING SHELL WAREHOUSE


LOCATION : POWERPLANT AREA - CLP - KID PELINTUNG
CLIENT : PT. CILIANDRA PERKASA
CONSULTANT :-
CONTRACTOR :-
YEAR : 2022
REVISE : 0 (Nol)
BILL OF QUANTITY
UNIT RATE AMOUNT
NO. ITEM OF WORK UOM VOLUME REMARKS
MATERIAL LABOUR MATERIAL LABOUR TOTAL
A MANPOWER + COMSUMABLE 50.450.000.00
1 Mechanical Worker day
Mandor day 18.00 450.000.00 - 8.100.000.00 8.100.000.00
Welder day 18.00 350.000.00 - 6.300.000.00 6.300.000.00
Fitter day 18.00 250.000.00 - 4.500.000.00 4.500.000.00
Helper day 18.00 170.000.00 - 3.060.000.00 3.060.000.00
Safety Man day 18.00 250.000.00 - 4.500.000.00 4.500.000.00
2 Transportation Team day 18.00 500.000.00 - 9.000.000.00 9.000.000.00
3 Crane 35t day 18.00 - - - Support by Owner
4 Oksigen Las Cap. 6m3 ( isi ulang ) Incld. Brander Tools pcs 6.00 140.000.00 840.000.00 - 840.000.00
5 Elpiji cap.50 kg ( Isi Ulang ) Incld. Brander Tools pcs 4.00 1.400.000.00 5.600.000.00 - 5.600.000.00
6 Welding Electrode LB-52 E 7016 dia.3.2mm by Kobe ( @ 5kg ) box 12.00 210.000.00 2.520.000.00 - 2.520.000.00
7 Mata Gerinda Potong dia.4"x 1.2mm pcs 30.00 15.000.00 450.000.00 - 450.000.00
8 Mata Gerinda Poles dia.4" pcs 20.00 17.000.00 340.000.00 340.000.00
9 Sika Anchord Fix-1 tube 8.00 - - Support by Owner
10 Anchord Bolt M14 L=30cm pcs 32.00 - - - Support by Owner
11 Skrup zink 5cm @ 3 kotak = 250pcs kotak 3.00 180.000.00 540.000.00 - 540.000.00
12 All Support Tools Mechanic Ls 1.00 4.700.000.00 4.700.000.00 - 4.700.000.00
C STEEL STRUCTURE
C.1 PEKERJAAN DISMANTLING + RESTRUCTURE STEEL BUILDING FOLLOW DWG -
1 Dismatling all zink Roof m2 544.70
Sebagian besar sdh dibongkar
2 Dismantling Zink Cladding area Repair + Removal m2 300.60
3 Dismantling Zink Canopy area Repair + Removal m2 136.80
4 Dismantling CNP 150.50.2.3,2 Gording roof area Repair + Removal btg 110.00
5 Dismantling CNP 150.50.2.3,2 Cladding area Repair + Removal btg 57.00
6 Dismantling CNP 150.50.2.3,2 Canopy area Repair + Removal btg 30.00
7 Dismantling Damaged Rafter IWF250.125.6.9 area Repair + Removal Point 12.00
8 Dismantling Damaged Column IWF250.125.6.9 area Repair + Removal Point 12.00
9 Dismantling Rafter Canopy 1/2x IWF250.125.6.9 area Repair + Removal point 15.00
10 Drilling 12-15cm + Install Anchord Bolt M14 incld Chemical Anchord Point 28.00
11 Modification Embeded Plate Column Dim 200x300mm thk 14mm Point 7.00
12 Modification/Repair + Re Install Steel Column IWF250 Point 8.00
13 Modification/Repair + Re Install Steel Rafter IWF250 Point 6.00
14 Re Install CNP 150.50.2.3,2 Roof btg 66.00
15 Re Install CNP 150.50.2.3,2 Cladding btg 20.00
16 Re Install Steel Rafter Canopy 1/2 x IWF250 btg 5.00
17 Re Install CNP 150.50.2.3,2 Canopy btg 12.00
18 Re Install Sagrod Rebar 10mm Cladding ( Welded Joint ) btg 15.00
19 Re Install Sagrod Rebar 10mm Roof ( Welded Joint ) btg 60.00
20 Re Install Sagrod Rebar 10mm Canopy ( Welded Joint ) btg 6.00
21 Re Install Zink Roof m2 714.92
22 Re Install Zink Cladding m2 87.00
23 Re Install Zink Canopy m2 7.50
24 Dismantling Coal Crusher Hopper + Inclined Conveyor Unit 1.00

Note : Volume Hari kerja + Tools dapat disesuaikan menurut analisa Contractor 14.990.000.00 35.460.000.00 50.450.000.00