Ref; ASGC-PK105-MACE-0197 |
Date: 4 March 2021 =
Mis MACE Egypt for Project Management L.L.C
10 Obour Buildings, Apt. 101, Salah Salim St., Cairo 11371, Egypt.
(In the Capacity of “Contract Administrator’ as per the Employer's appointment letter ref.
UTC/Gen/EMAAR/ASGCIAH/11-2019/LET-0003, hereinafter referred to as "MACE")
Attention: Eng. Ahmed Al Garf
Contract Administrator's Representative, MACE,
Construction Package PKG#105
Uptown Cairo Project - Construction of Village B’
Consequences of Delayed Response to the Dispatched Settlement of the
Social Insurance Amounts.
Dear Sir,
Further to the Contractors letter ref. ASGC-PK105-MACE-0172 dated 26 January 2021 and its
subsequent response from the Contract Administrator (CA) ref. Mace/ASGC/UTC4105/L/00167
dated 15 February 2021, concerning the Contractor's settlement of the Social Insurance amounts.
Unfortunately, and due to the delayed response in receiving such stamped Documents, the
Ministry of Social Insurance have already charged the Contractor to pay a total amount of EGP.
5,283 (only five thousand, two hundred and eighty-three Egyptian Pounds), as interest fee against
delayed settlement for such amounts.
Considering the above mentioned and knowing that such delays were beyond the Contractor's
reasonable control; the Contractor hereby kindly requests the Employer's intervention and
directives to release of the aforementioned violation penalty amounts; as the Contractor has
already justified its position and absolved itself from such responsibility. Accordingly and in light
of the above, the Contractor hereby reserve all its rights under the Contract to be indemnified
against such penalties, due to the delayed issuance of the stamped Social Insurance Settlement
amounts; whereas the said delays are solely attributed to the delays encountered in dispatching
such documents to the Contractor by the Employer.
This is for the CA's kind attention and urgent arrangements at the earliest convenience please,
order and the Contractor continue to assure you of its closest
}st endeavors at all times.
= ASST
U_ iown Calro
Fountain Side Resi
PK#105 Social Insurance Interest Fee (1x A4 size)
CC: Eng. Ahmed Hemmat Projects Director i Emaar Misr
Eng. Mohamed Yehia Senior Project Manager” Emaar Misr
Eng. Mohamed Fathy Project Manager_ Emaar Misr