CONSTRUCTION METHOD AND

PROJECT
FCONPRL – CIVP39

Submitted by:
Corbilla, Vincent Allen B.
Ladrera, Carl Lorenz B.
Miranda, Charlamagne F.

Submitted to:
Engr. Debbie Lyn Cabacungan
PROJECT TITLE : PROPOSED STANDARD THREE (3) UNITS HEALTH FACILITY TENT (without isolation cube)
LOCATION : Brgy. San Isidro, Bay, Laguna
SUBJECT : DETAILED ESTIMATES
GROUP MEMBERS:
CORBILLA, VINCENT ALLEN B.
LADRERA, CARL LORENZ B.
MIRANDA, CHARLAMAGNE F.

MATERIALS COST LABOR COST


ITEMS DESCRIPTION UNIT QTY TOTAL COST
per Unit Total per Unit Total
DIVISION 1: GENERAL REQUIREMENTS
1 Mobilization and Demobilization lot 1.00 145500 145500 145500

2 Field Personnel
2.1 Project Manager man-mos (3) 1.00 78,000 234000 234000
2.2 Site Engineer man-mos (3) 1.00 66000 198000 198000
2.3 QA/QC Engineer man-mos (3) 1.00 40320 120960 120960
2.4 Safety Engineer man-mos (3) 1.00 79200 237600 237600
2.5 Security Guard man-mos (3) 2.00 21557 96426 96426
2.6 Plumber man-mos (3) 2.00 48000 288000 288000
2.7 Electrician man-mos (3) 2.00 45120 270720 270720
2.8 Surveyor man-mos (3) 1.00 41280 123840 123840

3 Permits and Clearances lot 1.00 84350 84350 84350

4 Temporary Facilities and Utilities


4.1 Electricity Consumption lot 1.00 15000 15000 15000
4.2 Water Consumption lot 1.00 15000 15000 15000
4.3 Temporary Toilets pcs 3.00 58000 174000 174000

5 Construction Aids
5.1 Personal Protective Equipment
a. Safety Boots/Shoes pcs 20.00 470 9400 9400
b. Gloves pcs 20.00 350 7000 7000
c. Hard Hats pcs 20.00 490 9800 9800
d. Safety Goggles pcs 20.00 250 5000 5000

6 Temporary Barriers and Enclosures


6.3 Temporary Barricades pcs 10.00 5000 50000 50000

7 Project Identification
7.1 Temporary Project Signages
a. High intensity reflectorized, no post
pcs 5.00 2000 10000 10000
signs

8 Cleaning and Waste Management lot 1.00 25000 25000 25000

9 Equipment
9.1 Genset lot 2.00 90000 90000
9.2 Mobile Crane lot 2.00 520000 520000
9.3 Welding Machine lot 2.00 192000 192000
9.4 Forklift lot 2.00 2955680 2955680
9.5 Vibrator lot 2.00 20000 20000
9.6 Concrete Pump lot 1.00 388080 388080
9.7 Concreete Mixer lot 1.00 42240 42240
9.8 Dump Truck lot 2.00 38400 38400
9.9 Backhoe lot 1.00 96000 96000
9.10 Bulldozers lot 2.00 76800 76800
9.11 Plate Compactor lot 2.00 62400 62400
4481600
Total of General Requirements PHP 11082796

DIVISION 2: SITE CONDITIONS


1 Site Clearing and Layout lot 1.00 20000 20000 20000

2 Waste Disposal Services lot 1.00 25000 25000 25000

3 General Clearing lot 1.00 8850 8850 8850


4 Excavation cu.m 626.00 8340 8340 8340

5 Hand Backfilling and Compaction cu.m 579.86 75 43489.5 25944 25944 69433.5

7 Gravel Bedding cu.m 18.68 810 15130.8 1558.33 1558.33 16689.13

8 Hauling of Excess Soil lot 1.00 25000 25000 25000

Total of Site Conditions PHP 173312.63

DIVISION 3: CONCRETE
For Health Facility
1 Pre-Cast Concrete
1.1 Pedestal Column Base pcs 60.00 3300 198000 4800 4800 202800

2 100mm THK Concrete Slab on Fill cu.m 45.00 3482.5 156712.5 156712.5

Laborers days 4.63 1920 8889.6 8889.6


Productivity rate of 5.00 man-hour/cu.m

For Toilet Facility


3 Concrete Columns
3.1 C-1 (above FGL) cu.m 1.15 3482.5 4004.875 4004.875
3.2 C-1 (below FGL) cu.m 0.53 3482.5 1845.725 1845.725
Laborers days 0.60 1040 624 624
Productivity rate of 8.54 man-hour/cu.m

4 Concrete Roof Beam cu.m 1.83 3482.5 6372.975 6372.975


Laborers days 0.64 1040 665.6 665.6
Productivity rate of 8.54 man-hour/cu.m

5 Concrete Footing cu.m 0.96 3482.5 3343.2 3343.2


Laborers days 1.00 1040 1040 1040
Productivity rate of 8.54 man-hour/cu.m
6 Footing Tie Beam cu.m 2.67 3482.5 9298.275 9298.275
Laborers days 0.96 1040 998.4 998.4
Productivity rate of 8.54 man-hour/cu.m

7 Wall Footing cu.m 6.99 3482.5 24342.675 24342.675


Laborers days 2.48 1040 2579.2 2579.2
Productivity rate of 8.54 man-hour/cu.m

7 100mm THK Concrete Slab on Fill cu.m 3.50 3482.5 12188.75 12188.75
Laborers days 2.18 1040 2267.2 2267.2
Productivity rate of 5 man-hour/cu.m

Septic Tank
8 Concrete cu.m 1.08 3482.5 3761.1 3761.1
Laborers days 1.00 960 960 960
Productivity rate of 5 man-hour/cu.m

Total of Concrete PHP 442694.075

DIVISION 4: MASONRY
For Toilet Facility
1 100mm THK CHB Wall sq.m 95.77 40088.294 40088.294
Laborers - Masonry days 1.20 1400 1680 1680
2 Productivity rate of 10 sq.m/man-day

Plain Cement Plaster Finish sq.m 184.00 12169.423 12169.423


Laborers (Internal/External Plaster) days 4.56 5600 25536 25536
Productivity rate of 10.08 sq.m/man-day

Total of Masonry PHP 79473.717

DIVISION 5: METALS
For Health Facility
Column
1 1.1 HSSP 5x0.5x3.85m pcs/6m 34.65 5000 173250 173250
Truss
2 2.1 T-1
a. HSSP 3x0.25x5.22m pcs/6m 20.88 4500 93960 93960
b. HSSP 3x0.25x5m pcs/6m 20.00 4500 90000 90000
c. HSSP 3x0.25x1.5m pcs/6m 3.00 4500 13500 13500
d. HSSP 2.5x0.23x0.75m pcs/6m 3.00 3500 10500 10500
e. HSSP 2.5x0.23x2.61m pcs/6m 10.44 3500 36540 36540
2.2 T-2
a. HSSP 3x0.25x3m pcs/6m 9.00 4500 40500 40500
b. HSSP 2.5x0.23x2.12 m pcs/6m 6.36 3500 22260 22260
c. HSSP 2.5x0.23x1.5m pcs/6m 2.25 3500 7875 7875
2.3 T-3
a. HSSP 3x0.25x3m pcs/6m 13.00 4500 58500 58500
b. HSSP 2.5x0.23x0.75m pcs/6m 2.25 3500 7875 7875
c. HSSP 2.5x0.23x1.68m pcs/6m 10.08 3500 35280 35280
2.4 HT-1
a. HSSP 3x0.25x3m pcs/6m 3.00 4500 13500 13500
b.HSSP 3x0.25x3.35m pcs/6m 3.35 4500 15075 15075
c. HSSP 2.5x0.23x0.712m pcs/6m 6.00 3500 21000 21000
d. HSSP 2.5x0.23x2.12m pcs/6m 6.00 3500 21000 21000
2.5 HT-2
a. HSSP 3x0.25x5.831m pcs/6m 11.66 4500 52479 52479
b. HSSP 3x0.25x6.021m pcs/6m 12.04 4500 54189 54189
c. HSSP 2.5x0.23x0.707m pcs/6m 1.41 3500 4949 4949
d. HSSP 2.5x0.23x3m pcs/6m 6.00 3500 21000 21000
e. Ø16mm Bolt with STD Nuts and
pcs 1536.00 12.44 19107.84 19107.84
Washer

T-4
3 3.1 HSSP 3x0.25 (5m) pcs/6m 4.00 4500 18000 18000
3.2 HSSP 3x0.25 (1.48m) pcs/6m 2.00 4500 9000 9000
3.3 HSSP 3x0.25 (5.22m) pcs/6m 4.00 4500 18000 18000
3.4 HSSP 2.5x0.23 (1m) pcs/6m 4.00 3500 14000 14000
3.5 HSSP 2.5x0.23 (500mm) pcs/6m 4.00 3500 14000 14000
3.5 HSSP 2.5x0.23 (2.25m) pcs/6m 4.00 3500 14000 14000
3.6 HSSP 2.5x0.23 (1.95m) pcs/6m 4.00 3500 14000 14000
3.7 Ø16x300mm Anchor Bolts with STD nuts
pcs 1536.00 12.44 19107.84 19107.84
and Washer

Labor days 10.00 5040 50400 50400

For Toilet Facility


Column
4 4.1 Ø20mm Reinforcing Bar kgs 195.30 44 8593.244 8593.244
4.2 Ø10mm Reinforcing Bar kgs 109.82 44 4832.256 4832.256
Laborers days 2.59 2250 5827.5 5827.5
Productivity Rate of 117.6 kg/man-day

Footing
5 5.1 Ø20mm Reinforcing Bar kgs 94.69 44 4166.448 4166.448
Laborers days 0.80 2250 1800 1800
Productivity Rate of 117.6 kg/man-day

Roof Beam
6 6.1 Ø20mm Reinforcing Bar kgs 297.88 44 13106.896 13106.896
6.2 Ø12mm Reinforcing Bar kgs 53.64 44 2360.336 2360.336
6.3 Ø10mm Reinforcing Bar kgs 141.45 44 6223.888 6223.888
Laborers days 4.19 2250 9427.5 9427.5
Productivity Rate of 117.6 kg/man-day

Footing Tie Beam


7 7.1 Ø20mm Reinforcing Bar kgs 297.88 44 13106.8916 13106.8916
7.2 Ø12mm Reinforcing Bar kgs 53.64 44 2360.345 2360.3448
7.3 Ø10mm Reinforcing Bar kgs 178.68 44 7861.770 7861.7704
Laborers days 4.51 2250 10147.5 10147.5
Productivity Rate of 117.6 kg/man-day

Wall Footing
8 8.1 Ø10mm Reinforcing Bar kgs 17.47 44 768.68 768.68
Laborers days 0.15 2250 337.5 337.5
Productivity Rate of 117.6 kg/man-day

Septic Tank
9 Reinforcing Bars
9.1 Ø12mm Reinforcing Bar kgs 64.80 44 2851.2 2851.2
9.2 Ø16mm Reinforcing Bar kgs 111.60 44 4910.4 4910.4
Laborers days 2.45 2250 5512.5 5512.5
Productivity Rate of 117.6kg/man-day

Total of Metals PHP 1087042.535

DIVISION 7: THERMAL AND MOISTURE PROTECTION


For Health Facility
Double PVC Coated Polyester Textile
1 sq.m 1500.00 150000 150000
(Insulated-Tent)
Labor days 3.00 1600 4800 4800

For Toilet Facility


2 Roof
2.1 8mm THK Roof Insulation sq.m 35.00 1050 36750 36750
2.2 150x150mm GA 24 Pre-formed Pre-
lm 8.20 351 2878.2 2878.2
painted Gutter Sheet
2.3 0.40mm THK (Base Metal Thickness) with
Total Thickness of 0.43 - 0.45mm THK (with sq.m 45.92 423 19424.16 19424.16
Paint) Corrugated G.I. Sheet
2.4 0.40mm THK (Base Metal Thickness) with
Total Thickness of 0.43 - 0.45mm THK (with lm 8.20 261 2140.2 2140.2
Paint) G.I. Sheet Ridge Roll
2.5 GA 26 Preformed Pre-Painted G.I. Flashing
lm 11.20 323 3617.6 3617.6
Sheet
2.6 LC100x50x15x3mm THK Purlins pcs 23.00 1100 25300 25300
2.7 10mmØ Sagrods kgs 15.00 45 675 675
Laborers days 2.00 1930 3860 3860

Total of Thermal and Moisture Protection PHP 249445.16

DIVISION 8: Doors and Windows


For Toilet Facility
1 Doors with accessories
1.1 Hollow Core Flush Door Type (Two Face
Marine Plywood with Painted Finish) set 2.00 2400 4800 4800
2.1mHx1mW
1.2 19mm Phenolic Board with Painted Finish
set 12.00 900 10800 10800
(Bar Door)
Laborers days 3.00 1200 3600 3600

2 Windows with accessories 2mWx0.6mH sq.m 6.00 690 4140 4140


Laborers days 3.00 1200 3600 3600

Total of Doors and Windows PHP 26940

DIVISION 9: Finishes
For Toilet Facility
1 Ceiling Finishes
1.1 4.5mm THK Fiber Cement Ceiling Board on
sq.m 35.00 429/3 sq.m 5005 5005
Metal Furring Ceiling Frame
Laborers days 1.00 1500 1500 1500

2 Floor Finishes
2.1 300x300mm Vitrified Unglazed Floor Tile
sq.m 30.69 708 21728.52 21728.52
Finish
Laborers days 1.02 1400 1428 1428

3 Wall Finishes
3.1 300x300mm Vitrified Glazed Tile Wall
sq.m 81.33 1949 158512.17 158512.17
Finish
3.2 Lavatory
a. 3mm THK Facial Mirror in Aluminum
Framing
b. 300x300mm Vitrified Glazed Tiles
sq.m 4.29 1949 8361.21 8361.21
Counter Sink Finish
3.2 Handwashing Counter
a. 300x300mm Vitrified Glazed Tiles
sq.m 1.53 1949 2981.97 2981.97
Handwashing Back Flash Finish
b. 300x300mm Vitrified Glazed Tiles
sq.m 3.51 1949 6844.888 6844.888
Handwashing Counter Top Finish
Laborers days 3.39 1400 4746 4746

3.3 Paint Finish sq.m 34.30 300 10290 10290


Laborers days 1.43 1100 1573 1573

Total of Doors and Windows PHP 222970.758

DIVISION 15: Plumbing


For Toilet Facility
20mmØ Polypropylene Random Copolymer
1 lm/3m/pc 18.40 110.21 771.47 771.47
Cold Water Line
25mmØ Polypropylene Random Copolymer
lm/3m/pc 15.00 143.17 715.85 715.85
Cold Water Line

2 25mmØ PVC Drainage Pipe lm/3m/pc 15.00 143.17 715.85 715.85


75mmØ PVC Downspout lm/3m/pc 4.40 156.56 313.12 313.12
100mmØ PVC Downspout lm/3m/pc 19.55 196.39 1374.73 1374.73

3 100mmØ PVC Soil Pipe lm/3m/pc 20.70 196.39 1374.73 1374.73


50mmØ PVC Vent Pipe lm/3m/pc 11.40 78.28 313.12 313.12
50mmØ PVC Loop Vent lm/3m/pc 7.50 78.27 234.81 234.81
50mmØ PVC Vent Across Ceiling lm/3m/pc 7.00 78.27 234.81 234.81
50mmØ PVC Vent Through Wall lm/3m/pc 7.00 78.27 234.81 234.81

4 Clean Out pcs 10.00 118.3 1183 1183


Floor Drain pcs 4.00 378.37 1513.48 1513.48
Faucet pcs 16.00 299 4784 4784
Gate Valve pcs 8.00 3675 29400 29400
Lavatory Drain pcs 8.00 5020 40160 40160
Shower Drain pcs 6.00 500 3000 3000
Shower Head pcs 6.00 508.62 3051.72 3051.72
Water Closet pcs 6.00 3850 23100 23100

Total of Plumbing PHP 112475.5

DIVISION 16: Electrical


For Toilet Facility
28W Fluorescent lighting fixture, ceiling
1 pcs 4.00 647 2588 2588
mounted
28W Fluorescent lighting fixture on ceiling
pcs 24.00 647 15528 15528
steel frame
2 Single pole wall pcs 3.00 145 435 435
3 Single pole wall switches pcs 1.00 145 145 145
Duplex convenience outlet grounding type pcs 30.00 137 4110 4110
Special purpose outlet grounding type pcs 30.00 110 3300 3300
Automatic circuit breaker pcs 6.00 971 5826 5826
Distribution panel (DP) pcs 3.00 3599.75 10799.25 10799.25
Distribution panel (MDP) pcs 1.00 4999.75 4999.75 4999.75
Generating set, portable type pcs 3.00 50358 151074 151074
Service K WHR Meter pcs 1.00 2577 2577 2577

2 Underground conduit run lm 105.00 121 4235 4235


Concealed embedded conduit run lm 89.00 121 3589.67 3589.67

Total of Plumbing PHP 209206.67

TOTAL PHP 13686357.04


ID Task Task Name Duration Start Finish November December January February
Mode 11/7 11/14 11/21 11/28 12/5 12/12 12/19 12/26 1/2 1/9 1/16 1/23 1/30 2/6
1 Clearing 3 days Mon 11/15/21 Wed 11/17/21
2 Excavation 2 days Thu 11/18/21 Fri 11/19/21
3 Gravel Bedding 2 days Sat 11/20/21 Mon 11/22/21
4 Placing of Pre-Cast Footing Pedestal 3 days Tue 11/23/21 Thu 11/25/21
Columns for Health Facility

5 Reinforcement Works (Footing, 8 days Fri 11/26/21 Sat 12/4/21


Footing Tie Beam, Wall Footing,
Columns) for Toilet Facility
6 Concreting Works (Footing, 5 days Mon 12/6/21 Fri 12/10/21
Foooting Tie Beam, Wall Footing,
Columns) for Toilet Facility
7 Handback filling and compaction 9 days Sat 12/11/21 Tue 12/21/21
8 Plumbing Works 3 days Wed 12/22/21 Mon 12/27/21
9 Construction of Health Facility 18 days Tue 12/28/21 Wed 1/19/22
10 Concreting of Slabs 5 days Tue 12/28/21 Tue 1/4/22
11 Installation of Steel (Columns and 10 days Wed 1/5/22 Sat 1/15/22
Trusses)
12 Installation of Double PVC Coated 3 days Mon 1/17/22 Wed 1/19/22
Textile
13 For Toilet Facility 24 days Tue 12/28/21 Wed 1/26/22
14 Concreting of Slabs 1 day Tue 12/28/21 Tue 12/28/21
15 Masonry 2 days Wed 12/29/21 Thu 12/30/21
16 Roof Beam 4 days Mon 1/3/22 Thu 1/6/22
17 Plastering Works 5 days Fri 1/7/22 Wed 1/12/22
18 Truss Installation 3 days Thu 1/13/22 Sat 1/15/22
19 Roof Installation 1 day Mon 1/17/22 Mon 1/17/22
20 Electrical Installation 6 days Tue 1/18/22 Mon 1/24/22
21 Finishing Works 8 days Tue 1/25/22 Wed 2/2/22
22 Ceiling Works 1 day Tue 1/25/22 Tue 1/25/22
23 Floor Tiling 2 days Wed 1/26/22 Thu 1/27/22
24 Finishing Tiles (Wall and Sink) 4 days Fri 1/28/22 Tue 2/1/22
25 Painting Works 1 day Wed 2/2/22 Wed 2/2/22
26 For Septic Tanks 3 days Thu 2/3/22 Sat 2/5/22
27 Reinforcement Works 2 days Thu 2/3/22 Fri 2/4/22
28 Concreting Works 1 day Wed 1/5/22 Wed 1/5/22

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: Project1 Split External Tasks Inactive Summary Manual Summary Critical
Date: Wed 11/17/21 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress

Page 1
Clearing Excavation Gravel Bedding Placing of Pre-Cast Footing Pedestal Columns for Health Facility Handback filling and compaction Plumbing Works Construction of Health Facility Concreting of Slabs
Start: Mon 11/15/21
ID: 1 Start: Thu 11/18/21ID: 2 Start: Sat 11/20/21ID: 3 Start: Tue 11/23/21ID: 4 Start: Sat 12/11/21ID: 7 Start: Wed 12/22/21
ID: 8 Start: Tue 12/28/21ID: 9 Start: Thu 1/20/22ID: 10
Finish: Wed 11/17/21
Dur: 3 days Finish: Fri 11/19/21Dur: 2 days Finish: Mon 11/22/21
Dur: 2 days Finish: Thu 11/25/21
Dur: 3 days Finish: Tue 12/21/21
Dur: 9 days Finish: Mon 12/27/21
Dur: 3 days Finish: Wed 1/19/22Dur: 18 days Finish: Tue 1/25/22Dur: 5 days
Res: Res: Res: Res: Res: Res: Res: Res:

Installation of Steel (Columns and Trusses)


Start: Thu 1/20/22ID: 11
Finish: Mon 1/31/22Dur: 10 days
Res:

Installation of Double PVC Coated Textile


Start: Thu 1/20/22ID: 12
Finish: Sat 1/22/22 Dur: 3 days
Res:

For Toilet Facility Concreting of Slabs


Start: Tue 12/28/21ID: 13 Start: Thu 1/27/22ID: 14
Finish: Wed 1/26/22Dur: 24 days Finish: Thu 1/27/22Dur: 1 day
Res: Res:

Masonry
Start: Thu 1/27/22ID: 15
Finish: Fri 1/28/22 Dur: 2 days
Res:

Roof Beam
Start: Thu 1/27/22ID: 16
Finish: Mon 1/31/22Dur: 4 days
Res:

Plastering Works
Start: Thu 1/27/22ID: 17
Finish: Tue 2/1/22 Dur: 5 days
Res:

Truss Installation
Start: Thu 1/27/22ID: 18
Finish: Sat 1/29/22 Dur: 3 days
Res:

Roof Installation
Start: Thu 1/27/22ID: 19
Finish: Thu 1/27/22Dur: 1 day
Res:

Reinforcement Works (Footing, Footing Tie Beam, Wall Footing,


Concreting
Columns)
Worksfor
(Footing,
Toilet Facility
Foooting Tie Beam, Wall Footing, Columns) for Toilet Facility
Start: Fri 11/26/21ID: 5 Start: Mon 12/6/21ID: 6
Finish: Sat 12/4/21 Dur: 8 days Finish: Fri 12/10/21Dur: 5 days
Res: Res:

Page 1
Electrical Installation Finishing Works Ceiling Works For Septic Tanks Reinforcement Works
Start: Wed 2/2/22 ID: 20 Start: Wed 2/9/22 ID: 21 Start: Fri 2/18/22 ID: 22 Start: Wed 2/23/22ID: 26 Start: Thu 1/20/22ID: 27
Finish: Tue 2/8/22 Dur: 6 days Finish: Thu 2/17/22Dur: 8 days Finish: Fri 2/18/22 Dur: 1 day Finish: Fri 2/25/22 Dur: 3 days Finish: Fri 1/21/22 Dur: 2 days
Res: Res: Res: Res: Res:

Concreting Works
Start: Sat 1/22/22 ID: 28
Finish: Sat 1/22/22 Dur: 1 day
Res:

Floor Tiling
Start: Fri 2/18/22 ID: 23
Finish: Sat 2/19/22 Dur: 2 days
Res:

Finishing Tiles (Wall and Sink)


Start: Fri 2/18/22 ID: 24
Finish: Tue 2/22/22Dur: 4 days
Res:

Painting Works
Start: Fri 2/18/22 ID: 25
Finish: Fri 2/18/22 Dur: 1 day
Res:

Page 2
Critical Critical Milestone Critical Summary Critical Inserted Critical Marked Critical External Project Summary Highlighted Noncritical
Project: Project1
Date: Wed 11/17/21 Noncritical Milestone Summary Inserted Marked External Highlighted Critical

Page 3
S-CURVE
MONTH1 % % MONTH 1 MONTH 2 MONTH 3
WK1 WK1 WK2 WK3 WK4 WK1 WK2 WK3 WK4 WK1 WK2 WK3 WK4
Clearing 265050 18.339 32.9094 34.5715 36.6471 38.3693 43.1278 47.1638 62.0722 80.5438 90.4074 96.1834 100
Excavation 219540
Gravel Bedding 8344.565 492934.6 18.339
WK2
Gravel Bedding 8344.565
120
Placing of Pre-Cast 368402.1
Reinforcement Works 14891.75 391638.4 14.5704 100
WK3
Reinforcement Works 44675.24 44675.24 1.66209 80

WK4
60
Concreting works 48076.35
Handbackfilling and Compaction 7714.833 55791.18 2.07564 40

MONTH2 20

WK1
0
Handbackfilling and Compaction 46289 46289 1.72212 WK1 WK2 WK3 WK4 WK1 WK2 WK3 WK4 WK1 WK2 WK3 WK4
WK2
MONTH 1 MONTH 2 MONTH 3
Handbackfilling and Compaction 15429.67
Plumbing 112475.5 127905.2 4.75855
WK3
Concreting of Slabs HF 94027.5
Concreting of Slabs TF 14455.95 108483.5 4.03599
Masonry
WK4
Concreting of Slabs HF 62685
Installation of Steel 315917.9
Roof Beam 7038.575
Plastering Works 15082.17 400723.6 14.9084

MONTH 3
WK1
Installation of Steel 473876.8
Plastering Works 22623.35 496500.2 18.4717
Truss Installation
WK2
Roof Installation 90785.16
Electrical Installation 174338.9 265124.1 9.8636
WK3
Electrical Installation 34867.78
Ceiling 6505
Floor Tiling 23156.52
Wall Tiling 90723.12 155252.4 5.77597
WK4
Wall Tiling 90723.12
Painting works 11863 102586.1 3.81659
TOTAL 2687903
MANPOWER SCHEDULLING
MONTH 1 MONTH 2 MONTH 3
MANPOWER NOS
WK 1 WK 2 WK 3 WK4 WK1 WK2 WK3 WK4 WK1 WK2 WK3 WK4
Project Manager 1 6 6 6 6 6 6 6 6 6 6 0 0
Site Engineer 1 6 6 6 6 6 6 6 6 6 6 0 0
QA/QC Engineer 1 6 6 6 6 6 6 6 6 6 6 0 0
Safety Engineer 1 6 6 6 6 6 6 6 6 6 6 0 0
Surveyor 1 6 6 6 6 6 6 6 6 6 6 0 0

Laborers 8 30 56 56 56 56 56 56 56 56 56 0 0
Carpenter 4 0 0 0 12 24 24 24 24 24 0 0 0
Steel Fixers 3 0 18 18 18 18 18 18 18 18 18 18 0
Masons 8 0 0 0 0 0 16 32 24 32 24 24 0
Welders 5 0 0 0 0 0 5 20 30 30 30 0 0
Painters 2 0 0 0 0 0 0 0 0 0 0 2 0
Plumber 2 0 0 0 0 6 0 0 0 0 0 0 0
Electrician 2 0 0 0 0 0 0 0 0 0 0 12 0
Tile Setter 2 0 0 0 0 0 0 0 0 0 0 12 8
Equipment Operator 5 30 12 12 12 12 8 8 12 12 12 0 0
Security Guard 2 12 12 10 12 12 8 8 12 12 12 0 0
Total Man-Days 102 128 126 140 158 165 196 206 214 182 68 0

Total Man-Days
250

200

150

100

50

0
WK 1 WK 2 WK 3 WK4 WK1 WK2 WK3 WK4 WK1 WK2 WK3 WK4
MONTH 1 MONTH 2 MONTH 3

Total Man-Days
EQUIPMENT SCHEDULLING
EQUIPMENT NOS MONTH 1 MONTH 2 MONTH 3
WK 1 WK 2 WK 3 WK4 WK1 WK2 WK3 WK4 WK1 WK2 WK3 WK4
Dump Truck 2 12 12 0 0 0 0 0 0 0 0 0 0
Backhoe 1 6 0 0 0 0 0 0 0 0 0 0 0
Bull Dozers 2 4 0 0 0 0 0 0 0 0 0 0 0
Vibrator 2 0 0 0 12 12 12 8 12 12 0 0 0
Conrete Mixer 1 0 6 6 6 6 6 6 6 6 0 0 0
Concrete Pump 1 0 6 6 6 6 6 6 6 0 0 0 0
Plate Compactor 2 0 0 0 12 12 0 0 0 0 0 0 0
Mobile Crane 2 12 12 12 12 12 12 8 12 12 0 0 0
Forklift 2 12 12 12 12 12 12 8 12 12 12 0 0
Welding Machine 2 0 0 0 0 12 12 8 8 12 12 0 0
Genset 2 12 12 12 12 12 12 8 8 12 12 12 0
Total Man-Days 58 60 48 72 84 72 52 64 66 36 12 0

Total Man-Days
90
80
70
60
50
40
30
20
10
0
WK 1 WK 2 WK 3 WK4 WK1 WK2 WK3 WK4 WK1 WK2 WK3 WK4
NOS MONTH 1 MONTH 2 MONTH 3

Total Man-Days
PREPARED BY:
CORBILLA, VINCENT ALLEN B.
LADRERA, CARL LORENZ B.
MIRANDA, CHARLAMAGNE F.

FCONPRL
CIVP39
PROJECT BACKGROUND:
PROJECT NAME: DPWH Standard Three (3) Units Health
Facility Tent

LOCATION: Brgy. San Isidro Bay, Laguna

PROJECT START: November 15, 2021

PROJECT END: January 22, 2021

CONTRACT AMOUNT: P2,660,158.17


PROJECT INFORMATION:

Type of Construction : Institutional and Commercial

Gross Floor Area /


Area / Length: 800 sq. m

Contract Type: BOQ (Unit Price) Contract

Project Duration: 72 Calendar Days


PROJECT INFORMATION:
PERSPECTIVE
PROJECT INFORMATION:
PROJECT INFORMATION:
PROJECT SCHEDULE:
NETWORK DIAGRAM
PROJECT SCHEDULE:
CRITICAL PATH
PROJECT SCHEDULE:
GANTT CHART
S-CURVE
MANPOWER SCHEDULE:
EQUIPMENT SCHEDULE: