You are on page 1of 246

HSPK 2018

No Nama Barang Vol Daerah Daerah


Datar Pegunungan
1 2 3 4 5

3.6 LAMPU PENERANGAN JALAN DAN


LAMPU TAMAN SERTA PERALATAN
LISTRIK

3.6.1 LAMPU TAMAN DAN PERALATAN LISTRIK


3.6.1.1 Arde 08 mm M' 9,000.00 9,900.00
3.6.1.2 Arde 12 mm M' 14,000.00 15,400.00
3.6.1.3 Arde 14 mm M' 26,500.00 29,150.00
3.6.1.4 Arde 16 mm M' 30,000.00 33,000.00
3.6.1.5 Arde 16 mm yang panjang M' 55,000.00 60,500.00
3.6.1.6 Arde 18 mm M' 56,000.00 61,600.00
3.6.1.7 Balok 20 Watt Double Bh 65,000.00 71,500.00
3.6.1.8 Balok 40 Watt Double Bh 115,000.00 126,500.00
3.6.1.9 BC (kabel tembaga) 06 mm M' 1,500.00 1,650.00
3.6.1.10 BC (kabel tembaga) 16 mm Bh 25,000.00 27,500.00
3.6.1.11 BC (kabel tembaga) 25 mm Bh 35,000.00 38,500.00
3.6.1.12 Box MCB 1 grup Bh 600.00 660.00
3.6.1.13 Box MCB 2 grup Bh 9,500.00 10,450.00
3.6.1.14 Box MCB 3 grup Bh 14,500.00 15,950.00
3.6.1.15 Box meter MG Bh 17,500.00 19,250.00
3.6.1.16 Box Panel KWH 60x40x20 cm / outdoor Bh 800,000.00 880,000.00
3.6.1.17 Box panel saka 20x30x12 Bh 137,000.00 150,700.00
3.6.1.18 Box presto uticon 4 grup Bh 40,000.00 44,000.00
3.6.1.19 Box presto uticon 8 grup Bh 55,000.00 60,500.00
3.6.1.20 BUSBAR (Plat Tembaga) Nol & Arde (2x20mm) M' 45,000.00 49,500.00
3.6.1.21 Contactor Bh 340,000.00 374,000.00
3.6.1.22 Fitcing tempel ( broco) Bh 10,000.00 11,000.00
3.6.1.23 Fiting Halogen Stick 1000 Watt Bh 11,000.00 12,100.00
3.6.1.24 Fiting Halogen Stick 150 Watt Bh 9,000.00 9,900.00
3.6.1.25 Fiting Halogen Stick 500/300 Watt Bh 11,000.00 12,100.00
3.6.1.26 Fiting Sambung E40-E27 Bh 11,000.00 12,100.00
3.6.1.27 Fitting besi Kj E - 40 Bh 22,500.00 24,750.00
3.6.1.28 Ft besi gantung E - 27 Bh 10,000.00 11,000.00
3.6.1.29 Ft ceramic E-40 gantung Bh 18,000.00 19,800.00
3.6.1.30 Fuse box Broco 1 grup Bh 34,000.00 37,400.00
3.6.1.31 Fuse box Broco 2 grup Bh 41,000.00 45,100.00
3.6.1.32 Fuse box Broco 3 grup Bh 60,000.00 66,000.00
3.6.1.33 Fuse box Max 1 grup Bh 30,000.00 33,000.00
3.6.1.34 Hakiki NYAF srabut engkel NYAF = 0.75 mm(100m) Rol 145,000.00 159,500.00
3.6.1.35 Hakiki NYAF serabut engkel NYAF = 1.5 mm(100m) Rol 220,000.00 242,000.00
3.6.1.36 Hakiki NYAF srabut engkel NYAF = 1.5 mm(100m) Rol 236,000.00 259,600.00
3.6.1.37 Hakiki NYAF serabut engkel NYAF = 2.5 mm(100m) Rol 370,000.00 407,000.00
3.6.1.38 Hakiki NYAF serabut engkel NYAF = 4 mm(100m) Rol 640,000.00 704,000.00
3.6.1.39 Hakiki NYAF serabut engkel NYAF = 6 mm(100m) Rol 870,000.00 957,000.00
3.6.1.40 Halogen stic 1000W Philips Bh 40,000.00 44,000.00

1
1 2 3 4 5
3.6.1.41 Halogen stic 150W philips Bh 26,000.00 28,600.00
3.6.1.42 Halogen stic 300W Philips Bh 27,500.00 30,250.00
3.6.1.43 Halogen stic 500W Philips Bh 28,000.00 30,800.00
3.6.1.44 Handel G2 15 Bh 165,000.00 181,500.00
3.6.1.45 Handel G2 32 NISO Bh 225,000.00 247,500.00
3.6.1.46 Handel G2 63 Bh 155,000.00 155,000.00
3.6.1.47 Handel 63 A NISO Bh 650,000.00 715,000.00
3.6.1.48 HPIT 250W Philips Bh 168,000.00 184,800.00
3.6.1.49 HPIT 400W Philips Bh 179,000.00 196,900.00
3.6.1.50 Ignitor untuk Lampu Philips, S1- 51 putih Bh 36,000.00 39,600.00
3.6.1.51 Ignitor untuk Lampu Philips, SN- 58 kuning Bh 40,000.00 44,000.00
3.6.1.52 Isolasi Nachi Bh 8,500.00 9,350.00
3.6.1.53 Jet power lampu selang (soket) Bh 20,000.00 22,000.00
3.6.1.54 Kabel NYA 1.5 mm 100 m Rol 171,000.00 188,100.00
3.6.1.55 Kabel NYA 1.5 mm / eterna M' 2,500.00 2,750.00
3.6.1.56 Kabel NYA 2.5 mm 100 m Rol 272,000.00 299,200.00
3.6.1.57 Kabel NYA 2.5 mm M' 4,500.00 4,950.00
3.6.1.58 Kabel NYA 4 mm M' 5,000.00 5,500.00
3.6.1.59 Kabel NYA 6 mm M' 11,000.00 12,100.00
3.6.1.60 Kabel NYA 10 mm M' 19,000.00 20,900.00
3.6.1.61 Kabel NYM 2 x 1,5 mm M' 7,000.00 7,700.00
3.6.1.62 Kabel NYM 2 x 2,5 mm M' 9,500.00 10,450.00
3.6.1.63 Kabel NYM 3 x 1,5 mm M' 9,000.00 9,900.00
3.6.1.64 Kabel NYM 3 x 2,5 mm M' 13,000.00 14,300.00
3.6.1.65 Kabel NYM 3 x 4 mm M' 18,000.00 19,800.00
3.6.1.66 Kabel NYM 4 x 2,5 mm M' 16,500.00 18,150.00
3.6.1.67 Kabel MYM Focus 4 x 4 mm hakiki 100m Rol 2,120,000.00 2,332,000.00
3.6.1.68 Kabel NYM 3 x 4 mm Rol 18,000.00 19,800.00
3.6.1.69 Kabel NYM 4 x 2,5 mm Rol 16,500.00 18,150.00
3.6.1.70 Kabel Nymhy (serabut) 2 x 0.75 mm Roll 435,000.00 478,500.00
3.6.1.71 Kabel Nymhy (serabut) 2 x 2.5 mm Roll 1,100,000.00 1,210,000.00
3.6.1.72 Kabel Nymhy (serabut) 4 x 2.5 mm Roll 2,000,000.00 2,200,000.00
3.6.1.73 Kabel NYY 2 x 1,5 mm M' 10,000.00 11,000.00
3.6.1.74 Kabel NYY 2 x 2,5 mm M' 13,000.00 14,300.00
3.6.1.75 Kabel NYY 3 x 1,5 mm M' 13,000.00 14,300.00
3.6.1.76 Kabel NYY 3 x 2,5 mm M' 17,500.00 19,250.00
3.6.1.77 Kabel NYY 3 x 4 mm M' 25,000.00 27,500.00
3.6.1.78 Kabel NYY 4 x 2,5 mm M' 20,000.00 22,000.00
3.6.1.79 Kabel NYY 4 x 4 mm M' 30,000.00 33,000.00
3.6.1.80 Kabel NYY 4 x 6 mm M' 40,000.00 44,000.00
3.6.1.81 Kabel NYY 4 x 10 mm M' 63,000.00 69,300.00
3.6.1.82 Kabel NYY 2 x 1,5 mm @ 100 m Rol 800,000.00 880,000.00
3.6.1.83 Kabel NYY 2 x 2,5 mm @ 100 m Rol 1,060,000.00 1,166,000.00
3.6.1.84 Kabel NYY 3 x 1,5 mm @ 100 m Rol 970,000.00 1,067,000.00
3.6.1.85 Kabel NYY 3 x 2,5 mm @ 100 m Rol 1,325,000.00 1,457,500.00
3.6.1.86 Kabel NYY 4 x 2,5 mm @ 100 m Rol 1,625,000.00 1,787,500.00
3.6.1.87 Kabel NYY 4 x 4 mm @ 100 m Rol 2,350,000.00 2,585,000.00
3.6.1.88 Kabel NYY 4 x 6 mm @ 100 m Rol 3,300,000.00 3,630,000.00
3.6.1.89 Kabel NYY HYO 2 x 0,75 mm @ 100 m Rol 435,000.00 478,500.00
3.6.1.90 Kabel NYY HYO 2 x 1,5 mm @ 100 m Rol 740,000.00 814,000.00

2
1 2 3 4 5
3.6.1.91 Kabel NYY HYO 2x 2,5 mm @ 100 m Rol 1,100,000.00 1,210,000.00
3.6.1.92 Kabel NYY HYO 3 x 1,5 mm @ 100 m Rol 1,020,000.00 1,122,000.00
3.6.1.93 Kabel NYY HYO 3 x 2,5 mm @ 100 m Rol 1,475,000.00 1,622,500.00
3.6.1.94 Kabel PVC 2 x 23 mm Rol 200,000.00 220,000.00
3.6.1.95 Kabel Twistied 2 x 12 mm M' 8,000.00 8,800.00
3.6.1.96 Kabel Twistied 2 x 16 mm M' 7,250.00 7,975.00
3.6.1.97 Kabel Twistied 2 x 10 Pulong M' 6,000.00 6,600.00
3.6.1.98 Kabel Twistied 3 x 35 mm2 + 1 x 25 mm2 M' 21,000.00 23,100.00
3.6.1.99 Kabel Twistied 3 x 50 mm2 + 1 x 35 mm2 M' 28,000.00 30,800.00
3.6.1.100 Kabel Twistied 4 x 25 mm2 M' 37,000.00 40,700.00
3.6.1.101 Kap Lampu Tancap PAR Bh 59,000.00 64,900.00
3.6.1.102 Kap Halogen 1000 NISO Rol 108,000.00 118,800.00
3.6.1.103 Kap Halogen 150 NISO Rol 35,000.00 38,500.00
3.6.1.104 Kap Halogen 500/300 NISO Rol 54,000.00 59,400.00
3.6.1.105 Kap HPIT 250 Watt NISO Bh 335,000.00 368,500.00
3.6.1.106 Kap HPIT 400 Watt Bh 350,000.00 385,000.00
3.6.1.107 Kap ijo E- 27 pasific Bh 10,000.00 11,000.00
3.6.1.108 Kap ijo E- 40 dexta Bh 22,500.00 24,750.00
3.6.1.109 Kap Lampu TL 20 Watt balak TKOU 1 X 20 Bh 49,000.00 53,900.00
3.6.1.110 Kap Lampu TL 40 Watt balak TKOU 1 X 40 Bh 95,000.00 104,500.00
3.6.1.111 Kap Reflektor (putih) Kap. Industri 8" E40 Bh 50,000.00 55,000.00
3.6.1.112 Kap Totok MC Bh 1,250,000.00 1,375,000.00
3.6.1.113 Kapasitor 25 µ Bh 40,000.00 44,000.00
3.6.1.114 Kapasitor 30 µ Bh 45,000.00 49,500.00
3.6.1.115 Kawat Tarik uk 14 Kg 25,000.00 27,500.00
3.6.1.116 Klem Imundex no 10 Dos 6,250.00 6,875.00
3.6.1.117 Klem Imundex no 12 Dos 8,500.00 9,350.00
3.6.1.118 Klem Imundex no 17 Dos 13,900.00 15,290.00
3.6.1.119 Klem Imundex no 9 Dos 5,750.00 6,325.00
3.6.1.120 Konektor 6-25 mm Bh 9,000.00 9,900.00
3.6.1.121 Kontaktor Telemekanik SN 32 / 50A / 220V Bh 525,000.00 577,500.00
3.6.1.122 Lampu Spot JCDR 20 Watt Bh 12,000.00 13,200.00
3.6.1.123 Lampu Spot JCDR 50 Watt Bh 12,000.00 13,200.00
3.6.1.124 Lampu dop pijar 5 W Bh 5,000.00 5,500.00
3.6.1.125 Lampu selang LED Kotak / Putih Rol 1,750,000.00 1,925,000.00
3.6.1.126 Lampu LED 14 watt Bh 40,000.00 44,000.00
3.6.1.127 Lampu Selang Shinyoku 3 j / merah Rol 3,900,000.00 4,290,000.00
3.6.1.128 Lampu Hias Meteor Uk. 40 cm Bh 113,000.00 124,300.00
3.6.1.129 Lampu Hias Meteor Uk. 60 cm Bh 136,000.00 149,600.00
3.6.1.130 Lampu Hias Meteor Uk. 80 cm Bh 155,000.00 170,500.00
3.6.1.131 Lampu LHE 13 Watt ( E 27 ) Bh 34,000.00 37,400.00
3.6.1.132 Lampu LHE 18 Watt Spiral( E 27 ) Bh 31,500.00 34,650.00
3.6.1.133 Lampu LHE 23 Watt ( E 27 ) Bh 30,000.00 33,000.00
3.6.1.134 Lampu LHE 25 Watt Spiral ( E 27 ) Bh 35,000.00 38,500.00
3.6.1.135 Lampu LHE 36 Watt ( E 27 ) Bh 93,000.00 102,300.00
3.6.1.136 Lampu LHE 36 Watt Kuning ( E 27 ) Spiral Bh 84,000.00 92,400.00
3.6.1.137 Lampu LHE 45 Watt (E27) Bh 60,000.00 66,000.00
3.6.1.138 Lampu LHE 45 Watt Kuning (E27) Spiral Bh 95,000.00 104,500.00
3.6.1.139 Lampu LHE 65 Watt Kuning ( E 27 ) Spiral Bh 170,000.00 187,000.00
3.6.1.140 Lampu LHE 68 Watt ( E 27 ) Bh 165,000.00 181,500.00

3
1 2 3 4 5
3.6.1.141 Lampu LHE 85 Watt ( E 40 ) Spiral Visalux Bh 220,000.00 242,000.00
3.6.1.142 Lampu MC 125 Watt Bh 41,000.00 45,100.00
3.6.1.143 Lampu MC 250 Watt Bh 75,000.00 82,500.00
3.6.1.144 Lampu MC 400 Watt Bh 95,000.00 104,500.00
3.6.1.145 Lampu ML 160 Watt Bh 40,000.00 44,000.00
3.6.1.146 Lampu philips ML 500 W Bh 73,000.00 80,300.00
3.6.1.147 Lampu philips ML 250 W Bh 67,000.00 73,700.00
3.6.1.148 Lampu Sorot PAR 220 V 120 W Bh 102,000.00 112,200.00
3.6.1.149 Lampu Sorot PAR 220 V 80 W Bh 92,500.00 101,750.00
3.6.1.150 Lampu spot light 150 watt eks philips ( lengkap) Bh 106,000.00 116,600.00
3.6.1.151 Lampu spot light 300 watt eks philips ( lengkap) Bh 137,500.00 151,250.00
3.6.1.152 Lampu TL 20 watt komplit Bh 92,500.00 101,750.00
3.6.1.153 Lampu TL 40 watt komplit Bh 116,000.00 127,600.00
3.6.1.154 MC HPL-N 125W Philips (Trafo) Bh 120,000.00 132,000.00
3.6.1.155 MC HPL-N 250W Philips (Trafo) Bh 200,000.00 220,000.00
3.6.1.156 MC HPL-N 400W Philips (Trafo) Bh 203,000.00 223,300.00
3.6.1.157 MCB 2 A / 1 Phase / Merlin Gerin Bh 40,000.00 44,000.00
3.6.1.158 MCB 4 A / 1 Phase Bh 37,500.00 41,250.00
3.6.1.159 MCB 6 A / 1 Phase Bh 35,000.00 38,500.00
3.6.1.160 MCB 10 A / 1 Phase Bh 40,000.00 44,000.00
3.6.1.161 MCB 16 A / 1 Phase Bh 40,000.00 44,000.00
3.6.1.162 MCB 20 A / 1 Phase Bh 40,000.00 44,000.00
3.6.1.163 MCB 25 A / 1 Phase Bh 40,000.00 44,000.00
3.6.1.164 MCB 32 A / 1 Phase Bh 49,000.00 53,900.00
3.6.1.165 MCB 35 A / 1 Phase Bh 50,000.00 55,000.00
3.6.1.166 MCB 40 A / 1 Phase Bh 52,000.00 57,200.00
3.6.1.167 MCB 50 A / 1 Phase Bh 130,000.00 143,000.00
3.6.1.168 MCB 63 A / 1 Phase Bh 160,000.00 176,000.00
3.6.1.169 Mitsubishi Magnetic SN-35/220 Bh 410,000.00 451,000.00
3.6.1.170 NFB 100A Bh 603,000.00 663,300.00
3.6.1.171 NFB 125A Bh 1,030,000.00 1,133,000.00
3.6.1.172 NFB 75A Bh 603,000.00 663,300.00
3.6.1.173 NYM 2X1.5mm hakiki Roll 550,000.00 605,000.00
3.6.1.174 NYM 2X2.5mm hakiki Roll 794,000.00 873,400.00
3.6.1.175 NYM 2X4mm hakiki Roll 1,230,000.00 1,353,000.00
3.6.1.176 NYM 3X1.5mm hakiki Roll 710,000.00 781,000.00
3.6.1.177 NYM 3X2.5mm hakiki Roll 1,013,000.00 1,114,300.00
3.6.1.178 NYM 3X4mm hakiki Roll 1,586,500.00 1,745,150.00
3.6.1.179 NYM 3X6mm hakiki Roll 2,250,000.00 2,475,000.00
3.6.1.180 NYM 4X1.5mm hakiki Roll 900,000.00 990,000.00
3.6.1.181 NYM 4X2.5mm hakiki Roll 1,350,000.00 1,485,000.00
3.6.1.182 NYM 4X4mm hakiki Roll 2,120,000.00 2,332,000.00
3.6.1.183 NYZ 2X23 (oval) hakiki Roll 240,000.00 264,000.00
3.6.1.184 Ongkos pasang titik lampu + instalasi Ttk 150,000.00 165,000.00
3.6.1.185 Ornamen pipa medium 1,5" / 2 mm / 6 m unit 1,350,000.00 1,485,000.00
3.6.1.186 Panel Box (40x60x20) Bh 365,000.00 401,500.00
3.6.1.187 Pasang KWH Meter 900 VA Psg 2,700,000.00 2,970,000.00
3.6.1.188 Philips jari essential 11 w Bh 23,000.00 25,300.00
3.6.1.189 Philips jari essential 13 w Bh 31,000.00 31,000.00
3.6.1.190 Philips jari essential 14 w Bh 23,000.00 25,300.00

4
1 2 3 4 5
3.6.1.191 Philips jari essential 18 w Bh 25,000.00 27,500.00
3.6.1.192 Philips jari essential 23 w Bh 30,000.00 33,000.00
3.6.1.193 Philips jari essential 36 w Bh 54,000.00 59,400.00
3.6.1.194 Philips jari essential 45 w Bh 110,000.00 121,000.00
3.6.1.195 Philips jari essential 5 w Bh 16,000.00 17,600.00
3.6.1.196 Philips jari essential 65 w Bh 136,500.00 150,150.00
3.6.1.197 Philips jari essential 8 w Bh 18,500.00 20,350.00
3.6.1.198 Rel barr / 3 phase Pcs 39,000.00 42,900.00
3.6.1.199 Rel barr / 1 phase Lot 19,000.00 20,900.00
3.6.1.200 Saklar Panasonic (ganda) Bh 22,100.00 24,310.00
3.6.1.201 Saklar Panasonic (tunggal) Bh 13,700.00 15,070.00
3.6.1.202 Sambungan Jet P Lampu Selang Rol 20,000.00 22,000.00
3.6.1.203 Selcon photosel 06A Bh 45,000.00 49,500.00
3.6.1.204 Sevis (penguat tarikan) Bh 6,500.00 7,150.00
3.6.1.205 Shinyoku PLC 40w E-27 Bh 93,000.00 93,000.00
3.6.1.206 Shinyoku PLC 45w E-27 Bh 99,000.00 99,000.00
3.6.1.207 SISIR MCB 3 fase Lot 155,000.00 170,500.00
3.6.1.208 SKUN Kabel 16mm Bh 1,550.00 1,705.00
3.6.1.209 SKUN Kabel 25mm Bh 2,000.00 2,200.00
3.6.1.210 SON-H 250W Philips Bh 220,000.00 242,000.00
3.6.1.211 SON-H 350W Philips Bh 275,000.00 302,500.00
3.6.1.212 SON-T 250W Philips Bh 132,000.00 145,200.00
3.6.1.213 SON-T 400W Philips Bh 139,000.00 152,900.00
3.6.1.214 Steker arde Bh 9,500.00 10,450.00
3.6.1.215 T Dos 20 mm / bulat Bh 5,000.00 5,500.00
3.6.1.216 SON-T 70 Watt Bh 83,000.00 91,300.00
3.6.1.217 SON-T 150 Watt Bh 95,000.00 104,500.00
3.6.1.218 Stater / S2 Bh 3,000.00 3,300.00
3.6.1.219 Stop Kontak IB / Tanem Bh 12,000.00 13,200.00
3.6.1.220 T. Dos Kotak Bh 10,000.00 11,000.00
3.6.1.221 Tali Ties 10 cm Pak 4,500.00 4,950.00
3.6.1.222 Tali Ties 15 cm Pak 7,000.00 7,700.00
3.6.1.223 Tali Ties 20 cm Pak 10,000.00 11,000.00
3.6.1.224 Terminal 10 mm Bh 9,250.00 10,175.00
3.6.1.225 Terminal 16 mm Bh 20,000.00 22,000.00
3.6.1.226 Terminal 25 mm Bh 26,000.00 28,600.00
3.6.1.227 Terminal 6 mm Bh 6,500.00 7,150.00
3.6.1.228 Timer theben Bh 350,000.00 385,000.00
3.6.1.229 Trafo BSN 70 Watt / 3 kaki Bh 115,000.00 126,500.00
3.6.1.230 Trafo BSN 150 Watt / 3 kaki Bh 165,000.00 181,500.00
3.6.1.231 Trafo Elektrik TL 20 Watt ex, Philips Bh 30,000.00 33,000.00
3.6.1.232 Trafo Elektrik TL 40 Watt ex. Philips Bh 30,000.00 33,000.00
3.6.1.233 Trafo 5 Am Bh 80,000.00 88,000.00
3.6.1.234 Trafo MC 250 Watt Bh 200,000.00 220,000.00
3.6.1.235 Trafo MC 400 Watt Bh 203,000.00 223,300.00
3.6.1.236 Travo 125W Philips Bh 120,000.00 132,000.00
3.6.1.237 Travo 250W Philips kaki 3 Bh 225,000.00 247,500.00
3.6.1.238 Travo 400W Philips kaki 3 Bh 385,000.00 423,500.00
3.6.1.239 Trek Schok Bh 325,000.00 357,500.00
3.6.1.240 Kabel NYM 2 x 1,5 mm Rol 7,000.00 7,700.00

5
1 2 3 4 5
3.6.1.241 Saklar Panasonic (Tunggal) Buah 13,700.00 15,070.00
3.6.1.242 Sekering Matsuka 2 A - 10 A Buah 25,000.00 27,500.00
3.6.1.243 Kabel NYM 3 x 4 mm Rol 18,000.00 19,800.00
3.6.1.244 Kabel NYM 3 x 1,5 mm Rol 710,000.00 781,000.00
3.6.1.245 Fiiting TL Buah 2,000.00 2,200.00
3.6.1.246 Fuse Box Broco 1 Group Buah 36,000.00 39,600.00
3.6.1.247 Fiiting Tempel (Broco) Buah 10,000.00 11,000.00
3.6.1.248 Stop Kontak Panasonic Buah 16,500.00 18,150.00
3.6.1.249 T. Dos Buah 1,000.00 1,100.00
3.6.1.250 Paket PJU Solar Cell 4 m 100 Wp (30 Watt) Paket 25,630,000.00 28,193,000.00
3.6.1.251 Paket PJU Solar Cell 7 m 100 Wp (60 Watt) Paket 36,630,000.00 40,293,000.00
3.6.1.252 Paket PJU Solar Cell 9 m 100 Wp (80 Watt) Paket 45,870,000.00 50,457,000.00
3.6.1.253 Solar Panel 100 WP Unit 3,600,000.00 3,960,000.00
3.6.1.254 Panel Box Automatic Switcher Solar System Unit 11,000,000.00 12,100,000.00
3.6.1.255 Inverter 48 V 4000 Watt Unit 35,000,000.00 38,500,000.00
3.6.1.256 Charger Controller 48 V 75 Ah Unit 28,000,000.00 30,800,000.00
3.6.1.257 OPzV Gel Batteray 2 V 400 Ah Unit 5,400,000.00 5,940,000.00
3.6.1.258 Smart Controller And Inverter Automatic Detection 12/24 V Output 20 Amp Unit 1,800,000.00 1,980,000.00
3.6.1.259 Battery MF 12 V 100 Ah 2,750,000.00 3,025,000.00
3.6.1.260 LED Light 80 Watt Unit 5,500,000.00 5,500,000.00
3.6.1.261 LED Light 60 Watt Unit 5,350,000.00 5,350,000.00
3.6.1.262 LED Light 30 Watt Unit 4,500,000.00 4,500,000.00
3.6.1.263 Tiang Lampu Unit 4,500,000.00 4,500,000.00
3.6.1.264 Smart Controller 12 / 24 V Output 20 Amp Unit 1,500,000.00 1,650,000.00
3.6.1.265 Inverter Automatic Detection 12 / 24 V Output 20 Amp Unit 750,000.00 825,000.00
3.6.1.266 Trafo BSN 125W / kaki 3 Bh 106,000.00 106,000.00
3.6.1.267 Trafo BSN 250 Watt / kaki 3 Bh 210,000.00 210,000.00
3.6.1.268 Trafo BSN 400 Watt / kaki 3 Bh 360,000.00 360,000.00
3.6.1.269 Multi LED 60 watt Bh 2,400,000.00 2,640,000.00
3.6.1.270 Multi LED 80 watt Bh 2,600,000.00 2,860,000.00
3.6.1.271 Multi LED 100 watt Bh 3,250,000.00 3,575,000.00
3.6.1.272 LED runbay komplit / 5m Bh 300,000.00 330,000.00
3.6.1.273 Kap lampu kaca ukuran kecil Unit 130,000.00 143,000.00
3.6.1.274 Kap lampu kaca ukuran besar Unit 180,000.00 198,000.00
3.6.1.275 Multi LED 96 watt 220-240 V Bh 3,000,000.00 3,300,000.00
3.6.1.276 LED 59/NW 55 Watt 220-240 V DM Mpi Bh 4,250,000.00 4,675,000.00
3.6.1.277 LED 97/NW 90 Watt 220-240 V DM Mpi Bh 5,000,000.00 5,500,000.00
3.6.1.278 LED 138/NW 120 Watt 220-240 V DM Mpi Bh 5,750,000.00 6,325,000.00
3.6.1.279 LED 167/NW 150 Watt 220-240 V DM Mpi Bh 7,000,000.00 7,700,000.00
3.6.1.280 Ornamen pipa medium 1,5" / 3 m unit 1,100,000.00 1,210,000.00
3.6.1.281 Ornamen pipa medium 1,5" / 9 m unit 1,650,000.00 1,815,000.00
3.6.1.282 Tiang PJU pipa medium 4", 3", 2,5", 2" / 7 m unit 3,000,000.00 3,300,000.00
3.6.1.283 Ornamen pipa medium 1,5" / 2 m Unit 1,000,000.00 1,100,000.00
3.6.1.284 Ornamen pipa medium 1,5" / 4 m Unit 1,250,000.00 1,375,000.00
3.6.1.285 Ornamen pipa medium 1,5" / 5 m Unit 1,350,000.00 1,485,000.00
3.6.1.286 Tiang PJU pipa besi 7 m Unit 2,900,000.00 3,190,000.00
3.6.1.287 Tiang PJU besi 7 m / 2 ornamen Unit 4,000,000.00 4,400,000.00
3.6.1.288 Tiang PJU besi 7 m / 3 ornamen Unit 6,500,000.00 7,150,000.00
3.6.1.289 Tiang PJU besi 8 m Unit 4,500,000.00 4,950,000.00

6
1 2 3 4 5
3.6.2 Alat – alat listrik
3.6.2.1 Avo Meter Bh 375,000.00 412,500.00
3.6.2.2 Belenja Tanda Rambu Bh 80,000.00 88,000.00
3.6.2.3 Bor Listrik Bh 2,100,000.00 2,310,000.00
3.6.2.4 Gergaji Bh 120,000.00 132,000.00
3.6.2.5 Kunci inggris Bh 140,000.00 154,000.00
3.6.2.6 Kunci set Bh 1,200,000.00 1,320,000.00
3.6.2.7 Meteran ( 5 ) m Bh 20,000.00 22,000.00
3.6.2.8 Meteran ( 50 ) m Bh 115,000.00 126,500.00
3.6.2.9 Senter Bh 110,000.00 121,000.00
3.6.2.10 Senter Kepala Bh 165,000.00 181,500.00
3.6.2.11 Solder Bh 30,000.00 33,000.00
3.6.2.12 Tanda rambu (Trafic cone) Bh 300,000.00 330,000.00
3.6.2.13 Tang Bh 40,000.00 44,000.00
3.6.2.14 Tang meter Bh 500,000.00 550,000.00
3.6.2.15 Tang Skut Bh 200,000.00 220,000.00
3.6.2.16 Tang Wentes Bh 500,000.00 550,000.00
3.6.2.17 Tangga (aluminium) 4 m Bh 2,400,000.00 2,640,000.00
3.6.2.18 Tangga (aluminium) 6 m Bh 3,100,000.00 3,410,000.00
3.6.2.19 Tangga aluminium) 3 m Bh 1,700,000.00 1,870,000.00
3.6.2.20 Tangga fiber anti petir Bh 15,500,000.00 17,050,000.00
3.6.2.21 Testpen Bh 16,000.00 17,600.00
3.6.2.22 Tang Kombinasi Bh 40,000.00 44,000.00
3.6.2.23 Gerinda / Serkel Listrik Bh 550,000.00 605,000.00
3.6.2.24 Genset 3500 watt Bh 6,600,000.00 7,260,000.00

3.6.3 PAKAIAN KERJA DAN KELENGKAPAN ANTI STRUM


3.6.3.1 Helm Bh 150,000.00 165,000.00
3.6.3.2 Jas Hujan Bh 180,000.00 198,000.00
3.6.3.3 Kaos Panjang Bh 130,000.00 143,000.00
3.6.3.4 Kaos pendek Bh 115,000.00 126,500.00
3.6.3.5 Katelpak Stell 250,000.00 275,000.00
3.6.3.6 Rompi fosfor Bh 75,000.00 82,500.00
3.6.3.7 Sabuk Pengaman Set 1,500,000.00 1,650,000.00
3.6.3.8 Sarung tangan Psg 195,000.00 214,500.00
3.6.3.9 Sepatu Psg 500,000.00 550,000.00
3.6.3.10 Sepatu harian Psg 250,000.00 275,000.00
3.6.3.11 Topi kerja Bh 40,000.00 44,000.00

7
TANAMAN HIAS DAN TAMAN

HSPK
2018
No Nama Barang Satuan
Daerah Daerah
Datar Pegunungan
1 2 3 4 5

2.2.4 BIBIT TANAMAN HIAS DAN TAMAN


2.2.4.1 TANAMAN PENUTUP TANAH
2.2.4.1.1 Rumput Embun Lempengan M2 23,000.00 23,000.00
2.2.4.1.2 Rumput jepang M2 23,000.00 23,000.00
2.2.4.1.3 Rumput Manila Lempengan M2 40,000.00 40,000.00
2.2.4.1.4 Rumput Mutiara M2 10,000.00 10,000.00
2.2.4.1.5 Rumput Putih M2 10,000.00 10,000.00
2.2.4.1.6 Rumput Golf M2 20,000.00 20,000.00
2.2.4.1.7 Rumput Lumut Serpen Lempengan M2 25,000.00 25,000.00
2.2.4.1.8 Rumput Manila Tandus M2 30,000.00 30,000.00
2.2.4.1.9 Rumput Paitan Lempengan M2 32,000.00 32,000.00
2.2.4.1.10 Rumput Paitan Tandus M2 10,000.00 10,000.00
2.2.4.1.11 Rumput sawah M2 8,000.00 8,000.00
2.2.4.1.12 Rumput Swiss M2 32,000.00 32,000.00
2.2.4.1.13 Gajah mini M2 25,000.00 25,000.00

2.2.4.2 TANAMAN PENUTUP TANAH BERGUNA


2.2.4.2.1 Bayam Merah (tinggi= 0.5 m) Polibag 5,000.00 5,000.00
2.2.4.2.2 Bludru Coklat Pot 7,000.00 7,000.00
2.2.4.2.3 Bludru Hijau Pot 7,000.00 7,000.00
2.2.4.2.4 Cendrawasih Pot 6,000.00 6,000.00
2.2.4.2.5 Cengger Ayam Air Mancur Besar Pot 6,000.00 6,000.00
2.2.4.2.6 Cengger Ayam Air Mancur Kecil Pot 6,000.00 6,000.00
2.2.4.2.7 Cengger Ayam Pot Rol Besar Pot 30,000.00 30,000.00
2.2.4.2.8 Cengger Ayam Pot Rol Kecil Pot 25,000.00 25,000.00
2.2.4.2.9 Cocor Bebek Pot 20,000.00 20,000.00
2.2.4.2.10 Kucai Polibag 4,000.00 4,000.00
2.2.4.2.11 Lili Paris Bintang Pot 4,000.00 4,000.00
2.2.4.2.12 Lili Paris Kasar Pot 4,000.00 4,000.00
2.2.4.2.13 Lili Paris Kucai Pot 4,000.00 4,000.00
2.2.4.2.14 Lili Paris Umbi Pot 4,000.00 4,000.00
2.2.4.2.15 Meotan Pot 3,500.00 3,500.00
2.2.4.2.16 Mirten Perak Pot 6,000.00 6,000.00
2.2.4.2.17 Mirten Rebah Pot 7,000.00 7,000.00
2.2.4.2.18 Nanas Kerang Pot 11,000.00 11,000.00
2.2.4.2.19 Nanas Merah Pot 14,000.00 14,000.00
2.2.4.2.20 Pakis Gunung Pot 7,000.00 7,000.00
2.2.4.2.21 Pakis Kelabang Pot 7,000.00 7,000.00
2.2.4.2.22 Pakis Krol Batang 11,000.00 11,000.00
2.2.4.2.23 Pakis Moos Pot 16,000.00 16,000.00
2.2.4.2.24 Pakis Perak Pot 23,000.00 23,000.00
2.2.4.2.25 Pangkas Kuning Pot 4,000.00 4,000.00
2.2.4.2.26 Seruni Pot 25,000.00 25,000.00
2.2.4.2.27 Sugi Putih Pot 17,000.00 17,000.00
2.2.4.2.28 Sutra Bombay Banci Pot 25,000.00 25,000.00
2.2.4.2.29 Kacang - kacangan Polibag 5,000.00 5,000.00

8
2018
No Nama Barang Satuan
2.2.4.2.30 Heliconica Polibag 11,000.00 11,000.00
2.2.4.2.31 Kembang kertas Polibag 23,000.00 23,000.00
2.2.4.2.32 Krokot Polibag 5,000.00 5,000.00
2.2.4.2.33 Pacar banyu Polibag 13,000.00 13,000.00

2.2.4.3 TANAMAN DALAM RUANG


2.2.4.3.1 Anggrek Bulan Pot 150,000.00 150,000.00
2.2.4.3.2 Anggrek Dangless Pot 60,000.00 60,000.00
2.2.4.3.3 Anggrek Dekorobium Pot 75,000.00 75,000.00
2.2.4.3.4 Anthurium Uk. 30 - 60 cm Pot 75,000.00 75,000.00
2.2.4.3.5 Anthurium Uk. 60 - 80 cm Pot 150,000.00 150,000.00
2.2.4.3.6 Anthurium Uk. 80-100 cm Pot 200,000.00 200,000.00
2.2.4.3.7 Balanceng Bintik Pot 75,000.00 75,000.00
2.2.4.3.8 Balanceng Putih Pot 150,000.00 150,000.00
2.2.4.3.9 Begonia Daun Besar Pot 100,000.00 100,000.00
2.2.4.3.10 Begonia Kecil Pot 25,000.00 25,000.00
2.2.4.3.11 Begonia Perak Pot 30,000.00 30,000.00
2.2.4.3.12 Beras Tumpah Pot 45,000.00 45,000.00
2.2.4.3.13 Golden Shower Pot 50,000.00 50,000.00
2.2.4.3.14 Kuping Gajah Pot 40,000.00 40,000.00
2.2.4.3.15 Kuping Keledai Pot 67,000.00 67,000.00
2.2.4.3.16 Maustera Pot 17,000.00 17,000.00
2.2.4.3.17 Simbar Menjangan Pot 17,000.00 17,000.00
2.2.4.3.18 Sri Rejeki Pot 50,000.00 50,000.00
2.2.4.3.19 Suplir Foster Pot 75,000.00 75,000.00
2.2.4.3.20 Suplir Halus Pot 50,000.00 50,000.00
2.2.4.3.21 Tanduk Rusa (rumpun) /mata tunas 20,000.00 20,000.00
2.2.4.3.22 Wali Songo Pot 50,000.00 50,000.00

2.2.4.4 TANAMAN PERDU SEMAK


2.2.4.4.1 Agave Kodok Pot 60,000.00 60,000.00
2.2.4.4.2 Agave Strip Pot 50,000.00 50,000.00
2.2.4.4.3 Aglonema Pohon 250,000.00 250,000.00
2.2.4.4.4 Amarilis Polibag 2,500.00 2,500.00
2.2.4.4.5 Andong merah Pohon 12,000.00 12,000.00
2.2.4.4.6 Andong merah (tinggi= 0.5 m) Polibag 12,000.00 12,000.00
2.2.4.4.7 Anggrek Tanah Pohon 16,000.00 16,000.00
2.2.4.4.8 Anjuang Hijau Pot 10,000.00 10,000.00
2.2.4.4.9 Aralea Polibek 25,000.00 25,000.00
2.2.4.4.10 Bendron (tinggi=0,5m) Polibag 15,000.00 15,000.00
2.2.4.4.11 Bougenville Berbunga Penuh Pohon 75,000.00 75,000.00
2.2.4.4.12 Bougenville Berbunga Penuh (tinggi= 0.5 m) Polibag 75,000.00 75,000.00
2.2.4.4.13 Bougenville Besar Pot 250,000.00 250,000.00
2.2.4.4.14 Bougenville Hawai Pot 250,000.00 250,000.00
2.2.4.4.15 Bougenville Kecil Pot 40,000.00 40,000.00
2.2.4.4.16 Daun pandan wangi Glangsing 25,000.00 25,000.00
2.2.4.4.17 Drasaena Pohon 20,000.00 20,000.00
2.2.4.4.18 Jamburan Polibag 2,500.00 2,500.00
2.2.4.4.19 Kaca Piring Pohon 25,000.00 25,000.00
2.2.4.4.20 Kaktus Centong Pohon 150,000.00 150,000.00
2.2.4.4.21 Kaktus Tiang Pentung Pohon 180,000.00 180,000.00
2.2.4.4.22 Kamboja Merah Hati 1 - 1,5 m Pohon 150,000.00 150,000.00
2.2.4.4.23 Kamboja Merah Hati 2 - 2,5 m Pohon 850,000.00 850,000.00
2.2.4.4.24 Kamboja Pantai Pohon 750,000.00 750,000.00

9
2018
No Nama Barang Satuan
2.2.4.4.25 Kamboja Putih Pohon 350,000.00 350,000.00
2.2.4.4.26 Kana Biasa (tinggi= 0.5 m) Polibag 15,000.00 15,000.00
2.2.4.4.27 Kana Jepang Pot 18,000.00 18,000.00
2.2.4.4.28 Kastuba Pohon 37,000.00 37,000.00
2.2.4.4.29 Kalatea merah, puti Polibag 12,500.00 12,500.00
2.2.4.4.30 Kalatea loreng Polibag 15,000.00 15,000.00
2.2.4.4.31 Kalatea silver Polibag 20,000.00 20,000.00
2.2.4.4.32 Kembang Sepatu (tinggi= 0.5 m) Polibag 40,000.00 40,000.00
2.2.4.4.33 Kembang Sepatu 8 - 20 cm Polibag 35,000.00 35,000.00
2.2.4.4.34 Kembang Sepatu Putih Pohon 35,000.00 35,000.00
2.2.4.4.35 Kenanga Pohon 25,000.00 25,000.00
2.2.4.4.36 Kol Ganda Pohon 35,000.00 35,000.00
2.2.4.4.37 Korombusa Hijau Polibag 10,000.00 10,000.00
2.2.4.4.38 Korombusa Putih Besar Polibag 35,000.00 35,000.00
2.2.4.4.39 Korombusa Putih Kecil Polibag 15,000.00 15,000.00
2.2.4.4.40 Krisan Polibag 35,000.00 35,000.00
2.2.4.4.41 Lamtama Polibag 2,500.00 2,500.00
2.2.4.4.42 Lantana Pagar Pohon 7,000.00 7,000.00
2.2.4.4.43 Lavender Polibag 17,000.00 17,000.00
2.2.4.4.44 Lidah mertua (tinggi= 0.5 m) Polibag 20,000.00 20,000.00
2.2.4.4.45 Lusiana Tinggi Pohon 20,000.00 20,000.00
2.2.4.4.46 Lusiana Tinggi 1 m Pohon 50,000.00 50,000.00
2.2.4.4.47 Lusiana Tinggi 2 m Pohon 150,000.00 150,000.00
2.2.4.4.48 Mawar / Dendros Pohon 7,000.00 7,000.00
2.2.4.4.49 Mawar / Rose Hybrida Pohon 10,000.00 10,000.00
2.2.4.4.50 Mawar Jambe (tinggi= 0.5 m) Polibag 500,000.00 500,000.00
2.2.4.4.51 Melati Cina (tinggi= 0.5 m) Polibag 11,000.00 11,000.00
2.2.4.4.52 Nusa Indah (tinggi= 0.5 m) Polibag 20,000.00 20,000.00
2.2.4.4.53 Nusa Indah Putih Pohon 20,000.00 20,000.00
2.2.4.4.54 Palem Udang Pohon 60,000.00 60,000.00
2.2.4.4.55 Panca warna Polibag 20,000.00 20,000.00
2.2.4.4.56 Pandan Belgi (tinggi= 0.5 m) Polibag 17,000.00 17,000.00
2.2.4.4.57 Pandan Suci (tinggi= 0.5 m) Polibag 7,000.00 7,000.00
2.2.4.4.58 Pohon Pangkas (tinggi = 0,5 m) Pohon 20,000.00 20,000.00
2.2.4.4.59 Pohon Pangkas (tinggi = 1 m) Pohon 50,000.00 50,000.00
2.2.4.4.60 Pucuk Merah (tinggi= 0,5 m) Polibag 25,000.00 25,000.00
2.2.4.4.61 Pucuk Merah (tinggi= 1 m) Polibag 75,000.00 75,000.00
2.2.4.4.62 Pucuk Merah (tinggi= 2 m) Polibag 250,000.00 250,000.00
2.2.4.4.63 Puring Banci Pohon 15,000.00 15,000.00
2.2.4.4.64 Puring Bangkok (tinggi= 0.5 m) Polibag 100,000.00 100,000.00
2.2.4.4.65 Puring Bor (tinggi=0,5m) Polibag 15,000.00 15,000.00
2.2.4.4.66 Puring Buntut Ayam Pohon 15,000.00 15,000.00
2.2.4.4.67 Puring Gelatik Pohon 15,000.00 15,000.00
2.2.4.4.68 Puring Jet (tinggi= 0.5 m) Polibag 15,000.00 15,000.00
2.2.4.4.69 Puring Ketapang Pohon 20,000.00 20,000.00
2.2.4.4.70 Puring Lancur Polibag 15,000.00 15,000.00
2.2.4.4.71 Puring Nuri Pohon 15,000.00 15,000.00
2.2.4.4.72 Rosalia (tinggi= 0.5 m) Polibag 15,000.00 15,000.00
2.2.4.4.73 Rosindah Pohon 15,000.00 15,000.00
2.2.4.4.74 Sablo Pohon 15,000.00 15,000.00
2.2.4.4.75 Sakura tinggi 60cm Pohon 15,000.00 15,000.00
2.2.4.4.76 Sakura tinggi 75cm Pohon 25,000.00 25,000.00
2.2.4.4.77 Sakura tinggi 100cm Pohon 35,000.00 35,000.00
2.2.4.4.78 Sambang Darah Besar Polibag 80,000.00 80,000.00

10
2018
No Nama Barang Satuan
2.2.4.4.79 Sambang Darah Sedang Polibag 50,000.00 50,000.00
2.2.4.4.80 Schefflera Arboricol Pohon 50,000.00 50,000.00
2.2.4.4.81 Siklok (tinggi=0,5m) Polibag 15,000.00 15,000.00
2.2.4.4.82 Soka Bangkok Pohon 10,000.00 10,000.00
2.2.4.4.83 Soka Jepang Pohon 15,000.00 15,000.00
2.2.4.4.84 Soka Philipina Pohon 15,000.00 15,000.00
2.2.4.4.85 Soka Singapura Pohon 15,000.00 15,000.00
2.2.4.4.86 Soka Srantan Pohon 15,000.00 15,000.00
2.2.4.4.87 Spider Leli (tinggi= 0.5 m) Polibag 6,000.00 6,000.00
2.2.4.4.88 Terang Bulan Pohon 7,000.00 7,000.00
2.2.4.4.89 Tombak Raja Pohon 25,000.00 25,000.00
2.2.4.4.90 Tri colour (tinggi=05m) Polibag 15,000.00 15,000.00
2.2.4.4.91 Brokoli (tinggi = 0,5m) Polibag 10,000.00 10,000.00
2.2.4.4.92 Prambosa hijau (tinggi 0,5m) Polibag 20,000.00 20,000.00
2.2.4.4.93 Prambosa Silver (tinggi 0,5m) Polibag 20,000.00 20,000.00
2.2.4.4.94 Prambosa Kuning (tinggi 0,5m) Polibag 20,000.00 20,000.00
2.2.4.4.95 Cemara Kipas K (tinggi 0,5m) Polibag 25,000.00 25,000.00
2.2.4.4.96 Cemara Kipas B (tinggi 0,5m) Polibag 35,000.00 35,000.00
2.2.4.4.97 Song of India K (tinggi 0,5m) Polibag 8,000.00 8,000.00
2.2.4.4.98 Song of India B (tinggi 0,5m) Polibag 75,000.00 75,000.00
2.2.4.4.99 Bulu ayam 20cm Polibag 4,000.00 4,000.00
2.2.4.4.100 Puring bali Polibag 15,000.00 15,000.00
2.2.4.4.101 Puring kirana besar Polibag 60,000.00 60,000.00
2.2.4.4.102 Soka India Pohon 25,000.00 25,000.00
2.2.4.4.103 Soka merah muda Pohon 25,000.00 25,000.00
2.2.4.4.104 Bunga telek - telekan Polibag 10,000.00 10,000.00
2.2.4.4.105 Bunga tapak dara Polibag 10,000.00 10,000.00
2.2.4.4.106 Sikas tinggi 10 cm Glangsing 200,000.00 200,000.00
2.2.4.4.107 Sikas tinggi 40 cm Glangsing 600,000.00 600,000.00
2.2.4.4.108 Sikas tinggi 70 cm Glangsing 750,000.00 750,000.00
2.2.4.4.109 Seribu bintang Polibag 10,000.00 10,000.00
2.2.4.4.110 Samsiver variadata Pot 100,000.00 100,000.00
2.2.4.4.111 Rombusa hijau Polibag 60,000.00 60,000.00
2.2.4.4.112 Rombusa putih besar Polibag 75,000.00 75,000.00
2.2.4.4.113 Rombusa putih kecil Polibag 50,000.00 50,000.00
2.2.4.4.114 Rosalia (tinggi= 0.5 m) Polibag 15,000.00 15,000.00

2.2.4.5 TANAMAN MERAMBAT


2.2.4.5.1 Air Mata Pengantin Pot 20,000.00 20,000.00
2.2.4.5.2 Alamanda Pot 15,000.00 15,000.00
2.2.4.5.3 Mandivila Pot 25,000.00 25,000.00
2.2.4.5.4 Sirih Gading Pot 250,000.00 250,000.00
2.2.4.5.5 Stepanut Pot 25,000.00 25,000.00
2.2.4.5.6 Stepanut Ungu Pot 30,000.00 30,000.00

2.2.4.6 TANAMAN EKSOTIS ( A )


2.2.4.6.1 Agave (tinggi= 0.5 m) Polibag 35,000.00 35,000.00
2.2.4.6.2 Agave Putih Pohon 25,000.00 25,000.00
2.2.4.6.3 Bakung Pohon 30,000.00 30,000.00
2.2.4.6.4 Cemara Norfolk Pohon 50,000.00 50,000.00
2.2.4.6.5 Tiris (tinggi= 0.5 m) Polibag 4,000.00 4,000.00

2.2.4.7 TANAMAN EKSOTIS ( B )


2.2.4.7.1 Beringin Bonsai Pohon 100,000.00 100,000.00

11
2018
No Nama Barang Satuan
2.2.4.7.2 Beringin Bonsai Bentukan Pohon 270,000.00 270,000.00
2.2.4.7.3 Bonsai Serut Pohon 2,500,000.00 2,500,000.00
2.2.4.7.4 Bonsai Sianton Pohon 2,000,000.00 2,000,000.00
2.2.4.7.5 Cemara Norfolk Pohon 50,000.00 50,000.00
2.2.4.7.6 Cemara Pipa Mas Pohon 2,000,000.00 2,000,000.00
2.2.4.7.7 Hebbra Pohon 3,000,000.00 3,000,000.00
2.2.4.7.8 Jambu Bangkok Pohon 500,000.00 500,000.00
2.2.4.7.9 Jeruk Lingkit Pohon 400,000.00 400,000.00
2.2.4.7.10 Jeruk Sunkist Pohon 150,000.00 150,000.00
2.2.4.7.11 Pakis Monyet Pohon 360,000.00 360,000.00
2.2.4.7.12 Palem Putri Pot 80,000.00 80,000.00
2.2.4.7.13 Palem Ratu Pohon 250,000.00 250,000.00
2.2.4.7.14 Palem Regu Pot 70,000.00 70,000.00
2.2.4.7.15 Pinang Merah Pohon 1,500,000.00 1,500,000.00
2.2.4.7.16 Pisang Kipas 30 cm Pohon 1,500,000.00 1,500,000.00
2.2.4.7.17 Pisang Kipas 50 cm Pohon 3,100,000.00 4,000,000.00
2.2.4.7.18 Pule lingkar pohon 1 m Pohon 7,500,000.00 7,500,000.00
2.2.4.7.19 Pule lingkar pohon 2 m Pohon 15,000,000.00 15,000,000.00
2.2.4.7.20 Pule lingkar pohon 3 m Pohon 25,000,000.00 25,000,000.00
2.2.4.7.21 Pule lingkar pohon 4 m Pohon 35,000,000.00 35,000,000.00
2.2.4.7.22 Pule lingkar pohon 30 cm Pohon 750,000.00 825,000.00
2.2.4.7.23 Pule lingkar pohon 50 cm Pohon 3,100,000.00 3,410,000.00

2.2.4.8 TANAMAN BORDER


2.2.4.8.1 Anjuang Kribo, Srikit, Pakis, Gonongkes I Teduh M2 120,000.00 120,000.00
2.2.4.8.2 Balanceng Marandra, Dinding Klas II Teduh M2 85,000.00 85,000.00
2.2.4.8.3 Nusa Indah, Kelabang, Krokot Klas II Panas M2 90,000.00 90,000.00
2.2.4.8.4 Puring-puring Gelatik, Pakis Rol Klas I Panas M2 100,000.00 100,000.00

2.2.4.9 TANAMAN POHON PELINDUNG


2.2.4.9.1 Akasia Pohon 75,000.00 75,000.00
2.2.4.9.2 Angsana Ø20 cm tinggi= 3 m Pohon 75,000.00 75,000.00
2.2.4.9.3 Beringin 1,5 - 2 m Pohon 150,000.00 150,000.00
2.2.4.9.4 Beringin 10 - 30 cm Pohon 50,000.00 50,000.00
2.2.4.9.5 Bintaro Ø20 tinggi = 3 m Pohon 150,000.00 150,000.00
2.2.4.9.6 Bunga Sapu Tangan Pohon 150,000.00 150,000.00
2.2.4.9.7 Bungur Pohon 150,000.00 150,000.00
2.2.4.9.8 Dadap Kuning 8 - 20 cm Pohon 750,000.00 750,000.00
2.2.4.9.9 Dadap Merah 1,5 - 2 m Pohon 75,000.00 75,000.00
2.2.4.9.10 Dadap Merah 8 - 20 cm Pohon 75,000.00 75,000.00
2.2.4.9.11 Dipsul Pohon 75,000.00 75,000.00
2.2.4.9.12 Glodongan Pohon 75,000.00 75,000.00
2.2.4.9.13 Glodongan 3 M Pohon 150,000.00 150,000.00
2.2.4.9.14 Glodongan 4 M Pohon 250,000.00 250,000.00
2.2.4.9.15 Glodongan Tiang Tinggi Pohon 400,000.00 400,000.00
2.2.4.9.16 Jetrofa Ø20 cm tinggi= 2.5 m Pohon 250,000.00 250,000.00
2.2.4.9.17 Johar Pohon 80,000.00 80,000.00
2.2.4.9.18 Kayu Manis Pohon 50,000.00 50,000.00
2.2.4.9.19 Kayu Manis 10 - 25 cm Pohon 30,000.00 30,000.00
2.2.4.9.20 Kayu Putih Pohon 50,000.00 50,000.00
2.2.4.9.21 Kembang kupu - kupu 1,5 2 m Pohon 60,000.00 60,000.00
2.2.4.9.22 Kembang kupu - kupu 10 - 20 cm Pohon 35,000.00 35,000.00
2.2.4.9.23 Kiara Payung Pohon 50,000.00 50,000.00
2.2.4.9.24 Kobanda 10 - 20 cm Pohon 30,000.00 30,000.00

12
2018
No Nama Barang Satuan
2.2.4.9.25 Kupu-kupu Ø15 cm tinggi= 2.5 m Pohon 75,000.00 75,000.00
2.2.4.9.26 Mahoni Pohon 40,000.00 40,000.00
2.2.4.9.27 Matua Ø30 cm tinggi=3 m Pohon 150,000.00 150,000.00
2.2.4.9.28 Sepatu Dia 1,5 - 2 m Pohon 80,000.00 80,000.00
2.2.4.9.29 Sono Keling Pohon 100,000.00 100,000.00
2.2.4.9.30 Spathodeta Pohon 85,000.00 85,000.00
2.2.4.9.31 Tabir Buya 1,5 - 2,5 m Pohon 20,000.00 20,000.00
2.2.4.9.32 Tabir Buya Merah ø 15 Pohon 150,000.00 150,000.00
2.2.4.9.33 Tabir Buya Merah ø 20 Pohon 250,000.00 250,000.00
2.2.4.9.34 Tabir Buya Merah ø 30 Pohon 400,000.00 400,000.00
2.2.4.9.35 Tanjung Pohon 80,000.00 80,000.00
2.2.4.9.36 Trembesi Ø10 cm tinggi= < 3 m Pohon 180,000.00 180,000.00
2.2.4.9.37 Yanglu Pohon 350,000.00 350,000.00
2.2.4.9.38 Flamboyan Pohon 90,000.00 90,000.00

2.2.4.10 TANAMAN JENIS PALEM


2.2.4.10.1 Kelapa Sawit Pohon 1,500,000.00 1,500,000.00
2.2.4.10.2 Palem Anggur Pohon 3,000,000.00 3,000,000.00
2.2.4.10.3 Palem Bismar Æ 100cm (tinggi=2m) Pohon 2,500,000.00 2,500,000.00
2.2.4.10.4 Palem Botol Pohon 250,000.00 250,000.00
2.2.4.10.5 Palem Jepang Pohon 150,000.00 150,000.00
2.2.4.10.6 Palem Kol Pohon 60,000.00 60,000.00
2.2.4.10.7 Palem Kuning Pohon 60,000.00 60,000.00
2.2.4.10.8 Palem Kuning Pohon 60,000.00 60,000.00
2.2.4.10.9 Palem Phoenix Pohon 250,000.00 250,000.00
2.2.4.10.10 Palem Raja Pohon 250,000.00 250,000.00
2.2.4.10.11 Palem Sading Pohon 350,000.00 350,000.00
2.2.4.10.12 Palem Weregu Pohon 100,000.00 100,000.00
2.2.4.10.13 Wali Songo 0,5 - 1 m Pohon 80,000.00 80,000.00
2.2.4.10.14 Rumpun pinang merah kecil Pohon 500,000.00 500,000.00
2.2.4.10.15 Rumpun pinang merah sedang Pohon 2,000,000.00 2,000,000.00
2.2.4.10.16 Rumpun pinang merah besar Pohon 3,500,000.00 3,500,000.00
2.2.4.10.17 Palem doria Pohon 100,000.00 100,000.00
2.2.4.10.18 Palem ekor tupai Pohon 200,000.00 200,000.00

2.2.4.11 TANAMAN BAMBU CEMARA


2.2.4.11.1 Bambu Jepang Pohon 60,000.00 60,000.00
2.2.4.11.2 Bambu Kuning Pohon 30,000.00 30,000.00
2.2.4.11.3 Cemara Angin Pohon 75,000.00 75,000.00
2.2.4.11.4 Cemara Gembel Pohon 90,000.00 90,000.00
2.2.4.11.5 Cemara Halus Pohon 150,000.00 150,000.00
2.2.4.11.6 Cemara Natal Pohon 500,000.00 500,000.00
2.2.4.11.7 Pinus Pohon 500,000.00 500,000.00

2.2.4.12 BUNGA POTONGAN


2.2.4.12.1 Anggrek Macan Tangkai 75,000.00 75,000.00
2.2.4.12.2 Anyelir Tangkai 50,000.00 50,000.00
2.2.4.12.3 Apel Blossom Tangkai 30,000.00 30,000.00
2.2.4.12.4 Aster Tangkai 30,000.00 30,000.00
2.2.4.12.5 Bunga Rangkaian Buket 200,000.00 200,000.00
2.2.4.12.6 Denrobium Tangkai 30,000.00 30,000.00
2.2.4.12.7 Douglas Tangkai 30,000.00 30,000.00
2.2.4.12.8 Fortulaka Tangkai 25,000.00 25,000.00
2.2.4.12.9 Gladiol Tangkai 25,000.00 25,000.00

13
2018
No Nama Barang Satuan
2.2.4.12.10 Golden Shower Tangkai 50,000.00 50,000.00
2.2.4.12.11 Krisan Tangkai 35,000.00 35,000.00
2.2.4.12.12 Mawar Tangkai 60,000.00 60,000.00

2.2.4.13 ALAT PEMBERSIH PERTAMANAN


2.2.4.13.1 Cangkul Bh 90,000.00 90,000.00
2.2.4.13.2 Cetok Bh 35,000.00 35,000.00
2.2.4.13.3 Cikrak Bh 25,000.00 25,000.00
2.2.4.13.4 Cikrak seng Bh 35,000.00 35,000.00
2.2.4.13.5 Cikrak Seret Bh 200,000.00 200,000.00
2.2.4.13.6 Cintung riol Bh 50,000.00 50,000.00
2.2.4.13.7 Gagang cangkul Bh 40,000.00 40,000.00
2.2.4.13.8 Gagang sapu Bh 25,000.00 25,000.00
2.2.4.13.9 Ganco Bh 80,000.00 80,000.00
2.2.4.13.10 Garuk Bh 85,000.00 85,000.00
2.2.4.13.11 Kain pel Lbr 15,000.00 15,000.00
2.2.4.13.12 Karung plastik Bh 15,000.00 15,000.00
2.2.4.13.13 Keranjang Bh 30,000.00 30,000.00
2.2.4.13.14 Keranjang bambu Bh 35,000.00 35,000.00
2.2.4.13.15 Keranjang sampah Bh 50,000.00 50,000.00
2.2.4.13.16 Linggis Bh 160,000.00 160,000.00
2.2.4.13.17 Pacul Bh 70,000.00 70,000.00
2.2.4.13.18 Parang Bh 50,000.00 50,000.00
2.2.4.13.19 Rajut Sampah Bh 500,000.00 500,000.00
2.2.4.13.20 Sabit besar Bh 70,000.00 70,000.00
2.2.4.13.21 Sabit kecil Bh 60,000.00 60,000.00
2.2.4.13.22 Sapu lidi ikat 7,000.00 7,000.00
2.2.4.13.23 Skrop Bh 75,000.00 75,000.00
2.2.4.13.24 Tali ikat sapu Bh 5,000.00 5,000.00
2.2.4.13.25 Timbo Bh 25,000.00 25,000.00
2.2.4.13.26 Timbo cor Bh 12,000.00 12,000.00
2.2.4.13.27 Wangkil Bh 45,000.00 45,000.00
2.2.4.13.28 Mesin Potong Rumput Dorong Unit 3,500,000.00 3,500,000.00
2.2.4.13.29 Mesin Potong Rumput Gendong Unit 2,000,000.00 2,000,000.00
2.2.4.13.30 Mesin Potong Pohon / Senso Unit 16,000,000.00 16,000,000.00
2.2.4.13.31 Mesin Potong Pohon / Senso kecil Unit 3,500,000.00 3,500,000.00
2.2.4.13.32 Mata pisau potong rumput gendong Bh 45,000.00 45,000.00
2.2.4.13.33 Rantai senso kecil Bh 170,000.00 170,000.00
2.2.4.13.34 Kikir besar Bh 15,000.00 15,000.00
2.2.4.13.35 Kikir besar Bh 15,000.00 15,000.00
2.2.4.13.36 Gerobak dorong satu roda Unit 400,000.00 400,000.00
2.2.4.13.37 Senso telescopic unit 17,500,000.00 17,500,000.00
2.2.4.13.38 Breaker unit 22,000,000.00 22,000,000.00
2.2.4.13.39 Mata bor Breaker Bh 350,000.00 350,000.00

2.2.4.14 PAKAIAN KERJA LAPANGAN ( Pertamanan )


2.2.4.14.1 Helm Bh 150,000.00 150,000.00
2.2.4.14.2 Jas hujan Bh 70,000.00 70,000.00
2.2.4.14.3 Kaos Bh 65,000.00 65,000.00
2.2.4.14.4 Masker Bh 20,000.00 20,000.00
2.2.4.14.5 Pakaian kerja lapangan Stel 140,000.00 140,000.00
2.2.4.14.6 Sarung tangan Psg 20,000.00 20,000.00
2.2.4.14.7 Sepatu karet Psg 80,000.00 80,000.00
2.2.4.14.8 Sepatu lapang Psg 75,000.00 75,000.00

14
2018
No Nama Barang Satuan
2.2.4.14.9 Topi Bh 35,000.00 35,000.00

2.2.4.15 POT BUNGA


2.2.4.15.1 Pot bunga Ø 30 cm Set 50,000.00 50,000.00
2.2.4.15.2 Pot bunga Ø 40 cm Set 95,000.00 95,000.00
2.2.4.15.3 Pot bunga Ø 50 cm Set 125,000.00 125,000.00
2.2.4.15.4 Pot bunga Ø 60 cm Set 170,000.00 170,000.00
2.2.4.15.5 Polibag 20 x 20 kg 28,000.00 28,000.00
2.2.4.15.6 Polibag 30 x 30 kg 28,000.00 28,000.00
2.2.4.15.7 Polibag 40 x 40 kg 28,000.00 28,000.00
2.2.4.15.8 Polibag 50 x 50 kg 30,000.00 30,000.00
2.2.4.15.9 Polibag 50 x 60 kg 30,000.00 30,000.00

2.2.4.16 PUPUK TANAMAN


2.2.4.16.1 Pupuk NPK sak 120,000.00 120,000.00
2.2.4.16.2 Pupuk urea sak 80,000.00 80,000.00
2.2.4.16.3 Pupuk ZA sak 90,000.00 90,000.00
2.2.4.16.4 Pupuk SP 36 kg 100,000.00 100,000.00
2.2.4.16.5 Pupuk organik sak 25,000.00 25,000.00
2.2.4.16.6 Pupuk phonska kg 7,500.00 7,500.00
2.2.4.16.7 Pupuk kompos bungkus 17,000.00 17,000.00

2.2.4.17 OBAT HAMA TANAMAN


2.2.4.17.1 Puradan kg 15,000.00 15,000.00
2.2.4.17.2 Matador 250ml 51,000.00 51,000.00
2.2.4.17.3 Marshal kg 85,000.00 85,000.00
2.2.4.17.4 Racumin kg 9,000.00 9,000.00
2.2.4.17.5 Reagen kg 35,000.00 35,000.00

2.2.4.18 ALAT-ALAT PERSAMPAHAN


2.2.4.18.1 Alat pencacah Sampah organik Unit 25,410,000.00 25,410,000.00
2.2.4.18.2 Alat pengayak kompos Unit 17,325,000.00 17,325,000.00
2.2.4.18.3 Bin Container 3R Unit 2,541,000.00 2,541,000.00
2.2.4.18.4 Gerobak sampah 3R Unit 4,500,000.00 4,500,000.00
2.2.4.18.5 Gerobak Sampah PKL Unit 4,500,000.00 4,500,000.00
2.2.4.18.6 Kotak fermentasi Bh 462,000.00 462,000.00

2.2.4.19 PERLENGKAPAN KOLAM


2.2.4.19.1 Servis + Gulung Pompa Set 400,000.00 400,000.00
2.2.4.19.2 Laker Set 35,000.00 35,000.00
2.2.4.19.3 Kapasitor Set 40,000.00 40,000.00
2.2.4.19.4 Selang - -
2.2.4.19.4a - Spiral luar m 35,000.00 35,000.00
2.2.4.19.4b - Spiral dalam m 65,000.00 65,000.00
2.2.4.19.4c - Selang 3/4 dim rol 550,000.00 550,000.00
2.2.4.19.4d - Selang 5/8 dim rol 300,000.00 300,000.00
2.2.4.19.4e - Selang 1 1/2 dim rol 800,000.00 800,000.00
2.2.4.19.5 Pompa Speroni unit 3,200,000.00 3,200,000.00
2.2.4.19.6 Diesel Honda 2 dim unit 3,300,000.00 3,300,000.00
2.2.4.19.7 Diesel Honda 3 dim unit 3,700,000.00 3,700,000.00

15
PENENTUAN HSPK PADA DINAS PU- BINA MARGA DAN CIPTA KARYA
TAHUN ANGGARAN 2018 KABUPATEN TULUNGAGUNG
(BULAN PEBRUARI 2018)

Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5

1.2.7 UPAH KERJA


1.2.7.1 Buruh semi terlatih 1 Oh 74,250.00 74,250.00
1.2.7.2 Buruh terlatih 1 Oh 77,000.00 77,000.00
1.2.7.3 Kepala Tukang 1 Oh 93,500.00 93,500.00
1.2.7.4 Kernet 1 Oh 71,500.00 71,500.00
1.2.7.5 Mandor 1 Oh 94,500.00 94,500.00
1.2.7.6 Mekanik terlatih 1 Oh 89,500.00 89,500.00
1.2.7.7 Mekanik semi terlatih 1 Oh 84,000.00 84,000.00
1.2.7.8 Operator semi terlatih 1 Oh 89,500.00 89,500.00
1.2.7.9 Operator terlatih 1 Oh 94,500.00 94,500.00
1.2.7.10 Pekerja / Buruh tak terlatih 1 Oh 68,500.00 68,500.00
1.2.7.11 Pembantu Sopir 1 Oh 68,500.00 68,500.00
1.2.7.12 Pembantu operator 1 Oh 68,500.00 68,500.00
1.2.7.13 Penganyam 1 Oh 68,500.00 68,500.00
1.2.7.14 Penjaga 1 Oh 68,500.00 68,500.00
1.2.7.15 Sopir 1 Oh 81,500.00 81,500.00
1.2.7.16 Tukang batu 1 Oh 79,000.00 79,000.00
1.2.7.17 Tukang besi 1 Oh 84,000.00 84,000.00
1.2.7.18 Tukang cat 1 Oh 79,000.00 79,000.00
1.2.7.19 Tukang kayu 1 Oh 89,500.00 89,500.00
1.2.7.20 Tukang pipa 1 Oh 79,000.00 79,000.00
1.2.7.21 Tukang las 1 Oh 89,500.00 89,500.00
1.2.7.22 Juru Ukur Bangunan 1 Oh 100,000.00 100,000.00
1.2.7.23 Tenaga Fasilitator Lapangan 1 Ob 1,000,000.00 1,000,000.00
1.2.7.24 Penyapu Jalan 1 Ob 1,000,000.00 1,000,000.00
1.2.7.25 Perawat Taman 1 Ob 1,000,000.00 1,000,000.00
1.2.7.26 Teknisi PJU 1 Ob 1,000,000.00 1,000,000.00
- -
2.2 BAHAN BANGUNAN - -
2.2.1 BAHAN ALAM: PASIR, BATU, KERIKIL, BATA, ASPAL, SEMEN - -
2.2.1.1 Aspal Curah Kg 7,000.00 7,000.00
2.2.1.2 Aspal Kemas Kg 8,000.00 8,000.00
2.2.1.3 Batu marmo warna M2 117,800.00 129,580.00
2.2.1.4 Batu amyang Kg 4,300.00 4,730.00
2.2.1.5 Batu andesit M2 163,700.00 180,070.00
2.2.1.6 Batu andesit bakar M2 190,600.00 209,660.00
2.2.1.7 Batu Andesit alur M2 268,600.00 295,460.00
2.2.1.8 Batu Andesit Alur hitam M2 274,600.00 302,060.00

1
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.1.9 Batu andesit hitam bakar M2 264,100.00 290,510.00
2.2.1.10 Batu andesit hitam M2 213,000.00 234,300.00
2.2.1.11 Batu Andisit Hijau M2 196,400.00 216,040.00
2.2.1.12 Batu apung 3 - 5 cm M3 294,800.00 324,280.00
2.2.1.13 Batu Bali Green M2 129,600.00 142,560.00
2.2.1.14 Batu Bata / Merah Bj 900.00 990.00
2.2.1.15 Batu Bobos M2 146,100.00 160,710.00
2.2.1.16 Batu candi M2 141,400.00 155,540.00
2.2.1.17 Batu candi hitam M2 141,400.00 155,540.00
2.2.1.18 Batu granit black gold M2 2,310,000.00 2,541,000.00
2.2.1.19 Batu granit motif M2 220,100.00 242,110.00
2.2.1.20 Batu guary/batu besar ( uk. Crussher) M3 275,000.00 302,500.00
2.2.1.21 Batu koral putih M2 183,400.00 201,740.00
2.2.1.22 Batu koral sikat 179,100.00 197,010.00
2.2.1.23 Batu koral warna M2 190,900.00 209,990.00
2.2.1.24 Batu lempeng M2 111,000.00 122,100.00
2.2.1.25 Batu lempeng hijau M2 109,800.00 120,780.00
2.2.1.26 Batu lempeng coklat M2 75,100.00 82,610.00
2.2.1.27 Batu marmo biasa M2 93,400.00 102,740.00
2.2.1.28 Batu paras putih M2 127,100.00 139,810.00
2.2.1.29 Batu paras grobongan M2 110,100.00 121,110.00
2.2.1.30 Batu pecah 0,5-1 cm M3 340,000.00 350,000.00
2.2.1.31 Batu pecah 1-2 cm M3 340,000.00 350,000.00
2.2.1.32 Batu pecah 2-3 cm M3 300,000.00 320,000.00
2.2.1.33 Batu pecah 3-5 cm M3 285,000.00 300,000.00
2.2.1.34 Batu pecah 5-7 cm M3 250,000.00 265,000.00
2.2.1.35 Batu pecah 8-10 cm M3 275,000.00 302,500.00
2.2.1.36 Batu pecah 10-15 cm (15-20) M3 275,000.00 302,500.00
2.2.1.37 Batu plontos 5/7 cm M3 192,500.00 211,750.00
2.2.1.38 Batu putih / gunung M3 192,500.00 211,750.00
2.2.1.39 Batu putih pecah , 5 - 7 cm M3 185,000.00 205,000.00
2.2.1.40 Batu susun sirih M2 451,000.00 496,100.00
2.2.1.41 Batu Volcano 10-15 cm M3 467,500.00 514,250.00
2.2.1.42 Batu warna ( hias ) Zak 93,100.00 102,410.00
2.2.1.43 Grasak M3 147,300.00 162,030.00
2.2.1.44 Ijuk Kg 7,700.00 8,470.00
2.2.1.45 Kapur Batu ( sirih ) Kg 1,800.00 1,980.00
2.2.1.46 Kapur Batu m3 1,270,500.00 1,397,550.00
2.2.1.47 Kerikil halus 0.4 / 0.4 (hitam ) Kg 5,200.00 5,720.00
2.2.1.48 Kerikil halus 0.4 / 0.4 (putih ) Kg 3,300.00 3,630.00
2.2.1.49 Kerikil halus 0.4 x 0.4 ( hijau) Kg 1,800.00 1,980.00
2.2.1.50 Pasir pasang / beton M3 264,000.00 290,400.00
2.2.1.51 Pasir Urug M3 173,300.00 190,630.00

2
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.1.52 PC / Portland cement Kg 1,400.00 1,540.00
2.2.1.53 Semen Merah M3 150,200.00 165,220.00
2.2.1.54 Semen Putih / warna Kg 3,000.00 3,300.00
2.2.1.55 Sirtu royalti M3 187,000.00 205,700.00
2.2.1.56 Sirtu Urug M3 187,000.00 205,700.00
2.2.1.57 Susun Sirih, andisit hitam uk. 3 x 20 cm M2 181,500.00 199,650.00
2.2.1.58 Susun Sirih, andisit hitam uk. 3 x 30 cm M2 181,500.00 199,650.00
2.2.1.59 Susun Sirih, andisit hitam uk. 3 x 40 cm M2 181,500.00 199,650.00
2.2.1.60 Tali ijuk Kg 11,000.00 12,100.00
2.2.1.61 Tanah liat M3 49,500.00 54,450.00
2.2.1.62 Tanah urug M3 82,500.00 90,750.00
2.2.1.63 Urugan Taman M3 104,500.00 114,950.00
2.2.1.64 Tanah subur ( humus ) rit 231,000.00 254,100.00
2.2.1.65 Pasir putih halus rit 1,045,000.00 1,149,500.00
2.2.1.66 Solar ltr 6,200.00 6,820.00
- -
2.2.2 BAHAN KAYU DAN BAMBU : - -
2.2.2.1 Arang kayu Kg 4,100.00 4,510.00
2.2.2.2 Bambu (Dia 6 - 8 cm x 600cm) Btg 12,100.00 13,310.00
2.2.2.3 Bambu Ori (Dia 10-12 x 600 cm) Btg 28,900.00 31,790.00
2.2.2.4 Bambu Petung (p = 6 m) Ljr 31,200.00 34,320.00
2.2.2.5 Batang kelapa dia 30 cm M' 86,700.00 95,370.00
2.2.2.6 Betek / sesek kasar Uk. 2m x 3m Lbr 69,300.00 76,230.00
2.2.2.7 Bilik bambu Uk. 2m x 3m Lbr 30,000.00 33,000.00
2.2.2.8 Dolken bambu panjang 3 m Btg 46,200.00 50,820.00
2.2.2.9 Dolken Kayu jati lokal dia 10cm -15 cm, pjg = 3 m Btg 173,300.00 190,630.00
2.2.2.10 HPL 253,000.00 278,300.00
2.2.2.11 Kayu kaso ( 5/7 ) cm pjg 3 m,kayu bekisting Btg 20,800.00 22,880.00
2.2.2.12 Kayu bakar M3 187,000.00 205,700.00
2.2.2.13 Kayu Balau Balok M3 10,725,000.00 11,797,500.00
2.2.2.14 Kayu Balau Papan M3 11,825,000.00 13,007,500.00
2.2.2.15 Kayu bekisting M3 3,465,000.00 3,811,500.00
2.2.2.16 Kayu Jati Balok eks. Bojonegoro M3 30,800,000.00 33,880,000.00
2.2.2.17 Kayu Jati Balok lokal M3 20,900,000.00 22,990,000.00
2.2.2.18 Kayu Jati Papan eks. Bojonegoro M3 36,850,000.00 40,535,000.00
2.2.2.19 Kayu jati papan lokal M3 22,550,000.00 24,805,000.00
2.2.2.20 Kayu Kamper Balok M3 10,450,000.00 11,495,000.00
2.2.2.21 Kayu Kamper papan M3 11,550,000.00 12,705,000.00
2.2.2.22 Kayu kelapa / glugu 8/10 cm M' 77,000.00 84,700.00
2.2.2.23 Kayu kelapa / glugu Ø 20 cm M' 79,800.00 87,780.00
2.2.2.24 Kayu kelapa / glugu Ø 30 cm M' 85,300.00 93,830.00
2.2.2.25 Kayu kelapa / glugu Ø 40 cm M' 93,500.00 102,850.00
2.2.2.26 Kayu kelapa / glugu Ø 50 cm M' 99,000.00 108,900.00

3
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.2.27 Kayu kelapa / glugu usuk 4/6 cm M' 13,800.00 15,180.00
2.2.2.28 Kayu Kempas Balok M3 7,425,000.00 8,167,500.00
2.2.2.29 Kayu Kempas Papan M3 8,525,000.00 9,377,500.00
2.2.2.30 Kayu Kruing Balok M3 6,875,000.00 7,562,500.00
2.2.2.31 Kayu Kruing Papan M3 7,975,000.00 8,772,500.00
2.2.2.32 Kayu Meranti Balok M3 5,500,000.00 6,050,000.00
2.2.2.33 Kayu Meranti Papan M3 6,050,000.00 6,655,000.00
2.2.2.34 Kayu Tahun Balok ( Mauni/ Akasia ) M3 4,950,000.00 5,445,000.00
2.2.2.35 Kayu Tahun papan ( Mauni/akasia) M3 5,225,000.00 5,747,500.00
2.2.2.36 Kornis kayu jati lebar 10 cm + Finishing m' 110,000.00 121,000.00
- -
2.2.3 BAHAN PLAFOND, KERANGKA ATAP & PENUTUP ATAP: - -
2.2.3.1 Asbes Datar / Eternit 100 x 100 tbl = 3 mm Lbr 22,000.00 24,200.00
2.2.3.2 Asbes Datar / Eternit 40 x 200 tbl = 6 mm Lbr 65,000.00 71,500.00
2.2.3.3 Asbes Datar / Eternit 60 x 180 tbl = 4 mm Lbr 94,300.00 103,730.00
2.2.3.4 Asbes Datar / Eternit 60 x 180 tbl = 5 mm Lbr 155,500.00 171,050.00
2.2.3.5 Asbes Datar / Eternit 60 x 180 tbl = 6 mm Lbr 189,000.00 207,900.00
2.2.3.6 Asbes Datar / Eternit 60 x 200 tbl = 4 mm Lbr 21,700.00 23,870.00
2.2.3.7 Asbes Datar / Eternit 60 x 200 tbl = 5 mm Lbr 64,900.00 71,390.00
2.2.3.8 Asbes Gelombang besar 110 x 200 tbl = 5 mm Lbr 99,300.00 109,230.00
2.2.3.9 Asbes Gelombang besar 110 x 225 tbl = 5 mm Lbr 105,200.00 115,720.00
2.2.3.10 Asbes Gelombang besar 110 x 250 tbl = 5 mm Lbr 115,500.00 127,050.00
2.2.3.11 Asbes Gelombang besar 110 x 300 tbl = 5 mm Lbr 109,500.00 120,450.00
2.2.3.12 Asbes Gelombang besar 150 x 305 tbl = 5 mm Lbr 79,300.00 87,230.00
2.2.3.13 Asbes Gelombang besar 92 x 250 tbl = 5 mm Lbr 115,500.00 127,050.00
2.2.3.14 Asbes Gelombang besar Uk. 300x105x0,5 Cm Lbr 121,300.00 133,430.00
2.2.3.15 Asbes Gelombang Kecil Uk. 150x105x0,4 Cm Lbr 49,100.00 54,010.00
2.2.3.16 Asbes Gelombang Kecil Uk. 180x105x0,4 Cm Lbr 57,200.00 62,920.00
2.2.3.17 Asbes Gelombang Kecil Uk. 300x105x0,4 Cm Lbr 94,700.00 104,170.00
2.2.3.18 Asbes Gelombang kecil 105 x 150 tbl = 4 mm Lbr 50,400.00 55,440.00
2.2.3.19 Asbes Gelombang kecil 105 x 225 tbl = 4 mm Lbr 83,600.00 91,960.00
2.2.3.20 Asbes Gelombang kecil 105 x 240 tbl = 4 mm Lbr 67,800.00 74,580.00
2.2.3.21 Asbes Gelombang kecil 105 x 240 tbl = 5 mm Lbr 72,300.00 79,530.00
2.2.3.22 Asbes Gelombang kecil 105 x 270 tbl = 4 mm Lbr 75,700.00 83,270.00
2.2.3.23 Asbes Gelombang kecil 105 x 270 tbl = 5 mm Lbr 83,600.00 91,960.00
2.2.3.24 Asbes Gelombang kecil 105 x 300 tbl = 4 mm Lbr 62,900.00 69,190.00
2.2.3.25 Asbes Gelombang kecil 105 x 300 tbl = 5 mm Lbr 86,800.00 95,480.00
2.2.3.26 Asbes Gelombang kecil 105 x 300 tbl = 6 mm Lbr 93,000.00 102,300.00
2.2.3.27 Asbes Gelombang kecil 105 x 305 tbl = 4 mm Lbr 88,300.00 97,130.00
2.2.3.28 Asbes Gelombang kecil 92 x 180 tbl = 3 mm Lbr 55,600.00 61,160.00
2.2.3.29 Asbes Gelombang kecil 92 x 180 tbl = 4 mm Lbr 80,500.00 88,550.00
2.2.3.30 Asbes Gelombang kecil 92 x 200 tbl = 4 mm Lbr 67,800.00 74,580.00
2.2.3.31 Asbes Gelombang kecil 92 x 200 tbl = 5 mm Lbr 111,000.00 122,100.00

4
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.3.32 Asbes Gelombang nok kecil 105 x 150 tbl = 5 mm Lbr 51,600.00 56,760.00
2.2.3.33 Asbes Gelombang nok kecil 92 x 180 tbl = 5 mm Lbr 71,200.00 78,320.00
2.2.3.34 Asbes Gelombang nok kecil 92 x 200 tbl = 5 mm Lbr 84,500.00 92,950.00
2.2.3.35 Asbes Gelombang nok kecil 92 x 225 tbl = 5 mm Lbr 101,300.00 111,430.00
2.2.3.36 Asbes Nok 105 Lbr 38,700.00 42,570.00
2.2.3.37 Asbes Nok 92 Lbr 32,200.00 35,420.00
2.2.3.38 Asbes Nok Gelombang besar Lbr 69,300.00 76,230.00
2.2.3.39 Asbes Nok Gelombang kecil Lbr 37,500.00 41,250.00
2.2.3.40 Asbes Plat 90 x 180 tbl = 3 mm Lbr 20,600.00 22,660.00
2.2.3.41 Asbes Sirap 20 x 40 tbl = 3 mm Lbr 25,700.00 28,270.00
2.2.3.42 Atap galvalum ( Hollow 4cm ) M2 / psg 440,000.00 484,000.00
2.2.3.43 Atap galvalum tebal 0,25 M2 50,800.00 55,880.00
2.2.3.44 Atap galvalum tebal 0,30 M2 59,500.00 65,450.00
2.2.3.45 Atap galvalum tebal 0,35 M2 68,200.00 75,020.00
2.2.3.46 Atap galvalum tebal 0,40 M2 76,200.00 83,820.00
2.2.3.47 Atap Policarbonat stainlees steel M2 605,000.00 665,500.00
2.2.3.48 Atap Policarbonat 3 mm (Hollow 3 cm) M2 467,500.00 514,250.00
2.2.3.49 Atap policarbonat besi M2 440,000.00 484,000.00
2.2.3.50 Atap sirap M2 220,000.00 242,000.00
2.2.3.51 Atap Skylight / fiber M2 242,000.00 266,200.00
2.2.3.52 Awning M2 / psg 346,500.00 381,150.00
2.2.3.53 Block board 122 x 244 tbl = 10 mm Lbr 231,000.00 254,100.00
2.2.3.54 Bubung asbes gel besar (Ardek 1Stel 2 Lmbr) Unit 63,600.00 69,960.00
2.2.3.55 Bubung asbes gel kecil (Ardek 1Stel 2 Lmbr) Unit 34,700.00 38,170.00
2.2.3.56 Bubungan Glasur ex. Kanmuri Bh 20,200.00 22,220.00
2.2.3.57 Bubungan Multiroof (0,5m x 1 m) Lbr 34,700.00 38,170.00
2.2.3.58 Bubungan Tembaga Motif /Tekstur 0,5 M' 825,000.00 907,500.00
2.2.3.59 Bubungan Tembaga Motif /Tekstur 0,6 M' 935,000.00 1,028,500.00
2.2.3.60 Bubungan Tembaga Motif /Tekstur 0,8 M' 1,017,500.00 1,119,250.00
2.2.3.61 Clamp penggantung lengkap Unit 33,600.00 36,960.00
2.2.3.62 Eternit kembang M2 10,500.00 11,550.00
2.2.3.63 Eternit polos (Asbes) M2 14,300.00 15,730.00
2.2.3.64 Fiber Glass ex. Kano flash L=100cm m' 52,300.00 57,530.00
2.2.3.65 Formika (120x240)cm Lbr 275,000.00 302,500.00
2.2.3.66 Genteng Bubung MKP Bh 5,800.00 6,380.00
2.2.3.67 Genteng MKP Bh 2,600.00 2,860.00
2.2.3.68 Genteng Beton Bh 5,000.00 5,500.00
2.2.3.69 Genteng bubung beton Bh 4,800.00 5,280.00
2.2.3.70 Genteng bubung beton Bh 4,800.00 5,280.00
2.2.3.71 Genteng bubung Mantili ex. Trenggalek / Tulungagung Bh 6,400.00 7,040.00
2.2.3.72 Genteng bubung Prentul ex. Trenggalek / Tulungagung Bh 5,000.00 5,500.00
2.2.3.73 Genteng bubung Press Bh 4,800.00 5,280.00
2.2.3.74 Genteng Bubung Karang Pilang Bh 6,200.00 6,820.00

5
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.3.75 Genteng gelombang Bh 3,100.00 3,410.00
2.2.3.76 Genteng Glasur ex. Kanmuri Bh 10,000.00 11,000.00
2.2.3.77 Genteng Kaca (model Karang Pilang) Bh 11,400.00 12,540.00
2.2.3.78 Genteng Keramik motof Mantili bh 30,800.00 33,880.00
2.2.3.79 Genteng mantili Bh 3,200.00 3,520.00
2.2.3.80 Genteng Metal Lbr 65,200.00 71,720.00
2.2.3.81 Genteng Prentul ex. T.ggalek/Tulungagung Bh 2,000.00 2,200.00
2.2.3.82 Genteng pres biasa Bh 2,300.00 2,530.00
2.2.3.83 Gypsum board tebal 12mm ( 1,2 x 2,4 m ) Lbr 78,100.00 85,910.00
2.2.3.84 Gypsum board tebal 12mm ( 1,2 x 2,4 m ) KNAF Lbr 69,900.00 76,890.00
2.2.3.85 Gypsum board tebal 9mm ( 1,2 x 2,4 m ) Lbr 76,500.00 84,150.00
2.2.3.86 Gypsum tepung / cornise kg 5,200.00 5,720.00
2.2.3.87 Harpleks 4mm ( Uk 40cm x200cm) Lbr 17,600.00 19,360.00
2.2.3.88 Harpleks 4mm ( Uk 50cm x200cm) Lbr 20,400.00 22,440.00
2.2.3.89 Harpleks 4mm ( Uk 60cm x200cm) Lbr 23,100.00 25,410.00
2.2.3.90 Kalsiplang motif kayu lebar 20 cm m' 27,500.00 30,250.00
2.2.3.91 Kalsiplang polos lebar 30 cm m' 14,900.00 16,390.00
2.2.3.92 Kalsirata 1000×1000 tebal 3 mm lbr 15,000.00 16,500.00
2.2.3.93 Kalsirata 500×1000 tebal 3 mm lbr 7,800.00 8,580.00
2.2.3.94 Kalsirata 600×2000 tebal 3 mm lbr 18,100.00 19,910.00
2.2.3.95 Kalsirata 500×2000 tebal 3 mm lbr 15,500.00 17,050.00
2.2.3.96 Kalsirata 400×2000 tebal 3 mm lbr 12,400.00 13,640.00
2.2.3.97 Kalsiplank 200×2400 tebal 8mm lbr 27,900.00 30,690.00
2.2.3.98 Kalsiplank 200×3000 tebal 8mm lbr 35,100.00 38,610.00
2.2.3.99 Kalsiplank 300×2400 tebal 8mm lbr 41,800.00 45,980.00
2.2.3.100 Kalsiplank 300×3000 tebal 8mm lbr 52,600.00 57,860.00
2.2.3.101 Kalsiplank Jati 200×2400 tebal 8mm lbr 29,400.00 32,340.00
2.2.3.102 Kalsiplank Jati 200×3000 tebal 8mm lbr 36,900.00 40,590.00
2.2.3.103 Kalsiplank Jati 300×3000 tebal 8mm lbr 55,400.00 60,940.00
2.2.3.104 Kalsiplank 200×2400 tebal 12mm lbr 42,300.00 46,530.00
2.2.3.105 Kalsiplank 200×3000 tebal 12mm lbr 52,600.00 57,860.00
2.2.3.106 Kalsiplank 300×2400 tebal 12mm lbr 63,900.00 70,290.00
2.2.3.107 Wood Plank Elephant 4050×100 tebal 8mm lbr 51,500.00 56,650.00
2.2.3.108 Wood Plank Elephant 4050×200 tebal 8mm lbr 67,000.00 73,700.00
2.2.3.109 Wood Plank Elephant 4050×300 tebal 8mm lbr 82,400.00 90,640.00
2.2.3.110 Big Flat Elephant 122×244 tebal 4mm lbr 46,400.00 51,040.00
2.2.3.111 Big Flat Elephant 122×244 tebal 6mm lbr 74,200.00 81,620.00
2.2.3.112 Big Flat Elephant 122×244 tebal 8mm lbr 101,000.00 111,100.00
2.2.3.113 Kalsiboard 1,2 x 2,4 m tebal 4 mm lbr 62,000.00 68,200.00
2.2.3.114 Kalsiplank polos 20 cm 20 cm x 3 m tebal 8 mm lbr 40,000.00 44,000.00
2.2.3.115 Kalsiplank polos 30 cm 30 cm x 3 m tgebal 8 mm lbr 60,000.00 66,000.00
2.2.3.116 Kalsiplank Jati 20 cm 20 cm x 3 m tebal 8 mm lbr 44,000.00 48,400.00
2.2.3.117 kalsiplank jati 30 cm 30 cm x 3 m tebal 8 mm lbr 64,000.00 70,400.00

6
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.3.118 Superplank 10 cm 10 cm x 2.44 m tebal 9 mm lbr 28,000.00 30,800.00
2.2.3.119 Superplank 20 cm 20 cm x 2.44 m tebal 9 mm lbr 45,000.00 49,500.00
2.2.3.120 Superplank 30 cm 30 cm x 2.44 tebal 9 mm lbr 65,000.00 71,500.00
2.2.3.121 Kalsirata 1,00 x 1,00 tebal 3 mm lbr 13,996.00 15,395.60
2.2.3.122 Kalsirata 0,50 x 1,00 tebal 3 mm lbr 8,000.00 8,800.00
2.2.3.123 Kalsirata 1,00 x 2,00 tebal 3 mm lbr 34,550.00 38,005.00
2.2.3.124 Kalsirata 0,50 x 2,00 tebal 3 mm lbr 15,850.00 17,435.00
2.2.3.125 Kalsirata 1,22 x 2,44 tebal 3,5 mm lbr 62,800.00 69,080.00
2.2.3.126 Kalsirata 1,20 x 2,40 tebal 3,5 mm lbr 60,400.00 66,440.00
2.2.3.127 Kalsiling 1,22 x 2,44 tebal 4,5 mm lbr 86,550.00 95,205.00
2.2.3.128 Kalsiling 1,20 x 2,40 tebal 4,5 mm lbr 83,350.00 91,685.00
2.2.3.129 Kalsiling 1,20 x 2,44 tebal 6 mm lbr 122,350.00 134,585.00
2.2.3.130 Kalsiling 1,20 x 2,40 tebal 6 mm lbr 117,750.00 129,525.00
2.2.3.131 Kalsiling 1,20 x 2,70 tebal 6 mm lbr 132,450.00 145,695.00
2.2.3.132 Kalsiling 1,20 x 3,00 tebal 6 mm lbr 148,600.00 163,460.00
2.2.3.133 Kalsiling 1,22 x 2,44 tebal 6 mm R2 lbr 125,550.00 138,105.00
2.2.3.134 Kalsiling 1,20 x 2,40 tebal 6 mm R2 lbr 120,800.00 132,880.00
2.2.3.135 Kalsiling 1,20 x 2,70 tebal 6 mm R2 lbr 135,900.00 149,490.00
2.2.3.136 Kalsiling 1,20 x 3,00 tebal 6 mm R2 lbr 149,650.00 164,615.00
2.2.3.137 Kalsiling 1,22 x 2,44 tebal 6 mm R4 lbr 126,850.00 139,535.00
2.2.3.138 Kalsiling 1,20 x 2,40 tebal 6 mm R4 lbr 122,050.00 134,255.00
2.2.3.139 Kalsiling 1,20 x 2,70 tebal 6 mm R4 lbr 137,200.00 150,920.00
2.2.3.140 Kalsiling 1,20 x 3,00 tebal 6 mm R4 lbr 152,500.00 167,750.00
2.2.3.141 Kalsipart 1,22 x 2,44 tebal 8 mm lbr 164,850.00 181,335.00
2.2.3.142 Kalsipart 1,20 x 2,40 tebal 8 mm lbr 158,600.00 174,460.00
2.2.3.143 Kalsipart 1,20 x 2,70 tebal 8 mm lbr 178,400.00 196,240.00
2.2.3.144 Kalsipart 1,20 x 3,00 tebal 8 mm lbr 198,150.00 217,965.00
2.2.3.145 Kalsipart 1,22 x 2,44 tebal 8 mm R2 lbr 169,000.00 185,900.00
2.2.3.146 Kalsipart 1,20 x 2,40 tebal 8 mm R2 lbr 162,650.00 178,915.00
2.2.3.147 Kalsipart 1,20 x 2,70 tebal 8 mm R2 lbr 183,000.00 201,300.00
2.2.3.148 Kalsipart 1,20 x 3,00 tebal 8 mm R2 lbr 202,100.00 222,310.00
2.2.3.149 Kalsipart 1,22 x 2,44 tebal 8 mm R4 lbr 170,650.00 187,715.00
2.2.3.150 Kalsipart 1,20 x 2,40 tebal 8 mm R4 lbr 164,250.00 180,675.00
2.2.3.151 Kalsipart 1,20 x 2,70 tebal 8 mm R4 lbr 184,700.00 203,170.00
2.2.3.152 Kalsipart 1,20 x 3,00 tebal 8 mm R4 lbr 204,100.00 224,510.00
2.2.3.153 Kalsiclad 1,22 x 2,44 tebal 10 mm lbr 208,000.00 228,800.00
2.2.3.154 Kalsiclad 1,20 x 2,40 tebal 10 mm lbr 200,100.00 220,110.00
2.2.3.155 Kalsiclad 1,20 x 2,70 tebal 10 mm lbr 225,100.00 247,610.00
2.2.3.156 Kalsiclad 1,20 x 2,70 tebal 10 mm lbr 225,100.00 247,610.00
2.2.3.157 Kalsiclad 1,22 x 2,44 tebal 12 mm lbr 251,850.00 277,035.00
2.2.3.158 Kalsiclad 1,20 x 2,40 tebal 12 mm lbr 242,450.00 266,695.00
2.2.3.159 Kalsiclad 1,20 x 2,70 tebal 12 mm lbr 272,650.00 299,915.00
2.2.3.160 Kalsiclad 1,20 x 3,00 tebal 12 mm lbr 303,150.00 333,465.00

7
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.3.161 Kalsiplang 0,2 x 2,40 tebal 8 mm lbr 31,500.00 34,650.00
2.2.3.162 Kalsiplang 0,2 x 3,00 tebal 8 mm lbr 39,350.00 43,285.00
2.2.3.163 Kalsiplang 0,2 x 2,40 tebal 8 mm lbr 31,500.00 34,650.00
2.2.3.164 Kalsiplang 0,2 x 3,00 tebal 8 mm lbr 39,350.00 43,285.00
2.2.3.165 Kalsiplang jati 0,20 x 2,40 tebal 8 mm lbr 33,000.00 36,300.00
2.2.3.166 Kalsiplang jati 0,20 x 3,00 tebal 8 mm lbr 41,350.00 45,485.00
2.2.3.167 Kalsiplang jati 0,30 x 3,00 tebal 8 mm lbr 62,000.00 68,200.00
2.2.3.168 Kalsiplang 0,20 x 2,40 tebal 12 mm lbr 46,450.00 51,095.00
2.2.3.169 Kalsiplang 0,20 x 3,00 tebal 12 mm lbr 57,900.00 63,690.00
2.2.3.170 Kalsiplang 0,30 x 2,40 tebal 12 mm lbr 69,350.00 76,285.00
2.2.3.171 Kalsiplang 0,30 x 3,00 tebal 12 mm lbr 86,700.00 95,370.00
2.2.3.172 Kalsifloor 1,20 x 2,40 tebal 20 mm lbr 553,000.00 608,300.00
2.2.3.173 Wood plank Elephant 4050 x 100 tebal 8 mm lbr 50,000.00 55,000.00
2.2.3.174 Wood plank Elephant 4050 x 200 tebal 8 mm lbr 65,000.00 71,500.00
2.2.3.175 Wood plank Elephant 4050 x 300 tebal 8 mm lbr 80,000.00 88,000.00
2.2.3.176 Big Flat Elephant 122 x 244 tebal 4 mm lbr 45,000.00 49,500.00
2.2.3.177 Big Flat Elephant 122 x 244 tebal 6 mm lbr 72,000.00 79,200.00
2.2.3.178 Big Flat Elephant 122 x 244 tebal 8 mm lbr 98,000.00 107,800.00
2.2.3.179 Kalsirata 1000 x 1000 tebal 3 mm lbr 14,500.00 15,950.00
2.2.3.180 Kalsirata 500 x 1000 tebal 3 mm lbr 7,500.00 8,250.00
2.2.3.181 Kalsirata 600 x 2000 tebal 3 mm lbr 17,500.00 19,250.00
2.2.3.182 Kalsirata 500 x 2000 tebal 3 mm lbr 15,000.00 16,500.00
2.2.3.183 Kalsirata 400 x 2000 tebal 3 mm lbr 12,000.00 13,200.00
2.2.3.184 Kalsiplank 200 x 2400 tebal 8 mm lbr 27,000.00 29,700.00
2.2.3.185 Kalsiplank 200 x 3000 tebal 8 mm lbr 34,000.00 37,400.00
2.2.3.186 Kalsiplank 300 x 2400 tebal 8 mm lbr 40,500.00 44,550.00
2.2.3.187 Kalsiplank 300 x 3000 tebal 8 mm lbr 51,000.00 56,100.00
2.2.3.188 Kalsiplank Jati 200 x 2400 tebal 8 mm lbr 28,500.00 31,350.00
2.2.3.189 Kalsiplank Jati 200 x 3000 tebal 8 mm lbr 35,750.00 39,325.00
2.2.3.190 Kalsiplank Jati 300 x 3000 tebal 8 mm lbr 53,750.00 59,125.00
2.2.3.191 Kalsiplank 200 x 2400 tebal 12 mm lbr 41,000.00 45,100.00
2.2.3.192 Kalsiplank 200 x 3000 tebal 12 mm lbr 51,000.00 56,100.00
2.2.3.193 Kalsiplank 300 x 2400 tebal 12 mm lbr 62,000.00 68,200.00
2.2.3.194 Kalsiplank 300 x 3000 tebal 12 mm lbr 73,500.00 80,850.00
2.2.3.195 Langit-langit Akustik ex. Jayaboard (30x30)cm Lbr 41,800.00 45,980.00
2.2.3.196 Langit-langit Akustik ex. Jayaboard (30x60)cm Lbr 47,300.00 52,030.00
2.2.3.197 Langit-langit Akustik ex. Jayaboard (60x120)cm Lbr 52,800.00 58,080.00
2.2.3.198 List Eternit ( kayu ) M' 3,000.00 3,300.00
2.2.3.199 List Profil besar ( gypsum ) M' 23,100.00 25,410.00
2.2.3.200 List Profil kecil ( gypsum ) M' 17,400.00 19,140.00
2.2.3.201 Multiplek 6 mm, uk 1,20 x 2,40 m Lbr 94,600.00 104,060.00
2.2.3.202 Multiplek 9 mm, uk. 1,20 x 2,40 m Lbr 140,800.00 154,880.00
2.2.3.203 Multiroof (0,6m x 1,00 m) Lbr 44,600.00 49,060.00

8
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.3.204 Nok atap genteng metal Lbr 36,900.00 40,590.00
2.2.3.205 Nok genteng keramik bh 53,900.00 59,290.00
2.2.3.206 Nok Stel Asbes Gelombang besar 108 Lbr 60,500.00 66,550.00
2.2.3.207 Nok Stel Asbes Gelombang kecil 105 Lbr 39,700.00 43,670.00
2.2.3.208 Partikel board t = 18 mm (1.22 m x 2.42 m ) Lbr 209,100.00 230,010.00
2.2.3.209 Plywood ( 110 x 210 ) cm, tbl. 4 mm Lbr 85,300.00 93,830.00
2.2.3.210 Plywood ( 110 x 240 ) cm, tbl. 3 mm Lbr 63,800.00 70,180.00
2.2.3.211 Plywood ( 120 x 240 ) cm, tbl. 2 mm Lbr 72,100.00 79,310.00
2.2.3.212 Plywood ( 120 x 240 ) cm, tbl. 4 mm Lbr 99,000.00 108,900.00
2.2.3.213 Plywood ( 120 x 240 ) cm, tbl. 6 mm Lbr 76,500.00 84,150.00
2.2.3.214 Plywood ( 90 x 220 ) cm, tbl. 4 mm Lbr 62,200.00 68,420.00
2.2.3.215 Plywood 122 x 244 tbl = 3 mm Lbr 94,600.00 104,060.00
2.2.3.216 Rangka plafond metal furing M' 13,200.00 14,520.00
2.2.3.217 Seng gelombang BJLS 0,02 cm 80 x 180 Lbr 56,100.00 61,710.00
2.2.3.218 Seng gelombang BJLS 0,03 cm 80 x 300 Lbr 91,300.00 100,430.00
2.2.3.219 Seng Gelombang Bjls 20 uk. 180x90x0,02 cm Lbr 55,600.00 61,160.00
2.2.3.220 Seng gelombang Bjls 20 uk. 305x90x0,02 cm Lbr 89,100.00 98,010.00
2.2.3.221 Seng Gelombang Bjls 30 uk 180x90x0,03 cm Lbr 74,300.00 81,730.00
2.2.3.222 Seng Gelombang Bjls 30 uk 305x90x0,02 cm Lbr 89,100.00 98,010.00
2.2.3.223 Seng gelombang Bjls 30 uk. 305x90x0,03 cm Lbr 123,800.00 136,180.00
2.2.3.224 Seng Plat BJLS 20 lebar 0,90 m M' 75,400.00 82,940.00
2.2.3.225 Seng Plat BJLS 27 lebar 0,60 m M' 22,600.00 24,860.00
2.2.3.226 Seng Plat BJLS 27 lebar 0,90 m M' 39,100.00 43,010.00
2.2.3.227 Seng Plat BJLS 30 lebar 0,45 m M' 24,200.00 26,620.00
2.2.3.228 Seng Plat BJLS 30 lebar 0,60 m M' 31,400.00 34,540.00
2.2.3.229 Seng Plat BJLS 30 lebar 0,90 m M' 42,400.00 46,640.00
2.2.3.230 Talang Karet L=55cm m' 21,500.00 23,650.00
2.2.3.231 Talang Karet L=90cm m' 34,700.00 38,170.00
2.2.3.232 Talang PVC U 4" M' 41,800.00 45,980.00
2.2.3.233 Teakwood 122 x 244 tbl = 3 mm Lbr 74,300.00 81,730.00
2.2.3.234 Teakwood tebal 3mm (90 x 210) Cm Lbr 80,300.00 88,330.00
2.2.3.235 Teakwood tebal 4mm (110 x 240) Cm Lbr 90,200.00 99,220.00
2.2.3.236 Teakwood tebal 4mm (120 x 240) Cm Lbr 83,700.00 92,070.00
2.2.3.237 Tekwood dilapis aluminium Lbr 98,200.00 108,020.00
2.2.3.238 Tripleks 122 x 244 tbl = 12 mm Lbr 179,100.00 197,010.00
2.2.3.239 Tripleks 122 x 244 tbl = 15 mm Lbr 225,300.00 247,830.00
2.2.3.240 Tripleks 122 x 244 tbl = 16 mm Lbr 231,000.00 254,100.00
2.2.3.241 Tripleks 122 x 244 tbl = 2 mm Lbr 37,400.00 41,140.00
2.2.3.242 Tripleks 122 x 244 tbl = 3 mm Lbr 51,200.00 56,320.00
2.2.3.243 Tripleks 122 x 244 tbl = 4 mm Lbr 79,800.00 87,780.00
2.2.3.244 Tripleks 122 x 244 tbl = 6 mm Lbr 83,100.00 91,410.00
2.2.3.245 Tripleks 122 x 244 tbl = 9 mm Lbr 133,100.00 146,410.00
2.2.3.246 Tripleks tebal 4 mm ( 1.20 x 2.40 ) m Lbr 77,000.00 84,700.00

9
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.3.247 Tripleks tebal 3 mm ( 0.90 x 2.40 ) m Lbr 53,400.00 58,740.00
2.2.3.248 Tripleks tebal 4 mm ( 0.90 x 2.00 ) m Lbr 58,300.00 64,130.00
2.2.3.249 Tripleks tebal 4 mm ( 1.10 x 2.10 ) m Lbr 71,500.00 78,650.00
2.2.3.250 Tripleks tebal 4 mm ( 1.22 x 2.44 ) m Lbr 75,900.00 83,490.00
2.2.3.251 Twekblock 122 x 244 tbl = 18 mm Lbr 247,500.00 272,250.00
- -
2.2.4 BAHAN BESI / LOGAM : - -
2.2.4.1 Aluminium strip ( l = 5 - 10 cm) M' 16,500.00 18,150.00
2.2.4.2 Alumunium Composite Panel Ex. Alucopan M2 660,000.00 726,000.00
2.2.4.3 Alumunium foil M2 11,000.00 12,100.00
2.2.4.4 Baja Galvanis Kg 22,000.00 24,200.00
2.2.4.5 Baja Galvanis 6m ljr 44,000.00 48,400.00
2.2.4.6 Baja Profil Kg 15,400.00 16,940.00
2.2.4.7 Baja siku L 30.30.3 Kg 19,300.00 21,230.00
2.2.4.8 Besi Angker dia 25 mm P 50 cm Bh 73,400.00 80,740.00
2.2.4.9 Besi Beton / tulangan beton Kg 10,500.00 11,550.00
2.2.4.10 Besi Beugel/Baut Kg 18,700.00 20,570.00
2.2.4.11 Besi lis kaca (1 x 1) cm M' 17,600.00 19,360.00
2.2.4.12 Besi pengaman pipa dia 12 mm Unit 200,500.00 220,550.00
2.2.4.13 Besi plat Kg 17,900.00 19,690.00
2.2.4.14 Besi plat strip / Strip plate Kg 17,900.00 19,690.00
2.2.4.15 Besi siku Kg 11,000.00 12,100.00
2.2.4.16 Besi Square tube M' 6,400.00 7,040.00
2.2.4.17 Besi strip + Mur Baut Kg 18,700.00 20,570.00
2.2.4.18 Daun jendela kaca aluminium 4" M2 462,000.00 508,200.00
2.2.4.19 Daun Jendela kaca aluminium YKK M3 937,300.00 1,031,030.00
2.2.4.20 Daun pintu Kaca pegas lengkap (kunci,engsel dan handle) M' 5,093,600.00 5,602,960.00
2.2.4.21 Grill besi M2 351,700.00 386,870.00
2.2.4.22 Huruf logo nama stainlees uk. 20-30 cm Kg 73,400.00 80,740.00
2.2.4.23 Huruf logo nama stainlees uk. 30-40 cm M2 87,800.00 96,580.00
2.2.4.24 Huruf logo nama stainlees uk. 40-50 cm M2 102,200.00 112,420.00
2.2.4.25 Jaring kawat baja dilas (wiremesh) Kg 28,900.00 31,790.00
2.2.4.26 Kawat Ayakan Pasir (untuk pasang) Kg 18,200.00 20,020.00
2.2.4.27 Kawat Ayakan Pasir (untuk plesteran) Kg 19,400.00 21,340.00
2.2.4.28 Kawat ayaman bronjong galvanis Ø 3mm M' 22,600.00 24,860.00
2.2.4.29 Kawat ayaman bronjong galvanis Ø 4mm M2 24,400.00 26,840.00
2.2.4.30 Kawat Beton / bendraat Bh 17,600.00 19,360.00
2.2.4.31 Kawat duri Kg 11,600.00 12,760.00
2.2.4.32 Kawat Harmonika Kg 31,400.00 34,540.00
2.2.4.33 Kawat Las karbit Kg 13,800.00 15,180.00
2.2.4.34 kawat las listrik biasa M2 75,000.00 82,500.00
2.2.4.35 Kawat Nyamuk aluminium M2 25,300.00 27,830.00
2.2.4.36 Kawat Nyamuk kasa plastik M2 18,700.00 20,570.00

10
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.4.37 Kisi - kisi almunium M' 485,100.00 533,610.00
2.2.4.38 Kawat Nyamuk aluminium M' 25,300.00 27,830.00
2.2.4.39 Kawat Nyamuk kasa plastik Unit 18,700.00 20,570.00
2.2.4.40 Kisi - kisi almunium Bh 485,100.00 533,610.00
2.2.4.41 Kisi - kisi almunium 4" Bh 77,400.00 85,140.00
2.2.4.42 Kisi - kisi aluminium 3" M2 66,400.00 73,040.00
2.2.4.43 Manhole (tutup plat besi 0.5 x 0.5) Unit 346,500.00 381,150.00
2.2.4.44 Tutup Besi Baja Manhole Diameter 50 cm tebal= 0,5cm Bh 1,045,000.00 1,149,500.00
2.2.4.45 Mur, Baut baja dia 3/4" panjang 10 cm Bh 13,900.00 15,290.00
2.2.4.46 Mur, Baut biasa dia 3/4" panjang 10 cm M2/Psg 11,600.00 12,760.00
2.2.4.47 Pagar Besi BRC Pabrikasi ( Besi Ø6" - Ø8" Uk. 90 x 240 )cm Bh/Psg 263,300.00 289,630.00
2.2.4.48 Pagar Besi BRC Pabrikasi ( Besi Ø6"- Ø8" Uk.120 x 240 )cm Bh/Psg 255,300.00 280,830.00
2.2.4.49 Pagar Besi BRC Pabrikasi ( Besi Ø6"- Ø8" Uk.150 x 240 )cm Bh/Psg 241,500.00 265,650.00
2.2.4.50 Pagar Besi Tuang Ø14" M2/Psg 404,300.00 444,730.00
2.2.4.51 Pagar Besi Tuang Ø16" M2/Psg 467,800.00 514,580.00
2.2.4.52 Pagar pipa besi holo (20.20.1)mm,Rangka besi holo (50.50.2)mm dicat M2/Psg 444,700.00 489,170.00
2.2.4.53 Pagar pipa besi holo (20.20.2)mm,Rangka besi holo (50.50.2)mm dicat M2/Psg 526,700.00 579,370.00
2.2.4.54 Pintu aluminium coklat / hitam 4" ( 2 sisi ) cm / Psg 702,800.00 773,080.00
2.2.4.55 Las besi / baja M2 2,300.00 2,530.00
2.2.4.56 Pintu besi lipat ( Bukan Harmonika) M2 447,000.00 491,700.00
2.2.4.57 Pintu besi lipat ( harmonika) M2 1,067,200.00 1,173,920.00
2.2.4.58 Pintu dorong BRC/PMG (120x300)cm M2 1,374,500.00 1,511,950.00
2.2.4.59 Pintu kaca sliding unit 5,512,900.00 6,064,190.00
2.2.4.60 Pintu Pagar besi holo (20.20.2)mm, Rangka besi holo (50.50.2)mm dicat mo Bh 523,300.00 575,630.00
2.2.4.61 Pintu Pagar Besi Tuang Ø14" (komplit) M2/Psg 365,500.00 402,050.00
2.2.4.62 Pintu Pagar Besi Tuang Ø16" (komplit) M2/Psg 487,400.00 536,140.00
2.2.4.63 Pintu Pagar pipa besi holo (20.20.1)mm, Rangka besi holo (50.50.2)mm dic M2 460,900.00 506,990.00
2.2.4.64 Pintu Plat Harmonika Unit 1,297,100.00 1,426,810.00
2.2.4.65 Pintu PVC Lipat (70x210)cm Unit 499,000.00 548,900.00
2.2.4.66 Pintu PVC Polos (70x210)cm M2 219,500.00 241,450.00
2.2.4.67 Pintu Roling Door aluminium M2 378,800.00 416,680.00
2.2.4.68 Pintu Roling Door besi unit 548,700.00 603,570.00
2.2.4.69 Pintu Swing Ganda BRC (121x300)cm M' 1,365,200.00 1,501,720.00
2.2.4.70 Pipa Besi  2/4 Tebal= 1.2 mm M' 12,000.00 13,200.00
2.2.4.71 Pipa Besi  2/4 Tebal= 1.4 mm M' 13,600.00 14,960.00
2.2.4.72 Pipa Besi  4/4 Tebal= 1.2 mm M' 14,700.00 16,170.00
2.2.4.73 Pipa Besi  4/4 Tebal= 1.4 mm Btg 17,400.00 19,140.00
2.2.4.74 Pipa galvanis spindo SNI 1 - 1/2" x 2,8 - 3 M' 67,900.00 74,690.00
2.2.4.75 Pipa galvanis spindo SNI 1 - 1/4" x 2,8 - 3 M' 59,200.00 65,120.00
2.2.4.76 Pipa galvanis spindo SNI 1" x 2,8 - 3 M' 44,800.00 49,280.00
2.2.4.77 Pipa galvanis spindo SNI 1/2" x 2,3 - 2,5 M' 23,100.00 25,410.00
2.2.4.78 Pipa galvanis spindo SNI 2 - 1/2" x 3,2 - 3,5 M' 118,400.00 130,240.00
2.2.4.79 Pipa galvanis spindo SNI 2" x 3,2 - 3,3 M' 92,400.00 101,640.00

11
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.4.80 Pipa galvanis spindo SNI 3" x 3,5 - 5 M' 150,200.00 165,220.00
2.2.4.81 Pipa galvanis spindo SNI 3/4" x 2,3 - 2,5 M' 28,900.00 31,790.00
2.2.4.82 Pipa galvanis spindo SNI 4" x 4 - 4,4 M' 215,400.00 236,940.00
2.2.4.83 Pipa galvanis spindo SNI 5" x 4,1 - 4,6 M' 288,800.00 317,680.00
2.2.4.84 Pipa galvanis spindo SNI 6" x 4,1 - 4,8 M' 346,500.00 381,150.00
2.2.4.85 Pipa Gas ( selang ) M' 92,400.00 101,640.00
2.2.4.86 Pipa hitam spindo SNI 1 - 1/2" M' 47,600.00 52,360.00
2.2.4.87 Pipa hitam spindo SNI 1 - 1/4" M' 40,500.00 44,550.00
2.2.4.88 Pipa hitam spindo SNI 1" M' 31,800.00 34,980.00
2.2.4.89 Pipa hitam spindo SNI 1/2" M' 15,800.00 17,380.00
2.2.4.90 Pipa hitam spindo SNI 2 - 1/2" M' 80,900.00 88,990.00
2.2.4.91 Pipa hitam spindo SNI 2" M' 65,000.00 71,500.00
2.2.4.92 Pipa hitam spindo SNI 3" M' 104,000.00 114,400.00
2.2.4.93 Pipa hitam spindo SNI 3/4" M' 21,700.00 23,870.00
2.2.4.94 Pipa hitam spindo SNI 4" M' 151,600.00 166,760.00
2.2.4.95 Pipa hitam spindo SNI 5" M' 202,200.00 222,420.00
2.2.4.96 Pipa hitam spindo SNI 6" M' 241,100.00 265,210.00
2.2.4.97 Profil aluminium T (Metal Furring) Bh 37,700.00 41,470.00
2.2.4.98 Profil daun pintu almunium coklat / hitam M' 89,300.00 98,230.00
2.2.4.99 Profil kusen almunium coklat / hitam 4" M' 101,900.00 112,090.00
2.2.4.100 Profil kusen aluminium 4" M2 90,300.00 99,330.00
2.2.4.101 Profil kusen aluminium 4"ykk M2 / Psg 176,300.00 193,930.00
2.2.4.102 Ralling tangga / grill stainlees Dia 2" M2 / Psg 924,000.00 1,016,400.00
2.2.4.103 Ralling tangga / pagar besi Unit 548,700.00 603,570.00
2.2.4.104 Rel pintu dorong unit 270,800.00 297,880.00
2.2.4.105 Rel pintu dorong l. 90 Unit 156,000.00 171,600.00
2.2.4.106 Rol baja dia 19 mm lengkap M2 133,400.00 146,740.00
2.2.4.107 Sun Screen Aluminium Unit 630,100.00 693,110.00
2.2.4.108 Tangga Pipa GI Ǿ 1" M2 571,800.00 628,980.00
2.2.4.109 Teralis Besi btg 283,600.00 311,960.00
2.2.4.110 Teralis stainlees M2 473,600.00 520,960.00
2.2.4.111 Tiang Pagar BRC ( Ø 2", t=120) Unit 78,800.00 86,680.00
2.2.4.112 Tutup Besi Baja Manhole Diameter 50 cm tebal= 0,5 cm 880,000.00 968,000.00
- -
2.2.5 BAHAN PENUTUP LANTAI & DINDING : - -
2.2.5.1 Bata berongga expose Bh 8,500.00 9,350.00
2.2.5.2 Bata ringan 60 x 25 x 10 cm Bh 11,000.00 12,100.00
2.2.5.3 Batacote Kg 5,200.00 5,720.00
2.2.5.4 Batako (30x25x10)cm Bh 3,900.00 4,290.00
2.2.5.5 Batu granit Kg 4,200.00 4,620.00
2.2.5.6 Batu teraso Kg 2,300.00 2,530.00
2.2.5.7 Dinding partisi ex.Calsy bord (uk. 122x244x0.3 cm) Lbr 62,400.00 68,640.00
2.2.5.8 Glasswoll panjang 5,00 lebar 0,60 M2 715,000.00 786,500.00

12
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.5.9 Granit (ex Granito) tekstur Uk. 40x40 cm M2 161,700.00 177,870.00
2.2.5.10 Granit (ex Granito) tekstur Uk. 60x60 cm M2 207,900.00 228,690.00
2.2.5.11 Granit (ex Granito) polos Uk. 40x40 cm M2 203,300.00 223,630.00
2.2.5.12 Granit (ex Granito) polos Uk. 60x60 cm M2 311,900.00 343,090.00
2.2.5.13 Granit (ex Granito) warna gelap Uk. 40x40 cm M2 225,300.00 247,830.00
2.2.5.14 Granit (ex Granito) warna gelap Uk. 60x60 cm M2 323,400.00 355,740.00
2.2.5.15 Granit (ex Granito) warna terang Uk. 40x40 cm M2 146,700.00 161,370.00
2.2.5.16 Granit (ex Granito) warna terang Uk. 60x60 cm M2 85,000.00 228,690.00
2.2.5.17 Keramik Granit 60 x 60 220 - Ivory dan 280 Joyc M2 175,000.00 192,500.00
2.2.5.18 Keramik Granit 60 x 60 242 - Sara M2 200,000.00 220,000.00
2.2.5.19 Keramik Granit 60 x 60 240 - White M2 200,000.00 220,000.00
2.2.5.20 Keramik Granit 60 x 60 989 - Granit Black M2 240,000.00 264,000.00
2.2.5.21 Karpet m2 27,300.00 30,030.00
2.2.5.22 Keramik Arstistik Uk. 10 x 20 cm M' 93,000.00 102,300.00
2.2.5.23 Keramik cutting Uk. 30cm x 50 cm M2 79,100.00 87,010.00
2.2.5.24 Keramik cutting Uk. 31cm x 63 cm M2 116,700.00 128,370.00
2.2.5.25 Keramik dinding motif Uk. 20cm x 25 cm M2 64,700.00 71,170.00
2.2.5.26 Keramik dinding putih ukuran 20/25 Cm M2 50,300.00 55,330.00
2.2.5.27 Keramik dinding Uk. 20cm x 33 cm M2 54,300.00 59,730.00
2.2.5.28 Keramik dinding Uk. 20cm x 50 cm M2 80,900.00 88,990.00
2.2.5.29 Keramik dinding 20 X 40 cm M2 103,400.00 113,740.00
2.2.5.30 Keramik dinding 20 X 45 cm M2 106,200.00 116,820.00
2.2.5.31 Keramik dinding 20 X 50 cm INA motif M2 99,000.00 108,900.00
2.2.5.32 Keramik dinding 20 X 50 cm Platinum motif M2 61,600.00 67,760.00
2.2.5.33 Keramik dinding 20 X 50 cm M2 94,600.00 104,060.00
2.2.5.34 Keramik dinding 30 X 60 cm M2 172,700.00 189,970.00
2.2.5.35 Keramik Dinding Roman 20 x 20 Golongan A M2 84,000.00 92,400.00
2.2.5.36 Keramik Dinding Roman 20 x 20 Golongan B M2 90,000.00 99,000.00
2.2.5.37 Keramik Dinding Roman 20 x 25 Golongan A M2 84,000.00 92,400.00
2.2.5.38 Keramik Dinding Roman 20 x 25 Golongan B M2 90,000.00 99,000.00
2.2.5.39 Keramik Dinding Roman 20 x 25 Golongan C M2 93,500.00 102,850.00
2.2.5.40 Keramik Dinding Roman 25 x 25 Golongan A M2 85,000.00 93,500.00
2.2.5.41 Keramik Dinding Roman 25 x 25 Golongan B M2 91,500.00 100,650.00
2.2.5.42 Keramik Dinding Roman 25 x 25 Golongan C M2 103,000.00 113,300.00
2.2.5.43 Keramik Dinding Roman 30 x 30 Golongan B (match 20 x 60) M2 118,000.00 129,800.00
2.2.5.44 Keramik Dinding Roman 30 x 30 Golongan C (match 20 x 60) M2 128,000.00 140,800.00
2.2.5.45 Keramik Dinding Roman 30 x 30 Golongan D (match 20 x 60) M2 143,000.00 157,300.00
2.2.5.46 Keramik Dinding Roman 30 x 30 Golongan A (match 30 x 60) M2 113,000.00 124,300.00
2.2.5.47 Keramik Dinding Roman 30 x 30 Golongan B (match 30 x 60) M2 118,000.00 129,800.00
2.2.5.48 Keramik Dinding Roman 30 x 30 Golongan C (match 30 x 60) M2 128,000.00 140,800.00
2.2.5.49 Keramik Dinding Roman 30 x 30 Golongan D (match 30 x 60) M2 143,000.00 157,300.00
2.2.5.50 Keramik Dinding Roman 25 x 33.3 Golongan A M2 84,000.00 92,400.00
2.2.5.51 Keramik Dinding Roman 25 x 33.3 Golongan B M2 90,000.00 99,000.00

13
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.5.52 Keramik Dinding Roman 25 x 33.3 Golongan C M2 93,500.00 102,850.00
2.2.5.53 Keramik Dinding Roman 20 x 40 Golongan A M2 84,000.00 92,400.00
2.2.5.54 Keramik Dinding Roman 20 x 40 Golongan B M2 90,000.00 99,000.00
2.2.5.55 Keramik Dinding Roman 25 x 45 Golongan A M2 92,500.00 101,750.00
2.2.5.56 Keramik Dinding Roman 25 x 45 Golongan B M2 103,500.00 113,850.00
2.2.5.57 Keramik Dinding Roman 25 x 45 Golongan D M2 122,500.00 134,750.00
2.2.5.58 Keramik Dinding Roman 32.5 x 32.5 Golongan A match 32.5 x 65,6 M2 126,000.00 138,600.00
2.2.5.59 Keramik Dinding Roman 32.5 x 32.5 Golongan B match 32.5 x 65,6 M2 131,000.00 144,100.00
2.2.5.60 Keramik Dinding Roman 32.5 x 32.5 Golongan A match 32.5 x 97,5 M2 126,000.00 138,600.00
2.2.5.61 Keramik Dinding Roman 20 x 60 Golongan A M2 128,500.00 141,350.00
2.2.5.62 Keramik Dinding Roman 20 x 60 Golongan B M2 140,000.00 154,000.00
2.2.5.63 Keramik Dinding Roman 20 x 60 Golongan C M2 155,000.00 170,500.00
2.2.5.64 Keramik Dinding Roman 20 x 60 Golongan D M2 175,000.00 192,500.00
2.2.5.65 Keramik Dinding Roman 30 x 60 Golongan A M2 128,500.00 141,350.00
2.2.5.66 Keramik Dinding Roman 30 x 60 Golongan B M2 140,000.00 154,000.00
2.2.5.67 Keramik Dinding Roman 30 x 60 Golongan C M2 155,000.00 170,500.00
2.2.5.68 Keramik Dinding Roman 30 x 60 Golongan D M2 175,000.00 192,500.00
2.2.5.69 Keramik Dinding Roman 30 x 60 Golongan E M2 185,000.00 203,500.00
2.2.5.70 Keramik Dinding Roman 32.5 x 65.6 Golongan A Rectified M2 191,500.00 210,650.00
2.2.5.71 Keramik Dinding Roman 32.5 x 65.6 Golongan B Rectified M2 207,000.00 227,700.00
2.2.5.72 Keramik Dinding Roman 32.5 x 65.6 Golongan C Rectified M2 226,000.00 248,600.00
2.2.5.73 Keramik Dinding Roman 32.5 x 97.5 Golongan A Rectified M2 283,000.00 311,300.00
2.2.5.74 Keramik Dinding Roman 32.5 x 97.5 Golongan B Rectified M2 323,000.00 355,300.00
2.2.5.75 Galaxy black, brown, cream, grey, white KW- A M2 39,500.00 43,450.00
2.2.5.76 Petra cream, terracota KW- A M2 39,500.00 43,450.00
2.2.5.77 Roxy black, blue, brown, green, grey, red KW-A M2 39,500.00 43,450.00
2.2.5.78 Alpha blue, green KW- A M2 42,000.00 46,200.00
2.2.5.79 Track brown, grey KW- A M2 44,500.00 48,950.00
2.2.5.80 Jungle red, green, grey, red KW- A M2 36,500.00 40,150.00
2.2.5.81 Capri brown, grey KW- A M2 37,000.00 40,700.00
2.2.5.82 Marble brown KW- A M2 38,000.00 41,800.00
2.2.5.83 Newton brown, green, grey KW- A M2 38,000.00 41,800.00
2.2.5.84 Mahoni brown, cream KW- A M2 39,000.00 42,900.00
2.2.5.85 Cargo, brown, grey, dark brown, dark grey KW-A M2 46,000.00 50,600.00
2.2.5.86 Clarin, bone, brown, grey KW- A M2 46,000.00 50,600.00
2.2.5.87 Cordon, bone, brown, cream KW- A M2 46,000.00 50,600.00
2.2.5.88 2Bintan, bone, brown, cream KW- A M2 47,500.00 52,250.00
2.2.5.89 Ecco grey, brown KW- A M2 70,000.00 77,000.00
2.2.5.90 Gobi cream, grey KW- A M2 700,000.00 770,000.00
2.2.5.91 Cavalli, cream, white KW- A M2 82,300.00 90,530.00
2.2.5.92 Fredo, cream, grey KW- A M2 82,300.00 90,530.00
2.2.5.93 Fresno, cream, grey KW- A M2 82,300.00 90,530.00
2.2.5.94 Salsa, cream, grey KW- A M2 82,300.00 90,530.00

14
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.5.95 Sicillia, grey KW- A M2 82,300.00 90,530.00
2.2.5.96 Sonata, brown KW- A M2 82,300.00 90,530.00
2.2.5.97 Strata, cream, grey KW- A M2 82,300.00 90,530.00
2.2.5.98 Tequila, cream, white KW- A M2 82,300.00 90,530.00
2.2.5.99 Tosca, cream, white KW- A M2 82,300.00 90,530.00
2.2.5.100 Tudor, cream, white KW- A M2 82,300.00 90,530.00
2.2.5.101 Teakwood, beige, brown, latte KW- A M2 82,300.00 90,530.00
2.2.5.102 Warna Tua 20 x 20 M2 37,500.00 41,250.00
2.2.5.103 Warna Muda 20 x 20 M2 35,000.00 38,500.00
2.2.5.104 Warna Putih 30 x 30 M2 31,500.00 34,650.00
2.2.5.105 Warna Marble 30 x 30 M2 36,000.00 39,600.00
2.2.5.106 Warna Fancy 30 x 30 M2 40,500.00 44,550.00
2.2.5.107 Warna Putih 40 x 40 M2 37,500.00 41,250.00
2.2.5.108 Warna Marble 40 x 40 M2 42,500.00 46,750.00
2.2.5.109 Warna Tua 20 x 20 M2 37,500.00 41,250.00
2.2.5.110 Warna Muda 20 x 20 M2 35,000.00 38,500.00
2.2.5.111 Warna Putih 30 x 30 M2 31,500.00 34,650.00
2.2.5.112 Warna Marble 30 x 30 M2 36,000.00 39,600.00
2.2.5.113 Warna Impresso 30 x 30 M2 40,000.00 44,000.00
2.2.5.114 Pure Color 50 x 50 M2 94,500.00 103,950.00
2.2.5.115 Classy Color 50 x 50 M2 103,000.00 113,300.00
2.2.5.116 Fancy Color 50 x 50 M2 113,500.00 124,850.00
2.2.5.117 Accent Color 50 x 50 M2 186,000.00 204,600.00
2.2.5.118 Pure Color 25 x 50 M2 79,500.00 87,450.00
2.2.5.119 Classy Color 25 x 50 M2 86,000.00 94,600.00
2.2.5.120 Fancy Color 25 x 50 M2 97,500.00 107,250.00
2.2.5.121 Accent Color 25 x 50 M2 171,000.00 188,100.00
2.2.5.122 Pure Color 25 x 25 M2 73,000.00 80,300.00
2.2.5.123 Classy Color 25 x 25 M2 79,000.00 86,900.00
2.2.5.124 Fancy Color 25 x 25 M2 91,000.00 100,100.00
2.2.5.125 Accent Color 25 x 25 M2 163,500.00 179,850.00
2.2.5.126 Putih 40 x 40 M2 50,500.00 55,550.00
2.2.5.127 Median 40 x 40 M2 52,000.00 57,200.00
2.2.5.128 Gelap 40 x 40 M2 54,500.00 59,950.00
2.2.5.129 Rustic 33 x 33 M2 45,000.00 49,500.00
2.2.5.130 Rustic 40 x 40 M2 46,250.00 50,875.00
2.2.5.131 Supermilan 25 x 33 - Golongan A M2 56,500.00 62,150.00
2.2.5.132 Supermilan 25 x 33 - Golongan B M2 58,000.00 63,800.00
2.2.5.133 Supermilan 40 x 40 - Putih M2 50,500.00 55,550.00
2.2.5.134 Supermilan 40 x 40 - Median M2 54,000.00 59,400.00
2.2.5.135 Supermilan 40 x 40 - Gelap M2 55,000.00 60,500.00
2.2.5.136 Supermilan 50 x 50 - Putih M2 73,500.00 80,850.00
2.2.5.137 Keramik Dinding Hercules - Gelap 40 x 40 M2 48,750.00 53,625.00

15
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.5.138 Keramik Dinding Hercules - Motif Khusus 40 x 40 M2 43,150.00 47,465.00
2.2.5.139 Keramik Dinding Hercules - Putih 40 x 40 M2 39,850.00 43,835.00
2.2.5.140 Keramik Dinding Hercules - Motif Dasar Putih 40 x 40 M2 45,500.00 50,050.00
2.2.5.141 Keramik Dinding Hercules - Motif Dasar Gelap 40 x 40 M2 46,500.00 51,150.00
2.2.5.142 Keramik Dinding Galaxy black, brown, cream, grey, white KW- A M2 39,500.00 43,450.00
2.2.5.143 Keramik Dinding Petra cream, terracota KW- A M2 39,500.00 43,450.00
2.2.5.144 Keramik Dinding Roxy black, blue, brown, green, grey, red KW- A M2 39,500.00 43,450.00
2.2.5.145 Keramik Dinding Alpha blue, green KW- A M2 42,000.00 46,200.00
2.2.5.146 Keramik Dinding Track brown, grey KW- A M2 44,500.00 48,950.00
2.2.5.147 Keramik Lantai platinum 30 x 30 Jungle red, green, grey, red KW- A M2 36,500.00 40,150.00
2.2.5.148 Keramik Lantai platinum 30 x 30 Capri brown, grey KW- A M2 37,000.00 40,700.00
2.2.5.149 Keramik Lantai platinum 30 x 30 Marble brown KW- A M2 38,000.00 41,800.00
2.2.5.150 Keramik Lantai platinum 30 x 30 Newton brown, green, grey KW- A M2 38,000.00 41,800.00
2.2.5.151 Keramik Lantai platinum 30 x 30 Mahoni brown, cream KW- A M2 39,000.00 42,900.00
2.2.5.152 Keramik Lantai platinum 30 x 30 Cargo, brown, grey, dark brown, dark gr M2 46,000.00 50,600.00
2.2.5.153 Keramik Lantai platinum 30 x 30 Clarin, bone, brown, grey KW- A M2 46,000.00 50,600.00
2.2.5.154 Keramik Lantai platinum 30 x 30 Cordon, bone, brown, cream KW- A M2 46,000.00 50,600.00
2.2.5.155 Keramik Lantai platinum 30 x 30 Bintan, bone, brown, cream KW- A M2 47,500.00 52,250.00
2.2.5.156 Keramik Lantai platinum 50 x 50 Ecco grey, brown KW- A M2 70,000.00 77,000.00
2.2.5.157 Keramik Lantai platinum 50 x 50 Gobi cream, grey KW- A M2 70,000.00 77,000.00
2.2.5.158 Keramik Lantai platinum 60 x 60 Cavalli, cream, white KW- A M2 82,300.00 90,530.00
2.2.5.159 Keramik Lantai platinum 60 x 60 Fredo, cream, grey KW- A M2 82,300.00 90,530.00
2.2.5.160 Keramik Lantai platinum 60 x 60 Fresno, cream, grey KW- A M2 82,300.00 90,530.00
2.2.5.161 Keramik Lantai platinum 60 x 60 Salsa, cream, grey KW- A M2 82,300.00 90,530.00
2.2.5.162 Keramik Lantai platinum 60 x 60 Sicillia, grey KW- A M2 82,300.00 90,530.00
2.2.5.163 Keramik Lantai platinum 60 x 60 Sonata, brown KW- A M2 82,300.00 90,530.00
2.2.5.164 Keramik Lantai platinum 60 x 60 Strata, cream, grey KW- A M2 82,300.00 90,530.00
2.2.5.165 Keramik Lantai platinum 60 x 60 Tequila, cream, white KW- A M2 82,300.00 90,530.00
2.2.5.166 Keramik Lantai platinum 60 x 60 Tosca, cream, white KW- A M2 82,300.00 90,530.00
2.2.5.167 Keramik Lantai platinum 60 x 60 Tudor, cream, white KW- A M2 82,300.00 90,530.00
2.2.5.168 Keramik Lantai platinum 60 x 60 Teakwood, beige, brown, latte KW- A M2 82,300.00 90,530.00
2.2.5.169 Keramik Lantai Arwana Warna Tua 20 x 20 M2 37,500.00 41,250.00
2.2.5.170 Keramik Lantai Arwana Warna Muda 20 x 20 M2 35,000.00 38,500.00
2.2.5.171 Keramik Lantai Arwana Warna Putih 30 x 30 M2 31,500.00 34,650.00
2.2.5.172 Keramik Lantai Arwana Warna Marble 30 x 30 M2 36,000.00 39,600.00
2.2.5.173 Keramik Lantai Arwana Warna Fancy 30 x 30 M2 40,500.00 44,550.00
2.2.5.174 Keramik Lantai Arwana Warna Putih 40 x 40 M2 37,500.00 41,250.00
2.2.5.175 Keramik Lantai Arwana Warna Marble 40 x 40 M2 42,500.00 46,750.00
2.2.5.176 Keramik Lantai Mulia Warna Tua 20 x 20 M2 38,500.00 42,350.00
2.2.5.177 Keramik Lantai Mulia Warna Muda 20 x 20 M2 36,000.00 39,600.00
2.2.5.178 Keramik Lantai Mulia Warna Putih 30 x 30 M2 32,500.00 35,750.00
2.2.5.179 Keramik Lantai Mulia Warna Marble 30 x 30 M2 37,000.00 40,700.00
2.2.5.180 Keramik Lantai Mulia Warna Impresso 30 x 30 M2 40,000.00 44,000.00

16
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.5.181 Keramik Lantai Milan Pure Color 50 x 50 M2 94,500.00 103,950.00
2.2.5.182 Keramik Lantai Milan Classy Color 50 x 50 M2 103,000.00 113,300.00
2.2.5.183 Keramik Lantai Milan Fancy Color 50 x 50 M2 113,500.00 124,850.00
2.2.5.184 Keramik Lantai Milan Accent Color 50 x 50 M2 186,000.00 204,600.00
2.2.5.185 Keramik Lantai Milan Pure Color 25 x 50 M2 79,500.00 87,450.00
2.2.5.186 Keramik Lantai Milan Classy Color 25 x 50 M2 86,000.00 94,600.00
2.2.5.187 Keramik Lantai Milan Fancy Color 25 x 50 M2 97,500.00 107,250.00
2.2.5.188 Keramik Lantai Milan Accent Color 25 x 50 M2 171,000.00 188,100.00
2.2.5.189 Keramik Lantai Milan Pure Color 25 x 25 M2 73,000.00 80,300.00
2.2.5.190 Keramik Lantai Milan Classy Color 25 x 25 M2 79,000.00 86,900.00
2.2.5.191 Keramik Lantai Milan Fancy Color 25 x 25 M2 91,000.00 100,100.00
2.2.5.192 Keramik Lantai Milan Accent Color 25 x 25 M2 163,500.00 179,850.00
2.2.5.193 Keramik Lantai Milan Putih 40 x 40 M2 50,500.00 55,550.00
2.2.5.194 Keramik Lantai Milan Median 40 x 40 M2 52,000.00 57,200.00
2.2.5.195 Keramik Lantai Milan Gelap 40 x 40 M2 54,500.00 59,950.00
2.2.5.196 Keramik Lantai Milan Rustic 33 x 33 M2 45,000.00 49,500.00
2.2.5.197 Keramik Lantai Milan Rustic 40 x 40 M2 46,250.00 50,875.00
2.2.5.198 Keramik Lantai Milan Supermilan 25 x 33 - Golongan A M2 56,500.00 62,150.00
2.2.5.199 Keramik Lantai Milan Supermilan 25 x 33 - Golongan B M2 58,000.00 63,800.00
2.2.5.200 Keramik Lantai Milan Supermilan 40 x 40 - Putih M2 50,500.00 55,550.00
2.2.5.201 Keramik Lantai Milan Supermilan 40 x 40 - Median M2 54,000.00 59,400.00
2.2.5.202 Keramik Lantai Milan Supermilan 40 x 40 - Gelap M2 55,000.00 60,500.00
2.2.5.203 Keramik Lantai Milan Supermilan 50 x 50 - Putih M2 73,500.00 80,850.00
2.2.5.204 Keramik Lantai Hercules - Gelap 40 x 40 M2 48,750.00 53,625.00
2.2.5.205 Keramik Lantai Hercules - Motif Khusus 40 x 40 M2 43,150.00 47,465.00
2.2.5.206 Keramik Lantai Hercules - Putih 40 x 40 M2 39,850.00 43,835.00
2.2.5.207 Keramik Lantai Hercules - Motif Dasar Putih 40 x 40 M2 45,500.00 50,050.00
2.2.5.208 Keramik Lantai Hercules - Motif Dasar Gelap 40 x 40 M2 46,500.00 51,150.00
2.2.5.209 Keramik Lantai Roman 20 x 20 Golongan A M2 87,000.00 95,700.00
2.2.5.210 Keramik Lantai Roman 20 x 20 Golongan B M2 90,000.00 99,000.00
2.2.5.211 Keramik Lantai Roman 20 x 20 Golongan D M2 100,000.00 110,000.00
2.2.5.212 Keramik Lantai Roman 30 x 30 Golongan B M2 87,000.00 95,700.00
2.2.5.213 Keramik Lantai Roman 30 x 30 Golongan C M2 91,000.00 100,100.00
2.2.5.214 Keramik Lantai Roman 33.3 x 33.3 Golongan A M2 97,000.00 106,700.00
2.2.5.215 Keramik Lantai Roman 33.3 x 33.3 Golongan C M2 137,500.00 151,250.00
2.2.5.216 Keramik Lantai Roman 40 x 40 Golongan A M2 97,000.00 106,700.00
2.2.5.217 Keramik Lantai Roman 40 x 40 Golongan B M2 105,000.00 115,500.00
2.2.5.218 Keramik Lantai Roman 40 x 40 Golongan C M2 107,000.00 117,700.00
2.2.5.219 Keramik Lantai Roman 40 x 40 Golongan D M2 112,000.00 123,200.00
2.2.5.220 Keramik Lantai Roman 45 x 45 Golongan A M2 107,000.00 117,700.00
2.2.5.221 Keramik Lantai Roman 45 x 45 Golongan B M2 113,000.00 124,300.00
2.2.5.222 Keramik Lantai Roman 45 x 45 Golongan E M2 150,000.00 165,000.00
2.2.5.223 Keramik Lantai Roman 50 x 50 Golongan A M2 123,500.00 135,850.00

17
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.5.224 Keramik Lantai Roman 50 x 50 Golongan B M2 132,500.00 145,750.00
2.2.5.225 Keramik Lantai Roman 50 x 50 Golongan C M2 150,500.00 165,550.00
2.2.5.226 Keramik Lantai Roman 60 x 60 Golongan A M2 155,000.00 170,500.00
2.2.5.227 Keramik Lantai Roman 60 x 60 Golongan B M2 175,000.00 192,500.00
2.2.5.228 Keramik Lantai Roman 60 x 60 Golongan C M2 200,000.00 220,000.00
2.2.5.229 Keramik Lantai Roman 16.5 x 66.6 Golongan A M2 192,000.00 211,200.00
2.2.5.230 Keramik Lantai Roman 33.3 x 66.6 Golongan A M2 172,000.00 189,200.00
2.2.5.231 Keramik Lantai Roman 33.3 x 66.6 Golongan B M2 193,000.00 212,300.00
2.2.5.232 Keramik Lantai Roman 33.3 x 66.6 Golongan C M2 212,500.00 233,750.00
2.2.5.233 Keramik Lantai Roman 8 x 30 Hospital Skirting M2 474,000.00 521,400.00
2.2.5.234 Keramik Lantai Roman 10 x 20 Step Nosing M2 515,000.00 566,500.00
2.2.5.235 Keramik Lantai Asia 20 x 20 Zeus grey, white, brown M2 48,000.00 52,800.00
2.2.5.236 Keramik Lantai Asia 20 x 20 Zion grey, white M2 48,000.00 52,800.00
2.2.5.237 Keramik Lantai Asia 20 x 20 Alpha blue, black, cream, green M2 50,000.00 55,000.00
2.2.5.238 Keramik Lantai Asia 20 x 20 Galaxy black, brown, cream M2 50,000.00 55,000.00
2.2.5.239 Keramik Lantai Asia 20 x 20 Oscar black, cream, wite M2 50,000.00 55,000.00
2.2.5.240 Keramik motif Uk. 30 cm x 30 cm M2 52,600.00 57,860.00
2.2.5.241 Keramik motif Uk. 40 cm x 40 cm M2 57,200.00 62,920.00
2.2.5.242 Keramik motif Uk. 50 cm x 50 cm M2 63,600.00 69,960.00
2.2.5.243 Keramik putih Uk. 30 cm x 30 cm M2 47,400.00 52,140.00
2.2.5.244 Keramik putih Uk. 40cm x 40 cm M2 54,300.00 59,730.00
2.2.5.245 Keramik Roman Uk. 20 X 20 cm M2 96,300.00 105,930.00
2.2.5.246 Keramik Roman Uk. 30 X 30 cm M2 99,000.00 108,900.00
2.2.5.247 Keramik Roman Uk. 40 X 40 cm M2 117,700.00 129,470.00
2.2.5.248 Keramik Roman Uk. 50 X 50 cm M2 165,600.00 182,160.00
2.2.5.249 Keramik Roman Uk. 60 X 60 cm M2 170,500.00 187,550.00
2.2.5.250 Keramik tekstur cutting Uk. 31cm x 63 cm M2 123,600.00 135,960.00
2.2.5.251 Keramik tekstur Uk. 20cm x 20 cm M2 50,800.00 55,880.00
2.2.5.252 Keramik tekstur Uk. 30cm x 30 cm M2 50,300.00 55,330.00
2.2.5.253 Keramik Uk. 20Cm x 20Cm M2 50,800.00 55,880.00
2.2.5.254 Keramik warna muda Uk. 20 X 20 cm M2 52,800.00 58,080.00
2.2.5.255 Keramik warna tua Uk. 20 X 20 cm M2 54,500.00 59,950.00
2.2.5.256 Laminate Florring Ex. Belgium + Foam sheet M2 213,100.00 234,410.00
2.2.5.257 Laminate Florring Ex. China + Foam sheet M2 156,000.00 171,600.00
2.2.5.258 Laminate Florring Ex. Germany + Foam sheet M2 630,100.00 693,110.00
2.2.5.259 Laminate Florring Lokal + Foam sheet M2 236,200.00 259,820.00
2.2.5.260 List Keramik (10x20)cm Bh 17,400.00 19,140.00
2.2.5.261 Marmer bakar M2 109,100.00 120,010.00
2.2.5.262 Marmer Hitam M2 112,600.00 123,860.00
2.2.5.263 Marmer Putih M2 189,400.00 208,340.00
2.2.5.264 Marmer Slab lebar (1.80 x 2.40) m M2 352,300.00 387,530.00
2.2.5.265 Ornamen 30 x 30 cm Bh 73,900.00 81,290.00
2.2.5.266 Papan Peredam Suara 120 x 60 x 5 cm Bh 121,000.00 133,100.00

18
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.5.267 Paving Stone (12x12) 5 warna tebal 6 cm M2 77,000.00 84,700.00
2.2.5.268 Paving Stone abu - abu t= 8 cm, K225 M2 80,300.00 88,330.00
2.2.5.269 Paving Stone abu - abu t= 6 cm, K225 M2 67,100.00 73,810.00
2.2.5.270 Paving Stone abu - abu t= 6 cm, K300 M2 77,000.00 84,700.00
2.2.5.271 Paving Stone abu - abu t= 6 cm, K400 M2 72,600.00 79,860.00
2.2.5.272 Paving Stone abu - abu t= 8 cm, K300 M2 93,500.00 102,850.00
2.2.5.273 Paving Stone abu - abu t= 8 cm, K350 M2 99,000.00 108,900.00
2.2.5.274 Paving Stone abu - abu t= 8 cm, K400 M2 110,000.00 121,000.00
2.2.5.275 Paving Stone abu - abu t= 6 cm M2 60,500.00 66,550.00
2.2.5.276 Paving Stone abu - abu t= 8 cm M2 73,700.00 81,070.00
2.2.5.277 Paving Stone segi 6 abu - abu t= 6 cm M2 55,000.00 60,500.00
2.2.5.278 Paving Stone segi 6 abu - abu t= 8 cm M2 60,500.00 66,550.00
2.2.5.279 Paving Stone segi 6 merah t= 6 cm M2 57,200.00 62,920.00
2.2.5.280 Paving Stone segi 6 merah t= 8 cm M2 71,500.00 78,650.00
2.2.5.281 Paving Stone warna t= 6 cm, K225 bh 71,500.00 78,650.00
2.2.5.282 Paving Stone warna t= 8 cm, K225 Bh 88,000.00 96,800.00
2.2.5.283 Plint Keramik / kuku macan Bh 1,100.00 1,210.00
2.2.5.284 Rooster Batu Alam Uk. 20 x 20 cm Bh 57,200.00 62,920.00
2.2.5.285 Rooster Batu Alam Uk. 30 x 30 cm Bh 71,100.00 78,210.00
2.2.5.286 Rooster Beton Uk. 10 x 30 cm Bh 22,000.00 24,200.00
2.2.5.287 Rooster Beton Uk. 20 x 20 cm M2 22,000.00 24,200.00
2.2.5.288 Rooster Lokal Bata Merah Uk. 20 x 20 cm M2 19,700.00 21,670.00
2.2.5.289 Ubin Abu-abu Uk. 20Cm x 20Cm M2 30,600.00 33,660.00
2.2.5.290 Ubin Teraso Uk 30 Cm x 30 Cm M2 52,600.00 57,860.00
2.2.5.291 Ubin Wafel Uk 20Cm x 20Cm Bh 44,400.00 48,840.00
2.2.5.292 Wallpaper Classic m2 16,300.00 17,930.00
2.2.5.293 Wallpaper Minimalis m2 22,005.00 24,205.50
2.2.5.294 Wallpaper Korea m2 60,200.00 66,220.00
2.2.5.295 Wallpaper ( standart ) m2 7,500.00 8,250.00
2.2.5.296 Wallpaper Sticker m2 90,000.00 99,000.00
2.2.5.297 Wallpaper Smart Wall ukuran 0.53m x 10.00m m2 70,000.00 77,000.00
2.2.5.298 Wallpaper Grand City ukuran 0.53m x 10.00m m2 261,750.00 287,925.00
2.2.5.299 Wallpaper Dream World ukuran 1.06m x 15.60m roll 673,500.00 740,850.00
2.2.5.300 Wallpaper Jade 3d Image ukuran 0.53m x 10.00m roll 216,000.00 237,600.00
2.2.5.301 Wallpaper Clear Spirit ukuran 0.53m x 10.00m roll 328,500.00 361,350.00
2.2.5.302 Wallpaper Modern Wallcoverings ukuran 0.53m x 10.00m roll 216,000.00 237,600.00
2.2.5.303 Wallpaper Jack & Ros ukuran 0.53m x 10.00m roll 268,500.00 295,350.00
2.2.5.304 Wallpaper Daon Vol 3 ukuran 1.06m x 15.60m roll 591,000.00 650,100.00
2.2.5.305 Wallpaper Silk House ukuran 1.06m x 15.60m roll 637,500.00 701,250.00
2.2.5.306 Wallpaper Polaris Vol 3 ukuran 1.06m x 15.60m roll 600,500.00 660,550.00
2.2.5.307 Wallpaper Zinnia ukuran 1.06m x 15.60m roll 735,000.00 808,500.00
2.2.5.308 Wallpaper Kahn Design ukuran 1.06m x 15.60m roll 426,000.00 468,600.00
- -

19
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.6 BAHAN PENGECATAN & BAHAN CAIR LAINNYA : - -
2.2.6.1 Air bersih Lt 100.00 110.00
2.2.6.2 Aquaproof Kg 69,300.00 76,230.00
2.2.6.3 Cat besi Kg 59,500.00 65,450.00
2.2.6.4 Cat genteng Kg 52,000.00 57,200.00
2.2.6.5 Cat termoplastik Kg 89,000.00 97,900.00
2.2.6.6 Cat Dasar Kayu Kg 30,600.00 33,660.00
2.2.6.7 Cat Dasar wheathershield Kg 61,800.00 67,980.00
2.2.6.8 Cat Kayu Kg 64,100.00 70,510.00
2.2.6.9 Cat Marka Kg 89,000.00 97,900.00
2.2.6.10 Cat Meny besi Kg 30,000.00 33,000.00
2.2.6.11 Cat Meny kayu Kg 27,200.00 29,920.00
2.2.6.12 Cat Tembok Kg 24,300.00 26,730.00
2.2.6.13 Cat Tembok exterior wheathershield Kg 121,300.00 133,430.00
2.2.6.14 Cat Tembok interior premium Kg 54,900.00 60,390.00
2.2.6.15 Cat Untuk Pekerjaan Baja Jembatan Kg 57,800.00 63,580.00
2.2.6.16 Clear melamin impra dof / gloos Kg 63,600.00 69,960.00
2.2.6.17 Coatting Ltr 75,100.00 82,610.00
2.2.6.18 Dempul Kayu Kg 32,300.00 35,530.00
2.2.6.19 HCL / air keras Ltr 12,100.00 13,310.00
2.2.6.20 Kalsium Kg 1,800.00 1,980.00
2.2.6.21 Kertas gosok ( rempelas ) Lbr 3,500.00 3,850.00
2.2.6.22 Kuas 3 " Bj 15,100.00 16,610.00
2.2.6.23 Kuas 4 " Bj 20,200.00 22,220.00
2.2.6.24 Lem ( Kayu + Tembok ) Bh 13,900.00 15,290.00
2.2.6.25 Lem PVC Tube 8,100.00 8,910.00
2.2.6.26 Meni besi Kg 34,700.00 38,170.00
2.2.6.27 Minyak bekisting Ltr 5,800.00 6,380.00
2.2.6.28 Minyak Cat / Thiner A Ltr 30,000.00 33,000.00
2.2.6.29 Minyak Cat / Thiner B Ltr 16,200.00 17,820.00
2.2.6.30 Minyak Pelumas Ltr 37,500.00 41,250.00
2.2.6.31 Minyak Tanah Ltr 12,700.00 13,970.00
2.2.6.32 Oli Gardan Ltr 40,500.00 44,550.00
2.2.6.33 Oli rem Ltr 75,100.00 82,610.00
2.2.6.34 Oli Hidrolis Ltr 30,000.00 33,000.00
2.2.6.35 Oli Presneleng Ltr 40,500.00 44,550.00
2.2.6.36 Paint Stone Zak 427,400.00 470,140.00
2.2.6.37 Plamur kayu Kg 27,200.00 29,920.00
2.2.6.38 Plamur Tembok Kg 15,600.00 17,160.00
2.2.6.39 Politur jadi Ltr 55,400.00 60,940.00
2.2.6.40 Residu ( Ter ) Ltr 5,800.00 6,380.00
2.2.6.41 Rol kuas Bh 17,400.00 19,140.00
2.2.6.42 Sabun Kg 11,600.00 12,760.00

20
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.6.43 Sending impra ( melamine) Kg 67,000.00 73,700.00
2.2.6.44 Soda api Kg 17,400.00 19,140.00
2.2.6.45 Spiritus Ltr 16,200.00 17,820.00
2.2.6.46 Stempet / Gemuk Kg 34,700.00 38,170.00
2.2.6.47 Teak oil Ltr 8,100.00 8,910.00
2.2.6.48 Vernis Ltr 40,500.00 44,550.00
2.2.6.49 Vet Pkt 57,800.00 63,580.00
2.2.6.50 Water prooffing Kg 75,100.00 82,610.00
2.2.6.51 Wood filler impra ( dempul jati ) Kg 37,000.00 40,700.00
2.2.6.52 Wood stain impra ( Pewarna melamine) Kg 69,300.00 76,230.00
- -
2.2.7 BAHAN PENGGANTUNG DAN PENGUNCI : - -
2.2.7.1 Door Closer ex. Beluci Bh 216,600.00 238,260.00
2.2.7.2 Door Stoper Stainless Bh 50,300.00 55,330.00
2.2.7.3 Engsel pintu kupu - kupu Bh 41,000.00 45,100.00
2.2.7.4 Engsel Jendela ( H ) Bh 16,700.00 18,370.00
2.2.7.5 Engsel Jendela (Arch ) Bh 17,400.00 19,140.00
2.2.7.6 Engsel jendela (kupu-kupu) 3" Bh 20,200.00 22,220.00
2.2.7.7 Engsel jendela ex. Union 3" Bh 35,900.00 39,490.00
2.2.7.8 Engsel kuningan Arc Asli ex. Elitech 4" Set 79,100.00 87,010.00
2.2.7.9 Engsel Pintu ( H ) Bh 14,400.00 15,840.00
2.2.7.10 Engsel Pintu (Arch ) nylon Bh 9,800.00 10,780.00
2.2.7.11 Engsel pintu ex. Union 4" Bh 47,400.00 52,140.00
2.2.7.12 Engsel sendok Bh 12,100.00 13,310.00
2.2.7.13 Engsel Stainlesstel Dekson 3" (GOMPO ) Bh 16,700.00 18,370.00
2.2.7.14 Engsel Stainlesstel Dekson 4" (GOMPO ) Bh 20,200.00 22,220.00
2.2.7.15 Engsel Stainlesstel Dekson 5" (GOMPO ) Bh 26,000.00 28,600.00
2.2.7.16 Grendel biasa (Besar) 8" (GOMPO ) Bh 17,400.00 19,140.00
2.2.7.17 Grendel biasa (Kecil) 3" Bh 6,900.00 7,590.00
2.2.7.18 Engsel Stainlesstel Dekson 3" 304 Bh 68,200.00 75,020.00
2.2.7.19 Engsel Stainlesstel Dekson 3" Bh 53,100.00 58,410.00
2.2.7.20 Engsel Stainlesstel Dekson 4" Bh 124,700.00 137,170.00
2.2.7.21 Engsel Stainlesstel Dekson 5" Bh 142,700.00 156,970.00
2.2.7.22 Grendel biasa (Besar) 8" Bh 14,400.00 15,840.00
2.2.7.23 Grendel biasa (Kecil) 3" Bh 6,900.00 7,590.00
2.2.7.24 Grendel ex. AEG Bh 32,300.00 35,530.00
2.2.7.25 Grendel jendela merk SES Bh 23,700.00 26,070.00
2.2.7.26 Grendel Pintu Panjang ( sespen ) Bh 52,000.00 57,200.00
2.2.7.27 Grendel pintu ganda Dekson 40 cm komplit Bh 184,800.00 203,280.00
2.2.7.28 Grendel Tanam Kuningan Besar ex. Cavel 60mm Set 268,000.00 294,800.00
2.2.7.29 Grendel Tanam Kuningan Besar ex. Cavel 10mm Set 80,900.00 88,990.00
2.2.7.30 Grendel Tanam Kuningan Kecil ex. Beluci 4" Bh 156,000.00 171,600.00
2.2.7.31 Grendel tanam merk SES Set 41,000.00 45,100.00

21
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.7.32 Hak Angin Set 17,400.00 19,140.00
2.2.7.33 Hak angin (Sikutan) biasa Set 21,300.00 23,430.00
2.2.7.34 Hak angin 4mm Lurus/plat 4x150mm Bh 18,500.00 20,350.00
2.2.7.35 Hak angin lurus Bh 36,400.00 40,040.00
2.2.7.36 Hak angin Merk SES Set 33,600.00 36,960.00
2.2.7.37 Handle Bh 84,400.00 92,840.00
2.2.7.38 Handle pintu ganda Dekson 30 cm komplit Set 114,400.00 125,840.00
2.2.7.39 Handle pintu ganda Dekson 40 cm komplit Set 270,300.00 297,330.00
2.2.7.40 Handle pintu stanless steel besar Psg 510,500.00 561,550.00
2.2.7.41 Handle pintu stanless steel kecil Bh 201,000.00 221,100.00
2.2.7.42 Kunci gembok besar stainless 40mm Bh 32,900.00 36,190.00
2.2.7.43 Kunci gembok sedang stainless 30mm Bh 35,200.00 38,720.00
2.2.7.44 Kunci laci (088) Bh 15,100.00 16,610.00
2.2.7.45 Kunci lemari Bh 14,400.00 15,840.00
2.2.7.46 Kunci Slot 2 Putaran ex.CAVEL (dengan handle) Bh 209,700.00 230,670.00
2.2.7.47 Kunci Slot 2 Putaran ex.Kodai Bh 107,500.00 118,250.00
2.2.7.48 Kunci Slot 2 Putaran ex.YALE (dengan handle) Bh 123,600.00 135,960.00
2.2.7.49 Kunci Slot Tanam Kamar Mandi ex.Miller Bh 72,800.00 80,080.00
2.2.7.50 Kunci tanam merk SES ( pelor ) Bh 217,100.00 238,810.00
2.2.7.51 Kunci Tanam Pintu Antik ex. Miler Bh 236,800.00 260,480.00
2.2.7.52 Kunci tanam Slot ex.Kuda (2x Putaran) Bh 70,500.00 77,550.00
2.2.7.53 Pegangan pintu handle Marmer Bh 113,200.00 124,520.00
2.2.7.54 Pegangan pintu handle Marmer Bh 113,200.00 124,520.00
2.2.7.55 Pegangan pintu P=20 Bh 69,900.00 76,890.00
2.2.7.56 Selot ( kunci pintu ) merk SES Bh 283,000.00 311,300.00
2.2.7.57 Selot Rossete Dekson Bh 314,700.00 346,170.00
2.2.7.58 Slot ( Kunci-kunci pintu ) lokal Bh 95,900.00 105,490.00
2.2.7.59 Slot Tanam Kamar Mandi Bh 138,600.00 152,460.00
- -
2.2.8 BAHAN SANITAIR : - -
2.2.8.1 Avor plastik / floor drain Bh 11,200.00 12,320.00
2.2.8.2 Avor staninlees steel Bh 47,400.00 52,140.00
2.2.8.3 Bak cuci traso M2 205,000.00 225,500.00
2.2.8.4 Bak Cuci Stainlesstel (Royal) Bh 253,000.00 278,300.00
2.2.8.5 Bak Kip Bh 1,991,200.00 2,190,320.00
2.2.8.6 Bak Mandi Fiber glass, 0.3 m3 Bh 186,600.00 205,260.00
2.2.8.7 Bak Mandi Fiber glass, 1.00 m x 1.00 m Bh 300,900.00 330,990.00
2.2.8.8 Bak Mandi teraso Bh 110,300.00 121,330.00
2.2.8.9 Bak mandi teraso volume 0.3 m3 Bh 182,500.00 200,750.00
2.2.8.10 Double Kran Dupon Bh 206,800.00 227,480.00
2.2.8.11 Kloset Duduk Keramik Bh 601,800.00 661,980.00
2.2.8.12 Kloset Duduk Keramik Komplit ex.AMSTAD Bh 2,086,500.00 2,295,150.00
2.2.8.13 Kloset Duduk Keramik Komplit ex.INA Bh 1,376,800.00 1,514,480.00

22
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.8.14 Kloset Duduk Keramik Komplit ex.TOTO Bh 2,673,200.00 2,940,520.00
2.2.8.15 Kloset Jongkok Keramik ex.AMSTAD Bh 237,900.00 261,690.00
2.2.8.16 Kloset Jongkok Keramik ex.INA Bh 142,700.00 156,970.00
2.2.8.17 Kloset Jongkok teraso Bh 140,900.00 154,990.00
2.2.8.18 Kloset Monoblok Lokal Bh 974,300.00 1,071,730.00
2.2.8.19 Knee drat dalam PVC AW Ø 0,5" Bh 2,300.00 2,530.00
2.2.8.20 Knee drat dalam PVC AW Ø 0,75" Bh 3,500.00 3,850.00
2.2.8.21 Knee PVC AW Ø 0,5" Bh 1,800.00 1,980.00
2.2.8.22 Knee PVC AW Ø 0,75" Bh 2,900.00 3,190.00
2.2.8.23 Knee PVC AW Ø 1" Bh 4,100.00 4,510.00
2.2.8.24 Knee PVC AW Ø 1,5" Bh 6,900.00 7,590.00
2.2.8.25 Knee PVC AW Ø 2" Bh 9,800.00 10,780.00
2.2.8.26 Knee PVC AW Ø 2,5" Bh 13,900.00 15,290.00
2.2.8.27 Knee PVC AW Ø 3" Bh 20,800.00 22,880.00
2.2.8.28 Knee PVC AW Ø 4" Bh 43,900.00 48,290.00
2.2.8.29 Kran cucian dia 3/4" Bh 75,700.00 83,270.00
2.2.8.30 Kran Dia 1/2 " Bh 27,700.00 30,470.00
2.2.8.31 Kran Dia 3/4 " Bh 32,900.00 36,190.00
2.2.8.32 Kran Dupon Bh 159,900.00 175,890.00
2.2.8.33 Kran Toto 1/2" Bh 306,700.00 337,370.00
2.2.8.34 Pipa kurasan plastik Bh 8,700.00 9,570.00
2.2.8.35 Pipa PVC Class B Ø 1,25" Mof (limbah) M' / bhn 18,000.00 19,800.00
2.2.8.36 Pipa PVC Class B Ø 1,5" Mof (limbah) M' / bhn 22,700.00 24,970.00
2.2.8.37 Pipa PVC Class B Ø 2" Mof (limbah) M' / bhn 29,500.00 32,450.00
2.2.8.38 Pipa PVC Class B Ø 2,5" Mof (limbah) M' / bhn 34,700.00 38,170.00
2.2.8.39 Pipa PVC Class B Ø 3" Mof (limbah) M' / bhn 44,600.00 49,060.00
2.2.8.40 Pipa PVC Class B Ø 4" Mof (limbah) M' / bhn 55,100.00 60,610.00
2.2.8.41 Pipa PVC Class B Ø 6" Mof (limbah) M' / bhn 95,500.00 105,050.00
2.2.8.42 Pipa PVC Class B Ø 8" Mof (limbah) M' / bhn 164,700.00 181,170.00
2.2.8.43 PVC AW Dia 0.5 " ( putih ) M' / bhn 3,100.00 3,410.00
2.2.8.44 PVC AW Dia 0.75 " ( putih ) M' / bhn 4,100.00 4,510.00
2.2.8.45 PVC AW Dia 1 " ( putih ) M' / bhn 5,800.00 6,380.00
2.2.8.46 PVC AW Dia 1,25 " ( putih ) M' / bhn 8,100.00 8,910.00
2.2.8.47 PVC AW Dia 1,5 " ( putih ) M' / bhn 9,800.00 10,780.00
2.2.8.48 PVC AW Dia 2 " ( putih ) M' / bhn 12,800.00 14,080.00
2.2.8.49 PVC AW Dia 2 ,5" ( putih ) M' / bhn 21,300.00 23,430.00
2.2.8.50 PVC AW Dia 3 " ( putih ) M' / bhn 25,400.00 27,940.00
2.2.8.51 PVC AW Dia 4 " ( putih ) M' / bhn 42,100.00 46,310.00
2.2.8.52 PVC AW Dia 5 " ( putih ) M' / bhn 67,000.00 73,700.00
2.2.8.53 PVC AW Dia 6 " ( putih ) M' / bhn 93,600.00 102,960.00
2.2.8.54 PVC AW Dia 8 " ( putih ) M' / bhn 145,500.00 160,050.00
2.2.8.55 PVC AW Dia 10 " ( putih ) M' / bhn 230,500.00 253,550.00
2.2.8.56 PVC AW Dia 12 " ( putih ) M' / bhn 329,200.00 362,120.00

23
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.8.57 PVC AW Dia 0.5 " ( abu - abu ) M' / bhn 2,900.00 3,190.00
2.2.8.58 PVC AW Dia 0.75 " ( abu - abu ) M' / bhn 8,700.00 9,570.00
2.2.8.59 PVC AW Dia 1 " ( abu - abu ) M' / bhn 11,000.00 12,100.00
2.2.8.60 PVC AW Dia 1,25 " ( abu - abu ) M' / bhn 14,400.00 15,840.00
2.2.8.61 PVC AW Dia 1,5 " ( abu - abu ) M' / bhn 17,400.00 19,140.00
2.2.8.62 PVC AW Dia 2 " ( abu - abu ) M' / bhn 20,200.00 22,220.00
2.2.8.63 PVC AW Dia 2 ,5" ( abu - abu ) M' / bhn 28,900.00 31,790.00
2.2.8.64 PVC AW Dia 3 " ( abu - abu ) M' / bhn 34,700.00 38,170.00
2.2.8.65 PVC AW Dia 4 " ( abu - abu ) M' / bhn 52,000.00 57,200.00
2.2.8.66 PVC AW Dia 5 " ( abu - abu ) M' / bhn 84,400.00 92,840.00
2.2.8.67 PVC AW Dia 6 " ( abu - abu ) M' / bhn 114,400.00 125,840.00
2.2.8.68 PVC AW Dia 8 " ( abu - abu ) M' / bhn 184,800.00 203,280.00
2.2.8.69 PVC AW Dia 10 " ( abu - abu ) M' / bhn 285,900.00 314,490.00
2.2.8.70 PVC AW Dia 12 " ( abu - abu ) M' / bhn 351,700.00 386,870.00
2.2.8.71 PVC AW Dia 14 " ( abu - abu ) M' / bhn 512,300.00 563,530.00
2.2.8.72 PVC AW Dia 16 " ( abu - abu ) M' / bhn 618,500.00 680,350.00
2.2.8.73 PVC (Class C) Dia 1.5 " M' / bhn 11,100.00 12,210.00
2.2.8.74 PVC (Class C) Dia 2 " M' / bhn 13,200.00 14,520.00
2.2.8.75 PVC (Class C) Dia 2.5 " M' / bhn 17,600.00 19,360.00
2.2.8.76 PVC (Class C) Dia 3 " M' / bhn 23,000.00 25,300.00
2.2.8.77 PVC (Class C) Dia 4 " M' / bhn 32,100.00 35,310.00
2.2.8.78 PVC (Class D) Dia 1.25 " ( putih ) M' / bhn 5,200.00 5,720.00
2.2.8.79 PVC (Class D) Dia 1.5 " ( putih ) M' / bhn 6,400.00 7,040.00
2.2.8.80 PVC (Class D) Dia 2 " ( putih ) M' / bhn 17,400.00 19,140.00
2.2.8.81 PVC (Class D) Dia 2.5 " ( putih ) M' / bhn 20,200.00 22,220.00
2.2.8.82 PVC (Class D) Dia 3 " ( putih ) M' / bhn 28,900.00 31,790.00
2.2.8.83 PVC (Class D) Dia 4 " ( putih ) M' / bhn 40,500.00 44,550.00
2.2.8.84 PVC (Class D) Dia 5 " ( putih ) M' / bhn 43,300.00 47,630.00
2.2.8.85 PVC (Class D) Dia 6 " ( putih ) M' / bhn 59,000.00 64,900.00
2.2.8.86 PVC (Class D) Dia 8 " ( putih ) M' / bhn 83,200.00 91,520.00
2.2.8.87 PVC (Class D) Dia 10 " ( putih ) M' / bhn 132,200.00 145,420.00
2.2.8.88 PVC (Class D) Dia 12 " ( putih ) M' / bhn 192,900.00 212,190.00
2.2.8.89 PVC (Class D) Dia 1.25 " ( abu - abu ) M' / bhn 6,900.00 7,590.00
2.2.8.90 PVC (Class D) Dia 1.5 " ( abu - abu ) M' / bhn 7,500.00 8,250.00
2.2.8.91 PVC (Class D) Dia 2 " ( abu - abu ) M' / bhn 14,700.00 16,170.00
2.2.8.92 PVC (Class D) Dia 2.5 " ( abu - abu ) M' / bhn 21,000.00 23,100.00
2.2.8.93 PVC (Class D) Dia 3 " ( abu - abu ) M' / bhn 31,500.00 34,650.00
2.2.8.94 PVC (Class D) Dia 4 " ( abu - abu ) M' / bhn 42,500.00 46,750.00
2.2.8.95 PVC (Class D) Dia 5 " ( abu - abu ) M' / bhn 69,300.00 76,230.00
2.2.8.96 PVC (Class D) Dia 6 " ( abu - abu ) M' / bhn 91,000.00 100,100.00
2.2.8.97 PVC (Class D) Dia 8 " ( abu - abu ) M' / bhn 147,300.00 162,030.00
2.2.8.98 PVC (Class D) Dia 10 " ( abu - abu ) M' / bhn 175,000.00 192,500.00
2.2.8.99 PVC (Class D) Dia 12 " ( abu - abu ) M' / bhn 241,500.00 265,650.00

24
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.8.100 PVC (Class D) Dia 14 " ( abu - abu ) M' / bhn 315,900.00 347,490.00
2.2.8.101 PVC (Class D) Dia 16 " ( abu - abu ) M' / bhn 408,900.00 449,790.00
2.2.8.102 PVC (Class D) Dia 20 " ( abu - abu ) M' / bhn 705,800.00 776,380.00
2.2.8.103 Shock drat dalam PVC AW Ø 0,5" Bh 2,300.00 2,530.00
2.2.8.104 Shock drat dalam PVC AW Ø 0,75" Bh 3,500.00 3,850.00
2.2.8.105 Shock PVC AW Ø 0,5" Bh 1,200.00 1,320.00
2.2.8.106 Shock PVC AW Ø 0,75" Bh 2,300.00 2,530.00
2.2.8.107 Shock PVC AW Ø 1" Bh 3,500.00 3,850.00
2.2.8.108 Shock PVC AW Ø 1,5" Bh 4,600.00 5,060.00
2.2.8.109 Shock PVC AW Ø 2" Bh 6,900.00 7,590.00
2.2.8.110 Shock PVC AW Ø 2,5" Bh 9,800.00 10,780.00
2.2.8.111 Shock PVC AW Ø 3" Bh 16,200.00 17,820.00
2.2.8.112 Shock PVC AW Ø 4" Bh 28,900.00 31,790.00
2.2.8.113 Shower Dupon Set 209,000.00 229,900.00
2.2.8.114 Slang Spiral Saluran Pembuangan Bak Cuci Bh 25,400.00 27,940.00
2.2.8.115 Seal Tape Bh 23,100.00 25,410.00
2.2.8.116 Stop Kran Dia 1 " Bh 23,700.00 26,070.00
2.2.8.117 Stop Kran Dia 1/2 " Bh 31,200.00 34,320.00
2.2.8.118 Stop Kran Dia 3/4 " Bh 20,200.00 22,220.00
2.2.8.119 Stop kran dia 1" kuningan Bh 80,900.00 88,990.00
2.2.8.120 Stop kran dia 1" plastik Bh 20,800.00 22,880.00
2.2.8.121 Stop kran dia 1/2" kuningan Bh 76,800.00 84,480.00
2.2.8.122 Stop kran dia 3/4" kuningan Bh 59,500.00 65,450.00
2.2.8.123 Stop Kran Ǿ 1/2" Bh 26,000.00 28,600.00
2.2.8.124 Tandon Air fiberglass ex.Grand Kap.1.100 Ltr (Profil Tank) Bh 1,430,000.00 1,573,000.00
2.2.8.125 Tandon Air Fiberglass ex.Grand Kap.800 Ltr (Profil Tank) Bh 1,155,000.00 1,270,500.00
2.2.8.126 Tandon air stainlees steel kap. 1.000 ltr Bh 3,135,000.00 3,448,500.00
2.2.8.127 Tandon air stainlees steel kap. 550 ltr Bh 1,815,000.00 1,996,500.00
2.2.8.128 Tee PVC AW Ø 0,5" Bh 2,300.00 2,530.00
2.2.8.129 Tee PVC AW Ø 0,75" Bh 3,500.00 3,850.00
2.2.8.130 Tee PVC AW Ø 1" Bh 5,800.00 6,380.00
2.2.8.131 Tee PVC AW Ø 1,5" Bh 8,100.00 8,910.00
2.2.8.132 Tee PVC AW Ø 2" Bh 9,200.00 10,120.00
2.2.8.133 Tee PVC AW Ø 2,5" Bh 16,200.00 17,820.00
2.2.8.134 Tee PVC AW Ø 3" Bh 23,100.00 25,410.00
2.2.8.135 Tee PVC AW Ø 4" Bh 46,200.00 50,820.00
2.2.8.136 Tempat Sabun Keramik ex.INA Bh 31,200.00 34,320.00
2.2.8.137 Urinoir Bh 1,148,100.00 1,262,910.00
2.2.8.138 Wastafel Besar Warna Muda ex.INA Bh 269,500.00 296,450.00
2.2.8.139 Wastafel Besar Warna Tua ex.INA Kg 298,700.00 328,570.00
2.2.8.140 Wiremesh M7 Uk. (2,1x5.4) m - 12,800.00 14,080.00
- -
2.2.9 BAHAN JENIS KACA : - -

25
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.9.1 Cutting Stiker M2 157,600.00 173,360.00
2.2.9.2 Glass bird Kg 49,700.00 54,670.00
2.2.9.3 Glass Block Bening (20x20)cm Bh 22,600.00 24,860.00
2.2.9.4 Glass Block Buram (20x20)cm Bh 23,700.00 26,070.00
2.2.9.5 Kaca air 5 Cm M2 94,700.00 104,170.00
2.2.9.6 Kaca bluegreen t=8mm M2 752,000.00 827,200.00
2.2.9.7 Kaca patry M2 2,505,800.00 2,756,380.00
2.2.9.8 Kaca Bening t= 3 mm M2 62,900.00 69,190.00
2.2.9.9 Kaca Bening t= 5 mm M2 106,300.00 116,930.00
2.2.9.10 Kaca Bening t= 7 mm M2 150,700.00 165,770.00
2.2.9.11 Kaca Bening t= 10 mm M2 231,000.00 254,100.00
2.2.9.12 Kaca Buram t=3mm M2 112,600.00 123,860.00
2.2.9.13 Kaca Cermin t=3mm M2 126,000.00 138,600.00
2.2.9.14 Kaca Cermin t=5mm M2 144,400.00 158,840.00
2.2.9.15 Kaca Es t=3mm M2 115,500.00 127,050.00
2.2.9.16 Kaca profil (Bevel / moulding) M' 7,500.00 8,250.00
2.2.9.17 Kaca Ray-band t= 5 mm M2 113,200.00 124,520.00
2.2.9.18 Kaca Ray-band t= 7 mm M2 176,100.00 193,710.00
2.2.9.19 Kaca Ray-band t= 10 mm M2 369,600.00 406,560.00
2.2.9.20 Kaca Stained Glass M2 1,253,200.00 1,378,520.00
2.2.9.21 Kaca clear tempered t = 5 mm M2 231,000.00 254,100.00
2.2.9.22 Kaca clear tempered t = 6 mm M2 288,800.00 317,680.00
2.2.9.23 Kaca clear tempered t = 8 mm M2 433,200.00 476,520.00
2.2.9.24 Kaca clear tempered t = 10 mm M2 462,000.00 508,200.00
2.2.9.25 Kaca clear tempered t = 12 mm M2 519,800.00 571,780.00
2.2.9.26 Kaca clear tempered t = 15 mm M2 2,252,300.00 2,477,530.00
2.2.9.27 Kaca clear tempered t = 19 mm M2 2,829,800.00 3,112,780.00
2.2.9.28 Kaca Warna t - 5 mm M2 109,800.00 120,780.00
2.2.9.29 Naco (Kerangka dan Daun ) M2 264,600.00 291,060.00
2.2.9.30 Sealant Tube 19,000.00 20,900.00
- -
2.2.10 BAHAN BETON CETAKAN : - -
2.2.10.1 Box culvert BC. 80.80.120.11 cm (gandar 10T) unit 3,476,000.00 3,823,600.00
2.2.10.2 Box culvert BC. 80.80.120.11 cm (gandar 20T) unit 3,624,500.00 3,986,950.00
2.2.10.3 Box culvert BC. 100.100.120.12,5 cm (gandar 10T) unit 3,911,600.00 4,302,760.00
2.2.10.4 Box culvert BC. 100.100.120.12,5 cm (gandar 20T) unit 4,614,500.00 5,075,950.00
2.2.10.5 Box culvert BC. 150.150.120.20 cm (gandar 10T) unit 6,505,400.00 7,155,940.00
2.2.10.6 Box culvert BC. 150.150.120.20 cm (gandar 20T) unit 8,572,300.00 9,429,530.00
2.2.10.7 Box culvert BC. 200.2000.120.20 cm (gandar 10T) unit 9,606,300.00 10,566,930.00
2.2.10.8 Box culvert BC. 200.2000.120.20 cm (gandar 20T) unit 10,759,100.00 11,835,010.00
2.2.10.9 Tiang pancang 20.20 (k.500) m' 132,000.00 145,200.00
2.2.10.10 Tiang pancang 25.25 (k.500) m' 165,000.00 181,500.00
2.2.10.11 Buis Beton 1/2 ø 20 Cm M' 40,500.00 44,550.00

26
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.10.12 Buis Beton 1/2 ø 30 Cm M' 60,100.00 66,110.00
2.2.10.13 Buis Beton 1/2 ø 40 Cm M' 63,600.00 69,960.00
2.2.10.14 Buis Beton ø 100 Cm M' 404,300.00 444,730.00
2.2.10.15 Buis Beton ø 20 Cm M' 63,600.00 69,960.00
2.2.10.16 Buis Beton ø 30 Cm M' 86,700.00 95,370.00
2.2.10.17 Buis Beton ø 40 Cm M' 115,500.00 127,050.00
2.2.10.18 Buis Beton ø 50 Cm M' 173,300.00 190,630.00
2.2.10.19 Buis Beton ø 60 Cm M' 184,800.00 203,280.00
2.2.10.20 Buis Beton ø 80 Cm M' 231,000.00 254,100.00
2.2.10.21 Concrete Block 20 Bh 57,200.00 62,920.00
2.2.10.22 Concrete Block 15 Bh 46,800.00 51,480.00
2.2.10.23 Concrete Block 10 Bh 35,200.00 38,720.00
2.2.10.24 CU - ditch 30.8.120 cm G. 10T Unit 257,000.00 282,700.00
2.2.10.25 CU - ditch 40.12.120 cm G. 10T Unit 381,200.00 419,320.00
2.2.10.26 CU - ditch 60.12.120 cm G. 10T Unit 531,300.00 584,430.00
2.2.10.27 CU - ditch 30.40.120.5 cm G. 10T Unit 467,800.00 514,580.00
2.2.10.28 CU - ditch 40.50.120.6 cm G. 10T Unit 652,600.00 717,860.00
2.2.10.29 CU - ditch 60.70.120.8 cm G. 10T Unit 1,155,000.00 1,270,500.00
2.2.10.30 Hollow Block 20 Bh 79,100.00 87,010.00
2.2.10.31 Hollow Block 15 Bh 56,700.00 62,370.00
2.2.10.32 Hollow Block 10 Bh 35,200.00 38,720.00
2.2.10.33 Kanstin (K225) uk. 40x20x10 cm Bh 34,700.00 38,170.00
2.2.10.34 Kanstin (K225) uk. 40x20x15 cm Bh 41,600.00 45,760.00
2.2.10.35 Pasang tiang listrik cor beton Titik 8,250,000.00 9,075,000.00
2.2.10.36 U-DITCH (300X300X1200)mm, berat = 160 Kg unit 442,900.00 487,190.00
2.2.10.37 U-DITCH (300X400X1200)mm, berat = 190 Kg unit 515,500.00 567,050.00
2.2.10.38 U-DITCH (300X500X1200)mm, berat = 220 Kg unit 589,500.00 648,450.00
2.2.10.39 U-DITCH (400X400X1200)mm, berat = 250 Kg unit 646,100.00 710,710.00
2.2.10.40 U-DITCH (400X500X1200)mm, berat = 270 Kg unit 736,200.00 809,820.00
2.2.10.41 U-DITCH (400X600X1200)mm, berat = 320 Kg unit 804,400.00 884,840.00
2.2.10.42 U-DITCH (500X500X1200)mm, berat = 380 Kg unit 872,700.00 959,970.00
2.2.10.43 U-DITCH (500X600X1200)mm, berat = 420 Kg unit 962,700.00 1,058,970.00
2.2.10.44 U-DITCH (600X600X1200)mm, berat = 480 Kg unit 1,030,900.00 1,133,990.00
2.2.10.45 U-DITCH (600X700X1200)mm, berat = 500 Kg unit 1,122,400.00 1,234,640.00
2.2.10.46 U-DITCH (600X800X1200)mm, berat = 550 Kg unit 1,224,000.00 1,346,400.00
2.2.10.47 U-DITCH (800X800X1200)mm, berat = 730 Kg unit 1,264,700.00 1,391,170.00
2.2.10.48 U-DITCH (800X900X1200)mm, berat = 890 Kg unit 1,332,900.00 1,466,190.00
2.2.10.49 U-DITCH (800X1000X1200)mm, berat = 950 Kg unit 1,710,500.00 1,881,550.00
2.2.10.50 U-DITCH (800X1200X1200)mm, berat = 1100 Kg unit 1,937,000.00 2,130,700.00
2.2.10.51 U-DITCH (1000X1000X1200)mm, berat = 1250 Kg unit 2,831,400.00 3,114,540.00
2.2.10.52 U-DITCH (1000X1200X1200)mm, berat = 1450 Kg unit 3,092,800.00 3,402,080.00
2.2.10.53 U-DITCH (1200X1200X1200)mm, berat = 1650 Kg unit 3,454,300.00 3,799,730.00
2.2.10.54 U-DITCH (1200X1400X1200)mm, berat = 1800 Kg unit 3,704,100.00 4,074,510.00

27
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.10.55 U-DITCH (1500X1500X1200)mm, berat = 2950 Kg unit 5,810,900.00 6,391,990.00
2.2.10.56 U-DITCH (1500X1600X1200)mm, berat = 3050 Kg unit 6,014,200.00 6,615,620.00
2.2.10.57 U-DITCH (1500X1700X1200)mm, berat = 3150 Kg unit 6,285,700.00 6,914,270.00
2.2.10.58 U-DITCH (1800X1800X1200)mm, berat = 3500 Kg unit 6,920,200.00 7,612,220.00
2.2.10.59 U-DITCH (1800X1900X1200)mm, berat = 3600 Kg unit 7,170,000.00 7,887,000.00
2.2.10.60 U-DITCH (1800X2000X1200)mm, berat = 3700 Kg unit 7,418,300.00 8,160,130.00
2.2.10.61 U-DITCH (2000X2000X1200)mm, berat = 3900 Kg unit 7,713,000.00 8,484,300.00
2.2.10.62 U-DITCH (2000X2100X1200)mm, berat = 4000 Kg unit 7,984,500.00 8,782,950.00
2.2.10.63 U-DITCH (2000X2200X1200)mm, berat = 4100 Kg unit 8,234,300.00 9,057,730.00
2.2.10.64 Tutup U-DITCH 300-60/1200 mm, Berat = 75Kg Gandar = 5 ton/m' unit 273,000.00 300,300.00
2.2.10.65 Tutup U-DITCH 400-80/1200 mm, Berat = 120Kg Gandar = 5 ton/m' unit 339,800.00 373,780.00
2.2.10.66 Tutup U-DITCH 500-80/1200 mm, Berat = 130Kg Gandar = 5 ton/m' unit 431,200.00 474,320.00
2.2.10.67 Tutup U-DITCH 600-100/1200 mm, Berat = 250Kg Gandar = 5 ton/m' unit 509,700.00 560,670.00
2.2.10.68 Tutup U-DITCH 800-100/1200 mm, Berat = 290Kg Gandar = 5 ton/m' unit 714,400.00 785,840.00
2.2.10.69 Tutup U-DITCH 1000-120/1200 mm, Berat = 470Kg Gandar = 5 ton/m' unit 906,000.00 996,600.00
2.2.10.70 Tutup U-DITCH 1200-120/1200 mm, Berat = 520Kg Gandar = 5 ton/m' unit 1,292,300.00 1,421,530.00
2.2.10.71 Tutup U-DITCH 1500-150/1200 mm, Berat = 820Kg Gandar = 5 ton/m' unit 2,016,800.00 2,218,480.00
2.2.10.72 Tutup U-DITCH 1800-150/1200 mm, Berat = 950Kg Gandar = 5 ton/m' unit 2,604,900.00 2,865,390.00
2.2.10.73 Tutup U-DITCH 2000-150/1200 mm, Berat = 1050Kg Gandar = 5 ton/m' unit 2,831,400.00 3,114,540.00
2.2.10.74 Tutup U-DITCH 300-100/1200 mm, Berat = 120Kg Gandar = 10 ton/m' unit 381,900.00 420,090.00
2.2.10.75 Tutup U-DITCH 400-110/1200 mm, Berat = 170Kg Gandar = 10 ton/m' unit 577,900.00 635,690.00
2.2.10.76 Tutup U-DITCH 500-110/1200 mm, Berat = 210Kg Gandar = 10 ton/m' unit 679,500.00 747,450.00
2.2.10.77 Tutup U-DITCH 600-150/1200 mm, Berat = 330Kg Gandar = 10 ton/m' unit 884,300.00 972,730.00
2.2.10.78 Tutup U-DITCH 800-150/1200 mm, Berat = 420Kg Gandar = 10 ton/m' unit 1,065,800.00 1,172,380.00
2.2.10.79 Tutup U-DITCH 1000-150/1200 mm, Berat = 600Kg Gandar = 10 ton/m' unit 1,529,000.00 1,681,900.00
2.2.10.80 Tutup U-DITCH 1200-150/1200 mm, Berat = 630Kg Gandar = 10 ton/m' unit 1,982,000.00 2,180,200.00
2.2.10.81 Tutup U-DITCH 1500-200/1200 mm, Berat = 1100Kg Gandar = 10 ton/m' unit 2,718,100.00 2,989,910.00
2.2.10.82 Tutup U-DITCH 1800-200/1200 mm, Berat = 1300Kg Gandar = 10 ton/m' unit 3,126,200.00 3,438,820.00
2.2.10.83 Tutup U-DITCH 2000-200/1200 mm, Berat = 1400Kg Gandar = 10 ton/m' unit 3,397,700.00 3,737,470.00
2.2.10.84 BC 80.80.120.11 cm Gandar = 10 ton unit 2,851,200.00 3,136,320.00
2.2.10.85 BC 100.100.120.12,5 cm Gandar = 10 ton unit 3,373,900.00 3,711,290.00
2.2.10.86 BC 150.150.120.20 cm Gandar = 10 ton unit 7,806,500.00 8,587,150.00
2.2.10.87 BC 200.200.120.20 cm Gandar = 10 ton unit 10,207,600.00 11,228,360.00
2.2.10.88 BC 80.80.120.11 cm Gandar = 20 ton unit 3,029,400.00 3,332,340.00
2.2.10.89 BC 100.100.120.12,5 cm Gandar = 20 ton unit 4,217,400.00 4,639,140.00
2.2.10.90 BC 150.150.120.20 cm Gandar = 20 ton unit 8,966,800.00 9,863,480.00
2.2.10.91 BC 200.200.120.20 cm Gandar = 20 ton unit 11,590,900.00 12,749,990.00
- -
2.2.11 BAHAN PIPA - -
2.2.11.1 POMPA AIR MINUM - -
2.11.1.1.1 Pompa GRUNDFOS, Type CM 10-3 Unit 13,503,600.00 14,853,960.00
2.11.1.1.2 Panel 2,2 KW/3x380Volt/Single WLC Unit 8,385,300.00 9,223,830.00
2.11.1.1.3 Pompa GRUNDFOS, Type CM 10-2 Unit 9,111,300.00 10,022,430.00

28
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.11.1.1.4 Panel 2,2 KW/3x380Volt/Single WLC Unit 8,385,300.00 9,223,830.00
2.11.1.1.5 Pompa GRUNDFOS, Type CR 20-17, 18,5 KW Unit 123,662,000.00 136,028,200.00
2.11.1.1.6 Panel 18,5 KW/3x380Volt/Single WLC Unit 11,313,500.00 12,444,850.00
2.11.1.1.7 Pompa GRUNDFOS, Type CR 15-14, 11 KW Unit 84,733,000.00 93,206,300.00
2.11.1.1.8 Panel 11 KW/3x380Volt/Single WLC Unit 11,313,500.00 12,444,850.00
2.11.1.1.9 Pompa GRUNDFOS, Type CR 10-22, 7,5 KW Unit 58,140,500.00 63,954,550.00
2.11.1.1.10 Panel 7,5 KW/3x380Volt/Single WLC Unit 9,982,500.00 10,980,750.00
2.11.1.1.11 Pompa GRUNDFOS, Type CR 5-20, 3 KW Unit 29,306,200.00 32,236,820.00
2.11.1.1.12 Panel 3 KW/3x380Volt/Single WLC Unit 8,385,300.00 9,223,830.00
2.11.1.1.13 Pompa GRUNDFOS, Type CR 10-9, 3 KW Unit 31,060,700.00 34,166,770.00
2.11.1.1.14 Panel 3 KW/3x380Volt/Single WLC Unit 8,385,300.00 9,223,830.00
2.11.1.1.15 Pompa GRUNDFOS, Type SP 17-37, 22 KW Unit 185,735,000.00 204,308,500.00
2.11.1.1.16 Panel 22 KW/3x380Volt/Single WLC Unit 12,644,500.00 13,908,950.00
2.11.1.1.17 Pompa GRUNDFOS, Type SP 8A-37, 5,5 KW Unit 70,990,700.00 78,089,770.00
2.11.1.1.18 Panel 5,5 KW/3x380Volt/Single WLC Unit 8,651,500.00 9,516,650.00
2.11.1.1.19 Pompa GRUNDFOS, Type SP 5A-33, 3 KW Unit 33,121,000.00 36,433,100.00
2.11.1.1.20 Panel 3 KW/3x380Volt/Single WLC Unit 8,385,300.00 9,223,830.00
2.11.1.1.21 Pompa JD Basic 5 Unit 7,235,800.00 7,959,380.00
2.11.1.1.22 Pompa GRUNDFOS, Type CR 10-16, 5,5 KW Unit 50,927,300.00 56,020,030.00
2.11.1.1.23 Panel Pompa > 10 KW Unit 9,847,200.00 10,831,920.00
2.11.1.1.24 Panel Pompa < 10 KW Unit 10,551,200.00 11,606,320.00
2.11.1.1.25 Pompa GRUNDFOS, Type CR 15-17, 15 KW Unit 88,400,000.00 88,400,000.00
2.11.1.1.26 Panel 15 KW start Delta Unit 13,000,000.00 13,000,000.00
2.11.1.1.27 Pompa GRUNDFOS, Type CR 45-12, 15 KW Unit 240,400,000.00 240,400,000.00
2.11.1.1.28 Panel 45 KW start Delta Unit 14,000,000.00 14,000,000.00
- -
2.2.11.2 PIPA AIR MINUM - -
2.2.11.2.1 Pipa GI Med. Ø 0,5" (SNI 0039:2013) M' 22,900.00 25,190.00
2.2.11.2.2 Pipa GI Med. Ø 0,75" (SNI 0039:2013) M' 29,400.00 32,340.00
2.2.11.2.3 Pipa GI Med. Ø 1" (SNI 0039:2013) M' 45,000.00 49,500.00
2.2.11.2.4 Pipa GI Med. Ø 1,5" (SNI 0039:2013) M' 68,200.00 75,020.00
2.2.11.2.5 Pipa GI Med. Ø 2" (SNI 0039:2013) M' 93,100.00 102,410.00
2.2.11.2.6 Pipa GI Med. Ø 2,5" (SNI 0039:2013) M' 118,800.00 130,680.00
2.2.11.2.7 Pipa GI Med. Ø 3" (SNI 0039:2013) M' 153,500.00 168,850.00
2.2.11.2.8 Pipa GI Med. Ø 4" (SNI 0039:2013) M' 222,100.00 244,310.00
2.2.11.2.9 Pipa PN-10 Diameter 1" (Pipa PE) M' 12,000.00 13,200.00
2.2.11.2.10 Pipa PN-10 Diameter 1,5" (Pipa PE) M' 25,000.00 27,500.00
2.2.11.2.11 Pipa PN-10 Diameter 2" (Pipa PE) M' 39,900.00 43,890.00
2.2.11.2.12 Pipa PN-10 Diameter 2,5" (Pipa PE) M' 54,900.00 60,390.00
2.2.11.2.13 Pipa PN-10 Diameter 3" (Pipa PE) M' 79,000.00 86,900.00
2.2.11.2.14 Pipa PN-10 Diameter 4" (Pipa PE) M' 118,000.00 129,800.00
2.2.11.2.15 Pipa PN-10 Diameter 6" (Pipa PE) M' 247,200.00 271,920.00
2.2.11.2.16 PVC. Diameter 0,5" (S 12,5) (MOF) M' 2,600.00 2,860.00

29
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.11.2.17 PVC. Diameter 0,75" (S 12,5) (MOF) M' 4,100.00 4,510.00
2.2.11.2.18 PVC. Diameter 1" (S 12,5) (MOF) M' 6,400.00 7,040.00
2.2.11.2.19 PVC. Diameter 1,25" (S 12,5) (MOF) M' 9,800.00 10,780.00
2.2.11.2.20 PVC. Diameter 1,5" (S 12,5) (MOF) M' 15,000.00 16,500.00
2.2.11.2.21 PVC. Diameter 2" (S 12,5) (RR) M' 24,400.00 26,840.00
2.2.11.2.22 PVC. Diameter 2,5" (S 12,5) (RR) M' 34,500.00 37,950.00
2.2.11.2.23 PVC. Diameter 3" (S 12,5) (RR) M' 48,300.00 53,130.00
2.2.11.2.24 PVC. Diameter 4" (S 12,5) (RR) M' 70,700.00 77,770.00
2.2.11.2.25 PVC. Diameter 6" (S 12,5) (RR) M' 148,200.00 163,020.00
2.2.11.2.26 PVC. Diameter 8" (S 12,5) (RR) M' 239,400.00 263,340.00
2.2.11.2.27 Pipa HDPE s-12,5 diameter 2" (pipa PE) M' 19,400.00 21,340.00
2.2.11.2.28 Pipa HDPE s-12,5 diameter 2,5" (pipa PE) M' 27,500.00 30,250.00
2.2.11.2.29 Pipa HDPE s-12,5 diameter 3" (pipa PE) M' 39,800.00 43,780.00
- -
2.2.11.3 ACEESORIES PIPA AIR MINUM - -
2.2.11.3.1 Ball Valve Ǿ 2" Bh 71,800.00 78,980.00
2.2.11.3.2 Bend All Flange 22.5 GI Ǿ 2" Bh 339,200.00 373,120.00
2.2.11.3.3 Bend All Flange 22.5 GI Ǿ 2,5" Bh 498,800.00 548,680.00
2.2.11.3.4 Bend All Flange 22.5 GI Ǿ 3" Bh 428,100.00 470,910.00
2.2.11.3.5 Bend All Flange 22.5 GI Ǿ 4" Bh 504,000.00 554,400.00
2.2.11.3.6 Bend All Flange 45 Ǿ 2" Bh 362,300.00 398,530.00
2.2.11.3.7 Bend All Flange 45 Ǿ 2,5" Bh 395,200.00 434,720.00
2.2.11.3.8 Bend All Flange 45 Ǿ 3" Bh 428,100.00 470,910.00
2.2.11.3.9 Bend All Flange 45 Ǿ 4" Bh 553,400.00 608,740.00
2.2.11.3.10 Bend All Flange 90 Ǿ 2" Bh 345,800.00 380,380.00
2.2.11.3.11 Bend All Flange 90 Ǿ 2,5" Bh 444,600.00 489,060.00
2.2.11.3.12 Bend All Flange 90 Ǿ 3" Bh 543,400.00 597,740.00
2.2.11.3.13 Bend All Flange 90 Ǿ 4" Bh 625,900.00 688,490.00
2.2.11.3.14 Bend GI. Ǿ 2" Bh 38,600.00 42,460.00
2.2.11.3.15 Bend GI. Ǿ 2,5" Bh 72,200.00 79,420.00
2.2.11.3.16 Bend GI. Ǿ 3" Bh 109,400.00 120,340.00
2.2.11.3.17 Bend GI. Ǿ 4" Bh 195,900.00 215,490.00
2.2.11.3.18 Bend PVC All Socket 45 Ǿ 2" Bh 115,900.00 127,490.00
2.2.11.3.19 Bend PVC All Socket 45 Ǿ 2,5" Bh 143,600.00 157,960.00
2.2.11.3.20 Bend PVC All Socket 45 Ǿ 3" Bh 173,300.00 190,630.00
2.2.11.3.21 Bend PVC All Socket 45 Ǿ 4" Bh 252,600.00 277,860.00
2.2.11.3.22 Bend PVC All Socket 90 Ǿ 1,5" Bh 72,800.00 75,000.00
2.2.11.3.23 Bend PVC All Socket 90 Ǿ 2" Bh 128,600.00 141,460.00
2.2.11.3.24 Bend PVC All Socket 90 Ǿ 2,5" Bh 157,300.00 173,030.00
2.2.11.3.25 Bend PVC All Socket 90 Ǿ 3" Bh 202,100.00 222,310.00
2.2.11.3.26 Bend PVC All Socket 90 Ǿ 4" Bh 281,300.00 309,430.00
2.2.11.3.27 Bend PVC 45 Ǿ 1,5" Bh 62,200.00 68,420.00
2.2.11.3.28 Bend PVC 90 Ǿ 2" Bh 83,700.00 92,070.00

30
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.11.3.29 Chek Valve Ǿ 2" Bh 643,500.00 707,850.00
2.2.11.3.30 Chek Valve Ǿ 2,5" Bh 1,260,200.00 1,386,220.00
2.2.11.3.31 Chek Valve Ǿ 3" Bh 1,876,900.00 2,064,590.00
2.2.11.3.32 Chek Valve Ǿ 4" Bh 2,681,300.00 2,949,430.00
2.2.11.3.33 Clam Sadle Ǿ 1 1/2" x 1/2" Bh 42,200.00 46,420.00
2.2.11.3.34 Clam Sadle Ǿ 1 1/2" x 3/4" Bh 48,300.00 53,130.00
2.2.11.3.35 Clam Sadle Ǿ 2" x 1/2" Bh 50,600.00 55,660.00
2.2.11.3.36 Clam Sadle Ǿ 2" x 3/4" Bh 62,000.00 68,200.00
2.2.11.3.37 Clam Sadle Ǿ 3" x 1/2" Bh 65,200.00 71,720.00
2.2.11.3.38 Clam Sadle Ǿ 3" x 3/4" Bh 93,200.00 102,520.00
2.2.11.3.39 Clam Sadle Ǿ 4" x 1/2" Bh 98,100.00 107,910.00
2.2.11.3.40 Clam Sadle Ǿ 4" x 3/4" Bh 142,800.00 157,080.00
2.2.11.3.41 Coupler / Join Ǿ 2,5" Bh 311,200.00 342,320.00
2.2.11.3.42 Coupler / Join Ǿ 3" Bh 395,600.00 435,160.00
2.2.11.3.43 Dobel Neple GI Ǿ 1/2" Bh 5,700.00 6,270.00
2.2.11.3.44 Dobel Neple Ǿ 1" Bh 10,300.00 11,330.00
2.2.11.3.45 Dobel Neple Ǿ 1,25" Bh 14,300.00 15,730.00
2.2.11.3.46 Dobel Neple Ǿ 1,5" Bh 21,000.00 23,100.00
2.2.11.3.47 Dobel Neple Ǿ 2" Bh 29,000.00 31,900.00
2.2.11.3.48 Dobel Neple Ǿ 2,5" Bh 48,300.00 53,130.00
2.2.11.3.49 Doble Neple Ǿ 3" Bh 82,000.00 90,200.00
2.2.11.3.50 Dobel Neple Ǿ 4" Bh 130,400.00 143,440.00
2.2.11.3.51 Dop GI dia 1" Bh 8,800.00 9,680.00
2.2.11.3.52 Dop GI dia 1.5" Bh 17,200.00 18,920.00
2.2.11.3.53 Dop GI dia 2" Bh 236,500.00 260,150.00
2.2.11.3.54 Dop GI dia 2.5" Bh 48,300.00 53,130.00
2.2.11.3.55 Dop GI dia 3" Bh 67,000.00 73,700.00
2.2.11.3.56 Dop GI dia 4" Bh 111,800.00 122,980.00
2.2.11.3.57 Dop PVC Ø 1,5'' Bh 28,700.00 31,570.00
2.2.11.3.58 Dop PVC dia 2" RRJ Bh 29,700.00 32,670.00
2.2.11.3.59 Dop PVC dia 2.5" RRJ Bh 40,500.00 44,550.00
2.2.11.3.60 Dop PVC dia 3" RRJ Bh 47,500.00 52,250.00
2.2.11.3.61 Dop PVC dia 4" RRJ Bh 79,400.00 87,340.00
2.2.11.3.62 Dop PVC dia 1" Moof Bh 6,600.00 7,260.00
2.2.11.3.63 Dop PVC dia 1,5" Moof Bh 18,200.00 20,020.00
2.2.11.3.64 Dop PVC dia 2" Moof Bh 29,700.00 32,670.00
2.2.11.3.65 Dop PVC dia 2,5" Moof Bh 40,500.00 44,550.00
2.2.11.3.66 Dop PVC dia 3" Moof Bh 36,500.00 40,150.00
2.2.11.3.67 Dop PVC dia 4" Moof Bh 79,400.00 87,340.00
2.2.11.3.68 Equal Elbow Coupling Ø 2,5'' Bh 368,200.00 405,020.00
2.2.11.3.69 Equal Elbow Coupling Ø Ø 3'' Bh 471,400.00 518,540.00
2.2.11.3.70 Flange Drat GI Dia 2" Bh 22,900.00 25,190.00
2.2.11.3.71 Flange Drat GI Dia 2,5" Bh 80,100.00 88,110.00

31
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.11.3.72 Flange Drat GI Dia 3" Bh 98,700.00 108,570.00
2.2.11.3.73 Flange Drat GI Dia 4" Bh 120,100.00 132,110.00
2.2.11.3.74 Flange Las Dia 2" Bh 55,600.00 61,160.00
2.2.11.3.75 Flange Las Dia 2,5" Bh 91,500.00 100,650.00
2.2.11.3.76 Flange Las Dia 3" Bh 83,200.00 91,520.00
2.2.11.3.77 Flange Las Dia 4" Bh 94,800.00 104,280.00
2.2.11.3.78 Flange Socket Ǿ 2" Bh 217,600.00 239,360.00
2.2.11.3.79 Flange Socket Ǿ 2,5" Bh 268,600.00 295,460.00
2.2.11.3.80 Flange Socket Ǿ 3" Bh 319,600.00 351,560.00
2.2.11.3.81 Flange Socket Ǿ 4" Bh 388,100.00 426,910.00
2.2.11.3.82 Gate Valve GI Ǿ 2" Bh 760,100.00 836,110.00
2.2.11.3.83 Gate Valve GI Ǿ 2,5" Bh 1,031,600.00 1,134,760.00
2.2.11.3.84 Gate Valve GI Ǿ 3" Bh 1,303,500.00 1,433,850.00
2.2.11.3.85 Gate Valve GI Ǿ 4" Bh 1,520,200.00 1,672,220.00
2.2.11.3.86 Gibol Joint Ǿ 2" Bh 175,000.00 180,000.00
2.2.11.3.87 Gibol Joint Ǿ 3" Bh 215,300.00 236,830.00
2.2.11.3.88 Gibol Joint Ǿ 4" Bh 225,000.00 410,000.00
2.2.11.3.89 Gibol Joint Ǿ 6" Bh 400,000.00 566,000.00
2.2.11.3.90 Gibol Joint Ǿ 8" Bh 550,000.00 400,000.00
2.2.11.3.91 Karet packing Ǿ 1,5" Bh 5,800.00 6,380.00
2.2.11.3.92 Karet packing Ǿ 2" Bh 6,900.00 7,590.00
2.2.11.3.93 Karet packing Ǿ 2,5" Bh 7,700.00 8,470.00
2.2.11.3.94 Karet packing Ǿ 3" Bh 8,600.00 9,460.00
2.2.11.3.95 Karet packing Ǿ 4" Bh 11,200.00 12,320.00
2.2.11.3.96 Knee drat GI Ǿ 1" Bh 13,000.00 14,300.00
2.2.11.3.97 Knee drat GI Ǿ 1,5" Bh 26,000.00 28,600.00
2.2.11.3.98 Knee drat GI Ǿ 2" Bh 40,800.00 44,880.00
2.2.11.3.99 Knee drat GI Ǿ 2,5" Bh 78,000.00 85,800.00
2.2.11.3.100 Knee drat GI Ǿ 3" Bh 119,100.00 131,010.00
2.2.11.3.101 Knee drat GI Ǿ 4" Bh 216,000.00 237,600.00
2.2.11.3.102 Knee PVC AW Ǿ 0,5" Bh 1,900.00 2,090.00
2.2.11.3.103 Knee drat dalam PVC AW Ǿ 0,5" Bh 2,400.00 2,640.00
2.2.11.3.104 Knee PVC Ǿ 1" Bh 6,500.00 7,150.00
2.2.11.3.105 Knee PVC Ǿ 1,5" Bh 14,300.00 15,730.00
2.2.11.3.106 Knee PVC Ǿ 2" Bh 22,600.00 24,860.00
2.2.11.3.107 Knee PVC Ǿ 2,5" Bh 37,300.00 41,030.00
2.2.11.3.108 Knee PVC Ǿ 3" Unit 59,300.00 65,230.00
2.2.11.3.109 Knee PVC Ǿ 4" Unit 141,100.00 155,210.00
2.2.11.3.110 Reducer GI Ǿ 1 - Ǿ 3/4 Unit 11,500.00 12,650.00
2.2.11.3.111 Reducer GI Ǿ 1,5 - Ǿ 1,25 Unit 19,700.00 21,670.00
2.2.11.3.112 Reducer GI Ǿ 1 1/4 - Ǿ 2 Unit 27,800.00 30,580.00
2.2.11.3.113 Reducer GI Ǿ 2 - Ǿ 1 Unit 26,500.00 29,150.00
2.2.11.3.114 Reducer GI Ǿ 2 - Ǿ 1,5 Bh 30,600.00 33,660.00

32
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.11.3.115 Reducer GI Ǿ 3 - Ǿ 2 Unit 79,900.00 87,890.00
2.2.11.3.116 Reducer GI Ǿ 4 - Ǿ 2 Bh 150,200.00 165,220.00
2.2.11.3.117 Reducer GI Ǿ 4 - Ǿ 3 Bh 156,900.00 172,590.00
2.2.11.3.118 Reducer PVC Ǿ 1,5" - 1" Bh 23,800.00 26,180.00
2.2.11.3.119 Reducer PVC Ǿ 2 x 1,5" Bh 34,600.00 38,060.00
2.2.11.3.120 Reducer PVC Ǿ 2,5 - 2" Bh 93,100.00 102,410.00
2.2.11.3.121 Reducer PVC Ǿ 3" - 2" Bh 183,600.00 201,960.00
2.2.11.3.122 Reducer PVC Ǿ 3" - 2,5" Bh 252,900.00 278,190.00
2.2.11.3.123 Reducer PVC Ǿ 4" - 3" Bh 306,000.00 336,600.00
2.2.11.3.124 Screen Ǿ 2" Bh 230,200.00 253,220.00
2.2.11.3.125 Screen Ǿ 3" Bh 684,200.00 752,620.00
2.2.11.3.126 Screen Ǿ 4" Bh 945,200.00 1,039,720.00
2.2.11.3.127 Single Air Valve Dia 1" Bh 312,800.00 344,080.00
2.2.11.3.128 Single Air Valve Dia 1,5" Bh 732,900.00 806,190.00
2.2.11.3.129 Single Air Valve Dia 2" Bh 1,152,800.00 1,268,080.00
2.2.11.3.130 Single Air Valve Dia 2,5" Bh 1,276,000.00 1,403,600.00
2.2.11.3.131 Single Air Valve Dia 3" Bh 1,399,800.00 1,539,780.00
2.2.11.3.132 Single Air Valve Dia 4" Bh 1,564,200.00 1,720,620.00
2.2.11.3.133 Sock Drat GI 1" Bh 11,000.00 12,100.00
2.2.11.3.134 Sock Drat GI 1,5 " Bh 19,400.00 21,340.00
2.2.11.3.135 Sock Drat GI 2 " Bh 29,700.00 32,670.00
2.2.11.3.136 Sock Drat GI 2,5 " Bh 55,900.00 61,490.00
2.2.11.3.137 Sock Drat GI 3" Bh 82,000.00 90,200.00
2.2.11.3.138 Sock Drat GI 4 " Bh 134,000.00 147,400.00
2.2.11.3.139 Scok Drat dalam PVC Ǿ 1,5 " Bh 4,800.00 5,280.00
2.2.11.3.140 Scok Drat luar Ǿ 1/2" Bh 4,800.00 5,280.00
2.2.11.3.141 Scok Drat luar PVC Ǿ 2" Bh 38,700.00 42,570.00
2.2.11.3.142 Stop Kran Ǿ 1" Bh 148,100.00 162,910.00
2.2.11.3.143 Stop Kran Ǿ 1,5 " Bh 345,700.00 380,270.00
2.2.11.3.144 Stop Kran Ǿ 2 " Bh 510,500.00 561,550.00
2.2.11.3.145 Stop Kran Ǿ 2,5 " Bh 942,900.00 1,037,190.00
2.2.11.3.146 Stop Kran Ǿ 3" Bh 1,375,600.00 1,513,160.00
2.2.11.3.147 Stop Kran Ǿ 4 " Bh 1,737,500.00 1,911,250.00
2.2.11.3.148 Stop Kran PVC Ǿ 3" Bh 215,300.00 236,830.00
2.2.11.3.149 Tee All Socket PVC RR Ǿ 2" x 2" Bh 242,000.00 266,200.00
2.2.11.3.150 Tee All Socket PVC RR Ǿ 3" x 2" Bh 350,400.00 385,440.00
2.2.11.3.151 Tee All Socket PVC RR Ǿ 3" x 3" Bh 398,800.00 438,680.00
2.2.11.3.152 Tee All Socket PVC RR Ǿ 4" x 2" Bh 538,700.00 592,570.00
2.2.11.3.153 Tee All Socket PVC RR Ǿ 4" x 3" Bh 601,000.00 661,100.00
2.2.11.3.154 Tee All Socket PVC RR Ǿ 4" x 4" Bh 660,800.00 726,880.00
2.2.11.3.155 Tee All Socket PVC Ǿ 8" x 3" Bh 1,178,800.00 1,213,650.00
2.2.11.3.156 Tee Drat GI Ǿ 1" Bh 24,600.00 27,060.00
2.2.11.3.157 Tee Drat GI Ǿ 1,5" Bh 47,200.00 51,920.00

33
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.11.3.158 Tee Drat GI Ǿ 2" Bh 70,600.00 77,660.00
2.2.11.3.159 Tee Drat GI Ǿ 2,5" Bh 161,200.00 177,320.00
2.2.11.3.160 Tee Drat GI Ǿ 3" Bh 211,800.00 232,980.00
2.2.11.3.161 Tee Drat GI Ǿ 4" Bh 383,200.00 421,520.00
2.2.11.3.162 Tee All Socket PVC Moof Ǿ 1,5" x Ǿ 1,5" Bh 32,300.00 35,530.00
2.2.11.3.163 Tee All Socket PVC Moof Ǿ 2" x Ǿ 1,5" Bh 53,600.00 58,960.00
2.2.11.3.164 Tee All Socket PVC Moof Ǿ 2" x Ǿ 2" Bh 181,000.00 199,100.00
2.2.11.3.165 Tee All Socket PVC Moof Ǿ 3" x Ǿ 2" Bh 188,500.00 207,350.00
2.2.11.3.166 Tee All Socket PVC Moof Ǿ 3" x Ǿ 3" Bh 224,700.00 247,170.00
2.2.11.3.167 Tee All Socket PVC Moof Ǿ 4" x Ǿ 2" Bh 298,900.00 328,790.00
2.2.11.3.168 Tee All Socket PVC Moof Ǿ 4" x Ǿ 3" Bh 350,000.00 385,000.00
2.2.11.3.169 Tee All Socket PVC Moof Ǿ 4" x Ǿ 4" Bh 370,600.00 407,660.00
2.2.11.3.170 Tee Y All Flange Ǿ 2" x 2" Bh 181,000.00 199,100.00
2.2.11.3.171 Tee Y All Flange Ǿ 3" x 2" Bh 188,500.00 207,350.00
2.2.11.3.172 Tee Y All Flange Ǿ 3" x 3" Bh 224,700.00 247,170.00
2.2.11.3.173 Tee Y All Flange Ǿ 4" x 2" Bh 298,900.00 328,790.00
2.2.11.3.174 Tee Y All Flange Ǿ 4" x 3" Bh 350,000.00 385,000.00
2.2.11.3.175 Tee Y All Flange Ǿ 4" x 4" Bh 370,600.00 407,660.00
2.2.11.3.176 Tee PVC Ǿ 1,5" x Ǿ 1,5" Bh 52,600.00 57,860.00
2.2.11.3.177 Tee PVC Ǿ 2" x Ǿ 1" Bh 57,400.00 63,140.00
2.2.11.3.178 Tee PVC Ǿ 2" x Ǿ 1,5" Bh 62,200.00 68,420.00
2.2.11.3.179 Tee PVC Ǿ 3" x Ǿ 1,5" Bh 71,800.00 78,980.00
2.2.11.3.180 Tee PVC Ǿ 3" x Ǿ 2" Bh 76,500.00 84,150.00
2.2.11.3.181 Tee PVC Ǿ 2" x Ǿ 2" Bh 72,800.00 75,000.00
2.2.11.3.182 Tee GI Ǿ 2" x Ǿ 0,5" Bh 287,100.00 315,810.00
2.2.11.3.183 Tusen Klap GI Ǿ 1,5" Bh 191,400.00 210,540.00
2.2.11.3.184 Tusen Klap GI Ǿ 2" Bh 248,800.00 273,680.00
2.2.11.3.185 Tusen Klap GI Ǿ 3" Bh 680,000.00 700,000.00
2.2.11.3.186 Tusen Klap GI Ǿ 4" Bh 1,020,000.00 1,050,000.00
2.2.11.3.187 Vent GI Ǿ 2" Bh 697,100.00 766,810.00
2.2.11.3.188 Vent GI Ǿ 3" Bh 1,018,600.00 1,120,460.00
2.2.11.3.189 Vent GI Ǿ 4" Bh 1,340,600.00 1,474,660.00
2.2.11.3.190 Wall Pipe Seal Bh 145,900.00 160,490.00
2.2.11.3.191 Water Meter Ǿ 0,5" m 241,300.00 265,430.00
2.2.11.3.192 Water Meter Ǿ 1" m 858,000.00 943,800.00
2.2.11.3.193 Water Meter Ǿ 1,5" m 1,501,500.00 1,651,650.00
2.2.11.3.194 Water Meter Ǿ 2" m 2,145,000.00 2,359,500.00
2.2.11.3.195 Water Meter Ǿ 2,5" m 2,600,400.00 2,860,440.00
2.2.11.3.196 Water Meter Ǿ 3" m 3,055,800.00 3,361,380.00
2.2.11.3.197 Water Mur GI Ǿ 1" m 33,500.00 36,850.00
2.2.11.3.198 Water Mur GI Ǿ 1,5" m 47,900.00 52,690.00
2.2.11.3.199 Water Mur GI Ǿ 2" m 239,300.00 263,230.00
2.2.11.3.200 Waterstop (Lebar 150mm) m 47,900.00 52,690.00

34
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.11.3.201 Waterstop (Lebar 200mm) m 64,500.00 70,950.00
2.2.11.3.202 Waterstop (Lebar 250mm) m 90,600.00 99,660.00
- -
2.2.12 BAHAN JENIS PAKU : - -
2.2.12.1 Paku biasa Kg 16,200.00 17,820.00
2.2.12.2 Paku Eternit / Triplek Kg 19,700.00 21,670.00
2.2.12.3 Paku Gypsum Kg 24,300.00 26,730.00
2.2.12.4 Paku Kalsiboard Kg 27,700.00 30,470.00
2.2.12.5 Paku Kayu Uk.2,5"-5" Kg 15,100.00 16,610.00
2.2.12.6 Paku Reng Kayu 2" Kg 15,600.00 17,160.00
2.2.12.7 Paku Usuk 3" Kg 15,600.00 17,160.00
2.2.12.8 Paku Asbes Kg 27,200.00 29,920.00
2.2.12.9 Paku beton 5cm Bh 600.00 660.00
2.2.12.10 Paku Kait ( pancing ) Bh 1,200.00 1,320.00
2.2.12.11 Paku Ramset / dinabolt Bh 2,900.00 3,190.00
2.2.12.12 Paku Sekrup Bh 600.00 660.00
2.2.12.13 Paku Seng ( Paku payung ) Kg 26,000.00 28,600.00
2.2.12.14 Paku Sumbat Bh 1,800.00 1,980.00
2.2.12.15 Skrup Fixer Bh 800.00 880.00
- -
2.2.13 BAHAN FABRIKASI, ELEKTRIK, POMPA : - -
2.2.13.1 Alat - alat kerja Set 137,500.00 151,250.00
2.2.13.2 Arde Bh 210,100.00 231,110.00
2.2.13.3 Beton 1 : 1 1/2 : 2 1/2 m3 605,000.00 665,500.00
2.2.13.4 Beton Pracetak (Kolom) (5x50x200) Btg 104,500.00 114,950.00
2.2.13.5 Beton Pracetak (Panel) (5x50x200) Lbr 192,500.00 211,750.00
2.2.13.6 Biaya Penyambungan dan Uji PLN Titik 48,315,300.00 53,146,830.00
2.2.13.7 Boull Valve Bh 31,200.00 34,320.00
2.2.13.8 Box Meter Bh 44,300.00 48,730.00
2.2.13.9 BPU VA 704,600.00 775,060.00
2.2.13.10 Cassing Pompa PVC dia 10" S 10 Bh 3,143,800.00 3,458,180.00
2.2.13.11 Elektroda Kg 156,200.00 171,820.00
2.2.13.12 Exhaust dinding 20 x 20 cm Unit 368,000.00 404,800.00
2.2.13.13 Exhaust dinding 30 x 30 cm Unit 495,000.00 544,500.00
2.2.13.14 Exhaust dinding 40 x 40 cm Unit 605,000.00 665,500.00
2.2.13.15 Exhaust langit-langit 20/20 cm M' 262,900.00 289,190.00
2.2.13.16 Exhaust langit-langit 25/25 cm Unit 420,200.00 462,220.00
2.2.13.17 Kabel cocial Bh 15,400.00 16,940.00
2.2.13.18 Kipas Angin langit-langit Bh 459,800.00 505,780.00
2.2.13.19 Kompor Gas 1 tungku ( untuk biogas ) Bh 192,500.00 211,750.00
2.2.13.20 Kompor Gas 2 tungku ( untuk biogas ) Bh 302,500.00 332,750.00
2.2.13.21 Large angle Bh 166,400.00 183,040.00
2.2.13.22 Manometer Bh 599,000.00 658,900.00

35
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.2.13.23 Manometer Kecil Bh 250,000.00 275,000.00
2.2.13.24 Mesin Diesel 5 HP / 2200 RPM Unit 9,355,500.00 10,291,050.00
2.2.13.25 Pompa Tangan Unit 275,000.00 302,500.00
2.2.13.26 Pompa diesel (ex. honda wb 30 xh) Unit 3,850,000.00 4,235,000.00
2.2.13.27 Storox-100 Unit 40,200.00 44,220.00
2.2.13.28 Venetion Blinds And Vertical Blinds (Tirai) Unit 109,500.00 120,450.00
2.2.13.29 Pompa air listrik 40 lt/menit 125 watt Unit 550,000.00 605,000.00
2.2.13.30 Panel kontrol 2WLC DOL 7,5 kw 3x380 V 50 Hz Unit 6,501,000.00 7,151,100.00
2.2.13.31 Pelampung/water level kontrol Bh 508,000.00 558,800.00
2.2.13.32 Perbaikan Pintu Ulir Unit 4,950,000.00 5,445,000.00
2.2.13.33 Pintu air Type A Unit 110,125,400.00 121,137,940.00
2.2.13.34 Pintu air Type A* Unit 70,789,400.00 77,868,340.00
2.2.13.35 Pintu air Type B Unit 53,606,300.00 58,966,930.00
2.2.13.36 Pintu air Type B* Unit 35,171,400.00 38,688,540.00
2.2.13.37 Pintu air Type C2 Unit 20,722,900.00 22,795,190.00
2.2.13.38 Pintu air Type C3 Unit 11,905,300.00 13,095,830.00
2.2.13.39 Pintu air Type C5 Unit 2,358,400.00 2,594,240.00
2.2.13.40 Pintu air WIN WERK Unit 50,175,400.00 55,192,940.00
2.2.13.41 Pintu Scot Balk Balau M3 12,664,600.00 13,931,060.00
2.2.13.42 Pompa air Alcon Dia 3" (setara Honda WB 30 XT) Unit 4,070,000.00 4,477,000.00
2.2.13.43 Pompa air listrik 40 lt/menit 125 watt Bh 550,000.00 605,000.00
2.2.13.44 Pompa Sub Mersible Sp. 17.37 Unit 165,000,000.00 181,500,000.00
2.2.13.45 Pompa Tangan Bh 275,000.00 302,500.00
2.2.13.46 Rambu lalu lintas Bh 330,000.00 363,000.00
2.2.13.47 Storox-100 Kg 40,200.00 44,220.00
2.2.13.48 TC (Twisted Cable) : 3 x 70 + 1 x 50 Bh 79,900.00 87,890.00
2.2.13.49 Travo Unit 5,989,500.00 6,588,450.00
2.2.13.50 Trek Schok Bh 99,800.00 109,780.00
2.2.13.51 Treker dia 12 mm Unit 66,600.00 73,260.00
2.2.13.52 Venetion Blinds And Vertical Blinds (Tirai) M2 109,500.00 120,450.00
2.2.13.53 Water Meter Dia 0.5" Bh 308,000.00 338,800.00
2.2.13.54 Water Meter Dia 1" Bh 364,400.00 400,840.00
2.2.13.55 Water Meter Dia 1.25" Bh 401,700.00 441,870.00
2.2.13.56 Water Meter Dia 1.5" Bh 613,100.00 674,410.00
2.2.13.57 Water Meter Dia 2" Bh 1,444,300.00 1,588,730.00
2.2.13.58 Water Meter Dia 2.5" Bh 1,568,700.00 1,725,570.00
2.2.13.59 Water Meter Dia 3" Bh 1,673,900.00 1,841,290.00
2.2.13.60 Water Meter Dia 4" Bh 2,008,700.00 2,209,570.00
2.2.13.61 Waterstop (Lbr 150mm) m 62,200.00 68,420.00
2.2.13.62 Waterstop (Lbr 200mm) m 75,600.00 83,160.00
2.2.13.63 Waterstop (Lbr 230-320mm) m 79,400.00 87,340.00
- -
2.3.7 BIAYA TES KEGIATAN DI LABORATORIUM - -

36
Harga 2018

No Jenis Bahan SAT. Daerah


Daerah Datar (Rp)
Pegunungan (Rp)

1 2 3 4 5
2.3.7.1 Tes Beton paket 385,000.00 423,500.00
2.3.7.2 Tes daya dukung tanah/CBR (DCP) ttk/km 1,375,000.00 1,512,500.00
2.3.7.3 Tes kedalaman tanah keras/sondir ttk/km 3,300,000.00 3,630,000.00
2.3.7.4 Tes Lapen ttk 192,500.00 211,750.00
2.3.7.5 Tes Telford ttk 66,000.00 72,600.00
2.3.7.6 Test abrasi /uji 165,000.00 181,500.00
2.3.7.7 Test kepadatan /uji 165,000.00 181,500.00
2.3.7.8 Hammer Test /uji 165,000.00 181,500.00
- -
2.4.13 BIAYA KEGIATAN LAIN-LAIN - -
2.4.13.1 Papan nama kegiatan unit 550,000.00 605,000.00
2.4.13.2 Prasasti batu marmer (uk. 50x80) cm unit 550,000.00 605,000.00
2.4.13.3 Pembersihan telford lama m2 2,200.00 2,420.00
2.4.13.4 Pengeboran sumur bor ( manual ) m1 33,000.00 36,300.00
2.4.13.5 Sewa alat ukur water pass per - hari 220,000.00 242,000.00
2.4.13.6 Sewa alat ukur theodolit per - hari 385,000.00 423,500.00
2.4.13.7 Sewa alat ukur GPS per - hari 55,000.00 60,500.00
2.4.13.8 Sewa kamera digital per - hari 55,000.00 60,500.00
2.4.13.9 Sewa direksi keet per-bulan 165,000.00 181,500.00
2.4.13.10 Sewa kantor konsultan per-bulan 825,000.00 907,500.00
2.4.13.11 Penebangan pohon : Ø < 50 cm ttk 330,000.00 363,000.00
2.4.13.12 Penebangan pohon : Ø ≥ 50 cm ttk 825,000.00 907,500.00
2.4.13.13 Pengukuran ( uitzet ) jalan > 500 m per - km 1,100,000.00 1,210,000.00

37
REKAPITULASI
ANALISA HARGA SATUAN PEKERJAAN ( AHSP )
BIDANG PEKERJAAN UMUM
KABUPATEN : TULUNGAGUNG
SISTEM : KONTRAK
HARGA : BAWAH DAN ATAS OVERHEAD DAN PROFIT 14%

HARGA SATUAN KONTRAK BAWAH HARGA SA


NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7

A.2.2.1 PEKERJAAN PERSIAPAN

A.2.2.1.1 1 m2 Pembuatan Pagar sementara dari kayu tinggi 2 meter 55,928.40 669,564.18 - 725,492.58 55,928.40
A.2.2.1.2 1 m2 Pembuatan Pagar Sementara dari seng gelombang tinggi 2m 60,716.40 802,619.28 - 863,335.68 60,716.40
A.2.2.1.3 1 m2 Pembuatan Pagar sementara dari kawat duri tinggi 1.8 M 50,513.40 537,044.88 - 587,558.28 50,513.40
A.2.2.1.4 1 m' Pengukuran dan pemasangan Bowplank 19,616.55 719,224.86 - 738,841.41 19,616.55
A.2.2.1.5 1 m2 Pembuatan kantor sementara lantai plesteran 487,663.50 1,614,040.50 6,771.60 2,108,475.60 487,663.50
A.2.2.1.6 1 m2 Pembuatan Rumah Jaga ( Kontrusi Kayu ) 252,510.00 2,193,690.60 - 2,446,200.60 252,510.00
A.2.2.1.7 1 m2 Pembuatan Gudang Semen dan Peralatan 289,668.30 1,732,817.10 - 2,022,485.40 289,668.30
A.2.2.1.8 1 m2 Pembuatan Bedeng Pekerja 289,668.30 1,661,669.70 - 1,951,338.00 289,668.30
A.2.2.1.9 1 m2 Pembersihan Lapangan dan perataan 13,195.50 - - 13,195.50 13,195.50
A.2.2.1.10 1 m2 Pembuatan Steger/Perancah dari bambu 289,668.30 18,875.21 - 308,543.51 289,668.30
A.2.2.1.11 1 bh Pembuatan Kotak adukan ukuran 40 cm x 50 cm x25 cm 33,806.70 255,412.44 - 289,219.14 33,806.70
A.2.2.1.12 1 m2 Pembuatan Jalan Sementara 78,628.65 80,814.60 - 159,443.25 78,628.65
A.2.2.1.13 1 m3 Pembongkaran Beton bertulang 1,113,000.24 - - 1,113,000.24 1,113,000.24
A.2.2.1.14 1 m3 Pembongkaran Dinding Tembok bata 556,500.12 - - 556,500.12 556,500.12
A.2.2.1.15 1 m2 Pemasangan pagar kawat jaring galvanis panjang 240 Cm 8,425.74 4,724.46 - 13,150.20 8,425.74
A.2.2.1.16 1 m2 Pemasangan panel Beton pracetak 5 x 50 x 213 Cm 55,378.92 324,028.47 - 379,407.39 55,378.92
A.2.2.1.17 10 m2 Membongkar lantai lama, berikut membersihkan bata-bata lama atau ubin-ubin yang dibongkar 88,863.00 - - 88,863.00 88,863.00
A.2.2.1.17a 10 m2 Menghapus plesteran yang lama 41,738.25 - - 41,738.25 41,738.25
A.2.2.1.17b 10 m2 Menurunkan atap genteng atau sirap (jika atap genteng atau sirap akan dipakai lagi) 26,391.00 - - 26,391.00 26,391.00
A.2.2.1.17c 10 m2 Menurunkan atap genteng atau sirap (jika atap genteng atau sirap tidak dipakai lagi) 26,391.00 - - 26,391.00 26,391.00
A.2.2.1.17d 10 m2 Menurunkan rangka atap dari kayu (jika kayu bongkaran hendak dipakai lagi) 135,631.50 - - 135,631.50 135,631.50
A.2.2.1.17e 10 m2 Menurunkan rangka atap dari kayu (jika kayu bongkaran tidak dipakai lagi) 83,476.50 - - 83,476.50 83,476.50
A.2.2.1.17f 1 m3 Membongkar kuda-kuda jika dipakai lagi 1,010,040.00 - - 1,010,040.00 1,010,040.00
A.2.2.1.17g 1 m3 Membongkar kuda-kuda jika tidak dipakai lagi 676,134.00 - - 676,134.00 676,134.00

A.2.3.1 PEKERJAAN TANAH

A.2.3.1.1 1 m3 Penggalian Tanah biasa sedalam 1 m 61,260.75 - - 61,260.75 61,260.75


A.2.3.1.2 1 m3 Penggalian Tanah biasa sedalam 2 m 75,128.85 - - 75,128.85 75,128.85
A.2.3.1.3 1 m3 Penggalian Tanah biasa sedalam 3 m 89,212.41 - - 89,212.41 89,212.41
A.2.3.1.4 1 m3 Penggalian Tanah keras sedalam 1 m 81,537.36 - - 81,537.36 81,537.36
A.2.3.1.5 1 m3 Penggalian Tanah cadas sedalam 1 m 123,598.80 - - 123,598.80 123,598.80
A.2.3.1.6 1 m3 Penggalian Tanah lumpur sedalam 1 m 98,555.85 - - 98,555.85 98,555.85
A.2.3.1.7 1 m2 Pengerjaan stripping tanah tebing setinngi 1 meter 4,443.15 - - 4,443.15 4,443.15
A.2.3.1.8 1 m3 Pembuangan tanah sejauh 30 meter 26,847.00 - - 26,847.00 26,847.00
A.2.3.1.9 1 m3 Pengurugan kembali galian tanah 44,431.50 - - 44,431.50 44,431.50
A.2.3.1.10 1 m3 Pemadatan tanah ( per 20 cm ) 44,431.50 - - 44,431.50 44,431.50
A.2.3.1.11 1 m3 Pengurugan dengan pasir urug 24,504.30 237,074.40 - 261,578.70 24,504.30
A.2.3.1.12 1 m3 Pemasangan lapisan pudel campuran 1 kp : 3 pp : 7 tl 111,378.00 369,409.59 - 480,787.59 111,378.00
A.2.3.1.13 1 m2 Pemasangan lapisan ijuk tebal 10 cm untuk bidang resapan 13,329.45 52,668.00 - 65,997.45 13,329.45
A.2.3.1.14 1 m3 Pengurugan sirtu padat 22,215.75 255,816.00 - 278,031.75 22,215.75
A.2.3.1.14a 1 m3 Pengurugan tanah 22,215.75 112,860.00 - 135,075.75 22,215.75

A.3.2.1 PEKERJAAN PONDASI

A.3.2.1.1 1 m3 Pasangan pondasi batu belah campuran 1 sp : 3 pp 200,754.00 844,557.60 - 1,045,311.60 200,754.00
A.3.2.1.2 1 m3 Pasangan pondasi batu belah campuran 1 sp : 4 pp 200,754.00 792,847.20 - 993,601.20 200,754.00
A.3.2.1.3 1 m3 Pasangan pondasi batu belah campuran 1 sp : 5 pp 200,754.00 756,978.24 - 957,732.24 200,754.00
A.3.2.1.4 1 m3 Pasangan pondasi batu belah campuran 1 sp : 6 pp 200,754.00 731,770.56 - 932,524.56 200,754.00
A.3.2.1.5 1 m3 Pasangan pondasi batu belah campuran 1 sp : 8 pp 200,754.00 697,196.64 - 897,950.64 200,754.00
A.3.2.1.6 1 m3 Pasangan pondasi batu belah campuran 1 sp : 1 kp : 2 pp 200,754.00 725,020.62 - 925,774.62 200,754.00
A.3.2.1.7 1 m3 Pasangan pondasi batu belah campuran 1 sp : 3 kp : 10 pp 200,754.00 834,538.71 - 1,035,292.71 200,754.00
A.3.2.1.8 1 m3 Pasangan pondasi batu belah campuran 1/4 sp : 1 kp : 4 pp 200,754.00 788,774.55 - 989,528.55 200,754.00
A.3.2.1.9 1 m3 Pasangan pondasi batu kosong ( anstamping ) 104,392.08 506,214.72 - 610,606.80 104,392.08
A.3.2.1.10 1 m3 Pasangan pondasi siklop 60 % beton campuran 1 sp : 2 pb : 3 kr dan 40% batu belah 369,862.17 2,258,394.72 - 2,628,256.89 369,862.17
A.3.2.1.11 1 m3 Pasangan pondasi sumuran diameter 100 cm 280,811.07 704,654.52 - 985,465.59 280,811.07
A.3.2.1.11a 1 m' Pembuatan tiang pancang (40 X 40) Cm, beton bertulang 150,958.23 1,124,704.28 - 1,275,662.51 150,958.23
A.3.2.1.11b 1 m' Pembuatan tiang pancang (35 X 35) Cm, beton bertulang 117,140.70 688,222.33 - 805,363.03 117,140.70

A.4.1.1 PEKERJAAN BETON

A.4.1.1.1 1 m3 Membuat Beton mutu fc=7,4 Mpa (K100), Slump (12±2) cm, w/c = 0,87 165,541.11 858,607.87 - 1,024,148.98 165,541.11
A.4.1.1.2 1 m3 Membuat Beton mutu fc=9,8 Mpa (K125), Slump (12±2) cm, w/c = 0,78 165,541.11 899,356.94 - 1,064,898.05 165,541.11
A.4.1.1.3 1 m3 Membuat Beton mutu fc=12,2 Mpa (K150), Slump (12±2) cm, w/c = 0,72 165,541.11 931,100.47 - 1,096,641.58 165,541.11
A.4.1.1.4 1 m3 Membuat lantai kerja beton mutu f'c=7,4 Mpa ( K100) Slump (3-6) cm, w/c = 0,87 120,315.60 842,021.78 - 962,337.38 120,315.60
A.4.1.1.5 1 m3 Membuat Beton mutu fc=14,5 Mpa (K175), Slump (12±2) cm, w/c = 0,66 165,541.11 968,869.58 - 1,134,410.69 165,541.11
A.4.1.1.6 1 m3 Membuat Beton mutu fc=15,9 Mpa (K200), Slump (12±2) cm, w/c = 0,61 165,541.11 1,004,618.62 - 1,170,159.73 165,541.11
A.4.1.1.7 1 m3 Membuat Beton mutu fc=19,3 Mpa (K225), Slump (12±2) cm, w/c = 0,58 165,541.11 1,031,939.86 - 1,197,480.97 165,541.11

1
HARGA SATUAN KONTRAK BAWAH HARGA SA
NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
A.4.1.1.8 1 m3 Membuat Beton mutu fc=21,7 Mpa (K250), Slump (12±2) cm, w/c = 0,56 165,541.11 1,049,341.73 - 1,214,882.84 165,541.11
A.4.1.1.9 1 m3 Membuat Beton mutu fc=24,0 Mpa (K275), Slump (12±2) cm, w/c = 0,53 165,541.11 1,079,446.32 - 1,244,987.43 165,541.11
A.4.1.1.10 1 m3 Membuat Beton mutu fc=26,4 Mpa (K300), Slump (12±2) cm, w/c = 0,52 165,541.11 1,088,699.54 - 1,254,240.65 165,541.11
A.4.1.1.11 1 m3 Membuat Beton mutu fc=28,8 Mpa (K325), Slump (12±2) cm, w/c = 0,49 210,552.30 1,124,051.86 - 1,334,604.16 210,552.30
A.4.1.1.12 1 m3 Membuat Beton mutu fc=31,2 Mpa (K350), Slump (12±2) cm, w/c = 0,48 244,128.15 1,136,214.74 - 1,380,342.89 244,128.15
A.4.1.1.13 1 m3 Membuat Beton kedap air dengan strorox - 100 210,552.30 1,111,454.40 - 1,322,006.70 210,552.30
A.4.1.1.14 1 m' Pasang PVC waterstop lebar 150 mm 8,030.16 57,336.30 - 65,366.46 8,030.16
A.4.1.1.15 1 m' Pasang PVC waterstop lebar 200 mm 9,798.87 77,206.50 - 87,005.37 9,798.87
A.4.1.1.16 1 m' Pasang PVC waterstop lebar 230 - 320 mm 10,706.88 108,448.20 - 119,155.08 10,706.88
A.4.1.1.17 10 kg Pembesian dengan besi polos atau ulir 13,346.55 128,694.60 - 142,041.15 13,346.55
A.4.1.1.18 10 kg Pemasangan kabel presstressed polos / strands 9,263.64 127,691.40 - 136,955.04 9,263.64
A.4.1.1.19 10 kg Pemasangan jaring kawat baja ( wiremesh ) 6,976.23 337,052.40 - 344,028.63 6,976.23
A.4.1.1.20 1 m2 Pemasangan bekisting untuk pondasi 72,706.92 164,205.60 - 236,912.52 72,706.92
A.4.1.1.21 1 m2 Pemasangan bekisting untuk sloof 72,706.92 183,956.10 - 256,663.02 72,706.92
A.4.1.1.22 1 m2 Pemasangan bekisting untuk kolom 92,281.86 309,732.30 - 402,014.16 92,281.86
A.4.1.1.23 1 m2 Pemasangan bekisting untuk balok 92,281.86 321,582.60 - 413,864.46 92,281.86
A.4.1.1.24 1 m2 Pemasangan bekisting untuk lantai 92,281.86 364,908.30 - 457,190.16 92,281.86
A.4.1.1.25 1 m2 Pemasangan bekisting untuk dinding 92,281.86 266,532.00 - 358,813.86 92,281.86
A.4.1.1.26 1 m2 Pemasangan bekisting untuk tangga 92,281.86 269,900.70 - 362,182.56 92,281.86
A.4.1.1.27 1 m2 Pemasangan jembatan untuk pengecoran beton 18,209.79 122,260.44 - 140,470.23 18,209.79
A.4.1.1.28 1 m3 Membuat pondasi beton bertulang ( 150 kg besi + bekisting ) 728,305.53 3,726,580.20 - 4,454,885.73 728,305.53
A.4.1.1.29 1 m3 Membuat sloof beton bertulang ( 200 kg besi + bekisting ) 824,121.96 4,657,116.60 - 5,481,238.56 824,121.96
A.4.1.1.30 1 m3 Membuat kolom beton bertulang ( 300 kg besi + bekisting ) 1,025,730.96 7,933,955.40 - 8,959,686.36 1,025,730.96
A.4.1.1.31 1 m3 Membuat balok beton bertulang (200 kg besi + bekisting ) 892,804.11 6,106,546.80 - 6,999,350.91 892,804.11
A.4.1.1.32 1 m3 Membuat kolom beton bertulang (150 kg besi + bekisting ) 728,625.30 5,604,775.80 - 6,333,401.10 728,625.30
A.4.1.1.33 1 m3 Membuat dinding beton bertulang (150 kg besi + bekisting ) 728,305.53 5,336,419.80 - 6,064,725.33 728,305.53
A.4.1.1.34 1 m3 Membuat dinding beton bertulang (200 kg besi + bekisting ) 824,121.96 5,609,706.30 - 6,433,828.26 824,121.96
A.4.1.1.35 1 m' Membuat kolom praktis beton bertulang (11 x 11 ) cm 21,422.31 72,225.84 - 93,648.15 21,422.31
A.4.1.1.36 1 m' Membuat ring balok beton bertulang (10 x 15 ) cm 35,373.63 80,865.90 - 116,239.53 35,373.63
A.4.1.1.37 1 m3 Membongkar bekisting dan perawatan beton 312,360.00 - - 312,360.00 312,360.00

A.4.1.2 PEKERJAAN BETON PRACETAK

A.4.1.2.1 1 m2 Pembuatan lahan produksi tebal 8 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm 13,256.49 77,508.14 - 90,764.63 13,256.49
A.4.1.2.2 1 m2 Pembuatan lahan produksi tebal 10 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm 16,588.14 96,883.13 - 113,471.27 16,588.14
A.4.1.2.3 1 m2 Pembuatan lahan produksi tebal 12 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm 19,830.87 105,090.22 - 124,921.09 19,830.87
A.4.1.2.4 1 m2 Pembuatan lahan produksi tebal 15 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm 24,885.63 145,309.64 - 170,195.27 24,885.63
A.4.1.2.5 1 m2 Pembuatan bekisting untuk plat pracetak ( 5 kali pakai ) 8,351.64 313,567.09 - 321,918.73 8,351.64
A.4.1.2.6 1 m2 Pembuatan bekisting untuk balok beton pracetak ( 10-12 kali pakai ) 4,268.73 32,143.44 - 36,412.17 4,268.73
A.4.1.2.7 1 m2 Pembuatan bekisting untuk kolom beton pracetak ( 10-12 kali pakai ) 4,268.73 30,063.74 - 34,332.47 4,268.73
A.4.1.2.8 1 bh Pemasangan dan membuka bekisting komponen plat beton pracetak 5,975.31 - - 5,975.31 5,975.31
A.4.1.2.9 1 bh Pemasangan dan membuka bekisting komponen balok beton pracetak 10,549.56 - - 10,549.56 10,549.56
A.4.1.2.10 1 bh Pemasangan dan membuka bekisting komponen kolom beton pracetak 8,531.76 - - 8,531.76 8,531.76
A.4.1.2.11 1 bh Penuangan/menebar beton untuk komponen plat beton pracetak 52,250.19 - - 52,250.19 52,250.19
A.4.1.2.12 1 bh Penuangan/menebar beton untuk komponen balok beton pracetak 53,857.59 - - 53,857.59 53,857.59
A.4.1.2.13 1 bh Penuangan/menebar beton untuk komponen balok beton pracetak 48,471.09 - - 48,471.09 53,857.59
A.4.1.2.22 1 titik Upah melakukan grouting pada join pracetak 44,925.69 - - 44,925.69 44,925.69
A.4.1.2.23 1 titik Pemasangan bekisting join pracetak 28,615.14 68,077.15 - 96,692.29 28,615.14
A.4.1.2.24 1 titik Upah join dengan sling 64,261.23 - - 64,261.23 64,261.23

A.4.2.1 PEKERJAAN BESI DAN ALUMINIUM

A.4.2.1.1 1 kg Pemasangan besi profil 13,206.33 20,189.40 - 33,395.73 13,206.33


A.4.2.1.2 1 kg Pemasangan rangka kuda-kuda baja IWF 11,769.93 20,189.40 - 31,959.33 11,769.93
A.4.2.1.3 100 kg Pengerjaan Pekerjaan perakitan 18,657.24 11,343.00 16,416.00 46,416.24 18,657.24
A.4.2.1.4 1 m2 Pembuatan besi plat baja tebal 2 mm rangkap, rangka baja siku 205,919.91 1,003,621.80 - 1,209,541.71 205,919.91
A.4.2.1.5 10 cm Pengerjaan pengelasan dengan las listrik 5,592.84 38,030.40 3,876.00 47,499.24 5,592.84
A.4.2.1.6 1 m2 Pemasangan rangka jendela besi scuare tube ( 25 x 5 ) cm 127,453.71 177,898.37 - 305,352.08 127,453.71
A.4.2.1.7 1 m2 Pemasangan pintu rolling door besi 229,581.18 625,518.00 - 855,099.18 229,581.18
A.4.2.1.8 1 m2 Pemasangan pintu lipat ( Folding door ) bahan plastik/PVC 86,312.82 509,580.00 - 595,892.82 86,312.82
A.4.2.1.9 1 m2 Pemasangan sunscreen aluminium 96,829.32 718,314.00 - 815,143.32 96,829.32
A.4.2.1.10 1 m2 Pemasangan rolling door aluminium 196,165.50 431,832.00 - 627,997.50 196,165.50
A.4.2.1.11 1 m Pemasangan kusen pintu aluminium 8,429.73 116,359.80 - 124,789.53 8,429.73
A.4.2.1.12 1 m2 Pemasangan pintu aluminium strip lebar 8 cm 16,668.68 727,570.80 - 744,239.48 16,668.68
A.4.2.1.13 1 m2 Pemasangan pintu kaca alumunium 16,808.16 1,004,112.00 - 1,020,920.16 16,808.16
A.4.2.1.14 1 m2 Pemasangan venetions blinds dan vertical blinds 68,711.79 124,830.00 - 193,541.79 68,711.79
A.4.2.1.15 1 m2 Pemasangan terali besi strip ( 2x3 ) mm 327,542.52 202,685.05 - 530,227.57 327,542.52
A.4.2.1.16 1 m2 Pemasangan kawat nyamuk 19,616.55 97,438.31 - 117,054.86 19,616.55
A.4.2.1.16a 1 m2 Pemasangan kawat harmonika 19,616.55 105,087.71 - 124,704.26 19,616.55
A.4.2.1.16b 1 m2 Pemasangan kawat kassa 19,616.55 89,161.91 - 108,778.46 19,616.55
A.4.2.1.16c 1 m2 Pemasangan kawat burung 19,616.55 88,534.91 - 108,151.46 19,616.55
A.4.2.1.17 1 m2 Pemasangan jendela nako dan tralis 38,263.53 487,874.40 - 526,137.93 38,263.53
A.4.2.1.18 1 m' Pemasangan talang datar/jurai seng bjls 28 lebar 90 cm 38,263.53 182,072.82 - 220,336.35 38,263.53
A.4.2.1.19 1 m Pemasangan talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm 46,382.04 61,596.48 - 107,978.52 46,382.04
A.4.2.1.20 1 m2 Pemasangan rangka besi hollow 1x40.40.2, modul 60x120 cm, dinding partisi 47,527.74 89,262.00 - 136,789.74 47,527.74
A.4.2.1.21 1 m2 Pemasangan rangka besi hollow 1x40.40.2, modul 60x60 cm, plafon 66,517.29 99,180.00 - 165,697.29 66,517.29

A.4.4.1 PEKERJAAN PASANGAN DINDING

2
HARGA SATUAN KONTRAK BAWAH HARGA SA
NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
A.4.4.1.1 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 2 pp 70,229.70 237,142.80 - 307,372.50 70,229.70
A.4.4.1.2 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 3 pp 70,229.70 223,615.56 - 293,845.26 70,229.70
A.4.4.1.3 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 4 pp 70,229.70 214,003.08 - 284,232.78 70,229.70
A.4.4.1.4 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 5 pp 70,229.70 209,769.12 - 279,998.82 70,229.70
A.4.4.1.5 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 6 pp 70,229.70 209,883.12 - 280,112.82 70,229.70
A.4.4.1.6 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 3 kp : 10 pp 70,229.70 228,545.78 - 298,775.48 70,229.70
A.4.4.1.7 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 2 pp 35,114.85 113,500.68 - 148,615.53 35,114.85
A.4.4.1.8 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 3 pp 35,114.85 106,792.92 - 141,907.77 35,114.85
A.4.4.1.9 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 4 pp 35,114.85 103,115.28 - 138,230.13 35,114.85
A.4.4.1.10 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 5 pp 35,114.85 100,812.48 - 135,927.33 35,114.85
A.4.4.1.11 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 6 pp 35,114.85 99,845.76 - 134,960.61 35,114.85
A.4.4.1.12 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 8 pp 35,114.85 97,242.00 - 132,356.85 35,114.85
A.4.4.1.13 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 3 kp : 8 pp 35,114.85 115,775.55 - 150,890.40 35,114.85
A.4.4.1.14 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sm : 1 kp : 1 pp 35,114.85 103,336.67 - 138,451.52 35,114.85
A.4.4.1.15 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sm : 1 kp : 2 pp 35,114.85 100,546.40 - 135,661.25 35,114.85
A.4.4.1.16 1 m3 Pemasangan dinding HB20 campuran 1 sp : 3 pp 44,378.49 1,400,633.64 - 1,445,012.13 44,378.49
A.4.4.1.16a 1 m3 Pemasangan dinding CB20 campuran 1 sp : 3 pp 44,378.49 1,088,558.64 - 1,132,937.13 44,378.49
A.4.4.1.17 1 m3 Pemasangan dinding HB20 campuran 1 sp : 4 pp 44,378.49 1,404,204.12 - 1,448,582.61 44,378.49
A.4.4.1.17a 1 m3 Pemasangan dinding CB20 campuran 1 sp : 4 pp 44,378.49 1,092,129.12 - 1,136,507.61 44,378.49
A.4.4.1.18 1 m3 Pemasangan dinding HB15 campuran 1 sp : 3 pp 54,311.88 1,015,765.08 - 1,070,076.96 54,311.88
A.4.4.1.18a 1 m3 Pemasangan dinding CB15 campuran 1 sp : 3 pp 54,311.88 874,690.08 - 929,001.96 54,311.88
A.4.4.1.19 1 m3 Pemasangan dinding HB15 campuran 1 sp : 4 pp 54,311.88 1,018,149.96 - 1,072,461.84 54,311.88
A.4.4.1.19a 1 m3 Pemasangan dinding CB15 campuran 1 sp : 4 pp 54,311.88 877,074.96 - 931,386.84 54,311.88
A.4.4.1.20 1 m3 Pemasangan dinding HB10 campuran 1 sp : 3 pp 35,114.85 641,313.84 - 676,428.69 35,114.85
A.4.4.1.20a 1 m3 Pemasangan dinding CB10 campuran 1 sp : 3 pp 35,114.85 641,313.84 - 676,428.69 35,114.85
A.4.4.1.21 1 m3 Pemasangan dinding HB10 campuran 1 sp : 4 pp 35,114.85 643,701.00 - 678,815.85 35,114.85
A.4.4.1.21a 1 m3 Pemasangan dinding CB10 campuran 1 sp : 4 pp 35,114.85 643,701.00 - 678,815.85 35,114.85
A.4.4.1.22 1 m2 Pemasangan dinding terawang (rooster)12x11x24 campuran 1 sp : 3 pp 35,114.85 701,829.60 - 736,944.45 35,114.85
A.4.4.1.23 1 m2 Pemasangan dinding terawang (rooster)12x11x24 campuran 1 sp : 4 pp 35,114.85 318,789.60 - 353,904.45 35,114.85
A.4.4.1.24 1 m2 Pemasangan dinding bata berongga ekspose 12x11x24 campuran 1 sp : 3 pp 40,150.80 710,274.72 - 750,425.52 40,150.80
A.4.4.1.24a 1 m2 Pasangan bataco 1 Pc : 3 Psr 34,845.53 94,371.48 - 129,217.01 34,845.53

A.4.4.2 PEKERJAAN PLESTERAN

A.4.4.2.1 1 m2 Pemasangan plesteran 1 sp : 1 pp tebal 15 mm 40,150.80 29,559.74 - 69,710.54 40,150.80


A.4.4.2.2 1 m2 Pemasangan plesteran 1 sp : 2 pp tebal 15 mm 40,150.80 22,336.70 - 62,487.50 40,150.80
A.4.4.2.3 1 m2 Pemasangan plesteran 1 sp : 3 pp tebal 15 mm 40,150.80 19,332.58 - 59,483.38 40,150.80
A.4.4.2.4 1 m2 Pemasangan plesteran 1 sp : 4 pp tebal 15 mm 40,150.80 17,182.08 - 57,332.88 40,150.80
A.4.4.2.5 1 m2 Pemasangan plesteran 1 sp : 5 pp tebal 15 mm 40,150.80 16,098.62 - 56,249.42 40,150.80
A.4.4.2.6 1 m2 Pemasangan plesteran 1 sp : 6 pp tebal 15 mm 40,150.80 15,173.86 - 55,324.66 40,150.80
A.4.4.2.7 1 m2 Pemasangan plesteran 1 sp : 7 pp tebal 15 mm 40,150.80 14,708.74 - 54,859.54 40,150.80
A.4.4.2.8 1 m2 Pemasangan plesteran 1 sp : 8 pp tebal 15 mm 40,150.80 14,243.62 - 54,394.42 40,150.80
A.4.4.2.9 1 m2 Pemasangan plesteran 1 sp : 1/2 kp : 3 pp tebal 15 mm 42,137.82 17,450.55 - 59,588.37 42,137.82
A.4.4.2.10 1 m2 Pemasangan plesteran 1 sp : 2 kp : 8 pp tebal 15 mm 42,137.82 18,049.05 - 60,186.87 42,137.82
A.4.4.2.11 1 m2 Pemasangan plesteran 1 sm : 1 kp : 1 pp tebal 15 mm 42,137.82 17,285.02 - 59,422.84 42,137.82
A.4.4.2.12 1 m2 Pemasangan plesteran 1 sm : 1 kp : 2 pp tebal 15 mm 42,137.82 15,851.59 - 57,989.41 42,137.82
A.4.4.2.13 1 m2 Pemasangan plesteran 1 sp : 1 pp tebal 20 mm 53,749.86 29,882.59 - 83,632.45 53,749.86
A.4.4.2.14 1 m2 Pemasangan plesteran 1 sp : 3 pp tebal 20 mm 41,847.69 25,877.09 - 67,724.78 41,847.69
A.4.4.2.15 1 m2 Pemasangan plesteran 1 sp : 4 pp tebal 20 mm 53,749.86 22,909.44 - 76,659.30 53,749.86
A.4.4.2.16 1 m2 Pemasangan plesteran 1 sp : 5 pp tebal 20 mm 53,749.86 21,565.15 - 75,315.01 53,749.86
A.4.4.2.17 1 m2 Pemasangan plesteran 1 sp : 6 pp tebal 20 mm 53,749.86 20,231.81 - 73,981.67 53,749.86
A.4.4.2.18 1 m2 Pemasangan plesteran 1 sp : 1 kp : 2 pp tebal 20 mm 58,887.84 19,993.66 - 78,881.50 58,887.84
A.4.4.2.19 1 m2 Pemasangan berapen 1 sp : 5 pp tebal 15 mm 20,182.56 16,098.62 - 36,281.18 20,182.56
A.4.4.2.20 1 m2 Pemasangan plesteran sconing 1 sp : 3 pp lebar 10 mm 46,965.72 4,710.48 - 51,676.20 46,965.72
A.4.4.2.21 1 m2 Pemasangan plesteran granit 1 sp : 2 granit tebal 1 cm 60,333.36 87,780.00 - 148,113.36 60,333.36
A.4.4.2.22 1 m2 Pemasangan plesteran traso 1 sp : 2 traso tebal 1 cm 60,333.36 55,290.00 - 115,623.36 60,333.36
A.4.4.2.23 1 m2 Pemasangan plesteran ciprat 1 sp : 2 pp 35,114.85 8,700.48 - 43,815.33 35,114.85
A.4.4.2.24 1 m2 Pemasangan finishing siar bata merah 20,182.56 4,960.37 - 25,142.93 20,182.56
A.4.4.2.25 1 m2 Pemasangan finishing siar pasangan conblock ekspose 9,475.68 2,553.60 - 12,029.28 9,475.68
A.4.4.2.26 1 m2 Pemasangan finishing siar pasangan batu kali, campuran 1 sp : 2 pp 40,150.80 13,730.16 - 53,880.96 40,150.80
A.4.4.2.27 1 m2 Pemasangan acian 26,767.20 5,187.00 - 31,954.20 26,767.20
A.4.4.2.28 1 m' Benangan / Tali Air / Sudut Kol Kolan 5,674.35 15,013.80 - 20,688.15 5,674.35

A.4.4.3 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.3 1 m2 Pemasangan lantai ubin PC abu - abu ukuran 20 x 20 Cm 36,242.88 67,118.64 - 103,361.52 36,242.88
A.4.4.3.8 1 m2 Pemasangan lantai ubin teraso ukuran 30 x 30 Cm 34,797.36 98,692.74 - 133,490.10 34,797.36
A.4.4.3.9 1 m2 Pemasangan lantai ubin Granit ukuran 40 x 40 Cm 33,566.16 229,175.75 - 262,741.91 33,566.16
A.4.4.3.32 1 m2 Pemasangan lantai keramik artistik 10 x 20 Cm 93,685.20 148,400.64 - 242,085.84 93,685.20
A.4.4.3.35 1 m2 Pemasangan lantai keramik polos ukuran 30 x 30 cm 93,685.20 92,359.86 - 186,045.06 93,685.20
A.4.4.3.35a 1 m2 Pemasangan lantai keramik motif ukuran 30 x 30 cm 93,685.20 98,692.74 - 192,377.94 93,685.20
A.4.4.3.35b 1 m2 Pemasangan lantai keramik (eks Granito ) tekstur ukuran 40 x 40 cm 93,685.20 231,561.49 - 325,246.69 93,685.20
A.4.4.3.35c 1 m2 Pemasangan lantai keramik (eks Granito ) tekstur ukuran 60 x 60 cm 93,685.20 287,826.71 - 381,511.91 93,685.20
A.4.4.3.35d 1 m2 Pemasangan lantai keramik (eks Granito ) warna gelap ukuran 40 x 40 cm 93,685.20 309,017.51 - 402,702.71 93,685.20
A.4.4.3.35e 1 m2 Pemasangan lantai keramik (eks Granito ) warna gelap ukuran 60 x 60 cm 93,685.20 428,489.77 - 522,174.97 93,685.20
A.4.4.3.35f 1 m2 Pemasangan lantai keramik (eks Granito ) warna terang ukuran 40 x 40 cm 93,685.20 213,293.56 - 306,978.76 93,685.20
A.4.4.3.35g 1 m2 Pemasangan lantai keramik (eks Granito ) warna terang ukuran 60 x 60 cm 93,685.20 138,151.47 - 231,836.67 93,685.20
A.4.4.3.35h 1 m2 Pemasangan lantai keramik cutting ukuran 30 x 50 cm 93,685.20 130,966.08 - 224,651.28 93,685.20
A.4.4.3.35i 1 m2 Pemasangan lantai keramik cutting ukuran 31 x 63 cm 93,685.20 176,757.70 - 270,442.90 93,685.20

3
HARGA SATUAN KONTRAK BAWAH HARGA SA
NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
A.4.4.3.35j 1 m2 Pemasangan lantai keramik motif ukuran 40 x 40 cm 93,685.20 103,805.85 - 197,491.05 93,685.20
A.4.4.3.35k 1 m2 Pemasangan lantai keramik polos ukuran 40 x 40 cm 93,685.20 100,298.84 - 193,984.04 93,685.20
A.4.4.3.35l 1 m2 Pemasangan lantai keramik tekstur cuttingukuran 31 x 63 cm 93,685.20 185,160.94 - 278,846.14 93,685.20
A.4.4.3.35m 1 m2 Pemasangan lantai keramik tekstur ukuran 20 x 20 cm 93,685.20 96,500.59 - 190,185.79 93,685.20
A.4.4.3.35n 1 m2 Pemasangan lantai keramik motif ukuran 30 x 30 cm 93,685.20 98,692.74 - 192,377.94 93,685.20
A.4.4.3.35o 1 m2 Pemasangan lantai keramik tekstur ukuran 30 x 30 cm 93,685.20 95,891.66 - 189,576.86 93,685.20
A.4.4.3.35p 1 m2 Pemasangan lantai keramik motif ukuran 50 x 50 cm 93,685.20 112,089.22 - 205,774.42 93,685.20
A.4.4.3.36 1 m2 Pemasangan lantai keramik ukuran 20 x 20 Cm 93,685.20 97,068.72 - 190,753.92 93,685.20
A.4.4.3.39 1 m1 Pemasangan plint keramik artistik ukuran 10 x 20 Cm 21,321.42 115,189.02 - 136,510.44 21,321.42
A.4.4.3.40 1 m1 Pemasangan plint keramik ukuran 10 x 20 Cm 19,402.80 23,919.48 - 43,322.28 19,402.80
A.4.4.3.43 1 m2 Pemasangan lantai marmer bakar ukuran 100 x 100 Cm 93,685.20 160,673.88 - 254,359.08 93,685.20
A.4.4.3.43a 1 m2 Pemasangan lantai marmer hitam ukuran 100 x 100 Cm 93,685.20 164,903.28 - 258,588.48 93,685.20
A.4.4.3.43b 1 m2 Pemasangan lantai marmer putih ukuran 100 x 100 Cm 93,685.20 257,708.40 - 351,393.60 93,685.20
A.4.4.3.43c 1 m2 Pemasangan lantai batu andesit 93,685.20 226,652.52 - 320,337.72 93,685.20
A.4.4.3.43d 1 m2 Pemasangan lantai batu andesit hijau 93,685.20 266,167.20 - 359,852.40 93,685.20
A.4.4.3.43e 1 m2 Pemasangan lantai batu candi 93,685.20 199,705.20 - 293,390.40 93,685.20
A.4.4.3.43f 1 m2 Pemasangan lantai batu candi hitam 93,685.20 199,705.20 - 293,390.40 93,685.20
A.4.4.3.43g 1 m2 Pemasangan lantai batu granit black gold 93,685.20 2,820,241.44 - 2,913,926.64 93,685.20
A.4.4.3.43h 1 m2 Pemasangan lantai batu granit motif 93,685.20 294,806.28 - 388,491.48 93,685.20
A.4.4.3.43i 1 m2 Pemasangan lantai batu lempeng 93,685.20 162,969.84 - 256,655.04 93,685.20
A.4.4.3.43j 1 m2 Pemasangan lantai batu lempeng hijau 93,685.20 161,519.76 - 255,204.96 93,685.20
A.4.4.3.43k 1 m2 Pemasangan lantai batu lempeng coklat 93,685.20 119,588.28 - 213,273.48 93,685.20
A.4.4.3.44 1 m2 Lantai karpet 33,402.00 35,910.00 - 69,312.00 33,402.00
A.4.4.3.49 1 m2 Pemasangan dinding keramik 10 cm x 20 cm 120,452.40 50,691.24 - 171,143.64 120,452.40
A.4.4.3.50 1 m2 Pemasangan dinding keramik tekture 20 cm x 20 cm 120,452.40 87,123.36 - 207,575.76 120,452.40
A.4.4.3.51 1 m2 Pemasangan dinding keramik artistik 10 x 20 cm 120,452.40 142,046.28 - 262,498.68 120,452.40
A.4.4.3.53 1 m2 Pemasangan dinding keramik artistik 10 x 20 cm 120,452.40 142,046.28 - 262,498.68 120,452.40
A.4.4.3.54 1 m2 Pemasangan dinding keramik 20 x 20 cm 120,452.40 88,281.60 - 208,734.00 120,452.40
A.4.4.3.54a 1 m2 Pemasangan dinding keramik motif 20 x 25 cm 120,452.40 105,078.36 - 225,530.76 120,452.40
A.4.4.3.54b 1 m2 Pemasangan dinding keramik putih 20 x 25 cm 120,452.40 87,677.40 - 208,129.80 120,452.40
A.4.4.3.54c 1 m2 Pemasangan dinding keramik 20 x 33 cm 120,452.40 92,511.00 - 212,963.40 120,452.40
A.4.4.3.54d 1 m2 Pemasangan dinding keramik 40 x 40 cm 120,452.40 92,511.00 - 212,963.40 120,452.40
A.4.4.3.54e 1 m2 Pemasangan dinding keramik tekstur cutting 31 x 63 cm 120,452.40 176,253.12 - 296,705.52 120,452.40
A.4.4.3.54f 1 m2 Pemasangan dinding keramik tekstur 20 x 20 cm 120,452.40 88,281.60 - 208,734.00 120,452.40
A.4.4.3.54g 1 m2 Pemasangan dinding keramik tekstur 30 x 30 cm 120,452.40 87,677.40 - 208,129.80 120,452.40
A.4.4.3.54h 1 m2 Pemasangan dinding batu marmo warna 120,452.40 169,244.40 - 289,696.80 120,452.40
A.4.4.3.54i 1 m2 Pemasangan dinding batu andesit 120,452.40 224,709.96 - 345,162.36 120,452.40
A.4.4.3.54j 1 m2 Pemasangan dinding batu andesit alur 120,452.40 351,471.12 - 471,923.52 120,452.40
A.4.4.3.54k 1 m2 Pemasangan dinding batu andesit alur hitam 120,452.40 358,721.52 - 479,173.92 120,452.40
A.4.4.3.54l 1 m2 Pemasangan dinding batu andesit hitam bakar 120,452.40 346,033.32 - 466,485.72 120,452.40
A.4.4.3.54m 1 m2 Pemasangan dinding batu andesit hitam 120,452.40 284,284.08 - 404,736.48 120,452.40
A.4.4.3.54n 1 m2 Pemasangan dinding batu andesit hijau 120,452.40 264,224.64 - 384,677.04 120,452.40
A.4.4.3.54o 1 m2 Pemasangan dinding batu bali green 120,452.40 183,503.52 - 303,955.92 120,452.40
A.4.4.3.54p 1 m2 Pemasangan dinding batu bobos 120,452.40 203,442.12 - 323,894.52 120,452.40
A.4.4.3.54q 1 m2 Pemasangan dinding batu candi 120,452.40 197,762.64 - 318,215.04 120,452.40
A.4.4.3.54r 1 m2 Pemasangan dinding batu candi hitam 120,452.40 197,762.64 - 318,215.04 120,452.40
A.4.4.3.54s 1 m2 Pemasangan dinding batu granit black gold 120,452.40 2,818,298.88 - 2,938,751.28 120,452.40
A.4.4.3.54t 1 m2 Pemasangan dinding batu granit motif 120,452.40 292,863.72 - 413,316.12 120,452.40
A.4.4.3.54u 1 m2 Pemasangan dinding batu lempeng 120,452.40 161,027.28 - 281,479.68 120,452.40
A.4.4.3.54v 1 m2 Pemasangan dinding batu marmo biasa 120,452.40 139,759.44 - 260,211.84 120,452.40
A.4.4.3.54w 1 m2 Pemasangan dinding batu paras putih 120,452.40 180,482.52 - 300,934.92 120,452.40
A.4.4.3.54x 1 m2 Pemasangan dinding batu paras grobongan 120,452.40 159,939.72 - 280,392.12 120,452.40
A.4.4.3.54y 1 m2 Pemasangan dinding batu susun sirih 120,452.40 571,883.28 - 692,335.68 120,452.40
A.4.4.3.54z 1 m2 Pemasangan dinding batu warna ( hias ) 120,452.40 139,396.92 - 259,849.32 120,452.40
A.4.4.3.54aa 1 m2 Pemasangan dinding susun sirih, andesit hitam 3 x 20 cm 120,452.40 246,219.48 - 366,671.88 120,452.40
A.4.4.3.54ab 1 m2 Pemasangan dinding susun sirih, andesit hitam 3 x 30 cm 120,452.40 246,219.48 - 366,671.88 120,452.40
A.4.4.3.54ac 1 m2 Pemasangan dinding susun sirih, andesit hitam 3 x 40 cm 120,452.40 246,219.48 - 366,671.88 120,452.40
A.4.4.3.55 1 m2 Pemasangan dinding marmer bakar 100 x 100 cm 173,986.80 357,677.28 - 531,664.08 173,986.80
A.4.4.3.55a 1 m2 Pemasangan dinding marmer hitam 100 x 100 cm 173,986.80 361,906.68 - 535,893.48 173,986.80
A.4.4.3.55b 1 m2 Pemasangan dinding marmer putih 100 x 100 cm 173,986.80 454,711.80 - 628,698.60 173,986.80
A.4.4.3.57 1 m2 Pemasangan dinding batu paras putih 93,685.20 188,670.00 - 282,355.20 120,452.40
A.4.4.3.57a 1 m2 Pemasangan dinding batu paras grobogan 93,685.20 167,352.00 - 261,037.20 93,685.20
A.4.4.3.58 1 m2 Pemasangan dinding batu tempel hitam 93,685.20 168,480.60 - 262,165.80 93,685.20
A.4.4.3.60 1 m2 Pemasangan wallpaper lebar 50 cm 45,119.49 22,771.50 - 67,890.99 45,119.49
A.4.4.3.63 1 m1 Pemasangan plint kayu tebal 2 cm lebar 10 cm 22,103.46 77,155.20 - 99,258.66 22,103.46
A.4.4.3.63a 1 m2 Lantai Patlag 1 Lapis Bata merah camp. 1 Sm : 1 Kpr : 3 Psr 22,073.25 61,049.74 - 83,122.99 22,073.25
A.4.4.3.63b 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm K225 21,021.60 111,229.80 - 132,251.40 21,021.60
A.4.4.3.63c 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm K225 21,021.60 94,677.00 - 115,698.60 21,021.60
A.4.4.3.63d 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm K300 21,021.60 127,782.60 - 148,804.20 21,021.60
A.4.4.3.63e 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm K300 21,021.60 107,091.60 - 128,113.20 21,021.60
A.4.4.3.63f 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm K400 21,021.60 148,473.60 - 169,495.20 21,021.60
A.4.4.3.63g 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm K400 21,021.60 101,574.00 - 122,595.60 21,021.60
A.4.4.3.63h 1 m2 Pasang Paving Stone Warna Tebal 8 Cm K225 21,021.60 120,885.60 - 141,907.20 21,021.60
A.4.4.3.63i 1 m2 Pasang Paving Stone Warna Tebal 6 Cm K225 21,021.60 100,194.60 - 121,216.20 21,021.60
A.4.4.3.63j 1 m2 Pasang Paving Stone Segi 6 Warna Tebal 8 Cm K225 21,021.60 120,885.60 - 141,907.20 21,021.60
A.4.4.3.63k 1 m2 Pasang Paving Stone Segi 6 Warna Tebal 6 Cm K225 21,021.60 100,194.60 - 121,216.20 21,021.60
A.4.4.3.63l 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm 21,021.60 102,953.40 - 123,975.00 21,021.60
A.4.4.3.63m 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm 21,021.60 86,400.60 - 107,422.20 21,021.60
A.4.4.3.63n 1 m2 Pasang Paving Stone Segi 6 abu abu Tebal 8 cm 21,021.60 86,400.60 - 107,422.20 21,021.60

4
HARGA SATUAN KONTRAK BAWAH HARGA SA
NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
A.4.4.3.63o 1 m2 Pasang Paving Stone Segi 6 abu abu Tebal 6 cm 21,021.60 79,503.60 - 100,525.20 21,021.60
A.4.4.3.63p 1 m2 Pasang Paving Stone Segi 6 Merah Tebal 8 Cm 21,021.60 100,194.60 - 121,216.20 21,021.60
A.4.4.3.63q 1 m2 Pasang Paving Stone Segi 6 Merah Tebal 6 Cm 21,021.60 82,262.40 - 103,284.00 21,021.60
A.4.4.3.63r 1 m2 Pasang Paving Stone (12 x 12) 5 warna Tebal 6 Cm 21,021.60 107,091.60 - 128,113.20 21,021.60

A.4.5.1 PEKERJAAN LANGIT - LANGIT ( PLAFOND )

A.4.5.1.1 1 m2 Pemasangan langit - langit Eternit Polos ( Asbes ) 10,661.85 18,242.28 - 28,904.13 10,661.85
A.4.5.1.1a 1 m2 Pemasangan langit - langit Eternit Kembang ( Asbes ) 10,661.85 13,477.08 - 24,138.93 10,661.85
A.4.5.1.2 1 m2 Pemasangan langit - langit akustik ukuran ( 30 x 30 ) cm 23,539.86 573,374.40 - 596,914.26 23,539.86
A.4.5.1.3 1 m2 Pemasangan langit - langit akustik ukuran ( 30 x 60 ) cm 23,539.86 314,298.00 - 337,837.86 23,539.86
A.4.5.1.4 1 m2 Pemasangan langit - langit akustik ukuran ( 60 x 120 ) cm 199,736.55 91,838.40 - 291,574.95 199,736.55
A.4.5.1.5 1 m2 Pemasangan langit - langit akustik ukuran ( 120 x 240 ) cm, tebal 3 mm,4mm & 6 mm 199,736.55 33,847.74 - 233,584.29 199,736.55
A.4.5.1.6 1 m2 Pemasangan langit - langit lambrisering kayu jati eks bojonegoro, tebal 9 mm 156,932.40 630,445.08 - 787,377.48 156,932.40
A.4.5.1.6a 1 m2 Pemasangan langit - langit lambrisering kayu jati lokal, tebal 9 mm 156,932.40 385,915.08 - 542,847.48 156,932.40
A.4.5.1.6b 1 m2 Pemasangan langit - langit lambrisering kayu kamfer, tebal 9 mm 156,932.40 197,815.08 - 354,747.48 156,932.40
A.4.5.1.6c 1 m2 Pemasangan langit - langit lambrisering kayu balau, tebal 9 mm 156,932.40 202,517.58 - 359,449.98 156,932.40
A.4.5.1.6d 1 m2 Pemasangan langit - langit lambrisering kayu kempas, tebal 9 mm 156,932.40 146,087.58 - 303,019.98 156,932.40
A.4.5.1.6e 1 m2 Pemasangan langit - langit lambrisering kayu kruing, tebal 9 mm 156,932.40 136,682.58 - 293,614.98 156,932.40
A.4.5.1.6f 1 m2 Pemasangan langit - langit lambrisering kayu meranti, tebal 9 mm 156,932.40 103,765.08 - 260,697.48 156,932.40
A.4.5.1.6g 1 m2 Pemasangan langit - langit lambrisering kayu tahun ( mauni / akasia ), tebal 9 mm 156,932.40 89,657.58 - 246,589.98 156,932.40
A.4.5.1.7 1 m2 Pemasangan langit - langit gypsum board ukuran ( 120 x 240 x 9 ) 9 mm 13,982.10 35,155.32 - 49,137.42 13,982.10
A.4.5.1.8 1 m2 Pemasangan langit - langit akustik ukuran ( 60 x 240 ) Cm rangka Alluminium 98,082.75 467,360.10 - 565,442.85 98,082.75
A.4.5.1.9 1 m' Pemasangan list langit - langit kayu profil 9,862.14 3,901.08 - 13,763.22 9,862.14
A.4.5.1.10 1 m2 Pemasangan rangka besi hollow 1x40.40.2, modul 60x60 cm, plafon 66,517.29 99,180.00 - 165,697.29 66,517.29
A.4.5.1.10a 1 m' List Plafond Gypsum Kecil 4,103.43 24,384.60 - 28,488.03 4,103.43
A.4.5.1.10b 1 m' List Plafond Gypsum Besar 4,103.43 31,207.50 - 35,310.93 4,103.43

A.4.5.2 HARGA SATUAN PENUTUP ATAP

A.4.5.2.1 1 m2 Pemasangan atap genteng MKP lokal 21,027.02 74,100.00 - 95,127.02 21,027.02
A.4.5.2.1a 1 m2 Pemasangan atap genteng Mantili 21,027.02 91,200.00 - 112,227.02 21,027.02
A.4.5.2.1b 1 m2 Pemasangan atap genteng Press biasa 21,027.02 65,550.00 - 86,577.02 21,027.02
A.4.5.2.1c 1 m2 Pemasangan atap genteng Prentul eks Trenggalek / Tulungagung 21,027.02 142,500.00 - 163,527.02 21,027.02
A.4.5.2.1d 1 m2 Pemasangan atap genteng Kaca ( model karangpilang) 21,027.02 324,900.00 - 345,927.02 21,027.02
A.4.5.2.2 1 m2 Pemasangan atap genteng glazuur eks Kanmuri 21,080.31 285,000.00 - 306,080.31 21,080.31
A.4.5.2.4 1 m2 Pemasangan bubung genteng MKP lokal 53,989.26 55,458.72 - 109,447.98 53,989.26
A.4.5.2.5 1 m2 Pemasangan bubung genteng glazuur eks Kanmuri 53,989.26 137,538.72 - 191,527.98 53,989.26
A.4.5.2.6a 1 m2 Pemasangan bubung genteng bubung mantili 51,595.26 51,582.72 - 103,177.98 51,595.26
A.4.5.2.6b 1 m2 Pemasangan bubung genteng bubung Prentul eks Trenggalek / Tulungagung 53,989.26 45,198.72 - 99,187.98 53,989.26
A.4.5.2.6c 1 m2 Pemasangan bubung genteng bubung Press 53,989.26 44,286.72 - 98,275.98 53,989.26
A.4.5.2.7 1 m2 Pemasangan roof light fibreglass 90 x 180 19,268.85 166,451.40 - 185,720.25 19,268.85
A.4.5.2.8 1 m2 Pemasangan atap asbes gelombang 0,92 m x 2,50 m x 5 mm 20,299.41 65,999.16 - 86,298.57 20,299.41
A.4.5.2.9 1 m2 Pemasangan atap asbes gelombang 0,92 m x 2,25 m x 5 mm 20,299.41 69,453.36 - 89,752.77 20,299.41
A.4.5.2.10 1 m2 Pemasangan atap asbes gelombang 0,92 m x 2,00 m x 5 mm 19,574.94 76,088.16 - 95,663.10 19,574.94
A.4.5.2.11 1 m2 Pemasangan atap asbes gelombang 0,92 m x 1,80 m x 5 mm 19,574.94 61,040.16 - 80,615.10 19,574.94
A.4.5.2.12 1 m2 Pemasangan atap asbes gelombang 1,05 m x 3,00 m x 4 mm 19,574.94 25,261.26 - 44,836.20 19,574.94
A.4.5.2.13 1 m2 Pemasangan atap asbes gelombang 1,05 m x 2,70 m x 4 mm 19,574.94 36,409.32 - 55,984.26 19,574.94
A.4.5.2.14 1 m2 Pemasangan atap asbes gelombang 1,05 m x 2,50 m x 4 mm 19,574.94 34,172.64 - 53,747.58 19,574.94
A.4.5.2.15 1 m2 Pemasangan atap asbes gelombang 1,05 m x 2,25 m x 4 mm 19,574.94 48,769.20 - 68,344.14 19,574.94
A.4.5.2.16 1 m2 Pemasangan atap asbes gelombang 1,05 m x 1,50 m x 4 mm 19,574.94 46,128.96 - 65,703.90 19,574.94
A.4.5.2.17 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 3,00 m x 5 mm 19,574.94 46,351.26 - 65,926.20 19,574.94
A.4.5.2.18 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 2,50 m x 5 mm 19,574.94 50,198.76 - 69,773.70 19,574.94
A.4.5.2.19 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 2,25 m x 5 mm 19,574.94 55,331.04 - 74,905.98 19,574.94
A.4.5.2.20 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 2,00 m x 5 mm 19,574.94 55,633.14 - 75,208.08 19,574.94
A.4.5.2.21 1 m2 Pemasangan atap asbes gelombang besar 0,92 x 2,50 m x 5 mm 19,574.94 75,216.06 - 94,791.00 19,574.94
A.4.5.2.22 1 m1 Pemasangan bumbungan stel gelombang 0,92 m 21,129.90 99,043.20 - 120,173.10 21,129.90
A.4.5.2.23 1 m1 Pemasangan bumbungan stel gelombang 1,05 m 21,129.90 99,145.80 - 120,275.70 21,129.90
A.4.5.2.24 1 m1 Pemasangan bumbungan stel gelombang 1,08 m 21,129.90 145,492.50 - 166,622.40 21,129.90
A.4.5.2.25 1 m1 Pemasangan nok paten 0,92 m 21,129.90 48,153.60 - 69,283.50 21,129.90
A.4.5.2.26 1 m1 Pemasangan nok paten 1,05 m 21,129.90 57,045.60 - 78,175.50 21,129.90
A.4.5.2.28 1 m1 Pemasangan nok stel rata 0,92 m 24,930.09 51,129.00 - 76,059.09 24,930.09
A.4.5.2.29 1 m1 Pemasangan nok stel rata 1,05 m 21,129.90 91,006.20 - 112,136.10 21,129.90
A.4.5.2.30 1 m2 Pemasangan genteng beton 27,964.20 62,720.52 - 90,684.72 27,964.20
A.4.5.2.32 1 m2 Pemasangan genteng metal 26,994.63 79,508.16 - 106,502.79 26,994.63
A.4.5.2.33 1 m2 Pemasangan atap sirap kayu 41,997.03 254,493.60 - 296,490.63 41,997.03
A.4.5.2.34 1 m1 Pemasangan nok genteng beton 55,928.40 50,362.92 - 106,291.32 55,928.40
A.4.5.2.36 1 m1 Pemasangan nok genteng metal 37,826.34 47,196.00 - 85,022.34 37,826.34
A.4.5.2.37 1 m1 Pemasangan nok sirap 38,579.88 21,181.20 - 59,761.08 38,579.88
A.4.5.2.38 1 m2 Pemasangan atap seng gelombang BJLS 30 Uk 180 x 90 x 0,03 cm 16,778.52 59,660.76 - 76,439.28 16,778.52
A.4.5.2.38a 1 m2 Pemasangan atap seng gelombang BJLS 20 Uk 180 x 90 x 0,02 cm 16,778.52 44,738.16 - 61,516.68 16,778.52
A.4.5.2.38b 1 m2 Pemasangan atap seng gelombang BJLS 30 Uk 305 x 90 x 0,03 cm 16,778.52 56,822.16 - 73,600.68 16,778.52
A.4.5.2.38c 1 m2 Pemasangan atap seng gelombang BJLS 20 Uk 305 x 90 x 0,02 cm 16,778.52 40,998.96 - 57,777.48 16,778.52
A.4.5.2.39 1 m2 Pemasangan atap seng BJLS 20 20,248.11 26,972.40 - 47,220.51 20,248.11
A.4.5.2.39a 1 m2 Pemasangan atap seng BJLS 27 20,248.11 14,557.80 - 34,805.91 20,248.11
A.4.5.2.39b 1 m2 Pemasangan atap seng BJLS 30 20,248.11 15,686.40 - 35,934.51 20,248.11
A.4.5.2.40 1 m2 Pemasangan atap alumunium tebal 0,25 mm 97,409.58 61,400.40 - 158,809.98 97,409.58
A.4.5.2.40a 1 m2 Pemasangan atap alumunium tebal 0,30 mm 97,409.58 71,814.30 - 169,223.88 97,409.58
A.4.5.2.40b 1 m2 Pemasangan atap alumunium tebal 0,35 mm 97,409.58 82,228.20 - 179,637.78 97,409.58

5
HARGA SATUAN KONTRAK BAWAH HARGA SA
NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
A.4.5.2.40c 1 m2 Pemasangan atap alumunium tebal 0,40 mm 97,409.58 91,804.20 - 189,213.78 97,409.58
A.4.5.2.41 1 m2 Pemasangan nok alumunium 34,057.50 23,757.60 - 57,815.10 34,057.50
A.4.5.2.42 1 m2 Pemasangan alumunium foil / sisalation 18,209.79 13,167.00 - 31,376.79 18,209.79

A.4.6.1 PEKERJAAN KAYU

A.4.6.1.1 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu jati eks Bojonegoro 2,950,804.50 38,662,131.00 - 41,612,935.50 2,950,804.50
A.4.6.1.1a 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu jati lokal 2,950,804.50 26,247,531.00 - 29,198,335.50 2,950,804.50
A.4.6.1.1b 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu kamfer 2,950,804.50 13,143,231.00 - 16,094,035.50 2,950,804.50
A.4.6.1.1c 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu balau 2,950,804.50 13,488,081.00 - 16,438,885.50 2,950,804.50
A.4.6.1.1d 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu kempas 2,950,804.50 9,349,881.00 - 12,300,685.50 2,950,804.50
A.4.6.1.1e 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu kruing 2,950,804.50 8,660,181.00 - 11,610,985.50 2,950,804.50
A.4.6.1.1f 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu meranti 2,950,804.50 6,935,931.00 - 9,886,735.50 2,950,804.50
A.4.6.1.1g 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu tahun ( mahuni/akasia ) 2,950,804.50 6,246,231.00 - 9,197,035.50 2,950,804.50
A.4.6.1.2 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu jati eks Bojonegoro 2,529,261.00 42,173,331.00 - 44,702,592.00 2,529,261.00
A.4.6.1.2a 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu jati lokal 2,529,261.00 28,630,131.00 - 31,159,392.00 2,529,261.00
A.4.6.1.2b 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu kamfer 2,529,261.00 14,334,531.00 - 16,863,792.00 2,529,261.00
A.4.6.1.2c 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu balau 2,529,261.00 14,710,731.00 - 17,239,992.00 2,529,261.00
A.4.6.1.2d 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu kempas 2,529,261.00 10,196,331.00 - 12,725,592.00 2,529,261.00
A.4.6.1.2e 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu kruing 2,529,261.00 9,443,931.00 - 11,973,192.00 2,529,261.00
A.4.6.1.2f 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu meranti 2,529,261.00 7,562,931.00 - 10,092,192.00 2,529,261.00
A.4.6.1.2g 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu tahun ( mauni / akasia ) 2,529,261.00 6,810,531.00 - 9,339,792.00 2,529,261.00
A.4.6.1.3 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu Jati eks Bojonegoro 147,594.09 1,681,283.40 - 1,828,877.49 147,594.09
A.4.6.1.3a 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu Jati 147,594.09 1,029,203.40 - 1,176,797.49 147,594.09
A.4.6.1.3b 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu kamfer 147,594.09 527,603.40 - 675,197.49 147,594.09
A.4.6.1.3c 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu balau 147,594.09 540,143.40 - 687,737.49 147,594.09
A.4.6.1.3d 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu kempas 147,594.09 389,663.40 - 537,257.49 147,594.09
A.4.6.1.3e 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu kruing 147,594.09 364,583.40 - 512,177.49 147,594.09
A.4.6.1.3f 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu meranti 147,594.09 276,803.40 - 424,397.49 147,594.09
A.4.6.1.3g 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu tahun ( mauni / akasia ) 147,594.09 239,183.40 - 386,777.49 147,594.09
A.4.6.1.4 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu Jati eks Bojonegoro 147,594.09 1,681,283.40 - 1,828,877.49 147,594.09
A.4.6.1.4a 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu Jati 147,594.09 1,029,203.40 - 1,176,797.49 147,594.09
A.4.6.1.4b 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu kamfer 147,594.09 527,603.40 - 675,197.49 147,594.09
A.4.6.1.4c 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu balau 147,594.09 540,143.40 - 687,737.49 147,594.09
A.4.6.1.4d 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu kempas 147,594.09 389,663.40 - 537,257.49 147,594.09
A.4.6.1.4e 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu kruing 147,594.09 364,583.40 - 512,177.49 147,594.09
A.4.6.1.4f 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu meranti 147,594.09 276,803.40 - 424,397.49 147,594.09
A.4.6.1.4g 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu tahun ( mauni / akasia ) 147,594.09 239,183.40 - 386,777.49 147,594.09
A.4.6.1.5 1 m2 Pembuatan dan pemasangan pintu panel, kayu Jati eks Bojonegoro 421,543.50 1,681,152.30 - 2,102,695.80 421,543.50
A.4.6.1.5a 1 m2 Pembuatan dan pemasangan pintu panel, kayu Jati lokal 421,543.50 1,029,072.30 - 1,450,615.80 421,543.50
A.4.6.1.5b 1 m2 Pembuatan dan pemasangan pintu panel, kayu kamfer 421,543.50 527,472.30 - 949,015.80 421,543.50
A.4.6.1.5c 1 m2 Pembuatan dan pemasangan pintu panel, kayu balau 421,543.50 540,012.30 - 961,555.80 421,543.50
A.4.6.1.5d 1 m2 Pembuatan dan pemasangan pintu panel, kayu kempas 421,543.50 389,532.30 - 811,075.80 421,543.50
A.4.6.1.5e 1 m2 Pembuatan dan pemasangan pintu panel, kayu kruing 421,543.50 364,452.30 - 785,995.80 421,543.50
A.4.6.1.5f 1 m2 Pembuatan dan pemasangan pintu panel, kayu meranti 421,543.50 276,672.30 - 698,215.80 421,543.50
A.4.6.1.5g 1 m2 Pembuatan dan pemasangan pintu panel, kayu tahun ( mauni / akasia ) 421,543.50 239,052.30 - 660,595.80 421,543.50
A.4.6.1.6 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu Jati eks Bojonegoro 337,234.80 1,012,969.80 - 1,350,204.60 337,234.80
A.4.6.1.6a 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu Jati lokal 337,234.80 621,721.80 - 958,956.60 337,234.80
A.4.6.1.6b 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu kamfer 337,234.80 320,761.80 - 657,996.60 337,234.80
A.4.6.1.6c 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu balau 337,234.80 328,285.80 - 665,520.60 337,234.80
A.4.6.1.6d 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu kempas 337,234.80 237,997.80 - 575,232.60 337,234.80
A.4.6.1.6e 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu kruing 337,234.80 222,949.80 - 560,184.60 337,234.80
A.4.6.1.6f 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu meranti 337,234.80 170,281.80 - 507,516.60 337,234.80
A.4.6.1.6g 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu Tahun papan ( Mauni/akasia) 337,234.80 147,709.80 - 484,944.60 337,234.80
A.4.6.1.7 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu Jati papan eks. Bojonegoro 421,543.50 2,696,499.00 - 3,118,042.50 421,543.50
A.4.6.1.7a 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu jati papan lokal 421,543.50 1,653,171.00 - 2,074,714.50 421,543.50
A.4.6.1.7b 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu kanfer 421,543.50 850,611.00 - 1,272,154.50 421,543.50
A.4.6.1.7c 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu balau 421,543.50 870,675.00 - 1,292,218.50 421,543.50
A.4.6.1.7d 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu kempas 421,543.50 629,907.00 - 1,051,450.50 421,543.50
A.4.6.1.7e 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu kruing 421,543.50 589,779.00 - 1,011,322.50 421,543.50
A.4.6.1.7f 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu meranti 421,543.50 449,331.00 - 870,874.50 421,543.50
A.4.6.1.7g 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu tahun ( mauni / akasia ) 421,543.50 389,139.00 - 810,682.50 421,543.50
A.4.6.1.8 1 m2 Pembuatan daun pintu plywood rangka kayu Jati eks Bojonegoro tertutup lebar sampai 90 Cm 295,080.45 1,129,610.04 - 1,424,690.49 295,080.45
A.4.6.1.8a 1 m2 Pembuatan daun pintu plywood rangka kayu Jati lokal tertutup lebar sampai 90 Cm 295,080.45 722,060.04 - 1,017,140.49 295,080.45
A.4.6.1.8b 1 m2 Pembuatan daun pintu plywood rangka kayu kamfer tertutup lebar sampai 90 Cm 295,080.45 408,560.04 - 703,640.49 295,080.45
A.4.6.1.8c 1 m2 Pembuatan daun pintu plywood rangka kayu balau tertutup lebar sampai 90 Cm 295,080.45 416,397.54 - 711,477.99 295,080.45
A.4.6.1.8d 1 m2 Pembuatan daun pintu plywood rangka kayu kempas tertutup lebar sampai 90 Cm 295,080.45 322,347.54 - 617,427.99 295,080.45
A.4.6.1.8e 1 m2 Pembuatan daun pintu plywood rangka kayu kruing tertutup lebar sampai 90 Cm 295,080.45 306,672.54 - 601,752.99 295,080.45
A.4.6.1.8f 1 m2 Pembuatan daun pintu plywood rangka kayu meranti tertutup lebar sampai 90 Cm 295,080.45 251,810.04 - 546,890.49 295,080.45
A.4.6.1.8g 1 m2 Pembuatan daun pintu plywood rangka kayu tahun ( mauni / akasia ) tertutup lebar sampai 90 Cm 295,080.45 228,297.54 - 523,377.99 295,080.45
A.4.6.1.9 1 m2 Pembuatan daun pintu plywood rangka expose kayu Jati eks Bojonegoro 337,234.80 2,431,889.04 - 2,769,123.84 337,234.80
A.4.6.1.9a 1 m2 Pembuatan daun pintu plywood rangka expose kayu Jati lokal 337,234.80 1,518,977.04 - 1,856,211.84 337,234.80
A.4.6.1.9b 1 m2 Pembuatan daun pintu plywood rangka expose kayu kamfer 337,234.80 816,737.04 - 1,153,971.84 337,234.80
A.4.6.1.9c 1 m2 Pembuatan daun pintu plywood rangka expose kayu balau 337,234.80 834,293.04 - 1,171,527.84 337,234.80
A.4.6.1.9d 1 m2 Pembuatan daun pintu plywood rangka expose kayu kempas 337,234.80 623,621.04 - 960,855.84 337,234.80
A.4.6.1.9e 1 m2 Pembuatan daun pintu plywood rangka expose kayu kruing 337,234.80 588,509.04 - 925,743.84 337,234.80
A.4.6.1.9f 1 m2 Pembuatan daun pintu plywood rangka expose kayu meranti 337,234.80 465,617.04 - 802,851.84 337,234.80
A.4.6.1.9g 1 m2 Pembuatan daun pintu plywood rangka expose kayu tahun ( mauni / akasia ) 337,234.80 412,949.04 - 750,183.84 337,234.80
A.4.6.1.10 1 m2 Pemasangan jalusi kusen, kayu Jati eks Bojonegoro 313,787.85 2,523,310.20 - 2,837,098.05 313,787.85

6
HARGA SATUAN KONTRAK BAWAH HARGA SA
NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
A.4.6.1.10a 1 m2 Pemasangan jalusi kusen, kayu Jati lokal 313,787.85 1,545,190.20 - 1,858,978.05 313,787.85
A.4.6.1.10b 1 m2 Pemasangan jalusi kusen, kayu kamfer 313,787.85 792,790.20 - 1,106,578.05 313,787.85
A.4.6.1.10c 1 m2 Pemasangan jalusi kusen, kayu balau 313,787.85 811,600.20 - 1,125,388.05 313,787.85
A.4.6.1.10d 1 m2 Pemasangan jalusi kusen, kayu kempas 313,787.85 585,880.20 - 899,668.05 313,787.85
A.4.6.1.10e 1 m2 Pemasangan jalusi kusen, kayu kruing 313,787.85 548,260.20 - 862,048.05 313,787.85
A.4.6.1.10f 1 m2 Pemasangan jalusi kusen, kayu meranti 313,787.85 416,590.20 - 730,378.05 313,787.85
A.4.6.1.10g 1 m2 Pemasangan jalusi kusen, kayu tahun ( mauni / akasia ) 313,787.85 360,160.20 - 673,948.05 313,787.85
A.4.6.1.11 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Jati eks Bojonegoro 337,234.80 1,147,074.84 - 1,484,309.64 337,234.80
A.4.6.1.11a 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Jati lokal 337,234.80 739,524.84 - 1,076,759.64 337,234.80
A.4.6.1.11b 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Kamfer 337,234.80 426,024.84 - 763,259.64 337,234.80
A.4.6.1.11c 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Balau 337,234.80 433,862.34 - 771,097.14 337,234.80
A.4.6.1.11d 1 m2 Pemasangan teakwood rangkap, rangka expose kayu kempas 337,234.80 339,812.34 - 677,047.14 337,234.80
A.4.6.1.11e 1 m2 Pemasangan teakwood rangkap, rangka expose kayu kruing 337,234.80 324,137.34 - 661,372.14 337,234.80
A.4.6.1.11f 1 m2 Pemasangan teakwood rangkap, rangka expose kayu meranti 337,234.80 269,274.84 - 606,509.64 337,234.80
A.4.6.1.11g 1 m2 Pemasangan teakwood rangkap, rangka expose kayu tahun ( mauni / akasia ) 337,234.80 245,762.34 - 582,997.14 337,234.80
A.4.6.1.12 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Jati eks Bojonegoro 358,365.84 1,311,747.84 - 1,670,113.68 358,365.84
A.4.6.1.12a 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Jati lokal 358,365.84 904,197.84 - 1,262,563.68 358,365.84
A.4.6.1.12b 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Kamfer 358,365.84 590,697.84 - 949,063.68 358,365.84
A.4.6.1.12c 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Balau 358,365.84 598,535.34 - 956,901.18 358,365.84
A.4.6.1.12d 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Kempas 358,365.84 504,485.34 - 862,851.18 358,365.84
A.4.6.1.12e 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Kruing 358,365.84 488,810.34 - 847,176.18 358,365.84
A.4.6.1.12f 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Meranti 358,365.84 433,947.84 - 792,313.68 358,365.84
A.4.6.1.12g 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu tahun ( mauni / akasia ) 358,365.84 410,435.34 - 768,801.18 358,365.84
A.4.6.1.13 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Jati Eks Bojonegoro bentang 6 meter 1,686,174.00 39,046,390.80 - 40,732,564.80 1,686,174.00
A.4.6.1.13a 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu lokal bentang 6 meter 1,686,174.00 26,631,790.80 - 28,317,964.80 1,686,174.00
A.4.6.1.13b 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Jati Kamfer bentang 6 meter 1,686,174.00 14,906,890.80 - 16,593,064.80 1,686,174.00
A.4.6.1.13c 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Balau bentang 6 meter 1,686,174.00 13,872,340.80 - 15,558,514.80 1,686,174.00
A.4.6.1.13d 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Kempas bentang 6 meter 1,686,174.00 9,734,140.80 - 11,420,314.80 1,686,174.00
A.4.6.1.13e 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Kruing bentang 6 meter 1,686,174.00 9,044,440.80 - 10,730,614.80 1,686,174.00
A.4.6.1.13f 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Meranti bentang 6 meter 1,686,174.00 7,320,190.80 - 9,006,364.80 1,686,174.00
A.4.6.1.13g 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu tahun ( mauni / akasia ) bentang 6 meter 1,686,174.00 6,630,490.80 - 8,316,664.80 1,686,174.00
A.4.6.1.14 1 m3 Pemasangan konstruksi kuda kuda expose kayu Jati eks Bojonegoro 2,824,341.45 42,557,590.80 - 45,381,932.25 2,824,341.45
A.4.6.1.14a 1 m3 Pemasangan konstruksi kuda kuda expose kayu Jati lokal 2,824,341.45 29,014,390.80 - 31,838,732.25 2,824,341.45
A.4.6.1.14b 1 m3 Pemasangan konstruksi kuda kuda expose kayu Kamfer 2,824,341.45 14,718,790.80 - 17,543,132.25 2,824,341.45
A.4.6.1.14c 1 m3 Pemasangan konstruksi kuda kuda expose kayu Balau 2,824,341.45 15,094,990.80 - 17,919,332.25 2,824,341.45
A.4.6.1.14d 1 m3 Pemasangan konstruksi kuda kuda expose kayu Kempas 2,824,341.45 10,580,590.80 - 13,404,932.25 2,824,341.45
A.4.6.1.14e 1 m3 Pemasangan konstruksi kuda kuda expose kayu Kruing 2,824,341.45 9,828,190.80 - 12,652,532.25 2,824,341.45
A.4.6.1.14f 1 m3 Pemasangan konstruksi kuda kuda expose kayu Meranti 2,824,341.45 7,947,190.80 - 10,771,532.25 2,824,341.45
A.4.6.1.14g 1 m3 Pemasangan konstruksi kuda kuda expose kayu Tahun ( mauni / akasia ) 2,824,341.45 7,194,790.80 - 10,019,132.25 2,824,341.45
A.4.6.1.15 1 m3 Pemasangan konstruksi gordeng, kayu Jati eks Bojonegoro 2,824,341.45 38,998,374.00 - 41,822,715.45 2,824,341.45
A.4.6.1.15a 1 m3 Pemasangan konstruksi gordeng, kayu Jati lokal 2,824,341.45 26,583,774.00 - 29,408,115.45 2,824,341.45
A.4.6.1.15b 1 m3 Pemasangan konstruksi gordeng, kayu kamfer 2,824,341.45 13,479,474.00 - 16,303,815.45 2,824,341.45
A.4.6.1.15c 1 m3 Pemasangan konstruksi gordeng, kayu Balau 2,824,341.45 13,824,324.00 - 16,648,665.45 2,824,341.45
A.4.6.1.15d 1 m3 Pemasangan konstruksi gordeng, kayu Kempas 2,824,341.45 9,686,124.00 - 12,510,465.45 2,824,341.45
A.4.6.1.15e 1 m3 Pemasangan konstruksi gordeng, kayu Kruing 2,824,341.45 8,996,424.00 - 11,820,765.45 2,824,341.45
A.4.6.1.15f 1 m3 Pemasangan konstruksi gordeng, kayu Meranti 2,824,341.45 7,272,174.00 - 10,096,515.45 2,824,341.45
A.4.6.1.15g 1 m3 Pemasangan konstruksi gordeng, kayu Tahun ( mauni / akasia ) 2,824,341.45 6,582,474.00 - 9,406,815.45 2,824,341.45
A.4.6.1.16 1 m2 Pemasangan rangka atap genteng keramik, kayu Jati eks Bojonegoro 19,616.55 622,588.20 - 642,204.75 19,616.55
A.4.6.1.16a 1 m2 Pemasangan rangka atap genteng keramik, kayu Jati lokal 19,616.55 423,954.60 - 443,571.15 19,616.55
A.4.6.1.16b 1 m2 Pemasangan rangka atap genteng keramik, kayu Kamfer 19,616.55 214,285.80 - 233,902.35 19,616.55
A.4.6.1.16c 1 m2 Pemasangan rangka atap genteng keramik, kayu Balau 19,616.55 219,803.40 - 239,419.95 19,616.55
A.4.6.1.16d 1 m2 Pemasangan rangka atap genteng keramik, kayu Kempas 19,616.55 153,592.20 - 173,208.75 19,616.55
A.4.6.1.16e 1 m2 Pemasangan rangka atap genteng keramik, kayu Kruing 19,616.55 142,557.00 - 162,173.55 19,616.55
A.4.6.1.16f 1 m2 Pemasangan rangka atap genteng keramik, kayu Meranti 19,616.55 114,969.00 - 134,585.55 19,616.55
A.4.6.1.16g 1 m2 Pemasangan rangka atap genteng keramik, kayu Tahun ( mauni / akasia ) 19,616.55 103,933.80 - 123,550.35 19,616.55
A.4.6.1.17 1 m2 Pemasangan rangka atap genteng beton, kayu Jati eks Bojonegoro 19,616.55 696,323.40 - 715,939.95 19,616.55
A.4.6.1.17a 1 m2 Pemasangan rangka atap genteng beton, kayu Jati lokal 19,616.55 473,989.20 - 493,605.75 19,616.55
A.4.6.1.17b 1 m2 Pemasangan rangka atap genteng beton, kayu Kamper 19,616.55 239,303.10 - 258,919.65 19,616.55
A.4.6.1.17c 1 m2 Pemasangan rangka atap genteng beton, kayu Balau 19,616.55 245,479.05 - 265,095.60 19,616.55
A.4.6.1.17d 1 m2 Pemasangan rangka atap genteng beton, kayu Kempas 19,616.55 171,367.65 - 190,984.20 19,616.55
A.4.6.1.17e 1 m2 Pemasangan rangka atap genteng beton, kayu Kruing 19,616.55 159,015.75 - 178,632.30 19,616.55
A.4.6.1.17f 1 m2 Pemasangan rangka atap genteng beton, kayu Meranti 19,616.55 128,136.00 - 147,752.55 19,616.55
A.4.6.1.17g 1 m2 Pemasangan rangka atap genteng beton, kayu Tahun ( mauni / akasia ) 19,616.55 128,136.00 - 147,752.55 19,616.55
A.4.6.1.18 1 m2 Pemasangan rangka atap sirap, kayu Jati eks Bojonegoro 19,616.55 492,620.68 - 516,160.54 19,616.55
A.4.6.1.18a 1 m2 Pemasangan rangka atap sirap, kayu Jati lokal 23,539.86 334,616.68 - 358,156.54 23,539.86
A.4.6.1.18b 1 m2 Pemasangan rangka atap sirap, kayu Kamfer 23,539.86 167,834.68 - 191,374.54 23,539.86
A.4.6.1.18c 1 m2 Pemasangan rangka atap sirap, kayu Balau 23,539.86 172,223.68 - 195,763.54 23,539.86
A.4.6.1.18d 1 m2 Pemasangan rangka atap sirap, kayu Kempas 23,539.86 119,555.68 - 143,095.54 23,539.86
A.4.6.1.18e 1 m2 Pemasangan rangka atap sirap, kayu Kruing 23,539.86 110,777.68 - 134,317.54 23,539.86
A.4.6.1.18f 1 m2 Pemasangan rangka atap sirap, kayu Meranti 23,539.86 88,832.68 - 112,372.54 23,539.86
A.4.6.1.18g 1 m2 Pemasangan rangka atap sirap, kayu Tahun ( mauni / akasia ) 23,539.86 80,054.68 - 103,594.54 23,539.86
A.4.6.1.19 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Jati eks Bojonegoro 53,599.95 544,418.40 - 598,018.35 53,599.95
A.4.6.1.19a 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Jati lokal 53,599.95 370,614.00 - 424,213.95 53,599.95
A.4.6.1.19b 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Kamfer 53,599.95 187,153.80 - 240,753.75 53,599.95
A.4.6.1.19c 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Balau 53,599.95 191,981.70 - 245,581.65 53,599.95
A.4.6.1.19d 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Kempas 53,599.95 134,046.90 - 187,646.85 53,599.95
A.4.6.1.19e 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Kruing 53,599.95 124,391.10 - 177,991.05 53,599.95
A.4.6.1.19f 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Meranti 53,599.95 100,251.60 - 153,851.55 53,599.95
A.4.6.1.19g 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Tahun ( mauni / akasia ) 53,599.95 90,595.80 - 144,195.75 53,599.95

7
HARGA SATUAN KONTRAK BAWAH HARGA SA
NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
A.4.6.1.20 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Jati eks Bojonegoro 50,502.00 576,942.60 - 627,444.60 50,502.00
A.4.6.1.20a 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Jati lokal 50,502.00 392,980.80 - 443,482.80 50,502.00
A.4.6.1.20b 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Kamfer 50,502.00 198,798.90 - 249,300.90 50,502.00
A.4.6.1.20c 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Balau 50,502.00 203,908.95 - 254,410.95 50,502.00
A.4.6.1.20d 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Kempas 50,502.00 142,588.35 - 193,090.35 50,502.00
A.4.6.1.20e 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Kruing 50,502.00 132,368.25 - 182,870.25 50,502.00
A.4.6.1.20f 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Meranti 50,502.00 106,818.00 - 157,320.00 50,502.00
A.4.6.1.20g 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Tahun 9 mauni / akasia ) 50,502.00 96,597.90 - 147,099.90 50,502.00
A.4.6.1.21 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Jati eks Bojonegoro 30,885.45 455,544.00 - 486,429.45 30,885.45
A.4.6.1.21a 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Jati lokal 30,885.45 279,482.40 - 310,367.85 30,885.45
A.4.6.1.21b 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Kamfer 30,885.45 144,050.40 - 174,935.85 30,885.45
A.4.6.1.21c 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Balau 30,885.45 147,436.20 - 178,321.65 30,885.45
A.4.6.1.21d 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Jati Kempas 30,885.45 106,806.60 - 137,692.05 30,885.45
A.4.6.1.21e 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Kruing 30,885.45 100,035.00 - 130,920.45 30,885.45
A.4.6.1.21f 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Meranti 30,885.45 76,334.40 - 107,219.85 30,885.45
A.4.6.1.21g 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Tahun ( mauni / akasia ) 30,885.45 66,177.00 - 97,062.45 30,885.45
A.4.6.1.22 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Jati eks Bojonegoro 30,885.45 463,022.40 - 493,907.85 30,885.45
A.4.6.1.22a 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Jati lokal 30,885.45 283,700.40 - 314,585.85 30,885.45
A.4.6.1.22b 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Kamfer 30,885.45 145,760.40 - 176,645.85 30,885.45
A.4.6.1.22c 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Balau 30,885.45 149,208.90 - 180,094.35 30,885.45
A.4.6.1.22d 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Kempas 30,885.45 107,826.90 - 138,712.35 30,885.45
A.4.6.1.22e 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Kruing 30,885.45 100,929.90 - 131,815.35 30,885.45
A.4.6.1.22f 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Meranti 30,885.45 76,790.40 - 107,675.85 30,885.45
A.4.6.1.22g 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Tahun ( mauni / akasia ) 30,885.45 66,444.90 - 97,330.35 30,885.45
A.4.6.1.23 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Jati eks Bojonegoro 63,285.39 1,179,022.20 - 1,242,307.59 63,285.39
A.4.6.1.23a 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Jati lokal 63,285.39 722,566.20 - 785,851.59 63,285.39
A.4.6.1.23b 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Kamfer 63,285.39 371,446.20 - 434,731.59 63,285.39
A.4.6.1.23c 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Balau 63,285.39 380,224.20 - 443,509.59 63,285.39
A.4.6.1.23d 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Kempas 63,285.39 274,888.20 - 338,173.59 63,285.39
A.4.6.1.23e 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Kruing 63,285.39 257,332.20 - 320,617.59 63,285.39
A.4.6.1.23f 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Meranti 63,285.39 195,886.20 - 259,171.59 63,285.39
A.4.6.1.23g 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Tahun ( mauni / akasia ) 63,285.39 169,552.20 - 232,837.59 63,285.39
A.4.6.1.24 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Jati eks Bojonegoro 63,285.39 1,076,839.44 - 1,140,124.83 63,285.39
A.4.6.1.24a 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Jati lokal 63,285.39 760,831.44 - 824,116.83 63,285.39
A.4.6.1.24b 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Kamfer 63,285.39 427,267.44 - 490,552.83 63,285.39
A.4.6.1.24c 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Balau 63,285.39 436,045.44 - 499,330.83 63,285.39
A.4.6.1.24d 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Kempas 63,285.39 330,709.44 - 393,994.83 63,285.39
A.4.6.1.24e 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Kruing 63,285.39 313,153.44 - 376,438.83 63,285.39
A.4.6.1.24f 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Meranti 63,285.39 269,263.44 - 332,548.83 63,285.39
A.4.6.1.24g 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Tahun ( mauni / akasia ) 63,285.39 251,707.44 - 314,992.83 63,285.39
A.4.6.1.25 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Jati eks Bojonegoro 94,004.40 1,091,839.56 - 1,185,843.96 94,004.40
A.4.6.1.25a 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Jati lokal 94,004.40 775,831.56 - 869,835.96 94,004.40
A.4.6.1.25b 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Kamfer 94,004.40 442,267.56 - 536,271.96 94,004.40
A.4.6.1.25c 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Balau 94,004.40 451,045.56 - 545,049.96 94,004.40
A.4.6.1.25d 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Kempas 94,004.40 345,709.56 - 439,713.96 94,004.40
A.4.6.1.25e 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Kruing 94,004.40 328,153.56 - 422,157.96 94,004.40
A.4.6.1.25f 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Meranti 94,004.40 284,263.56 - 378,267.96 94,004.40
A.4.6.1.25g 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Tahun ( mauni / akasia ) 94,004.40 266,707.56 - 360,711.96 94,004.40
A.4.6.1.26 1 m2 Pemasangan dinding lambrisering dari papan kayu Jati eks Bojoneoro 252,926.10 296,012.40 - 548,938.50 252,926.10
A.4.6.1.26a 1 m2 Pemasangan dinding lambrisering dari papan kayu Jati lokal 252,926.10 181,898.40 - 434,824.50 252,926.10
A.4.6.1.26b 1 m2 Pemasangan dinding lambrisering dari papan kayu Kamfer 252,926.10 94,118.40 - 347,044.50 252,926.10
A.4.6.1.26c 1 m2 Pemasangan dinding lambrisering dari papan kayu Balau 252,926.10 96,312.90 - 349,239.00 252,926.10
A.4.6.1.26d 1 m2 Pemasangan dinding lambrisering dari papan kayu Kempas 252,926.10 69,978.90 - 322,905.00 252,926.10
A.4.6.1.26e 1 m2 Pemasangan dinding lambrisering dari papan kayu Kruing 252,926.10 65,589.90 - 318,516.00 252,926.10
A.4.6.1.26f 1 m2 Pemasangan dinding lambrisering dari papan kayu Meranti 252,926.10 50,228.40 - 303,154.50 252,926.10
A.4.6.1.26g 1 m2 Pemasangan dinding lambrisering dari papan kayu Tahun ( mauni / akasia ) 252,926.10 43,644.90 - 296,571.00 252,926.10
A.4.6.1.27 1 m2 Pemasangan dinding lambrisering dari plywood ukuran 120 x 240 cm 10,564.95 46,067.40 - 56,632.35 10,564.95
A.4.6.1.28 1 m2 Pemasangan dinding bilik, rangka kayu Jati eks Bojonegoro 13,982.10 648,425.62 - 662,407.72 13,982.10
A.4.6.1.28a 1 m2 Pemasangan dinding bilik, rangka kayu Jati lokal 13,982.10 456,563.62 - 470,545.72 13,982.10
A.4.6.1.28b 1 m2 Pemasangan dinding bilik, rangka kayu Kamfer 13,982.10 254,042.62 - 268,024.72 13,982.10
A.4.6.1.28c 1 m2 Pemasangan dinding bilik, rangka kayu Balau 13,982.10 259,372.12 - 273,354.22 13,982.10
A.4.6.1.28d 1 m2 Pemasangan dinding bilik, rangka kayu Kempas 13,982.10 195,418.12 - 209,400.22 13,982.10
A.4.6.1.28e 1 m2 Pemasangan dinding bilik, rangka kayu Kruing 13,982.10 184,759.12 - 198,741.22 13,982.10
A.4.6.1.28f 1 m2 Pemasangan dinding bilik, rangka kayu Meranti 13,982.10 158,111.62 - 172,093.72 13,982.10
A.4.6.1.28g 1 m2 Pemasangan dinding bilik, rangka kayu Tahun ( mauni / akasia ) 13,982.10 147,452.62 - 161,434.72 13,982.10

A.4.6.2 PEKERJAAN KUNCI DAN KACA

A.4.6.2.1 1 bh Pemasangan kunci tanam antik eks Miler 72,621.99 269,952.00 - 342,573.99 72,621.99
A.4.6.2.1a 1 bh Pemasangan kunci tanam ( SES ) 72,621.99 247,494.00 - 320,115.99 72,621.99
A.4.6.2.2 1 bh Pemasangan kunci tanam biasa 57,664.05 80,370.00 - 138,034.05 57,664.05
A.4.6.2.2a 1 bh Pemasangan kunci tanam slot tanam eks Kuda 2x putaran 57,664.05 80,370.00 - 138,034.05 57,664.05
A.4.6.2.3 1 bh Pemasangan kunci Slot tanam kamar mandi eks Miler 57,058.14 82,992.00 - 140,050.14 57,058.14
A.4.6.2.3a 1 bh Pemasangan kunci Slot tanam kamar mandi 57,058.14 158,004.00 - 215,062.14 57,058.14
A.4.6.2.5 1 bh Pemasangan engsel pintu kupu - kupu 18,160.88 46,740.00 - 64,900.88 18,160.88
A.4.6.2.5a 1 bh Pemasangan engsel kuningan Arc Asli eks Elitech 4" 18,160.88 90,174.00 - 108,334.88 18,160.88
A.4.6.2.5b 1 bh Pemasangan engsel pintu ( H ) 18,160.88 16,416.00 - 34,576.88 18,160.88
A.4.6.2.5c 1 bh Pemasangan engsel pintu ( Arc ) nylon 18,160.88 11,172.00 - 29,332.88 18,160.88
A.4.6.2.5d 1 bh Pemasangan engsel pintu eks Union 4" 18,160.88 54,036.00 - 72,196.88 18,160.88

8
HARGA SATUAN KONTRAK BAWAH HARGA SA
NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
A.4.6.2.5e 1 bh Pemasangan engsel Stainlesstel Dekson 3" 18,160.88 60,534.00 - 78,694.88 18,160.88
A.4.6.2.5f 1 bh Pemasangan engsel Stainlesstel Dekson 4" 18,160.88 142,158.00 - 160,318.88 18,160.88
A.4.6.2.5g 1 bh Pemasangan engsel Stainlesstel Dekson 5" 18,160.88 162,678.00 - 180,838.88 18,160.88
A.4.6.2.5h 1 bh Pemasangan engsel Sendok 18,160.88 13,794.00 - 31,954.88 18,160.88
A.4.6.2.6 1 bh Pemasangan engsel jendela kupu kupu 12,103.67 23,028.00 - 35,131.67 12,103.67
A.4.6.2.6a 1 bh Pemasangan engsel jendela eks Union 3" 12,103.67 40,926.00 - 53,029.67 12,103.67
A.4.6.2.6b 1 bh Pemasangan engsel jendela ( H ) 12,103.67 19,038.00 - 31,141.67 12,103.67
A.4.6.2.6c 1 bh Pemasangan engsel jendela ( Arch ) 12,103.67 19,836.00 - 31,939.67 12,103.67
A.4.6.2.6d 1 bh Pemasangan grendel biasa ( besar ) 8" 12,103.67 16,416.00 - 28,519.67 12,103.67
A.4.6.2.6e 1 bh Pemasangan grendel biasa ( kecil ) 3" 12,103.67 7,866.00 - 19,969.67 12,103.67
A.4.6.2.6f 1 bh Pemasangan grendel eks AEG 12,103.67 36,822.00 - 48,925.67 12,103.67
A.4.6.2.6g 1 bh Pemasangan grendel jendela merk SES 12,103.67 27,018.00 - 39,121.67 12,103.67
A.4.6.2.6h 1 bh Pemasangan grendel pintu panjang ( sespen ) 12,103.67 59,280.00 - 71,383.67 12,103.67
A.4.6.2.6i 1 bh Pemasangan grendel pintu ganda Dekson 40 cm komplit 12,103.67 210,672.00 - 222,775.67 12,103.67
A.4.6.2.6j 1 bh Pemasangan grendel tanam kuningan besar eks Cavel 60 mm 12,103.67 305,520.00 - 317,623.67 12,103.67
A.4.6.2.6k 1 bh Pemasangan grendel tanam kuningan kecil eks beluci 4" 12,103.67 177,840.00 - 189,943.67 12,103.67
A.4.6.2.6l 1 bh Pemasangan grendel tanam merk SES 12,103.67 46,740.00 - 58,843.67 12,103.67
A.4.6.2.7 1 bh Pemasangan hak angin 30,400.67 19,836.00 - 50,236.67 30,400.67
A.4.6.2.7a 1 bh Pemasangan hak angin ( Sikutan ) biasa 30,400.67 24,282.00 - 54,682.67 30,400.67
A.4.6.2.7b 1 bh Pemasangan hak angin 4 mm lurus / plat 4 x 150 mm 30,400.67 21,090.00 - 51,490.67 30,400.67
A.4.6.2.7c 1 bh Pemasangan hak angin lurus 30,400.67 41,496.00 - 71,896.67 30,400.67
A.4.6.2.7d 1 bh Pemasangan hak angin merk SES 30,400.67 38,304.00 - 68,704.67 30,400.67
A.4.6.2.9 1 bh Pemasangan kait angin 18,936.54 19,836.00 - 38,772.54 18,936.54
A.4.6.2.10 1 bh Pemasangan door closer 60,572.19 246,924.00 - 307,496.19 60,572.19
A.4.6.2.11 1 bh Pemasangan kunci sloot 2 putaran eks CAVEL ( dengan handle ) 24,207.33 239,058.00 - 263,265.33 24,207.33
A.4.6.2.11a 1 bh Pemasangan kunci sloot 2 putaran eks kodai 24,207.33 122,550.00 - 146,757.33 24,207.33
A.4.6.2.11b 1 bh Pemasangan kunci sloot 2 putaran eks YALE ( dengan handle ) 24,207.33 140,904.00 - 165,111.33 24,207.33
A.4.6.2.11c 1 bh Pemasangan kunci sloot ( kunci pintu ) merk SES 24,207.33 322,620.00 - 346,827.33 24,207.33
A.4.6.2.11d 1 bh Pemasangan kunci sloot ( kunci pintu ) merk SES 24,207.33 322,620.00 - 346,827.33 24,207.33
A.4.6.2.11e 1 bh Pemasangan kunci sloot Rossete Dekson 24,207.33 358,758.00 - 382,965.33 24,207.33
A.4.6.2.11f 1 bh Pemasangan kunci sloot ( kunci pintu ) lokal 24,207.33 109,326.00 - 133,533.33 24,207.33
A.4.6.2.12a 1 bh Pemasangan Handle 60,572.19 96,216.00 - 156,788.19 60,572.19
A.4.6.2.12b 1 bh Pemasangan Handle pintu ganda Dekson 30 cm komplit 60,572.19 130,416.00 - 190,988.19 60,572.19
A.4.6.2.12c 1 bh Pemasangan Handle pintu ganda Dekson 40 cm komplit 60,572.19 308,142.00 - 368,714.19 60,572.19
A.4.6.2.12d 1 bh Pemasangan Handle ointu stainless steel besar 60,572.19 581,970.00 - 642,542.19 60,572.19
A.4.6.2.12e 1 bh Pemasangan Handle ointu stainless steel kecil 60,572.19 229,140.00 - 289,712.19 60,572.19
A.4.6.2.12h 1 bh Pemasangan Pegangan pintu P=20 60,572.19 79,686.00 - 140,258.19 60,572.19
A.4.6.2.13 1 bh Pemasangan Door stoper Stainlees 12,588.45 57,342.00 - 69,930.45 12,588.45
A.4.6.2.14 1 bh Pemasangan Rel pintu dorong 72,621.99 308,712.00 - 381,333.99 72,621.99
A.4.6.2.15 1 bh Pemasangan Kunci lemari 30,264.55 16,416.00 - 46,680.55 30,264.55
A.4.6.2.15a 1 bh Pemasangan Kunci laci ( 808 ) 30,264.55 17,214.00 - 47,478.55 30,264.55
A.4.6.2.15b 1 bh Pemasangan Kunci gembok besar stainless 40 mm 30,264.55 37,506.00 - 67,770.55 30,264.55
A.4.6.2.15c 1 bh Pemasangan Kunci gembok besar stainless 30 mm 30,264.55 40,128.00 - 70,392.55 30,264.55
A.4.6.2.16 1 m2 Pemasangan kaca bening tebal 3 mm 18,160.88 79,959.60 - 98,120.48 18,160.88
A.4.6.2.16a 1 m2 Pemasangan kaca buram tebal 3 mm 18,160.88 142,283.40 - 160,444.28 18,160.88
A.4.6.2.16b 1 m2 Pemasangan kaca Es tebal 3 mm 18,160.88 145,920.00 - 164,080.88 18,160.88
A.4.6.2.17 1 bh Pemasangan kaca bening tebal 5 mm 18,160.88 134,383.20 - 152,544.08 18,160.88
A.4.6.2.17a 1 bh Pemasangan kaca Ray band tebal 5 mm 18,160.88 143,035.80 - 161,196.68 18,160.88
A.4.6.2.18 1 m2 Pemasangan kaca bening tebal 7 mm 20,581.62 190,494.00 - 211,075.62 20,581.62
A.4.6.2.18a 1 m2 Pemasangan kaca Ray band tebal 7 mm 20,581.62 222,345.60 - 242,927.22 20,581.62
A.4.6.2.19 1 m2 Pemasangan kaca tebal 10 mm 30,264.55 291,190.20 - 321,454.75 30,264.55
A.4.6.2.20 1 m2 Pemasangan kaca cermin tebal 5 mm 18,936.54 181,077.60 - 200,014.14 18,936.54
A.4.6.2.21 1 m2 Pemasangan kaca cermin tebal 3 mm 21,454.23 158,004.00 - 179,458.23 21,454.23
A.4.6.2.22 1 m2 Pemasangan kaca Stained glass tebal 5 mm 18,936.54 1,571,512.80 - 1,590,449.34 18,936.54
A.4.6.2.22a 1 m2 Pemasangan kaca air tebal 5 mm 18,936.54 118,753.80 - 137,690.34 18,936.54
A.4.6.2.22b 1 m2 Pemasangan kaca bluegreen tebal 8 mm 18,936.54 943,008.00 - 961,944.54 18,936.54
A.4.6.2.22c 1 m2 Pemasangan kaca profil ( bevel / moulding ) 18,936.54 9,405.00 - 28,341.54 18,936.54
A.4.6.2.23 1 m2 Pemasangan kaca patri 23,191.02 3,143,356.20 - 3,166,547.22 23,191.02

A.4.7.1 PEKERJAAN PENGECATAN

A.4.7.1.1 1 m2 Pengikisan / pengerokan permukaan cat lama 12,036.69 991.80 - 13,028.49 12,036.69
A.4.7.1.2 1 m2 Pencucian Bidang permukaan tembok yang pernah dicat 12,036.69 661.20 - 12,697.89 12,036.69
A.4.7.1.3 1 m2 Pengerokan karat pada permukaan baja cara manual 12,575.34 661.20 - 13,236.54 12,575.34
A.4.7.1.4 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur , 1 lapis cat dasar , 2 lapis cat penutup) 7,239.57 37,306.50 - 44,546.07 7,239.57
A.4.7.1.5 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur , 1 lapis cat dasar , 3 lapis cat penutup) 15,672.15 43,883.16 - 59,555.31 15,672.15
A.4.7.1.6 1 m2 Pelaburan bidang kayu dengan teak oil 15,835.74 3,324.24 - 19,159.98 15,835.74
A.4.7.1.7 1 m2 Pelaburan bidang kayu dengan pelitur 10,555.83 40,947.43 - 51,503.26 10,555.83
A.4.7.1.8 1 m2 Pelaburan bidang kayu dengan cat residu dan ter 8,455.38 2,314.20 - 10,769.58 8,455.38
A.4.7.1.9 1 m2 Pelaburan bidang kayu dengan vernis 3,871.44 9,165.60 - 13,037.04 3,871.44
A.4.7.1.10 1 m2 Pengecatan tembok baru (1 lapis plamuur , 1 lapis dasar , 2 lapis cat penutup) 8,230.29 11,751.12 - 19,981.41 8,230.29
A.4.7.1.10a 1 m2 Pengecatan tembok Eksterior 8,230.29 51,559.92 - 59,790.21 8,230.29
A.4.7.1.10b 1 m2 Pengecatan tembok Interior 8,230.29 24,309.36 - 32,539.65 8,230.29
A.4.7.1.11 1 m2 Pengecatan tembok lama (1 lapis cat dasar ,2 lapis cat penutup) 6,739.91 8,310.60 - 15,050.51 6,739.91
A.4.7.1.13 1 m2 Pelaburan tembok dengan kapur sirih 12,083.54 5,010.30 - 17,093.84 12,083.54
A.4.7.1.14 1 m2 Pelaburan tembok lama dengan kapur sirih 3,896.52 5,717.10 - 9,613.62 3,896.52
A.4.7.1.15 1 m2 Pemasangan wallpaper 21,974.93 13,429.20 - 35,404.13 21,974.93
A.4.7.1.16 1 m2 Pengecatan permukaan baja dengan menie besi 21,974.93 4,114.26 - 26,089.19 21,974.93
A.4.7.1.17 1 m2 Pengecatan permukaan baja dengan menie besi dengan perancah 42,992.25 15,598.62 - 58,590.87 42,992.25

9
HARGA SATUAN KONTRAK BAWAH HARGA SA
NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7
A.4.7.1.18 1 m2 Pengecatan permukaan baja galvanis secara manual 4 lapis 44,842.30 11,050.02 - 55,892.32 44,842.30
A.4.7.1.19 1 m2 Pengecatan permukaan baja galvanis secara manual sistem 1 lapis cat terakhir 11,691.27 20,705.82 - 32,397.09 11,691.27
A.4.7.1.20 1 m2 Pengecatan permukaan baja galvanis secara manual sistem 3 lapis 113,965.80 24,775.62 - 138,741.42 113,965.80
A.4.7.1.21 1 m2 Pengecatan permukaan baja galvanis secara semprot sistem 3 lapis cat terakhir 103,893.90 20,691.00 - 124,584.90 103,893.90
A.4.7.1.21a 1 m2 Pengecatan langit-langit (plafond) 8,230.29 9,972.72 - 18,203.01 8,230.29
A.4.7.1.21b 1 m2 Couttting ( Glasur batu alam ) 11,834.91 32,171.94 - 44,006.85 11,834.91
A.4.7.1.21c 1 m2 Pengecatan genteng ( 1 lapis cat dasar, 2 lapis cat penutup) 6,686.04 17,784.00 - 24,470.04 6,686.04
A.4.7.1.21d 1 m2 Sending impra ( melamine) 42,123.00 71,392.50 399.00 113,914.50 42,123.00

A.5.1.1 PEKERJAAN SANITASI DALAM GEDUNG

A.5.1.1.1 1 Bh Pemasangan closet duduk keramik 375,065.70 727,215.12 - 1,102,280.82 375,065.70


A.5.1.1.1a 1 Bh Pemasangan closet duduk keramik komplit eks AMSTAD 375,065.70 2,521,326.60 - 2,896,392.30 375,065.70
A.5.1.1.1b 1 Bh Pemasangan closet duduk keramik komplit eks INA 375,065.70 1,663,725.12 - 2,038,790.82 375,065.70
A.5.1.1.1c 1 Bh Pemasangan closet duduk keramik komplit eks TOTO 375,065.70 3,230,294.88 - 3,605,360.58 375,065.70
A.5.1.1.1d 1 Bh Pemasangan closet monoblock lokal 375,065.70 1,177,344.12 - 1,552,409.82 375,065.70
A.5.1.1.2 1 Bh Pemasangan closet jongkok keramik eks AMSTAD 246,405.30 310,878.00 - 557,283.30 246,405.30
A.5.1.1.2a 1 Bh Pemasangan closet jongkok keramik eks INA 246,405.30 202,350.00 - 448,755.30 246,405.30
A.5.1.1.3 1 Bh Pemasangan closet duduk jongkok teraso 234,555.00 180,393.60 - 414,948.60 234,555.00
A.5.1.1.4 1 Bh Pemasangan urinoir 184,195.50 1,714,069.80 - 1,898,265.30 184,195.50
A.5.1.1.5 1 Bh Pemasangan wastafel besar warna muda eks INA 246,747.30 418,129.20 - 664,876.50 246,747.30
A.5.1.1.5a 1 Bh Pemasangan wastafel besar warna tua eks INA 246,747.30 462,069.36 - 708,816.66 246,747.30
A.5.1.1.6 1 Bh Pemasangan bathcuip porselen 81,719.19 2,723,961.60 - 2,805,680.79 81,719.19
A.5.1.1.7 1 Bh Pemasangan bak fiberglass vol 1 m3 741,826.50 384,189.12 - 1,126,015.62 741,826.50
A.5.1.1.8 1 Bh Pemasangan bak mandi batu vol 0,30 m3 773,928.90 691,608.82 - 1,465,537.72 773,928.90
A.5.1.1.9 1 Bh Pemasangan bak mandi teraso vol 0,30 m3 741,826.50 140,831.04 - 882,657.54 741,826.50
A.5.1.1.10 1 Bh Pemasangan bak mandi fiberglass vol 1 m3 70,366.50 384,189.12 - 454,555.62 70,366.50
A.5.1.1.11 1 Bh Pemasangan bak mandi beton vol 1 m3 685,853.64 3,931,936.49 - 4,617,790.13 685,853.64
A.5.1.1.12 1 Bh Pemasangan bak cuci piring stainlessteel 34,174.35 374,718.00 - 408,892.35 34,174.35
A.5.1.1.13 1 Bh Pemasangan bak cuci piring teraso 56,957.25 366,966.00 - 423,923.25 56,957.25
A.5.1.1.14 1 Bh Pemasangan floor drain plastik 11,391.45 12,768.00 - 24,159.45 11,391.45
A.5.1.1.14a 1 Bh Pemasangan floor drain staninlees steel 11,391.45 54,036.00 - 65,427.45 11,391.45
A.5.1.1.15 1 Bh Pemasangan bak kontrol pasangan bata 30x30 tinggi 35cm 241,310.58 193,480.80 - 434,791.38 241,310.58
A.5.1.1.16 1 Bh Pemasangan bak kontrol pasangan bata 45x45 tinggi 50cm 356,353.17 298,885.20 - 655,238.37 356,353.17
A.5.1.1.17 1 Bh Pemasangan bak kontrol pasangan bata 60x60 tinggi 65cm 356,353.17 468,974.34 - 825,327.51 356,353.17
A.5.1.1.18 1 m' Pemasangan pipa galvanis diameter 1/2" 16,190.28 40,464.30 - 56,654.58 16,190.28
A.5.1.1.19 1 m' Pemasangan kran diameter 1/2" 41,607.15 31,643.84 - 73,250.99 41,607.15
A.5.1.1.19a 1 m' Pemasangan kran diameter 3/4" 41,607.15 37,571.84 - 79,178.99 41,607.15
A.5.1.1.19b 1 m' Pemasangan kran dupon 41,607.15 182,351.84 - 223,958.99 41,607.15
A.5.1.1.19c 1 m' Pemasangan kran Toto 1/2" 41,607.15 349,703.84 - 391,310.99 41,607.15
A.5.1.1.19d 1 m' Pemasangan stop kran diameter 1" 41,607.15 27,083.84 - 68,690.99 41,607.15
A.5.1.1.19e 1 m' Pemasangan stop kran diameter 1/2" 41,607.15 35,633.84 - 77,240.99 41,607.15
A.5.1.1.19f 1 m' Pemasangan stop kran diameter 3/4" 41,607.15 23,093.84 - 64,700.99 41,607.15
A.5.1.1.19g 1 m' Pemasangan stop kran diameter 1" kuningan 41,607.15 92,291.84 - 133,898.99 41,607.15
A.5.1.1.19h 1 m' Pemasangan stop kran diameter 1/2" kuningan 41,607.15 87,617.84 - 129,224.99 41,607.15
A.5.1.1.19i 1 m' Pemasangan stop kran diameter 3/4" kuningan 41,607.15 67,895.84 - 109,502.99 41,607.15
A.5.1.1.19j 1 m' Pemasangan stop kran diameter 1" plastik 41,607.15 23,777.84 - 65,384.99 41,607.15
A.5.1.1.19k 1 m' Pemasangan stop kran diameter 1/2" 41,607.15 29,705.84 - 71,312.99 41,607.15
A.5.1.1.20 1 m' Pemasangan pipa galvanis diameter 3/4" 16,190.28 51,949.80 - 68,140.08 16,190.28
A.5.1.1.21 1 m' Pemasangan pipa galvanis diameter 1" 16,190.28 79,515.00 - 95,705.28 16,190.28
A.5.1.1.22 1 m' Pemasangan pipa galvanis diameter 1 1/2" 27,101.79 120,509.40 - 147,611.19 27,101.79
A.5.1.1.22a 1 m' Pemasangan pipa galvanis diameter 2" 27,101.79 164,507.70 - 191,609.49 27,101.79
A.5.1.1.22b 1 m' Pemasangan pipa galvanis diameter 2 1/2" 27,101.79 209,919.60 - 237,021.39 27,101.79
A.5.1.1.23 1 m' Pemasangan pipa galvanis diameter 3" 34,011.33 271,234.50 - 305,245.83 34,011.33
A.5.1.1.24 1 m' Pemasangan pipa galvanis diameter 4" 34,011.33 392,450.70 - 426,462.03 34,011.33
A.5.1.1.25 1 m' Pemasangan pipa PVC tipe AW diameter 1/2" 9,069.84 5,124.30 - 14,194.14 9,069.84
A.5.1.1.26 1 m' Pemasangan pipa PVC tipe AW diameter 3/4" 9,069.84 15,372.90 - 24,442.74 9,069.84
A.5.1.1.27 1 m' Pemasangan pipa PVC tipe AW diameter 1" 9,069.84 19,437.00 - 28,506.84 9,069.84
A.5.1.1.28 1 m' Pemasangan pipa PVC tipe AW diameter 11/2" 13,604.76 30,745.80 - 44,350.56 13,604.76
A.5.1.1.29 1 m' Pemasangan pipa PVC tipe AW diameter 2" 13,604.76 35,693.40 - 49,298.16 13,604.76
A.5.1.1.30 1 m' Pemasangan pipa PVC tipe AW diameter 21/2" 20,353.28 51,066.30 - 71,419.58 20,353.28
A.5.1.1.31 1 m' Pemasangan pipa PVC tipe AW diameter 3" 20,353.28 61,314.90 - 81,668.18 20,353.28
A.5.1.1.32 1 m' Pemasangan pipa PVC tipe AW diameter 4" 20,353.28 91,884.00 - 112,237.28 20,353.28
A.5.1.1.33 1 m' Pemasangan pipa air limbah jenis pipa tanah Ø 20 cm 10,706.88 178,845.71 - 189,552.59 10,706.88
A.5.1.1.35 1 m' Pemasangan pipa beton diameter 15-20 cm 18,737.04 129,151.97 - 147,889.01 18,737.04
A.5.1.1.36 1 m' Pemasangan pipa beton diameter 30 cm 50,857.68 200,242.94 - 251,100.62 50,857.68
A.5.1.1.36a 1 m' Pemasangan pipa beton diameter 40 cm 50,857.68 236,358.14 - 287,215.82 50,857.68
A.5.1.1.36b 1 m' Pemasangan pipa beton diameter 50 cm 50,857.68 308,839.34 - 359,697.02 50,857.68
A.5.1.1.36c 1 m' Pemasangan pipa beton diameter 60 cm 50,857.68 323,260.34 - 374,118.02 50,857.68
A.5.1.1.36d 1 m' Pemasangan pipa beton diameter 80 cm 50,857.68 381,195.14 - 432,052.82 50,857.68
A.5.1.1.36e 1 m' Pemasangan pipa beton diameter 100 cm 50,857.68 598,513.34 - 649,371.02 50,857.68

ANALISA TAMBAHAN

1 1 m2 Pemasangan lantai batu ampyang 136,212.62 126,973.20 - 263,185.82 136,212.62


2 1 m2 Pemasangan HPL 215,019.50 215,986.91 - 431,006.41 215,019.50
3 1 m2 Pengecatan Flexy 41,151.44 91,792.80 4,389.00 137,333.24 41,151.44
4 1 m2 Pemasangan Alumunium Composite Panel Ex. Alucopan 331,208.76 597,046.50 - 928,255.26 331,208.76

10
HARGA SATUAN KONTRAK BAWAH HARGA SA
NO URAIAN KEGIATAN UPAH BAHAN PERALATAN JUMLAH UPAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7

11
REKAPITULASI
HARGA SATUAN PEKERJAAN ( AHSP )
BIDANG PEKERJAAN UMUM

HARGA SATUAN KONTRAK ATAS


BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10

736,418.00 - 792,346.40
882,778.61 - 943,495.01
590,646.77 - 641,160.17
791,147.35 - 810,763.90
1,773,734.55 7,448.76 2,268,846.81
2,413,059.66 - 2,665,569.66
1,905,528.81 - 2,195,197.11
1,827,266.67 - 2,116,934.97
- - 13,195.50
20,762.73 - 310,431.03
280,953.68 - 314,760.38
87,870.06 - 166,498.71
- - 1,113,000.24
- - 556,500.12
5,196.91 - 13,622.65
354,766.92 - 410,145.84
- - 88,863.00
- - 41,738.25
- - 26,391.00
- - 26,391.00
- - 135,631.50
- - 83,476.50
- - 1,010,040.00
- - 676,134.00

- - 61,260.75
- - 75,128.85
- - 89,212.41
- - 81,537.36
- - 123,598.80
- - 98,555.85
- - 4,443.15
- - 26,847.00
- - 44,431.50
- - 44,431.50
260,781.84 - 285,286.14
406,350.55 - 517,728.55
57,934.80 - 71,264.25
281,397.60 - 303,613.35
124,146.00 - 146,361.75

929,013.36 - 1,129,767.36
872,131.92 - 1,072,885.92
832,676.06 - 1,033,430.06
804,947.62 - 1,005,701.62
766,916.30 - 967,670.30
797,522.68 - 998,276.68
917,992.58 - 1,118,746.58
867,652.01 - 1,068,406.01
556,836.19 - 661,228.27
2,478,898.99 - 2,848,761.16
769,784.77 - 1,050,595.84
1,235,464.71 - 1,386,422.94
755,619.57 - 872,760.27

936,032.66 - 1,101,573.77
980,747.20 - 1,146,288.31
1,015,622.90 - 1,181,164.01
917,551.98 - 1,037,867.58
1,057,067.46 - 1,222,608.57
1,096,374.30 - 1,261,915.41
1,126,292.00 - 1,291,833.11

12
HARGA SATUAN KONTRAK ATAS
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10
1,145,502.46 - 1,311,043.57
1,178,726.96 - 1,344,268.07
1,188,947.68 - 1,354,488.79
1,227,961.76 - 1,438,514.06
1,241,392.24 - 1,485,520.39
1,213,479.84 - 1,424,032.14
63,069.93 - 71,100.09
84,927.15 - 94,726.02
119,293.02 - 129,999.90
141,564.06 - 154,910.61
140,460.54 - 149,724.18
370,757.64 - 377,733.87
180,626.16 - 253,333.08
202,351.71 - 275,058.63
340,705.53 - 432,987.39
353,740.86 - 446,022.72
401,399.13 - 493,680.99
293,185.20 - 385,467.06
296,890.77 - 389,172.63
134,486.48 - 152,696.27
4,090,004.22 - 4,818,309.75
5,113,594.26 - 5,937,716.22
8,718,116.94 - 9,743,847.90
6,707,967.48 - 7,600,771.59
6,156,019.38 - 6,884,644.68
5,860,827.78 - 6,589,133.31
6,161,442.93 - 6,985,564.89
79,345.82 - 100,768.13
88,781.49 - 124,155.12
- - 312,360.00

84,563.56 - 97,820.05
105,702.76 - 122,290.90
114,556.14 - 134,387.01
158,537.59 - 183,423.22
343,267.51 - 351,619.15
35,357.78 - 39,626.51
33,070.11 - 37,338.84
- - 5,975.31
- - 10,549.56
- - 8,531.76
- - 52,250.19
- - 53,857.59
- - 53,857.59
- - 44,925.69
74,884.87 - 103,500.01
- - 64,261.23

22,208.34 - 35,414.67
22,208.34 - 33,978.27
12,477.30 16,416.00 47,550.54
1,103,983.98 - 1,309,903.89
41,833.44 3,876.00 51,302.28
195,688.20 - 323,141.91
688,069.80 - 917,650.98
560,538.00 - 646,850.82
790,145.40 - 886,974.72
475,015.20 - 671,180.70
127,995.78 - 136,425.51
800,327.88 - 816,996.56
1,104,523.20 - 1,121,331.36
137,313.00 - 206,024.79
222,953.55 - 550,496.07
107,182.14 - 126,798.69
115,596.48 - 135,213.03
98,078.10 - 117,694.65
97,388.40 - 117,004.95
536,661.84 - 574,925.37
200,280.10 - 238,543.63
67,756.13 - 114,138.17
98,188.20 - 145,715.94
109,098.00 - 175,615.29

13
HARGA SATUAN KONTRAK ATAS
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10
260,857.08 - 331,086.78
245,977.12 - 316,206.82
235,403.39 - 305,633.09
230,746.03 - 300,975.73
230,871.43 - 301,101.13
251,400.36 - 321,630.06
124,850.75 - 159,965.60
117,472.21 - 152,587.06
113,426.81 - 148,541.66
110,893.73 - 146,008.58
109,830.34 - 144,945.19
106,966.20 - 142,081.05
127,353.11 - 162,467.96
113,670.33 - 148,785.18
110,601.04 - 145,715.89
1,540,697.00 - 1,585,075.49
1,197,414.50 - 1,241,792.99
1,544,624.53 - 1,589,003.02
1,201,342.03 - 1,245,720.52
1,117,341.59 - 1,171,653.47
962,159.09 - 1,016,470.97
1,119,964.96 - 1,174,276.84
964,782.46 - 1,019,094.34
705,445.22 - 740,560.07
705,445.22 - 740,560.07
708,071.10 - 743,185.95
708,071.10 - 743,185.95
772,012.56 - 807,127.41
350,668.56 - 385,783.41
781,302.19 - 821,452.99
103,808.63 - 138,654.16

32,515.72 - 72,666.52
24,570.37 - 64,721.17
21,265.83 - 61,416.63
18,900.29 - 59,051.09
17,708.49 - 57,859.29
16,691.24 - 56,842.04
16,179.61 - 56,330.41
15,667.98 - 55,818.78
19,195.61 - 61,333.43
19,853.96 - 61,991.78
19,013.52 - 61,151.34
17,436.74 - 59,574.56
32,870.85 - 86,620.71
28,464.80 - 70,312.49
25,200.38 - 78,950.24
23,721.67 - 77,471.53
22,254.99 - 76,004.85
21,993.03 - 80,880.87
17,708.49 - 37,891.05
5,181.53 - 52,147.25
96,558.00 - 156,891.36
60,819.00 - 121,152.36
9,570.53 - 44,685.38
5,456.40 - 25,638.96
2,808.96 - 12,284.64
15,103.18 - 55,253.98
5,705.70 - 32,472.90
16,515.18 - 22,189.53

73,830.50 - 110,073.38
108,562.02 - 143,359.38
252,093.33 - 285,659.49
163,240.70 - 256,925.90
101,595.84 - 195,281.04
108,562.02 - 202,247.22
254,717.63 - 348,402.83
316,609.38 - 410,294.58
339,919.26 - 433,604.46
471,338.75 - 565,023.95
234,622.91 - 328,308.11
316,609.38 - 410,294.58
144,062.69 - 237,747.89
194,433.46 - 288,118.66

14
HARGA SATUAN KONTRAK ATAS
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10
114,186.44 - 207,871.64
110,328.72 - 204,013.92
203,677.04 - 297,362.24
106,150.64 - 199,835.84
108,562.02 - 202,247.22
105,480.83 - 199,166.03
123,298.15 - 216,983.35
106,775.59 - 200,460.79
126,707.92 - 148,029.34
26,311.43 - 45,714.23
176,741.27 - 270,426.47
181,393.61 - 275,078.81
283,479.24 - 377,164.44
249,317.77 - 343,002.97
292,783.92 - 386,469.12
219,675.72 - 313,360.92
219,675.72 - 313,360.92
3,102,265.58 - 3,195,950.78
324,286.91 - 417,972.11
179,266.82 - 272,952.02
177,671.74 - 271,356.94
131,547.11 - 225,232.31
39,501.00 - 72,903.00
55,760.36 - 176,212.76
95,835.70 - 216,288.10
156,250.91 - 276,703.31
156,250.91 - 276,703.31
97,109.76 - 217,562.16
115,586.20 - 236,038.60
96,445.14 - 216,897.54
101,762.10 - 222,214.50
101,762.10 - 222,214.50
193,878.43 - 314,330.83
97,109.76 - 217,562.16
96,445.14 - 216,897.54
186,168.84 - 306,621.24
247,180.96 - 367,633.36
386,618.23 - 507,070.63
394,593.67 - 515,046.07
380,636.65 - 501,089.05
312,712.49 - 433,164.89
290,647.10 - 411,099.50
201,853.87 - 322,306.27
223,786.33 - 344,238.73
217,538.90 - 337,991.30
217,538.90 - 337,991.30
3,100,128.77 - 3,220,581.17
322,150.09 - 442,602.49
177,130.01 - 297,582.41
153,735.38 - 274,187.78
198,530.77 - 318,983.17
175,933.69 - 296,386.09
629,071.61 - 749,524.01
153,336.61 - 273,789.01
270,841.43 - 391,293.83
270,841.43 - 391,293.83
270,841.43 - 391,293.83
393,445.01 - 567,431.81
398,097.35 - 572,084.15
500,182.98 - 674,169.78
198,530.77 - 318,983.17
184,087.20 - 277,772.40
185,328.66 - 279,013.86
25,048.65 - 70,168.14
84,870.72 - 106,974.18
67,154.71 - 89,227.96
122,352.78 - 143,374.38
104,144.70 - 125,166.30
140,560.86 - 161,582.46
117,800.76 - 138,822.36
163,320.96 - 184,342.56
111,731.40 - 132,753.00
132,974.16 - 153,995.76
110,214.06 - 131,235.66
132,974.16 - 153,995.76
110,214.06 - 131,235.66
113,248.74 - 134,270.34
95,040.66 - 116,062.26
95,040.66 - 116,062.26

15
HARGA SATUAN KONTRAK ATAS
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10
87,453.96 - 108,475.56
110,214.06 - 131,235.66
90,488.64 - 111,510.24
117,800.76 - 138,822.36

20,066.51 - 30,728.36
14,824.79 - 25,486.64
630,711.84 - 654,251.70
345,727.80 - 369,267.66
101,022.24 - 300,758.79
37,232.51 - 236,969.06
693,489.59 - 850,421.99
424,506.59 - 581,438.99
217,596.59 - 374,528.99
222,769.34 - 379,701.74
160,696.34 - 317,628.74
150,350.84 - 307,283.24
114,141.59 - 271,073.99
98,623.34 - 255,555.74
38,670.85 - 52,652.95
514,096.11 - 612,178.86
4,291.19 - 14,153.33
109,098.00 - 175,615.29
26,823.06 - 30,926.49
34,328.25 - 38,431.68

81,510.00 - 102,537.02
100,320.00 - 121,347.02
72,105.00 - 93,132.02
156,750.00 - 177,777.02
357,390.00 - 378,417.02
313,500.00 - 334,580.31
61,004.59 - 114,993.85
151,292.59 - 205,281.85
56,740.99 - 108,336.25
49,718.59 - 103,707.85
48,715.39 - 102,704.65
183,096.54 - 202,365.39
72,599.08 - 92,898.49
76,398.70 - 96,698.11
83,696.98 - 103,271.92
67,144.18 - 86,719.12
27,787.39 - 47,362.33
40,050.25 - 59,625.19
37,589.90 - 57,164.84
53,646.12 - 73,221.06
50,741.86 - 70,316.80
50,986.39 - 70,561.33
55,218.64 - 74,793.58
60,864.14 - 80,439.08
61,196.45 - 80,771.39
82,737.67 - 102,312.61
108,947.52 - 130,077.42
109,060.38 - 130,190.28
160,041.75 - 181,171.65
52,968.96 - 74,098.86
62,750.16 - 83,880.06
56,241.90 - 81,171.99
100,106.82 - 121,236.72
68,992.57 - 96,956.77
87,458.98 - 114,453.61
279,942.96 - 321,939.99
55,399.21 - 111,327.61
51,915.60 - 89,741.94
23,299.32 - 61,879.20
65,626.84 - 82,405.36
49,211.98 - 65,990.50
62,504.38 - 79,282.90
45,098.86 - 61,877.38
29,669.64 - 49,917.75
16,013.58 - 36,261.69
17,255.04 - 37,503.15
67,540.44 - 164,950.02
78,995.73 - 176,405.31
90,451.02 - 187,860.60

16
HARGA SATUAN KONTRAK ATAS
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10
100,984.62 - 198,394.20
26,133.36 - 60,190.86
14,483.70 - 32,693.49

42,528,344.10 - 45,479,148.60
28,872,284.10 - 31,823,088.60
14,457,554.10 - 17,408,358.60
14,836,889.10 - 17,787,693.60
10,284,869.10 - 13,235,673.60
9,526,199.10 - 12,477,003.60
7,629,524.10 - 10,580,328.60
6,870,854.10 - 9,821,658.60
46,390,664.10 - 48,919,925.10
31,493,144.10 - 34,022,405.10
15,767,984.10 - 18,297,245.10
16,181,804.10 - 18,711,065.10
11,215,964.10 - 13,745,225.10
10,388,324.10 - 12,917,585.10
8,319,224.10 - 10,848,485.10
7,491,584.10 - 10,020,845.10
1,849,411.74 - 1,997,005.83
1,132,123.74 - 1,279,717.83
580,363.74 - 727,957.83
594,157.74 - 741,751.83
428,629.74 - 576,223.83
401,041.74 - 548,635.83
304,483.74 - 452,077.83
263,101.74 - 410,695.83
1,849,411.74 - 1,997,005.83
1,132,123.74 - 1,279,717.83
580,363.74 - 727,957.83
594,157.74 - 741,751.83
428,629.74 - 576,223.83
401,041.74 - 548,635.83
304,483.74 - 452,077.83
263,101.74 - 410,695.83
1,849,267.53 - 2,270,811.03
1,131,979.53 - 1,553,523.03
580,219.53 - 1,001,763.03
594,013.53 - 1,015,557.03
428,485.53 - 850,029.03
400,897.53 - 822,441.03
304,339.53 - 725,883.03
262,957.53 - 684,501.03
1,114,266.78 - 1,451,501.58
683,893.98 - 1,021,128.78
352,837.98 - 690,072.78
361,114.38 - 698,349.18
261,797.58 - 599,032.38
245,244.78 - 582,479.58
187,309.98 - 524,544.78
162,480.78 - 499,715.58
2,966,148.90 - 3,387,692.40
1,818,488.10 - 2,240,031.60
935,672.10 - 1,357,215.60
957,742.50 - 1,379,286.00
692,897.70 - 1,114,441.20
648,756.90 - 1,070,300.40
494,264.10 - 915,807.60
428,052.90 - 849,596.40
1,242,571.04 - 1,537,651.49
794,266.04 - 1,089,346.49
449,416.04 - 744,496.49
458,037.29 - 753,117.74
354,582.29 - 649,662.74
337,339.79 - 632,420.24
276,991.04 - 572,071.49
251,127.29 - 546,207.74
2,675,077.94 - 3,012,312.74
1,670,874.74 - 2,008,109.54
898,410.74 - 1,235,645.54
917,722.34 - 1,254,957.14
685,983.14 - 1,023,217.94
647,359.94 - 984,594.74
512,178.74 - 849,413.54
454,243.94 - 791,478.74
2,775,641.22 - 3,089,429.07

17
HARGA SATUAN KONTRAK ATAS
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10
1,699,709.22 - 2,013,497.07
872,069.22 - 1,185,857.07
892,760.22 - 1,206,548.07
644,468.22 - 958,256.07
603,086.22 - 916,874.07
458,249.22 - 772,037.07
396,176.22 - 709,964.07
1,261,782.32 - 1,599,017.12
813,477.32 - 1,150,712.12
468,627.32 - 805,862.12
477,248.57 - 814,483.37
373,793.57 - 711,028.37
356,551.07 - 693,785.87
296,202.32 - 633,437.12
270,338.57 - 607,573.37
1,442,922.62 - 1,801,288.46
994,617.62 - 1,352,983.46
649,767.62 - 1,008,133.46
658,388.87 - 1,016,754.71
554,933.87 - 913,299.71
537,691.37 - 896,057.21
477,342.62 - 835,708.46
451,478.87 - 809,844.71
42,951,029.88 - 44,637,203.88
29,294,969.88 - 30,981,143.88
16,397,579.88 - 18,083,753.88
15,259,574.88 - 16,945,748.88
10,707,554.88 - 12,393,728.88
9,948,884.88 - 11,635,058.88
8,052,209.88 - 9,738,383.88
7,293,539.88 - 8,979,713.88
46,813,349.88 - 49,637,691.33
31,915,829.88 - 34,740,171.33
16,190,669.88 - 19,015,011.33
16,604,489.88 - 19,428,831.33
11,638,649.88 - 14,462,991.33
10,811,009.88 - 13,635,351.33
8,741,909.88 - 11,566,251.33
7,914,269.88 - 10,738,611.33
42,898,211.40 - 45,722,552.85
29,242,151.40 - 32,066,492.85
14,827,421.40 - 17,651,762.85
15,206,756.40 - 18,031,097.85
10,654,736.40 - 13,479,077.85
9,896,066.40 - 12,720,407.85
7,999,391.40 - 10,823,732.85
7,240,721.40 - 10,065,062.85
684,847.02 - 704,463.57
466,350.06 - 485,966.61
235,714.38 - 255,330.93
241,783.74 - 261,400.29
168,951.42 - 188,567.97
156,812.70 - 176,429.25
126,465.90 - 146,082.45
114,327.18 - 133,943.73
765,955.74 - 785,572.29
521,388.12 - 541,004.67
263,233.41 - 282,849.96
270,026.96 - 289,643.51
188,504.42 - 208,120.97
174,917.33 - 194,533.88
140,949.60 - 160,566.15
140,949.60 - 160,566.15
541,882.74 - 565,422.60
368,078.34 - 391,618.20
184,618.14 - 208,158.00
189,446.04 - 212,985.90
131,511.24 - 155,051.10
121,855.44 - 145,395.30
97,715.94 - 121,255.80
88,060.14 - 111,600.00
598,860.24 - 652,460.19
407,675.40 - 461,275.35
205,869.18 - 259,469.13
211,179.87 - 264,779.82
147,451.59 - 201,051.54
136,830.21 - 190,430.16
110,276.76 - 163,876.71
99,655.38 - 153,255.33

18
HARGA SATUAN KONTRAK ATAS
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10
634,636.86 - 685,138.86
432,278.88 - 482,780.88
218,678.79 - 269,180.79
224,299.85 - 274,801.85
156,847.19 - 207,349.19
145,605.08 - 196,107.08
117,499.80 - 168,001.80
106,257.69 - 156,759.69
501,098.40 - 531,983.85
307,430.64 - 338,316.09
158,455.44 - 189,340.89
162,179.82 - 193,065.27
117,487.26 - 148,372.71
110,038.50 - 140,923.95
83,967.84 - 114,853.29
72,794.70 - 103,680.15
509,324.64 - 540,210.09
312,070.44 - 342,955.89
160,336.44 - 191,221.89
164,129.79 - 195,015.24
118,609.59 - 149,495.04
111,022.89 - 141,908.34
84,469.44 - 115,354.89
73,089.39 - 103,974.84
1,296,924.42 - 1,360,209.81
794,822.82 - 858,108.21
408,590.82 - 471,876.21
418,246.62 - 481,532.01
302,377.02 - 365,662.41
283,065.42 - 346,350.81
215,474.82 - 278,760.21
186,507.42 - 249,792.81
1,184,523.38 - 1,247,808.77
836,914.58 - 900,199.97
469,994.18 - 533,279.57
479,649.98 - 542,935.37
363,780.38 - 427,065.77
344,468.78 - 407,754.17
296,189.78 - 359,475.17
276,878.18 - 340,163.57
1,201,023.52 - 1,295,027.92
853,414.72 - 947,419.12
486,494.32 - 580,498.72
496,150.12 - 590,154.52
380,280.52 - 474,284.92
360,968.92 - 454,973.32
312,689.92 - 406,694.32
293,378.32 - 387,382.72
325,613.64 - 578,539.74
200,088.24 - 453,014.34
103,530.24 - 356,456.34
105,944.19 - 358,870.29
76,976.79 - 329,902.89
72,148.89 - 325,074.99
55,251.24 - 308,177.34
48,009.39 - 300,935.49
50,674.14 - 61,239.09
713,268.18 - 727,250.28
502,219.98 - 516,202.08
279,446.88 - 293,428.98
285,309.33 - 299,291.43
214,959.93 - 228,942.03
203,235.03 - 217,217.13
173,922.78 - 187,904.88
162,197.88 - 176,179.98

296,947.20 - 369,569.19
272,243.40 - 344,865.39
88,407.00 - 146,071.05
88,407.00 - 146,071.05
91,291.20 - 148,349.34
173,804.40 - 230,862.54
51,414.00 - 69,574.88
99,191.40 - 117,352.28
18,057.60 - 36,218.48
12,289.20 - 30,450.08
59,439.60 - 77,600.48

19
HARGA SATUAN KONTRAK ATAS
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10
66,587.40 - 84,748.28
156,373.80 - 174,534.68
178,945.80 - 197,106.68
15,173.40 - 33,334.28
25,330.80 - 37,434.47
45,018.60 - 57,122.27
20,941.80 - 33,045.47
21,819.60 - 33,923.27
18,057.60 - 30,161.27
8,652.60 - 20,756.27
40,504.20 - 52,607.87
29,719.80 - 41,823.47
65,208.00 - 77,311.67
231,739.20 - 243,842.87
336,072.00 - 348,175.67
195,624.00 - 207,727.67
51,414.00 - 63,517.67
21,819.60 - 52,220.27
26,710.20 - 57,110.87
23,199.00 - 53,599.67
45,645.60 - 76,046.27
42,134.40 - 72,535.07
21,819.60 - 40,756.14
271,616.40 - 332,188.59
262,963.80 - 287,171.13
134,805.00 - 159,012.33
154,994.40 - 179,201.73
354,882.00 - 379,089.33
354,882.00 - 379,089.33
394,633.80 - 418,841.13
120,258.60 - 144,465.93
105,837.60 - 166,409.79
143,457.60 - 204,029.79
338,956.20 - 399,528.39
640,167.00 - 700,739.19
252,054.00 - 312,626.19
87,654.60 - 148,226.79
63,076.20 - 75,664.65
339,583.20 - 412,205.19
18,057.60 - 48,322.15
18,935.40 - 49,199.95
41,256.60 - 71,521.15
44,140.80 - 74,405.35
87,955.56 - 106,116.44
156,511.74 - 174,672.62
160,512.00 - 178,672.88
147,821.52 - 165,982.40
157,339.38 - 175,500.26
209,543.40 - 230,125.02
244,580.16 - 265,161.78
320,309.22 - 350,573.77
199,185.36 - 218,121.90
173,804.40 - 195,258.63
1,728,664.08 - 1,747,600.62
130,629.18 - 149,565.72
1,037,308.80 - 1,056,245.34
10,345.50 - 29,282.04
3,457,691.82 - 3,480,882.84

1,090.98 - 13,127.67
727.32 - 12,764.01
727.32 - 13,302.66
41,037.15 - 48,276.72
48,271.48 - 63,943.63
3,656.66 - 19,492.40
45,042.18 - 55,598.01
2,545.62 - 11,001.00
10,082.16 - 13,953.60
12,926.23 - 21,156.52
56,715.91 - 64,946.20
26,740.30 - 34,970.59
9,141.66 - 15,881.57
5,511.33 - 17,594.87
6,288.81 - 10,185.33
14,772.12 - 36,747.05
4,525.69 - 26,500.62
17,158.48 - 60,150.73

20
HARGA SATUAN KONTRAK ATAS
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10
12,155.02 - 56,997.32
22,776.40 - 34,467.67
27,253.18 - 141,218.98
22,760.10 - 126,654.00
10,969.99 - 19,200.28
35,389.13 - 47,224.04
19,562.40 - 26,248.44
71,392.50 399.00 113,914.50

799,936.63 - 1,175,002.33
2,773,459.26 - 3,148,524.96
1,830,097.63 - 2,205,163.33
3,553,324.37 - 3,928,390.07
1,295,078.53 - 1,670,144.23
341,965.80 - 588,371.10
222,585.00 - 468,990.30
198,432.96 - 432,987.96
1,885,476.78 - 2,069,672.28
459,942.12 - 706,689.42
508,276.30 - 755,023.60
2,996,357.76 - 3,078,076.95
422,608.03 - 1,164,434.53
760,769.70 - 1,534,698.60
154,914.14 - 896,740.64
422,608.03 - 492,974.53
4,299,886.95 - 4,985,740.59
412,189.80 - 446,364.15
403,662.60 - 460,619.85
14,044.80 - 25,436.25
59,439.60 - 70,831.05
212,030.88 - 453,341.46
328,545.72 - 684,898.89
515,495.57 - 871,848.74
44,510.73 - 60,701.01
34,808.22 - 76,415.37
41,329.02 - 82,936.17
200,587.02 - 242,194.17
384,674.22 - 426,281.37
29,792.22 - 71,399.37
39,197.22 - 80,804.37
25,403.22 - 67,010.37
101,521.02 - 143,128.17
96,379.62 - 137,986.77
74,685.42 - 116,292.57
26,155.62 - 67,762.77
32,676.42 - 74,283.57
57,144.78 - 73,335.06
87,466.50 - 103,656.78
132,560.34 - 159,662.13
180,958.47 - 208,060.26
230,911.56 - 258,013.35
298,357.95 - 332,369.28
431,695.77 - 465,707.10
5,636.73 - 14,706.57
16,910.19 - 25,980.03
21,380.70 - 30,450.54
33,820.38 - 47,425.14
39,262.74 - 52,867.50
56,172.93 - 76,526.21
67,446.39 - 87,799.67
101,072.40 - 121,425.68
196,730.28 - 207,437.16
142,067.16 - 160,804.20
220,267.23 - 271,124.91
259,993.95 - 310,851.63
339,723.27 - 390,580.95
355,586.37 - 406,444.05
419,314.65 - 470,172.33
658,364.67 - 709,222.35

139,670.52 - 275,883.14
237,585.60 - 452,605.10
91,792.80 4,389.00 137,333.24
656,751.15 - 987,959.91

21
HARGA SATUAN KONTRAK ATAS
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
8 9 10

22
ANALISA HARGA SATUAN PEKERJAAN ( AHSP )
BIDANG PEKERJAAN UMUM
KABUPATEN : TULUNGAGUNG
SISTEM : KONTRAK
HARGA : BAWAH
Overhead dan profit = 0.1400

HARGA JUMLAH HARGA


NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.2.2.1 PEKERJAAN PERSIAPAN

A.2.2.1.1 1 m2 Pembuatan Pagar sementara dari kayu tinggi 2 meter


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang Kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0200 94,500.00 1,890.00
Bahan
Dolken Kayu jati lokal dia 10cm -15 cm, pjg = 3 m 2.2.2.9 Batang 1.2500 173,300.00 216,625.00
PC / Portland cement 2.2.1.52 Kg 5.0000 1,400.00 7,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0050 264,000.00 1,320.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0090 300,000.00 2,700.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0720 4,950,000.00 356,400.00
Paku biasa 2.2.12.1 Kg 0.0600 16,200.00 972.00
Residu ( Ter ) 2.2.6.40 liter 0.4000 5,800.00 2,320.00
49,060.00 587,337.00 - 636,397.00
Overhead dan profit 0.1400 6,868.40 82,227.18 - 89,095.58
55,928.40 669,564.18 - 725,492.58

A.2.2.1.2 1 m2 Pembuatan Pagar Sementara dari seng gelombang tinggi 2m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang Kayu 1.2.7.19 oh 0.4000 89,500.00 35,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0200 94,500.00 1,890.00
Bahan #N/A
Dolken Kayu jati lokal dia 10cm -15 cm, pjg = 3 m 2.2.2.9 Batang 1.2500 173,300.00 216,625.00
PC / Portland cement 2.2.1.52 Kg 2.5000 1,400.00 3,500.00
Seng gelombang Bjls 20 uk. 305x90x0,02 cm 2.2.3.220 lembar 1.2000 89,100.00 106,920.00
Pasir pasang / beton 2.2.1.50 m3 0.0050 264,000.00 1,320.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0090 300,000.00 2,700.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0720 4,950,000.00 356,400.00
Paku biasa 2.2.12.1 Kg 0.0600 16,200.00 972.00
Meni besi 2.2.6.26 liter 0.4500 34,700.00 15,615.00
53,260.00 704,052.00 - 757,312.00
Overhead dan profit 0.1400 7,456.40 98,567.28 - 106,023.68
60,716.40 802,619.28 - 863,335.68

A.2.2.1.3 1 m2 Pembuatan Pagar sementara dari kawat duri tinggi 1.8 M


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang Kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0200 94,500.00 1,890.00
Bahan
Dolken Kayu jati lokal dia 10cm -15 cm, pjg = 3 m 2.2.2.9 Batang 1.0000 173,300.00 173,300.00
PC / Portland cement 2.2.1.52 Kg 2.0000 1,400.00 2,800.00
Kawat duri 2.2.4.31 M1 25.0000 11,600.00 290,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0050 264,000.00 1,320.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0090 300,000.00 2,700.00
Paku biasa 2.2.12.1 kg 0.0600 16,200.00 972.00
44,310.00 471,092.00 - 515,402.00
Overhead dan profit 0.1400 6,203.40 65,952.88 - 72,156.28
50,513.40 537,044.88 - 587,558.28

A.2.2.1.4 1 m' Pengukuran dan pemasangan Bowplank


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang Kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.1200 4,950,000.00 594,000.00
Paku biasa 2.2.12.1 Kg 0.0200 16,200.00 324.00
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0070 5,225,000.00 36,575.00
17,207.50 630,899.00 - 648,106.50
Overhead dan profit 0.1400 2,409.05 88,325.86 - 90,734.91
19,616.55 719,224.86 - 738,841.41

A.2.2.1.5 1 m2 Pembuatan kantor sementara lantai plesteran


Tenaga

1
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pekerja / Buruh tak terlatih 1.2.7.10 oh 2.0000 68,500.00 137,000.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Tukang batu 1.2.7.16 oh 1.0000 79,000.00 79,000.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Dolken Kayu jati lokal dia 10cm -15 cm, pjg = 3 m 2.2.2.9 Batang 1.2500 173,300.00 216,625.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.1800 4,950,000.00 891,000.00
Paku biasa 2.2.12.1 kg 0.0800 16,200.00 1,296.00
Besi plat strip / Strip plate 2.2.4.14 kg 1.1000 17,900.00 19,690.00
PC / Portland cement 2.2.1.52 kg 35.0000 1,400.00 49,000.00
Pasir pasang / beton 2.2.1.50 m3 0.1500 264,000.00 39,600.00
Pasir pasang / beton 2.2.1.50 m3 0.1000 264,000.00 26,400.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.1500 300,000.00 45,000.00
Batu Bata / Merah 2.2.1.14 Buah 30.0000 900.00 27,000.00
Seng gelombang Bjls 20 uk. 305x90x0,02 cm 2.2.3.220 lembar 0.2500 89,100.00 22,275.00
Naco (Kerangka dan Daun ) 2.2.9.29 buah 0.2000 264,600.00 52,920.00
Kaca Bening t= 5 mm 2.2.9.9 m2 0.0800 106,300.00 8,504.00
Kunci tanam Slot ex.Kuda (2x Putaran) 2.2.7.52 bh 0.1500 70,500.00 10,575.00
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 lembar 0.0600 99,000.00 5,940.00 5,940.00
427,775.00 1,415,825.00 5,940.00 1,849,540.00
Overhead dan profit 0.1400 59,888.50 198,215.50 831.60 258,935.60
487,663.50 1,614,040.50 6,771.60 2,108,475.60

A.2.2.1.6 1 m2 Pembuatan Rumah Jaga ( Kontrusi Kayu )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 1.5000 89,500.00 134,250.00
Kepala Tukang 1.2.7.3 oh 0.1500 93,500.00 14,025.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Dolken Kayu jati lokal dia 10cm -15 cm, pjg = 3 m 2.2.2.9 Batang 3.0000 173,300.00 519,900.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.2760 4,950,000.00 1,366,200.00
Paku biasa 2.2.12.1 kg 0.7000 16,200.00 11,340.00
Besi plat strip / Strip plate 2.2.4.14 kg 1.5000 17,900.00 26,850.00
221,500.00 1,924,290.00 - 2,145,790.00
Overhead dan profit 0.1400 31,010.00 269,400.60 - 300,410.60
252,510.00 2,193,690.60 - 2,446,200.60

A.2.2.1.7 1 m2 Pembuatan Gudang Semen dan Peralatan


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Dolken Kayu jati lokal dia 10cm -15 cm, pjg = 3 m 2.2.2.9 Batang 1.7000 173,300.00 294,610.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.2100 4,950,000.00 1,039,500.00
Paku biasa 2.2.12.1 kg 0.3000 16,200.00 4,860.00
PC / Portland cement 2.2.1.52 kg 10.5000 1,400.00 14,700.00
Pasir pasang / beton 2.2.1.50 m3 0.0300 264,000.00 7,920.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0500 300,000.00 15,000.00
Seng gelombang Bjls 20 uk. 305x90x0,02 cm 2.2.3.220 Lembar 1.5000 89,100.00 133,650.00
Seng Plat BJLS 27 lebar 0,90 m 2.2.3.226 Lembar 0.2500 39,100.00 9,775.00
254,095.00 1,520,015.00 - 1,774,110.00
Overhead dan profit 0.1400 35,573.30 212,802.10 - 248,375.40
289,668.30 1,732,817.10 - 2,022,485.40

A.2.2.1.8 1 m2 Pembuatan Bedeng Pekerja


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Dolken Kayu jati lokal dia 10cm -15 cm, pjg = 3 m 2.2.2.9 Batang 1.2500 173,300.00 216,625.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.1860 4,950,000.00 920,700.00
Paku biasa 2.2.12.1 kg 0.3000 16,200.00 4,860.00
PC / Portland cement 2.2.1.52 kg 18.0000 1,400.00 25,200.00
Pasir pasang / beton 2.2.1.50 m3 0.0300 264,000.00 7,920.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0500 300,000.00 15,000.00
Seng gelombang Bjls 20 uk. 305x90x0,02 cm 2.2.3.220 Lembar 1.5000 89,100.00 133,650.00
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 Lembar 1.3500 99,000.00 133,650.00
254,095.00 1,457,605.00 - 1,711,700.00
Overhead dan profit 0.1400 35,573.30 204,064.70 - 239,638.00
289,668.30 1,661,669.70 - 1,951,338.00

A.2.2.1.9 1 m2 Pembersihan Lapangan dan perataan


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00

2
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
11,575.00 - - -
Overhead dan profit 0.1400 1,620.50 - - 1,620.50
13,195.50 - - 13,195.50

A.2.2.1.10 1 m2 Pembuatan Steger/Perancah dari bambu


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 Batang 1.2500 12,100.00 15,125.00
Ijuk 2.2.1.44 m3 0.1860 7,700.00 1,432.20
254,095.00 16,557.20 - 270,652.20
Overhead dan profit 0.1400 35,573.30 2,318.01 - 37,891.31
289,668.30 18,875.21 - 308,543.51

A.2.2.1.11 1 bh Pembuatan Kotak adukan ukuran 40 cm x 50 cm x25 cm


Tenaga
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0360 5,225,000.00 188,100.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0070 4,950,000.00 34,650.00
Paku biasa 2.2.12.1 kg 0.0800 16,200.00 1,296.00
29,655.00 224,046.00 - 253,701.00
Overhead dan profit 0.1400 4,151.70 31,366.44 - 35,518.14
33,806.70 255,412.44 - 289,219.14

A.2.2.1.12 1 m2 Pembuatan Jalan Sementara


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 0.1500 275,000.00 41,250.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0900 300,000.00 27,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0100 264,000.00 2,640.00
68,972.50 70,890.00 - 139,862.50
Overhead dan profit 0.1400 9,656.15 9,924.60 - 19,580.75
78,628.65 80,814.60 - 159,443.25

A.2.2.1.13 1 m3 Pembongkaran Beton bertulang


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 13.3340 68,500.00 913,379.00
Mandor 1.2.7.5 oh 0.6660 94,500.00 62,937.00
976,316.00 - - -
Overhead dan profit 0.1400 136,684.24 - - 136,684.24
1,113,000.24 - - 1,113,000.24

A.2.2.1.14 1 m3 Pembongkaran Dinding Tembok bata


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.6670 68,500.00 456,689.50
Mandor 1.2.7.5 oh 0.3330 94,500.00 31,468.50
488,158.00 - - 488,158.00
Overhead dan profit 0.1400 68,342.12 - - 68,342.12
556,500.12 - - 556,500.12

A.2.2.1.15 1 m2 Pemasangan pagar kawat jaring galvanis panjang 240 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0420 68,500.00 2,877.00
Tukang kayu 1.2.7.19 oh 0.0040 89,500.00 358.00
Kepala Tukang 1.2.7.3 oh 0.0020 93,500.00 187.00
Mandor 1.2.7.5 oh 0.0420 94,500.00 3,969.00
Bahan
Jaring kawat baja dilas (wiremesh) 2.2.4.25 Lembar 0.1434 28,900.00 4,144.26
7,391.00 4,144.26 - 11,535.26
Overhead dan profit 0.1400 1,034.74 580.20 - 1,614.94
8,425.74 4,724.46 - 13,150.20

A.2.2.1.16 1 m2 Pemasangan panel Beton pracetak 5 x 50 x 213 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3750 68,500.00 25,687.50
Tukang batu 1.2.7.16 oh 0.1250 79,000.00 9,875.00
Kepala Tukang 1.2.7.3 oh 0.1200 93,500.00 11,220.00
Mandor 1.2.7.5 oh 0.0190 94,500.00 1,795.50
Bahan
Beton Pracetak (Kolom) (5x50x200) 2.2.13.4 Lembar 0.9860 104,500.00 103,037.00
Beton Pracetak (Kolom) (5x50x200) 2.2.13.4 Batang 0.5250 104,500.00 54,862.50
PC / Portland cement 2.2.1.52 Kg 45.0000 1,400.00 63,000.00

3
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pasir pasang / beton 2.2.1.50 m3 0.0740 264,000.00 19,536.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.1460 300,000.00 43,800.00
48,578.00 284,235.50 - 332,813.50
Overhead dan profit 0.1400 6,800.92 39,792.97 - 46,593.89
55,378.92 324,028.47 - 379,407.39

A.2.2.1.17 10 m2 Membongkar lantai lama, berikut membersihkan bata-bata lama atau ubin-ubin yang dibongkar
Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00
77,950.00 - - 77,950.00
Overhead dan profit 0.1400 10,913.00 - - 10,913.00
88,863.00 - - 88,863.00

A.2.2.1.17a 10 m2 Menghapus plesteran yang lama


Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.5000 68,500.00 34,250.00
Mandor 1.2.7.5 oh 0.0250 94,500.00 2,362.50
36,612.50 - - 36,612.50
Overhead dan profit 0.1400 5,125.75 - - 5,125.75
41,738.25 - - 41,738.25

A.2.2.1.17b 10 m2 Menurunkan atap genteng atau sirap (jika atap genteng atau sirap akan dipakai lagi)
Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00
23,150.00 - - 23,150.00
Overhead dan profit 0.1400 3,241.00 - - 3,241.00
26,391.00 - - 26,391.00

A.2.2.1.17c 10 m2 Menurunkan atap genteng atau sirap (jika atap genteng atau sirap tidak dipakai lagi)
Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00
23,150.00 - - 23,150.00
Overhead dan profit 0.1400 3,241.00 - - 3,241.00
26,391.00 - - 26,391.00

A.2.2.1.17d 10 m2 Menurunkan rangka atap dari kayu (jika kayu bongkaran hendak dipakai lagi)
Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 0.2500 89,500.00 22,375.00
Kepala Tukang 1.2.7.3 oh 0.2500 93,500.00 23,375.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
118,975.00 - - 118,975.00
Overhead dan profit 0.1400 16,656.50 - - 16,656.50
135,631.50 - - 135,631.50

A.2.2.1.17e 10 m2 Menurunkan rangka atap dari kayu (jika kayu bongkaran tidak dipakai lagi)
Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
73,225.00 - - 73,225.00
Overhead dan profit 0.1400 10,251.50 - - 10,251.50
83,476.50 - - 83,476.50

A.2.2.1.17f 1 m3 Membongkar kuda-kuda jika dipakai lagi


Mukomoko Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 4.0000 68,500.00 274,000.00
Tukang kayu 1.2.7.19 oh 6.0000 89,500.00 537,000.00
Kepala Tukang 1.2.7.3 oh 0.6000 93,500.00 56,100.00
Mandor 1.2.7.5 oh 0.2000 94,500.00 18,900.00
886,000.00 - - 886,000.00
Overhead dan profit 0.1400 124,040.00 - - 124,040.00
1,010,040.00 - - 1,010,040.00
Utk.bangunan yg tingginya kurang dari 3,5 m
/m3 = 2/3 x total

A.2.2.1.17g 1 m3 Membongkar kuda-kuda jika tidak dipakai lagi


Mukomoko Tenaga
Tukang kayu 1.2.7.19 6.0000 89,500.00 537,000.00
Kepala Tukang 1.2.7.3 0.6000 93,500.00 56,100.00
593,100.00 - - 593,100.00
Overhead dan profit 0.1400 83,034.00 - - 83,034.00
676,134.00 - - 676,134.00
Utk.bangunan yg tingginya kurang dari 3,5 m
/m3 = 2/3 x total

A.2.3.1 PEKERJAAN TANAH

4
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.2.3.1.1 1 m3 Penggalian Tanah biasa sedalam 1 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7500 68,500.00 51,375.00
Mandor 1.2.7.5 oh 0.0250 94,500.00 2,362.50
53,737.50 - - 53,737.50
Overhead dan profit 0.1400 7,523.25 - - 7,523.25
61,260.75 - - 61,260.75

A.2.3.1.2 1 m3 Penggalian Tanah biasa sedalam 2 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
65,902.50 - - 65,902.50
Overhead dan profit 0.1400 9,226.35 - - 9,226.35
75,128.85 - - 75,128.85

A.2.3.1.3 1 m3 Penggalian Tanah biasa sedalam 3 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0500 68,500.00 71,925.00
Mandor 1.2.7.5 oh 0.0670 94,500.00 6,331.50
78,256.50 - - 78,256.50
Overhead dan profit 0.1400 10,955.91 - - 10,955.91
89,212.41 - - 89,212.41

A.2.3.1.4 1 m3 Penggalian Tanah keras sedalam 1 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Mandor 1.2.7.5 oh 0.0320 94,500.00 3,024.00
71,524.00 - - 71,524.00
Overhead dan profit 0.1400 10,013.36 - - 10,013.36
81,537.36 - - 81,537.36

A.2.3.1.5 1 m3 Penggalian Tanah cadas sedalam 1 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.5000 68,500.00 102,750.00
Mandor 1.2.7.5 oh 0.0600 94,500.00 5,670.00
108,420.00 - - 108,420.00
Overhead dan profit 0.1400 15,178.80 - - 15,178.80
123,598.80 - - 123,598.80

A.2.3.1.6 1 m3 Penggalian Tanah lumpur sedalam 1 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.2000 68,500.00 82,200.00
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
86,452.50 - - 86,452.50
Overhead dan profit 0.1400 12,103.35 - - 12,103.35
98,555.85 - - 98,555.85

A.2.3.1.7 1 m2 Pengerjaan stripping tanah tebing setinngi 1 meter


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
3,897.50 - - 3,897.50
Overhead dan profit 0.1400 545.65 - - 545.65
4,443.15 - - 4,443.15

A.2.3.1.8 1 m3 Pembuangan tanah sejauh 30 meter


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3300 68,500.00 22,605.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
23,550.00 - - 23,550.00
Overhead dan profit 0.1400 3,297.00 - - 3,297.00
26,847.00 - - 26,847.00

A.2.3.1.9 1 m3 Pengurugan kembali galian tanah


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.5000 68,500.00 34,250.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
38,975.00 - - 38,975.00
Overhead dan profit 0.1400 5,456.50 - - 5,456.50
44,431.50 - - 44,431.50

A.2.3.1.10 1 m3 Pemadatan tanah ( per 20 cm )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.5000 68,500.00 34,250.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
38,975.00 - - 38,975.00
Overhead dan profit 0.1400 5,456.50 - - 5,456.50
44,431.50 - - 44,431.50

5
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.2.3.1.11 1 m3 Pengurugan dengan pasir urug


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Pasir urug 2.2.1.51 m3 1.2000 173,300.00 207,960.00
21,495.00 207,960.00 - 229,455.00
Overhead dan profit 0.1400 3,009.30 29,114.40 - 32,123.70
24,504.30 237,074.40 - 261,578.70

A.2.3.1.12 1 m3 Pemasangan lapisan pudel campuran 1 kp : 3 pp : 7 tl


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0800 94,500.00 7,560.00
Bahan
Kapur Batu 2.2.1.46 m3 0.1350 1,270,500.00 171,517.50
Pasir pasang / beton 2.2.1.50 m3 0.4000 264,000.00 105,600.00
Tanah Liat 2.2.1.61 m3 0.9480 49,500.00 46,926.00
97,700.00 324,043.50 - 421,743.50
Overhead dan profit 0.1400 13,678.00 45,366.09 - 59,044.09
111,378.00 369,409.59 - 480,787.59

A.2.3.1.13 1 m2 Pemasangan lapisan ijuk tebal 10 cm untuk bidang resapan


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Ijuk 2.2.1.44 kg 6.0000 7,700.00 46,200.00
11,692.50 46,200.00 - 57,892.50
Overhead dan profit 0.1400 1,636.95 6,468.00 - 8,104.95
13,329.45 52,668.00 - 65,997.45

A.2.3.1.14 1 m3 Pengurugan sirtu padat


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Mandor 1.2.7.5 oh 0.0250 94,500.00 2,362.50
Bahan
Sirtu Urug 2.2.1.56 kg 1.2000 187,000.00 224,400.00
19,487.50 224,400.00 - 243,887.50
Overhead dan profit 0.1400 2,728.25 31,416.00 - 34,144.25
22,215.75 255,816.00 - 278,031.75

A.2.3.1.14a 1 m3 Pengurugan tanah


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Mandor 1.2.7.5 oh 0.0250 94,500.00 2,362.50
Bahan
Tanah urug 2.2.1.62 kg 1.2000 82,500.00 99,000.00
19,487.50 99,000.00 - 118,487.50
Overhead dan profit 0.1400 2,728.25 13,860.00 - 16,588.25
22,215.75 112,860.00 - 135,075.75

A.3.2.1 PEKERJAAN PONDASI

A.3.2.1.1 1 m3 Pasangan pondasi batu belah campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.5000 68,500.00 102,750.00
Tukang batu 1.2.7.16 oh 0.7500 79,000.00 59,250.00
Kepala Tukang 1.2.7.3 oh 0.0750 93,500.00 7,012.50
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 1.2000 275,000.00 330,000.00
PC / Portland cement 2.2.1.52 kg 202.0000 1,400.00 282,800.00
Pasir pasang / beton 2.2.1.50 m3 0.4850 264,000.00 128,040.00
176,100.00 740,840.00 - 916,940.00
Overhead dan profit 0.1400 24,654.00 103,717.60 - 128,371.60
200,754.00 844,557.60 - 1,045,311.60

A.3.2.1.2 1 m3 Pasangan pondasi batu belah campuran 1 sp : 4 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.5000 68,500.00 102,750.00
Tukang batu 1.2.7.16 oh 0.7500 79,000.00 59,250.00
Kepala Tukang 1.2.7.3 oh 0.0750 93,500.00 7,012.50
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 1.2000 275,000.00 330,000.00

6
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
PC / Portland cement 2.2.1.52 kg 163.0000 1,400.00 228,200.00
Pasir pasang / beton 2.2.1.50 m3 0.5200 264,000.00 137,280.00
176,100.00 695,480.00 - 871,580.00
Overhead dan profit 0.1400 24,654.00 97,367.20 - 122,021.20
200,754.00 792,847.20 - 993,601.20

A.3.2.1.3 1 m3 Pasangan pondasi batu belah campuran 1 sp : 5 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.5000 68,500.00 102,750.00
Tukang batu 1.2.7.16 oh 0.7500 79,000.00 59,250.00
Kepala Tukang 1.2.7.3 oh 0.0750 93,500.00 7,012.50
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 1.2000 275,000.00 330,000.00
PC / Portland cement 2.2.1.52 kg 136.0000 1,400.00 190,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5440 264,000.00 143,616.00
176,100.00 664,016.00 - 840,116.00
Overhead dan profit 0.1400 24,654.00 92,962.24 - 117,616.24
200,754.00 756,978.24 - 957,732.24

A.3.2.1.4 1 m3 Pasangan pondasi batu belah campuran 1 sp : 6 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.5000 68,500.00 102,750.00
Tukang batu 1.2.7.16 oh 0.7500 79,000.00 59,250.00
Kepala Tukang 1.2.7.3 oh 0.0750 93,500.00 7,012.50
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan #N/A
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 1.2000 275,000.00 330,000.00
PC / Portland cement 2.2.1.52 kg 117.0000 1,400.00 163,800.00
Pasir pasang / beton 2.2.1.50 m3 0.5610 264,000.00 148,104.00
176,100.00 641,904.00 - 818,004.00
Overhead dan profit 0.1400 24,654.00 89,866.56 - 114,520.56
200,754.00 731,770.56 - 932,524.56

A.3.2.1.5 1 m3 Pasangan pondasi batu belah campuran 1 sp : 8 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.5000 68,500.00 102,750.00
Tukang batu 1.2.7.16 oh 0.7500 79,000.00 59,250.00
Kepala Tukang 1.2.7.3 oh 0.0750 93,500.00 7,012.50
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 1.2000 275,000.00 330,000.00
PC / Portland cement 2.2.1.52 kg 91.0000 1,400.00 127,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5840 264,000.00 154,176.00
176,100.00 611,576.00 - 787,676.00
Overhead dan profit 0.1400 24,654.00 85,620.64 - 110,274.64
200,754.00 697,196.64 - 897,950.64

A.3.2.1.6 1 m3 Pasangan pondasi batu belah campuran 1 sp : 1 kp : 2 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.5000 68,500.00 102,750.00
Tukang batu 1.2.7.16 oh 0.7500 79,000.00 59,250.00
Kepala Tukang 1.2.7.3 oh 0.0750 93,500.00 7,012.50
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 1.2000 275,000.00 330,000.00
Kapur Batu 2.2.1.46 m3 0.1700 1,270,500.00 215,985.00
PC / Portland cement 2.2.1.52 kg 0.1700 1,400.00 238.00
Pasir pasang / beton 2.2.1.50 m3 0.3400 264,000.00 89,760.00
176,100.00 635,983.00 - 812,083.00
Overhead dan profit 0.1400 24,654.00 89,037.62 - 113,691.62
200,754.00 725,020.62 - 925,774.62

A.3.2.1.7 1 m3 Pasangan pondasi batu belah campuran 1 sp : 3 kp : 10 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.5000 68,500.00 102,750.00
Tukang batu 1.2.7.16 oh 0.7500 79,000.00 59,250.00
Kepala Tukang 1.2.7.3 oh 0.0750 93,500.00 7,012.50
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 1.2000 275,000.00 330,000.00
PC / Portland cement 2.2.1.52 kg 61.0000 1,400.00 85,400.00
Kapur Batu 2.2.1.46 m3 0.1470 1,270,500.00 186,763.50
Pasir pasang / beton 2.2.1.50 m3 0.4920 264,000.00 129,888.00
176,100.00 732,051.50 - 908,151.50
Overhead dan profit 0.1400 24,654.00 102,487.21 - 127,141.21
200,754.00 834,538.71 - 1,035,292.71

A.3.2.1.8 1 m3 Pasangan pondasi batu belah campuran 1/4 sp : 1 kp : 4 pp


Tenaga

7
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.5000 68,500.00 102,750.00
Tukang batu 1.2.7.16 oh 0.7500 79,000.00 59,250.00
Kepala Tukang 1.2.7.3 oh 0.0750 93,500.00 7,012.50
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 1.2000 275,000.00 330,000.00
PC / Portland cement 2.2.1.52 kg 41.0000 1,400.00 57,400.00
Kapur Batu 2.2.1.46 m3 0.1310 1,270,500.00 166,435.50
Pasir pasang / beton 2.2.1.50 m3 0.5230 264,000.00 138,072.00
176,100.00 691,907.50 - 868,007.50
Overhead dan profit 0.1400 24,654.00 96,867.05 - 121,521.05
200,754.00 788,774.55 - 989,528.55

A.3.2.1.9 1 m3 Pasangan pondasi batu kosong ( anstamping )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7800 68,500.00 53,430.00
Tukang batu 1.2.7.16 oh 0.3900 79,000.00 30,810.00
Kepala Tukang 1.2.7.3 oh 0.0390 93,500.00 3,646.50
Mandor 1.2.7.5 oh 0.0390 94,500.00 3,685.50
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 1.2000 275,000.00 330,000.00
Pasir pasang / beton 2.2.1.50 m3 0.4320 264,000.00 114,048.00
91,572.00 444,048.00 - 535,620.00
Overhead dan profit 0.1400 12,820.08 62,166.72 - 74,986.80
104,392.08 506,214.72 - 610,606.80

A.3.2.1.10 1 m3 Pasangan pondasi siklop 60 % beton campuran 1 sp : 2 pb : 3 kr dan 40% batu belah
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.4000 68,500.00 232,900.00
Tukang batu 1.2.7.16 oh 0.8500 79,000.00 67,150.00
Kepala Tukang 1.2.7.3 oh 0.0850 93,500.00 7,947.50
Mandor 1.2.7.5 oh 0.1740 94,500.00 16,443.00
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 0.4800 275,000.00 132,000.00
PC / Portland cement 2.2.1.52 kg 194.0000 1,400.00 271,600.00
Pasir pasang / beton 2.2.1.50 m3 0.3120 264,000.00 82,368.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.4680 300,000.00 140,400.00
Besi Beton / tulangan beton 2.2.4.9 kg 126.0000 10,500.00 1,323,000.00
Kawat Beton / bendraat 2.2.4.30 kg 1.8000 17,600.00 31,680.00
324,440.50 1,981,048.00 - 2,305,488.50
Overhead dan profit 0.1400 45,421.67 277,346.72 - 322,768.39
369,862.17 2,258,394.72 - 2,628,256.89

A.3.2.1.11 1 m3 Pasangan pondasi sumuran diameter 100 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 2.4000 68,500.00 164,400.00
Tukang batu 1.2.7.16 oh 0.8000 79,000.00 63,200.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.1190 94,500.00 11,245.50
Bahan
Batu pecah 10-15 cm (15-20) 2.2.1.36 m3 0.4500 275,000.00 123,750.00
PC / Portland cement 2.2.1.52 kg 194.0000 1,400.00 271,600.00
Pasir pasang / beton 2.2.1.50 m3 0.3120 264,000.00 82,368.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.4680 300,000.00 140,400.00
246,325.50 618,118.00 - 864,443.50
Overhead dan profit 0.1400 34,485.57 86,536.52 - 121,022.09
280,811.07 704,654.52 - 985,465.59

A.3.2.1.11a 1 m' Pembuatan tiang pancang (40 X 40) Cm, beton bertulang
SNI 2002 3.17 Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 1.0000 68,500.00 68,500.00
Tukang batu 1.2.7.16 Oh 0.6700 79,000.00 52,930.00
Kepala Tukang 1.2.7.3 Oh 0.0670 93,500.00 6,264.50
Mandor 1.2.7.5 Oh 0.0500 94,500.00 4,725.00
Bahan
Pasir Urug 2.2.1.51 M3 0.0190 173,300.00 3,292.70
Pasir pasang / beton 2.2.1.50 M3 0.9400 264,000.00 248,160.00
Batu pecah 2-3 cm 2.2.1.32 M3 0.1500 300,000.00 45,000.00
PC / Portland cement 2.2.1.52 Kg 60.5000 1,400.00 84,700.00
Besi Beton / tulangan beton 2.2.4.9 Kg 45.0000 10,500.00 472,500.00
Kawat Beton / bendraat 2.2.4.30 Kg 0.9000 17,600.00 15,840.00
Kayu bekisting 2.2.2.15 M3 0.0320 3,465,000.00 110,880.00
Paku biasa 2.2.12.1 Kg 0.1200 16,200.00 1,944.00
Minyak bekisting 2.2.6.27 Lt 0.0900 5,800.00 522.00
Plamur Tembok 2.2.6.38 Kg 0.2400 15,600.00 3,744.00
132,419.50 986,582.70 - 1,119,002.20
Overhead dan profit 0.1400 18,538.73 138,121.58 - 156,660.31
150,958.23 1,124,704.28 - 1,275,662.51

A.3.2.1.11b 1 m' Pembuatan tiang pancang (35 X 35) Cm, beton bertulang

8
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
SNI 2002 3.18 Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.8000 68,500.00 54,800.00
Tukang batu 1.2.7.16 Oh 0.5000 79,000.00 39,500.00
Kepala Tukang 1.2.7.3 Oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 Oh 0.0400 94,500.00 3,780.00
Bahan
Pasir Urug 2.2.1.51 M3 0.0160 173,300.00 2,772.80
Pasir pasang / beton 2.2.1.50 M3 0.0800 264,000.00 21,120.00
Batu pecah 2-3 cm 2.2.1.32 M3 0.1250 300,000.00 37,500.00
PC / Portland cement 2.2.1.52 Kg 49.0000 1,400.00 68,600.00
Besi Beton / tulangan beton 2.2.4.9 Kg 34.5000 10,500.00 362,250.00
Kawat Beton / bendraat 2.2.4.30 Kg 0.7000 17,600.00 12,320.00
Kayu bekisting 2.2.2.15 M3 0.0270 3,465,000.00 93,555.00
Paku biasa 2.2.12.1 Kg 0.1200 16,200.00 1,944.00
Minyak bekisting 2.2.6.27 Lt 0.0900 5,800.00 522.00
Plamur Tembok 2.2.6.38 Kg 0.2000 15,600.00 3,120.00
102,755.00 603,703.80 - 706,458.80
Overhead dan profit 0.1400 14,385.70 84,518.53 - 98,904.23
117,140.70 688,222.33 - 805,363.03

A.4.1.1 PEKERJAAN BETON

A.4.1.1.1 1 m3 Membuat Beton mutu fc=7,4 Mpa (K100), Slump (12±2) cm, w/c = 0,87
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 68,500.00 113,025.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Kepala Tukang 1.2.7.3 oh 0.0280 93,500.00 2,618.00
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
PC / Portland cement 2.2.1.52 kg 247.0000 1,400.00 345,800.00
Pasir pasang / beton 2.2.1.50 m3 0.6207 264,000.00 163,864.80
Batu pecah 2-3 cm 2.2.1.32 m3 0.7400 300,000.00 222,000.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
145,211.50 753,164.80 - 898,376.30
Overhead dan profit 0.1400 20,329.61 105,443.07 - 125,772.68
165,541.11 858,607.87 - 1,024,148.98

A.4.1.1.2 1 m3 Membuat Beton mutu fc=9,8 Mpa (K125), Slump (12±2) cm, w/c = 0,78
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 68,500.00 113,025.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Kepala Tukang 1.2.7.3 oh 0.0280 93,500.00 2,618.00
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
PC / Portland cement 2.2.1.52 kg 276.0000 1,400.00 386,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5914 264,000.00 156,129.60
Batu pecah 2-3 cm 2.2.1.32 m3 0.7496 300,000.00 224,880.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
145,211.50 788,909.60 - 934,121.10
Overhead dan profit 0.1400 20,329.61 110,447.34 - 130,776.95
165,541.11 899,356.94 - 1,064,898.05

A.4.1.1.3 1 m3 Membuat Beton mutu fc=12,2 Mpa (K150), Slump (12±2) cm, w/c = 0,72
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 68,500.00 113,025.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Kepala Tukang 1.2.7.3 oh 0.0280 93,500.00 2,618.00
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
PC / Portland cement 2.2.1.52 kg 299.0000 1,400.00 418,600.00
Pasir pasang / beton 2.2.1.50 m3 0.5707 264,000.00 150,664.80
Batu pecah 2-3 cm 2.2.1.32 m3 0.7533 300,000.00 225,990.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
145,211.50 816,754.80 - 961,966.30
Overhead dan profit 0.1400 20,329.61 114,345.67 - 134,675.28
165,541.11 931,100.47 - 1,096,641.58

A.4.1.1.4 1 m3 Membuat lantai kerja beton mutu f'c=7,4 Mpa ( K100) Slump (3-6) cm, w/c = 0,87
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.2000 68,500.00 82,200.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0600 94,500.00 5,670.00
Bahan
PC / Portland cement 2.2.1.52 kg 230.0000 1,400.00 322,000.00
Pasir pasang / beton 2.2.1.50 m3 0.6379 264,000.00 168,405.60
Batu pecah 2-3 cm 2.2.1.32 m3 0.7607 300,000.00 228,210.00
Air bersih 2.2.6.1 ltr 200.0000 100.00 20,000.00
105,540.00 738,615.60 - 844,155.60
Overhead dan profit 0.1400 14,775.60 103,406.18 - 118,181.78

9
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
120,315.60 842,021.78 - 962,337.38

A.4.1.1.5 1 m3 Membuat Beton mutu fc=14,5 Mpa (K175), Slump (12±2) cm, w/c = 0,66
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 68,500.00 113,025.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Kepala Tukang 1.2.7.3 oh 0.0280 93,500.00 2,618.00
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
PC / Portland cement 2.2.1.52 kg 326.0000 1,400.00 456,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5429 264,000.00 143,325.60
Batu pecah 2-3 cm 2.2.1.32 m3 0.7622 300,000.00 228,660.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
145,211.50 849,885.60 - 995,097.10
Overhead dan profit 0.1400 20,329.61 118,983.98 - 139,313.59
165,541.11 968,869.58 - 1,134,410.69

A.4.1.1.6 1 m3 Membuat Beton mutu fc=15,9 Mpa (K200), Slump (12±2) cm, w/c = 0,61
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 68,500.00 113,025.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Kepala Tukang 1.2.7.3 oh 0.0280 93,500.00 2,618.00
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
PC / Portland cement 2.2.1.52 kg 352.0000 1,400.00 492,800.00
Pasir pasang / beton 2.2.1.50 m3 0.5221 264,000.00 137,834.40
Batu pecah 2-3 cm 2.2.1.32 m3 0.7637 300,000.00 229,110.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
145,211.50 881,244.40 - 1,026,455.90
Overhead dan profit 0.1400 20,329.61 123,374.22 - 143,703.83
165,541.11 1,004,618.62 - 1,170,159.73

A.4.1.1.7 1 m3 Membuat Beton mutu fc=19,3 Mpa (K225), Slump (12±2) cm, w/c = 0,58
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 68,500.00 113,025.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Kepala Tukang 1.2.7.3 oh 0.0280 93,500.00 2,618.00
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
PC / Portland cement 2.2.1.52 kg 371.0000 1,400.00 519,400.00
Pasir pasang / beton 2.2.1.50 m3 0.4986 264,000.00 131,630.40
Batu pecah 2-3 cm 2.2.1.32 m3 0.7756 300,000.00 232,680.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
145,211.50 905,210.40 - 1,050,421.90
Overhead dan profit 0.1400 20,329.61 126,729.46 - 147,059.07
165,541.11 1,031,939.86 - 1,197,480.97

A.4.1.1.8 1 m3 Membuat Beton mutu fc=21,7 Mpa (K250), Slump (12±2) cm, w/c = 0,56
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 68,500.00 113,025.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Kepala Tukang 1.2.7.3 oh 0.0280 93,500.00 2,618.00
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
PC / Portland cement 2.2.1.52 kg 384.0000 1,400.00 537,600.00
Pasir pasang / beton 2.2.1.50 m3 0.4943 264,000.00 130,495.20
Batu pecah 2-3 cm 2.2.1.32 m3 0.7696 300,000.00 230,880.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
145,211.50 920,475.20 - 1,065,686.70
Overhead dan profit 0.1400 20,329.61 128,866.53 - 149,196.14
165,541.11 1,049,341.73 - 1,214,882.84

A.4.1.1.9 1 m3 Membuat Beton mutu fc=24,0 Mpa (K275), Slump (12±2) cm, w/c = 0,53
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 68,500.00 113,025.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Kepala Tukang 1.2.7.3 oh 0.0280 93,500.00 2,618.00
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
PC / Portland cement 2.2.1.52 kg 406.0000 1,400.00 568,400.00
Pasir pasang / beton 2.2.1.50 m3 0.4886 264,000.00 128,982.74
Batu pecah 2-3 cm 2.2.1.32 m3 0.7600 300,000.00 228,000.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
145,211.50 946,882.74 - 1,092,094.24
Overhead dan profit 0.1400 20,329.61 132,563.58 - 152,893.19
165,541.11 1,079,446.32 - 1,244,987.43

A.4.1.1.10 1 m3 Membuat Beton mutu fc=26,4 Mpa (K300), Slump (12±2) cm, w/c = 0,52
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 68,500.00 113,025.00

10
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Kepala Tukang 1.2.7.3 oh 0.0280 93,500.00 2,618.00
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
PC / Portland cement 2.2.1.52 kg 413.0000 1,400.00 578,200.00
Pasir pasang / beton 2.2.1.50 m3 0.4864 264,000.00 128,409.60
Batu pecah 2-3 cm 2.2.1.32 m3 0.7563 300,000.00 226,890.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
145,211.50 954,999.60 - 1,100,211.10
Overhead dan profit 0.1400 20,329.61 133,699.94 - 154,029.55
165,541.11 1,088,699.54 - 1,254,240.65

A.4.1.1.11 1 m3 Membuat Beton mutu fc=28,8 Mpa (K325), Slump (12±2) cm, w/c = 0,49
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 2.1000 68,500.00 143,850.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.1050 94,500.00 9,922.50
Bahan
PC / Portland cement 2.2.1.52 kg 439.0000 1,400.00 614,600.00
Pasir pasang / beton 2.2.1.50 m3 0.4786 264,000.00 126,350.40
Batu pecah 2-3 cm 2.2.1.32 m3 0.7452 300,000.00 223,560.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
184,695.00 986,010.40 - 1,170,705.40
Overhead dan profit 0.1400 25,857.30 138,041.46 - 163,898.76
210,552.30 1,124,051.86 - 1,334,604.16

A.4.1.1.12 1 m3 Membuat Beton mutu fc=31,2 Mpa (K350), Slump (12±2) cm, w/c = 0,48
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 2.1000 68,500.00 143,850.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.3500 93,500.00 32,725.00
Mandor 1.2.7.5 oh 0.1050 94,500.00 9,922.50
Bahan
PC / Portland cement 2.2.1.52 kg 448.0000 1,400.00 627,200.00
Pasir pasang / beton 2.2.1.50 m3 0.4764 264,000.00 125,769.60
Batu pecah 2-3 cm 2.2.1.32 m3 0.7407 300,000.00 222,210.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
214,147.50 996,679.60 - 1,210,827.10
Overhead dan profit 0.1400 29,980.65 139,535.14 - 169,515.79
244,128.15 1,136,214.74 - 1,380,342.89

A.4.1.1.13 1 m3 Membuat Beton kedap air dengan strorox - 100


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 2.1000 68,500.00 143,850.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.1050 94,500.00 9,922.50
Bahan
PC / Portland cement 2.2.1.52 kg 400.0000 1,400.00 560,000.00
Pasir pasang / beton 2.2.1.50 m3 0.4800 264,000.00 126,720.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.8000 300,000.00 240,000.00
Storox-100 2.2.13.27 kg 1.2000 40,200.00 48,240.00
184,695.00 974,960.00 - 1,159,655.00
Overhead dan profit 0.1400 25,857.30 136,494.40 - 162,351.70
210,552.30 1,111,454.40 - 1,322,006.70

A.4.1.1.14 1 m' Pasang PVC waterstop lebar 150 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0600 68,500.00 4,110.00
Tukang batu 1.2.7.16 oh 0.0300 79,000.00 2,370.00
Kepala Tukang 1.2.7.3 oh 0.0030 93,500.00 280.50
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Waterstop (Lebar 150mm) 2.2.11.3.200 m' 1.0500 47,900.00 50,295.00
7,044.00 50,295.00 - 57,339.00
Overhead dan profit 0.1400 986.16 7,041.30 - 8,027.46
8,030.16 57,336.30 - 65,366.46

A.4.1.1.15 1 m' Pasang PVC waterstop lebar 200 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0700 68,500.00 4,795.00
Tukang batu 1.2.7.16 oh 0.0350 79,000.00 2,765.00
Kepala Tukang 1.2.7.3 oh 0.0040 93,500.00 374.00
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Waterstop (Lebar 200mm) 2.2.11.3.201 m' 1.0500 64,500.00 67,725.00
8,595.50 67,725.00 - 76,320.50
Overhead dan profit 0.1400 1,203.37 9,481.50 - 10,684.87
9,798.87 77,206.50 - 87,005.37

11
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.4.1.1.16 1 m' Pasang PVC waterstop lebar 230 - 320 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0800 68,500.00 5,480.00
Tukang batu 1.2.7.16 oh 0.0400 79,000.00 3,160.00
Kepala Tukang 1.2.7.3 oh 0.0040 93,500.00 374.00
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Waterstop (Lebar 250mm) 2.2.11.3.202 m' 1.0500 90,600.00 95,130.00
9,392.00 95,130.00 - 104,522.00
Overhead dan profit 0.1400 1,314.88 13,318.20 - 14,633.08
10,706.88 108,448.20 - 119,155.08

A.4.1.1.17 10 kg Pembesian dengan besi polos atau ulir


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0700 68,500.00 4,795.00
Tukang besi 1.2.7.17 oh 0.0700 84,000.00 5,880.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Besi Beton / tulangan beton 2.2.4.9 kg 10.5000 10,500.00 110,250.00
Kawat Beton / bendraat 2.2.4.30 kg 0.1500 17,600.00 2,640.00
11,707.50 112,890.00 - 124,597.50
Overhead dan profit 0.1400 1,639.05 15,804.60 - 17,443.65
13,346.55 128,694.60 - 142,041.15

A.4.1.1.18 10 kg Pemasangan kabel presstressed polos / strands


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang batu 1.2.7.16 oh 0.0500 79,000.00 3,950.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Besi Beton / tulangan beton 2.2.4.9 kg 10.5000 10,500.00 110,250.00
Kawat Beton / bendraat 2.2.4.30 kg 0.1000 17,600.00 1,760.00
8,126.00 112,010.00 - 120,136.00
Overhead dan profit 0.1400 1,137.64 15,681.40 - 16,819.04
9,263.64 127,691.40 - 136,955.04

A.4.1.1.19 10 kg Pemasangan jaring kawat baja ( wiremesh )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0250 68,500.00 1,712.50
Tukang batu 1.2.7.16 oh 0.0250 79,000.00 1,975.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan
Jaring kawat baja dilas (wiremesh) 2.2.4.25 kg 10.2000 28,900.00 294,780.00
Kawat Beton / bendraat 2.2.4.30 kg 0.0500 17,600.00 880.00
6,119.50 295,660.00 - 301,779.50
Overhead dan profit 0.1400 856.73 41,392.40 - 42,249.13
6,976.23 337,052.40 - 344,028.63

A.4.1.1.20 1 m2 Pemasangan bekisting untuk pondasi


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.5200 68,500.00 35,620.00
Tukang kayu 1.2.7.19 oh 0.2600 89,500.00 23,270.00
Kepala Tukang 1.2.7.3 oh 0.0260 93,500.00 2,431.00
Mandor 1.2.7.5 oh 0.0260 94,500.00 2,457.00
Bahan
Kayu bekisting 2.2.2.15 m3 0.0400 3,465,000.00 138,600.00
Paku biasa 2.2.12.1 kg 0.3000 16,200.00 4,860.00
Minyak bekisting 2.2.6.27 ltr 0.1000 5,800.00 580.00
63,778.00 144,040.00 - 207,818.00
Overhead dan profit 0.1400 8,928.92 20,165.60 - 29,094.52
72,706.92 164,205.60 - 236,912.52

A.4.1.1.21 1 m2 Pemasangan bekisting untuk sloof


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.5200 68,500.00 35,620.00
Tukang kayu 1.2.7.19 oh 0.2600 89,500.00 23,270.00
Kepala Tukang 1.2.7.3 oh 0.0260 93,500.00 2,431.00
Mandor 1.2.7.5 oh 0.0260 94,500.00 2,457.00
Bahan
Kayu bekisting 2.2.2.15 m3 0.0450 3,465,000.00 155,925.00
Paku biasa 2.2.12.1 kg 0.3000 16,200.00 4,860.00
Minyak bekisting 2.2.6.27 ltr 0.1000 5,800.00 580.00
63,778.00 161,365.00 - 225,143.00
Overhead dan profit 0.1400 8,928.92 22,591.10 - 31,520.02
72,706.92 183,956.10 - 256,663.02

12
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
A.4.1.1.22 1 m2 Pemasangan bekisting untuk kolom
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6600 68,500.00 45,210.00
Tukang kayu 1.2.7.19 oh 0.3300 89,500.00 29,535.00
Kepala Tukang 1.2.7.3 oh 0.0330 93,500.00 3,085.50
Mandor 1.2.7.5 oh 0.0330 94,500.00 3,118.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.0400 3,465,000.00 138,600.00
Paku biasa 2.2.12.1 kg 0.4000 16,200.00 6,480.00
Minyak bekisting 2.2.6.27 ltr 0.2000 5,800.00 1,160.00
Kayu bekisting 2.2.2.15 m3 0.0150 3,465,000.00 51,975.00
Multiplek 9 mm, uk. 1,20 x 2,40 m 2.2.3.202 lbr 0.3500 140,800.00 49,280.00
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 btg 2.0000 12,100.00 24,200.00
80,949.00 271,695.00 - 352,644.00
Overhead dan profit 0.1400 11,332.86 38,037.30 - 49,370.16
92,281.86 309,732.30 - 402,014.16

A.4.1.1.23 1 m2 Pemasangan bekisting untuk balok


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6600 68,500.00 45,210.00
Tukang kayu 1.2.7.19 oh 0.3300 89,500.00 29,535.00
Kepala Tukang 1.2.7.3 oh 0.0330 93,500.00 3,085.50
Mandor 1.2.7.5 oh 0.0330 94,500.00 3,118.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.0400 3,465,000.00 138,600.00
Paku biasa 2.2.12.1 kg 0.4000 16,200.00 6,480.00
Minyak bekisting 2.2.6.27 ltr 0.2000 5,800.00 1,160.00
Kayu bekisting 2.2.2.15 m3 0.0180 3,465,000.00 62,370.00
Multiplek 9 mm, uk. 1,20 x 2,40 m 2.2.3.202 lbr 0.3500 140,800.00 49,280.00
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 btg 2.0000 12,100.00 24,200.00
80,949.00 282,090.00 - 363,039.00
Overhead dan profit 0.1400 11,332.86 39,492.60 - 50,825.46
92,281.86 321,582.60 - 413,864.46

A.4.1.1.24 1 m2 Pemasangan bekisting untuk lantai


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6600 68,500.00 45,210.00
Tukang kayu 1.2.7.19 oh 0.3300 89,500.00 29,535.00
Kepala Tukang 1.2.7.3 oh 0.0330 93,500.00 3,085.50
Mandor 1.2.7.5 oh 0.0330 94,500.00 3,118.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.0400 3,465,000.00 138,600.00
Paku biasa 2.2.12.1 kg 0.4000 16,200.00 6,480.00
Minyak bekisting 2.2.6.27 ltr 0.2000 5,800.00 1,160.00
Kayu bekisting 2.2.2.15 m3 0.0150 3,465,000.00 51,975.00
Multiplek 9 mm, uk. 1,20 x 2,40 m 2.2.3.202 lbr 0.3500 140,800.00 49,280.00
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 btg 6.0000 12,100.00 72,600.00
80,949.00 320,095.00 - 401,044.00
Overhead dan profit 0.1400 11,332.86 44,813.30 - 56,146.16
92,281.86 364,908.30 - 457,190.16

A.4.1.1.25 1 m2 Pemasangan bekisting untuk dinding


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6600 68,500.00 45,210.00
Tukang kayu 1.2.7.19 oh 0.3300 89,500.00 29,535.00
Kepala Tukang 1.2.7.3 oh 0.0330 93,500.00 3,085.50
Mandor 1.2.7.5 oh 0.0330 94,500.00 3,118.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.0300 3,465,000.00 103,950.00
Paku biasa 2.2.12.1 kg 0.4000 16,200.00 6,480.00
Minyak bekisting 2.2.6.27 ltr 0.2000 5,800.00 1,160.00
Kayu bekisting 2.2.2.15 m3 0.0200 3,465,000.00 69,300.00
Multiplek 9 mm, uk. 1,20 x 2,40 m 2.2.3.202 lbr 0.3500 140,800.00 49,280.00
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 btg 0.3000 12,100.00 3,630.00
80,949.00 233,800.00 - 314,749.00
Overhead dan profit 0.1400 11,332.86 32,732.00 - 44,064.86
92,281.86 266,532.00 - 358,813.86

A.4.1.1.26 1 m2 Pemasangan bekisting untuk tangga


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6600 68,500.00 45,210.00
Tukang kayu 1.2.7.19 oh 0.3300 89,500.00 29,535.00
Kepala Tukang 1.2.7.3 oh 0.0330 93,500.00 3,085.50
Mandor 1.2.7.5 oh 0.0330 94,500.00 3,118.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.0300 3,465,000.00 103,950.00
Paku biasa 2.2.12.1 kg 0.4000 16,200.00 6,480.00
Minyak bekisting 2.2.6.27 ltr 0.1500 5,800.00 870.00
Kayu bekisting 2.2.2.15 m3 0.0150 3,465,000.00 51,975.00
Multiplek 9 mm, uk. 1,20 x 2,40 m 2.2.3.202 lbr 0.3500 140,800.00 49,280.00

13
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 btg 2.0000 12,100.00 24,200.00
80,949.00 236,755.00 - 317,704.00
Overhead dan profit 0.1400 11,332.86 33,145.70 - 44,478.56
92,281.86 269,900.70 - 362,182.56

A.4.1.1.27 1 m2 Pemasangan jembatan untuk pengecoran beton


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu bekisting 2.2.2.15 m3 0.0264 3,465,000.00 91,476.00
Paku biasa 2.2.12.1 kg 0.6000 16,200.00 9,720.00
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 btg 0.5000 12,100.00 6,050.00
15,973.50 107,246.00 - 123,219.50
Overhead dan profit 0.1400 2,236.29 15,014.44 - 17,250.73
18,209.79 122,260.44 - 140,470.23

A.4.1.1.28 1 m3 Membuat pondasi beton bertulang ( 150 kg besi + bekisting )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 5.3000 68,500.00 363,050.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Tukang kayu 1.2.7.19 oh 1.3000 89,500.00 116,350.00
Tukang besi 1.2.7.17 oh 1.0500 84,000.00 88,200.00
Kepala Tukang 1.2.7.3 oh 0.2620 93,500.00 24,497.00
Mandor 1.2.7.5 oh 0.2650 94,500.00 25,042.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.2000 3,465,000.00 693,000.00
Paku biasa 2.2.12.1 kg 1.5000 16,200.00 24,300.00
Minyak bekisting 2.2.6.27 ltr 0.4000 5,800.00 2,320.00
Besi Beton / tulangan beton 2.2.4.9 kg 157.5000 10,500.00 1,653,750.00
Kawat Beton / bendraat 2.2.4.30 kg 2.2500 17,600.00 39,600.00
PC / Portland cement 2.2.1.52 kg 336.0000 1,400.00 470,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5400 264,000.00 142,560.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.8100 300,000.00 243,000.00
638,864.50 3,268,930.00 - 3,907,794.50
Overhead dan profit 0.1400 89,441.03 457,650.20 - 547,091.23
728,305.53 3,726,580.20 - 4,454,885.73

A.4.1.1.29 1 m3 Membuat sloof beton bertulang ( 200 kg besi + bekisting )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 5.6500 68,500.00 387,025.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Tukang kayu 1.2.7.19 oh 1.5600 89,500.00 139,620.00
Tukang besi 1.2.7.17 oh 1.4000 84,000.00 117,600.00
Kepala Tukang 1.2.7.3 oh 0.3230 93,500.00 30,200.50
Mandor 1.2.7.5 oh 0.2830 94,500.00 26,743.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.2700 3,465,000.00 935,550.00
Paku biasa 2.2.12.1 kg 2.0000 16,200.00 32,400.00
Minyak bekisting 2.2.6.27 ltr 0.6000 5,800.00 3,480.00
Besi Beton / tulangan beton 2.2.4.9 kg 210.0000 10,500.00 2,205,000.00
Kawat Beton / bendraat 2.2.4.30 kg 3.0000 17,600.00 52,800.00
PC / Portland cement 2.2.1.52 kg 336.0000 1,400.00 470,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5400 264,000.00 142,560.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.8100 300,000.00 243,000.00
722,914.00 4,085,190.00 - 4,808,104.00
Overhead dan profit 0.1400 101,207.96 571,926.60 - 673,134.56
824,121.96 4,657,116.60 - 5,481,238.56

A.4.1.1.30 1 m3 Membuat kolom beton bertulang ( 300 kg besi + bekisting )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 7.0500 68,500.00 482,925.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Tukang kayu 1.2.7.19 oh 1.6500 89,500.00 147,675.00
Tukang besi 1.2.7.17 oh 2.1000 84,000.00 176,400.00
Kepala Tukang 1.2.7.3 oh 0.4030 93,500.00 37,680.50
Mandor 1.2.7.5 oh 0.3530 94,500.00 33,358.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.4000 3,465,000.00 1,386,000.00
Paku biasa 2.2.12.1 kg 4.0000 16,200.00 64,800.00
Minyak bekisting 2.2.6.27 ltr 2.0000 5,800.00 11,600.00
Besi Beton / tulangan beton 2.2.4.9 kg 315.0000 10,500.00 3,307,500.00
Kawat Beton / bendraat 2.2.4.30 kg 4.5000 17,600.00 79,200.00
PC / Portland cement 2.2.1.52 kg 336.0000 1,400.00 470,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5400 264,000.00 142,560.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.8100 300,000.00 243,000.00
Kayu bekisting 2.2.2.15 m3 0.1500 3,465,000.00 519,750.00
Multiplek 9 mm, uk. 1,20 x 2,40 m 2.2.3.202 lbr 3.5000 140,800.00 492,800.00

14
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 bh 20.0000 12,100.00 242,000.00
899,764.00 6,959,610.00 - 7,859,374.00
Overhead dan profit 0.1400 125,966.96 974,345.40 - 1,100,312.36
1,025,730.96 7,933,955.40 - 8,959,686.36

A.4.1.1.31 1 m3 Membuat balok beton bertulang (200 kg besi + bekisting )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.3500 68,500.00 434,975.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Tukang kayu 1.2.7.19 oh 1.6500 89,500.00 147,675.00
Tukang besi 1.2.7.17 oh 1.4000 84,000.00 117,600.00
Kepala Tukang 1.2.7.3 oh 0.3330 93,500.00 31,135.50
Mandor 1.2.7.5 oh 0.3180 94,500.00 30,051.00
Bahan
Kayu bekisting 2.2.2.15 m3 0.3200 3,465,000.00 1,108,800.00
Paku biasa 2.2.12.1 kg 3.2000 16,200.00 51,840.00
Minyak bekisting 2.2.6.27 ltr 1.6000 5,800.00 9,280.00
Besi Beton / tulangan beton 2.2.4.9 kg 210.0000 10,500.00 2,205,000.00
Kawat Beton / bendraat 2.2.4.30 kg 3.0000 17,600.00 52,800.00
PC / Portland cement 2.2.1.52 kg 336.0000 1,400.00 470,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5400 264,000.00 142,560.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.8100 300,000.00 243,000.00
Kayu bekisting 2.2.2.15 m3 0.1400 3,465,000.00 485,100.00
Multiplek 9 mm, uk. 1,20 x 2,40 m 2.2.3.202 lbr 2.8000 140,800.00 394,240.00
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 bh 16.0000 12,100.00 193,600.00
783,161.50 5,356,620.00 - 6,139,781.50
Overhead dan profit 0.1400 109,642.61 749,926.80 - 859,569.41
892,804.11 6,106,546.80 - 6,999,350.91

A.4.1.1.32 1 m3 Membuat kolom beton bertulang (150 kg besi + bekisting )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 5.3000 68,500.00 363,050.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Tukang kayu 1.2.7.19 oh 1.3000 89,500.00 116,350.00
Tukang besi 1.2.7.17 oh 1.0500 84,000.00 88,200.00
Kepala Tukang 1.2.7.3 oh 0.2650 93,500.00 24,777.50
Mandor 1.2.7.5 oh 0.2650 94,500.00 25,042.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.3200 3,465,000.00 1,108,800.00
Paku biasa 2.2.12.1 kg 3.2000 16,200.00 51,840.00
Minyak bekisting 2.2.6.27 ltr 1.6000 5,800.00 9,280.00
Besi Beton / tulangan beton 2.2.4.9 kg 157.5000 10,500.00 1,653,750.00
Kawat Beton / bendraat 2.2.4.30 kg 2.2500 17,600.00 39,600.00
PC / Portland cement 2.2.1.52 kg 336.0000 1,400.00 470,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5400 264,000.00 142,560.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.8100 300,000.00 243,000.00
Kayu bekisting 2.2.2.15 m3 0.1200 3,465,000.00 415,800.00
Multiplek 9 mm, uk. 1,20 x 2,40 m 2.2.3.202 lbr 2.8000 140,800.00 394,240.00
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 bh 32.0000 12,100.00 387,200.00
639,145.00 4,916,470.00 - 5,555,615.00
Overhead dan profit 0.1400 89,480.30 688,305.80 - 777,786.10
728,625.30 5,604,775.80 - 6,333,401.10

A.4.1.1.33 1 m3 Membuat dinding beton bertulang (150 kg besi + bekisting )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 5.3000 68,500.00 363,050.00
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Tukang kayu 1.2.7.19 oh 1.3000 89,500.00 116,350.00
Tukang besi 1.2.7.17 oh 1.0500 84,000.00 88,200.00
Kepala Tukang 1.2.7.3 oh 0.2620 93,500.00 24,497.00
Mandor 1.2.7.5 oh 0.2650 94,500.00 25,042.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.2400 3,465,000.00 831,600.00
Paku biasa 2.2.12.1 kg 3.2000 16,200.00 51,840.00
Minyak bekisting 2.2.6.27 ltr 1.6000 5,800.00 9,280.00
Besi Beton / tulangan beton 2.2.4.9 kg 157.5000 10,500.00 1,653,750.00
Kawat Beton / bendraat 2.2.4.30 kg 2.2500 17,600.00 39,600.00
PC / Portland cement 2.2.1.52 kg 336.0000 1,400.00 470,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5400 264,000.00 142,560.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.8100 300,000.00 243,000.00
Kayu bekisting 2.2.2.15 m3 0.1600 3,465,000.00 554,400.00
Multiplek 9 mm, uk. 1,20 x 2,40 m 2.2.3.202 lbr 2.8000 140,800.00 394,240.00
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 bh 24.0000 12,100.00 290,400.00
638,864.50 4,681,070.00 - 5,319,934.50
Overhead dan profit 0.1400 89,441.03 655,349.80 - 744,790.83
728,305.53 5,336,419.80 - 6,064,725.33

A.4.1.1.34 1 m3 Membuat dinding beton bertulang (200 kg besi + bekisting )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 5.6500 68,500.00 387,025.00

15
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang batu 1.2.7.16 oh 0.2750 79,000.00 21,725.00
Tukang kayu 1.2.7.19 oh 1.5600 89,500.00 139,620.00
Tukang besi 1.2.7.17 oh 1.4000 84,000.00 117,600.00
Kepala Tukang 1.2.7.3 oh 0.3230 93,500.00 30,200.50
Mandor 1.2.7.5 oh 0.2830 94,500.00 26,743.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.2500 3,465,000.00 866,250.00
Paku biasa 2.2.12.1 kg 3.0000 16,200.00 48,600.00
Minyak bekisting 2.2.6.27 ltr 1.2000 5,800.00 6,960.00
Besi Beton / tulangan beton 2.2.4.9 kg 210.0000 10,500.00 2,205,000.00
Kawat Beton / bendraat 2.2.4.30 kg 3.0000 17,600.00 52,800.00
PC / Portland cement 2.2.1.52 kg 336.0000 1,400.00 470,400.00
Pasir pasang / beton 2.2.1.50 m3 0.5400 264,000.00 142,560.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.8100 300,000.00 243,000.00
Kayu bekisting 2.2.2.15 m3 0.1050 3,465,000.00 363,825.00
Multiplek 9 mm, uk. 1,20 x 2,40 m 2.2.3.202 lbr 2.5000 140,800.00 352,000.00
Bambu (Dia 6 - 8 cm x 600cm) 2.2.2.2 bh 14.0000 12,100.00 169,400.00
722,914.00 4,920,795.00 - 5,643,709.00
Overhead dan profit 0.1400 101,207.96 688,911.30 - 790,119.26
824,121.96 5,609,706.30 - 6,433,828.26

A.4.1.1.35 1 m' Membuat kolom praktis beton bertulang (11 x 11 ) cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1800 68,500.00 12,330.00
Tukang batu 1.2.7.16 oh 0.0200 79,000.00 1,580.00
Tukang kayu 1.2.7.19 oh 0.0200 89,500.00 1,790.00
Tukang besi 1.2.7.17 oh 0.0200 84,000.00 1,680.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0090 94,500.00 850.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.0020 3,465,000.00 6,930.00
Paku biasa 2.2.12.1 kg 0.0100 16,200.00 162.00
Minyak bekisting 2.2.6.27 ltr 1.2000 5,800.00 6,960.00
Besi Beton / tulangan beton 2.2.4.9 kg 3.0000 10,500.00 31,500.00
Kawat Beton / bendraat 2.2.4.30 kg 0.4500 17,600.00 7,920.00
PC / Portland cement 2.2.1.52 kg 4.0000 1,400.00 5,600.00
Pasir pasang / beton 2.2.1.50 m3 0.0060 264,000.00 1,584.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0090 300,000.00 2,700.00
18,791.50 63,356.00 - 82,147.50
Overhead dan profit 0.1400 2,630.81 8,869.84 - 11,500.65
21,422.31 72,225.84 - 93,648.15

A.4.1.1.36 1 m' Membuat ring balok beton bertulang (10 x 15 ) cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2970 68,500.00 20,344.50
Tukang batu 1.2.7.16 oh 0.0330 79,000.00 2,607.00
Tukang kayu 1.2.7.19 oh 0.0330 89,500.00 2,953.50
Tukang besi 1.2.7.17 oh 0.0330 84,000.00 2,772.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.0030 3,465,000.00 10,395.00
Paku biasa 2.2.12.1 kg 0.0200 16,200.00 324.00
Minyak bekisting 2.2.6.27 ltr 1.2000 5,800.00 6,960.00
Besi Beton / tulangan beton 2.2.4.9 kg 3.6000 10,500.00 37,800.00
Kawat Beton / bendraat 2.2.4.30 kg 0.0500 17,600.00 880.00
PC / Portland cement 2.2.1.52 kg 5.5000 1,400.00 7,700.00
Pasir pasang / beton 2.2.1.50 m3 0.0090 264,000.00 2,376.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0150 300,000.00 4,500.00
31,029.50 70,935.00 - 101,964.50
Overhead dan profit 0.1400 4,344.13 9,930.90 - 14,275.03
35,373.63 80,865.90 - 116,239.53

A.4.1.1.37 1 m3 Membongkar bekisting dan perawatan beton


BOW Tenaga :
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 4.0000 68,500.00 274,000.00
274,000.00 - - 274,000.00
Overhead dan profit 0.1400 38,360.00 - - 38,360.00
312,360.00 - - 312,360.00

A.4.1.2 PEKERJAAN BETON PRACETAK

A.4.1.2.1 1 m2 Pembuatan lahan produksi tebal 8 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1320 68,500.00 9,042.00
Tukang batu 1.2.7.16 oh 0.0220 79,000.00 1,738.00
Kepala Tukang 1.2.7.3 oh 0.0020 93,500.00 187.00
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
PC / Portland cement 2.2.1.52 kg 26.0800 1,400.00 36,512.00

16
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pasir pasang / beton 2.2.1.50 m3 0.0434 264,000.00 11,457.60
Batu pecah 2-3 cm 2.2.1.32 m3 0.0610 300,000.00 18,300.00
Air Bersih 2.2.6.1 ltr 17.2000 100.00 1,720.00
11,628.50 67,989.60 - 79,618.10
Overhead dan profit 0.1400 1,627.99 9,518.54 - 11,146.53
13,256.49 77,508.14 - 90,764.63

A.4.1.2.2 1 m2 Pembuatan lahan produksi tebal 10 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1650 68,500.00 11,302.50
Tukang batu 1.2.7.16 oh 0.0280 79,000.00 2,212.00
Kepala Tukang 1.2.7.3 oh 0.0030 93,500.00 280.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
PC / Portland cement 2.2.1.52 kg 32.6000 1,400.00 45,640.00
Pasir pasang / beton 2.2.1.50 m3 0.0543 264,000.00 14,335.20
Batu pecah 2-3 cm 2.2.1.32 m3 0.0762 300,000.00 22,860.00
Air Bersih 2.2.6.1 ltr 21.5000 100.00 2,150.00
14,551.00 84,985.20 - 99,536.20
Overhead dan profit 0.1400 2,037.14 11,897.93 - 13,935.07
16,588.14 96,883.13 - 113,471.27

A.4.1.2.3 1 m2 Pembuatan lahan produksi tebal 12 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1980 68,500.00 13,563.00
Tukang batu 1.2.7.16 oh 0.0330 79,000.00 2,607.00
Kepala Tukang 1.2.7.3 oh 0.0030 93,500.00 280.50
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
PC / Portland cement 2.2.1.52 kg 32.1200 1,400.00 44,968.00
Pasir pasang / beton 2.2.1.50 m3 0.0651 264,000.00 17,186.40
Batu pecah 2-3 cm 2.2.1.32 m3 0.0915 300,000.00 27,450.00
Air Bersih 2.2.6.1 ltr 25.8000 100.00 2,580.00
17,395.50 92,184.40 - 109,579.90
Overhead dan profit 0.1400 2,435.37 12,905.82 - 15,341.19
19,830.87 105,090.22 - 124,921.09

A.4.1.2.4 1 m2 Pembuatan lahan produksi tebal 15 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2480 68,500.00 16,988.00
Tukang batu 1.2.7.16 oh 0.0410 79,000.00 3,239.00
Kepala Tukang 1.2.7.3 oh 0.0040 93,500.00 374.00
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
PC / Portland cement 2.2.1.52 kg 48.9000 1,400.00 68,460.00
Pasir pasang / beton 2.2.1.50 m3 0.0814 264,000.00 21,489.60
Batu pecah 2-3 cm 2.2.1.32 m3 0.1143 300,000.00 34,290.00
Air Bersih 2.2.6.1 ltr 32.2500 100.00 3,225.00
21,829.50 127,464.60 - 149,294.10
Overhead dan profit 0.1400 3,056.13 17,845.04 - 20,901.17
24,885.63 145,309.64 - 170,195.27

A.4.1.2.5 1 m2 Pembuatan bekisting untuk plat pracetak ( 5 kali pakai )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0070 68,500.00 479.50
Tukang batu 1.2.7.16 oh 0.0760 79,000.00 6,004.00
Kepala Tukang 1.2.7.3 oh 0.0080 93,500.00 748.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan
Lantai kerja tebal 10 cm m3 0.0800 844,155.60 67,532.45
Pipa Besi  4/4 Tebal= 1.4 mm 2.2.4.73 kg 9.3940 17,400.00 163,455.60
Kayu bekisting 2.2.2.15 m3 0.0050 3,465,000.00 17,325.00
Tripleks 122 x 244 tbl = 12 mm 2.2.3.238 lbr 0.0800 179,100.00 14,328.00
minyak bekisting 2.2.6.27 l 0.2000 5,800.00 1,160.00
Paku Ramset / dinabolt 2.2.12.11 bh 3.8820 2,900.00 11,257.80
7,326.00 275,058.85 - 282,384.85
Overhead dan profit 0.1400 1,025.64 38,508.24 - 39,533.88
8,351.64 313,567.09 - 321,918.73

A.4.1.2.6 1 m2 Pembuatan bekisting untuk balok beton pracetak ( 10-12 kali pakai )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0040 68,500.00 274.00
Tukang batu 1.2.7.16 oh 0.0380 79,000.00 3,002.00
Kepala Tukang 1.2.7.3 oh 0.0040 93,500.00 374.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.0050 3,465,000.00 17,325.00
Tripleks 122 x 244 tbl = 12 mm 2.2.3.238 lbr 0.0430 179,100.00 7,701.30
minyak bekisting 2.2.6.27 l 0.2000 5,800.00 1,160.00
Paku Ramset / dinabolt 2.2.12.11 bh 0.6930 2,900.00 2,009.70

17
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
3,744.50 28,196.00 - 31,940.50
Overhead dan profit 0.1400 524.23 3,947.44 - 4,471.67
4,268.73 32,143.44 - 36,412.17

A.4.1.2.7 1 m2 Pembuatan bekisting untuk kolom beton pracetak ( 10-12 kali pakai )
Tenaga #N/A
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0040 68,500.00 274.00
Tukang batu 1.2.7.16 oh 0.0380 79,000.00 3,002.00
Kepala Tukang 1.2.7.3 oh 0.0040 93,500.00 374.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.0040 3,465,000.00 13,860.00
Tripleks 122 x 244 tbl = 12 mm 2.2.3.238 lbr 0.0480 179,100.00 8,596.80
minyak bekisting 2.2.6.27 l 0.2000 5,800.00 1,160.00
Paku biasa 2.2.12.1 kg 0.0460 16,200.00 745.20
Paku Ramset / dinabolt 2.2.12.11 bh 0.6930 2,900.00 2,009.70
3,744.50 26,371.70 - 30,116.20
Overhead dan profit 0.1400 524.23 3,692.04 - 4,216.27
4,268.73 30,063.74 - 34,332.47

A.4.1.2.8 1 bh Pemasangan dan membuka bekisting komponen plat beton pracetak


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0530 68,500.00 3,630.50
Tukang kayu 1.2.7.19 oh 0.0180 89,500.00 1,611.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
5,241.50 - - 5,241.50
Overhead dan profit 0.1400 733.81 - - 733.81
5,975.31 - - 5,975.31

A.4.1.2.9 1 bh Pemasangan dan membuka bekisting komponen balok beton pracetak


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0890 68,500.00 6,096.50
Tukang kayu 1.2.7.19 oh 0.0300 89,500.00 2,685.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
9,254.00 - - 9,254.00
Overhead dan profit 0.1400 1,295.56 - - 1,295.56
10,549.56 - - 10,549.56

A.4.1.2.10 1 bh Pemasangan dan membuka bekisting komponen kolom beton pracetak


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0710 68,500.00 4,863.50
Tukang kayu 1.2.7.19 oh 0.0240 89,500.00 2,148.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
7,484.00 - - 7,484.00
Overhead dan profit 0.1400 1,047.76 - - 1,047.76
8,531.76 - - 8,531.76

A.4.1.2.11 1 bh Penuangan/menebar beton untuk komponen plat beton pracetak


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0640 68,500.00 4,384.00
Tukang batu 1.2.7.16 oh 0.2440 79,000.00 19,276.00
Operator terlatih 1.2.7.9 oh 0.1280 94,500.00 12,096.00
Kepala Tukang 1.2.7.3 oh 0.0340 93,500.00 3,179.00
Mandor 1.2.7.5 oh 0.0730 94,500.00 6,898.50
45,833.50 - - 45,833.50
Overhead dan profit 0.1400 6,416.69 - - 6,416.69
52,250.19 - - 52,250.19

A.4.1.2.12 1 bh Penuangan/menebar beton untuk komponen balok beton pracetak


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0690 68,500.00 4,726.50
Tukang batu 1.2.7.16 oh 0.2420 79,000.00 19,118.00
Operator terlatih 1.2.7.9 oh 0.1380 94,500.00 13,041.00
Kepala Tukang 1.2.7.3 oh 0.0370 93,500.00 3,459.50
Mandor 1.2.7.5 oh 0.0730 94,500.00 6,898.50
47,243.50 - - 47,243.50
Overhead dan profit 0.1400 6,614.09 - - 6,614.09
53,857.59 - - 53,857.59

A.4.1.2.13 1 bh Penuangan/menebar beton untuk komponen balok beton pracetak


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0610 68,500.00 4,178.50
Tukang batu 1.2.7.16 oh 0.2130 79,000.00 16,827.00
Operator terlatih 1.2.7.9 oh 0.1220 94,500.00 11,529.00
Kepala Tukang 1.2.7.3 oh 0.0330 93,500.00 3,085.50
Mandor 1.2.7.5 oh 0.0730 94,500.00 6,898.50
42,518.50 - - 42,518.50
Overhead dan profit 0.1400 5,952.59 - - 5,952.59
48,471.09 - - 48,471.09

18
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
A.4.1.2.14 1 bh Mendirikan komponen plat pracetak
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0670 68,500.00 4,589.50
Tukang batu 1.2.7.16 oh 0.0670 79,000.00 5,293.00
Operator terlatih 1.2.7.9 oh 0.1340 94,500.00 12,663.00
Kepala Tukang 1.2.7.3 oh 0.0670 93,500.00 6,264.50
Mandor 1.2.7.5 oh 0.0670 94,500.00 6,331.50
Bahan
Solar 2.2.1.66 l 6.6760 6,200.00 41,391.20
Peralatan
Crane 10-15 ton HP 150 Kap.15 ton uh 0.0670 #N/A #N/A
Sewa pipe support uh 1.1000 #N/A #N/A
35,141.50 41,391.20 #N/A #N/A
Overhead dan profit 0.1400 4,919.81 5,794.77 #N/A #N/A
40,061.31 47,185.97 #N/A #N/A

A.4.1.2.15 1 bh Mendirikan komponen balok pracetak


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0610 68,500.00 4,178.50
Tukang batu 1.2.7.16 oh 0.0610 79,000.00 4,819.00
Operator terlatih 1.2.7.9 oh 0.1220 94,500.00 11,529.00
Operator terlatih 1.2.7.9 oh 0.0610 94,500.00 5,764.50
Pembantu operator 1.2.7.12 oh 0.0610 68,500.00 4,178.50
Kepala Tukang 1.2.7.3 oh 0.0610 93,500.00 5,703.50
Mandor 1.2.7.5 oh 0.0610 94,500.00 5,764.50
Bahan
Solar 2.2.1.66 l 6.1100 6,200.00 37,882.00
Peralatan
Crane 10-15 ton HP 150 Kap.15 ton uh 0.0610 #N/A #N/A
Sewa chaffolding uh 1.1000 #N/A #N/A
41,937.50 37,882.00 #N/A #N/A
Overhead dan profit 0.1400 5,871.25 5,303.48 #N/A #N/A
47,808.75 43,185.48 #N/A #N/A

A.4.1.2.16 1 bh Mendirikan komponen kolom pracetak


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0830 68,500.00 5,685.50
Tukang batu 1.2.7.16 oh 0.0830 79,000.00 6,557.00
Operator terlatih 1.2.7.9 oh 0.1660 94,500.00 15,687.00
Operator terlatih 1.2.7.9 oh 0.0830 94,500.00 7,843.50
Pembantu operator 1.2.7.12 oh 0.0830 68,500.00 5,685.50
Kepala Tukang 1.2.7.3 oh 0.0830 93,500.00 7,760.50
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
Solar 2.2.1.66 l 8.2770 6,200.00 51,317.40
Peralatan
Crane 10-15 ton HP 150 Kap.15 ton uh 0.0830 #N/A #N/A
Sewa pipe support uh 2.2000 #N/A #N/A
57,062.50 51,317.40 #N/A #N/A
Overhead dan profit 0.1400 7,988.75 7,184.44 #N/A #N/A
65,051.25 58,501.84 #N/A #N/A

A.4.1.2.17 1 bh Melangsir komponen plat pracetak (± 20 m )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0190 68,500.00 1,301.50
Kepala Tukang 1.2.7.3 oh 0.0380 93,500.00 3,553.00
Operator terlatih 1.2.7.9 oh 0.0190 94,500.00 1,795.50
Pembantu operator 1.2.7.12 oh 0.0190 68,500.00 1,301.50
Bahan
Solar 2.2.1.66 l 1.8970 6,200.00 11,761.40
Peralatan
Crane 10-15 ton HP 150 Kap.15 ton uh 0.0190 #N/A #N/A
#N/A 7,951.50 11,761.40 #N/A #N/A
Overhead dan profit 0.1400 1,113.21 1,646.60 #N/A #N/A
9,064.71 13,408.00 #N/A #N/A

A.4.1.2.18 1 bh Melangsir komponen balok pracetak (± 20 m )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0190 68,500.00 1,301.50
Kepala Tukang 1.2.7.3 oh 0.0380 93,500.00 3,553.00
Operator terlatih 1.2.7.9 oh 0.0190 94,500.00 1,795.50
Pembantu operator 1.2.7.12 oh 0.0190 68,500.00 1,301.50
Bahan
Solar 2.2.1.66 l 1.8970 6,200.00 11,761.40
Peralatan
Crane 10-15 ton HP 150 Kap.15 ton uh 0.0190 #N/A #N/A
7,951.50 11,761.40 #N/A #N/A
Overhead dan profit 0.1400 1,113.21 1,646.60 #N/A #N/A
9,064.71 13,408.00 #N/A #N/A

19
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
A.4.1.2.19 1 bh Melangsir komponen kolompracetak (± 20 m )
Tenaga #N/A
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0190 68,500.00 1,301.50
Kepala Tukang 1.2.7.3 oh 0.0380 93,500.00 3,553.00
Operator terlatih 1.2.7.9 oh 0.0190 94,500.00 1,795.50
Pembantu operator 1.2.7.12 oh 0.0190 68,500.00 1,301.50
Bahan
Solar 2.2.1.66 l 1.8970 6,200.00 11,761.40
Peralatan
Crane 10-15 ton HP 150 Kap.15 ton uh 0.0190 #N/A #N/A
7,951.50 11,761.40 #N/A #N/A
Overhead dan profit 0.1400 1,113.21 1,646.60 #N/A #N/A
9,064.71 13,408.00 #N/A #N/A

A.4.1.2.20 1 m3 Bahan grouting campuran


Bahan
Semen grout kg 1,200.0000 #N/A #N/A
Screening kg 650.0000 #N/A #N/A
Air Bersih 2.2.6.1 l 350.0000 100.00 35,000.00
9,064.71 13,408.00 #N/A #N/A
Overhead dan profit 0.1400 1,269.06 1,877.12 #N/A #N/A
10,333.77 15,285.12 #N/A #N/A

A.4.1.2.21 1 m3 Bahan grouting tidak campuran


Bahan
Semen grout kg 1,850.0000 #N/A #N/A
Air Bersih 2.2.6.1 l 400.0000 100.00 40,000.00
10,333.77 15,285.12 #N/A #N/A
Overhead dan profit 0.1400 1,446.73 2,139.92 #N/A #N/A
11,780.50 17,425.04 #N/A #N/A

A.4.1.2.22 1 titik Upah melakukan grouting pada join pracetak


Tenaga
Tukang batu 1.2.7.16 oh 0.3670 79,000.00 28,993.00
Kepala Tukang 1.2.7.3 oh 0.0740 93,500.00 6,919.00
Mandor 1.2.7.5 oh 0.0370 94,500.00 3,496.50
39,408.50 - - 39,408.50
Overhead dan profit 0.1400 5,517.19 - - 5,517.19
44,925.69 - - 44,925.69
A.4.1.2.23 1 titik Pemasangan bekisting join pracetak
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 0.1470 68,500.00 10,069.50
Tukang kayu 1.2.7.19 oh 0.1470 89,500.00 13,156.50
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu bekisting 2.2.2.15 m3 0.0120 3,465,000.00 41,580.00
Kayu bekisting 2.2.2.15 m3 0.0040 3,465,000.00 13,860.00
Paku biasa 2.2.12.1 kg 0.2640 16,200.00 4,276.80
25,101.00 59,716.80 - 84,817.80
Overhead dan profit 0.1400 3,514.14 8,360.35 - 11,874.49
28,615.14 68,077.15 - 96,692.29

A.4.1.2.24 1 titik Upah join dengan sling


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 0.2200 68,500.00 15,070.00
Tukang kayu 1.2.7.19 oh 0.2200 89,500.00 19,690.00
Kepala Tukang 1.2.7.3 oh 0.2200 93,500.00 20,570.00
Mandor 1.2.7.5 oh 0.0110 94,500.00 1,039.50
56,369.50 - - 56,369.50
Overhead dan profit 0.1400 7,891.73 - - 7,891.73
64,261.23 - - 64,261.23

A.4.2.1 PEKERJAAN BESI DAN ALUMINIUM

A.4.2.1.1 1 kg Pemasangan besi profil


Tenaga
Tukang las 1.2.7.21 oh 0.0600 89,500.00 5,370.00
Tukang las 1.2.7.21 oh 0.0600 89,500.00 5,370.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Baja Profil 2.2.4.6 kg 1.1500 15,400.00 17,710.00
#N/A 11,584.50 17,710.00 - 29,294.50
Overhead dan profit 0.1400 1,621.83 2,479.40 - 4,101.23
13,206.33 20,189.40 - 33,395.73

A.4.2.1.2 1 kg Pemasangan rangka kuda-kuda baja IWF


Tenaga

20
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0600 68,500.00 4,110.00
Tukang las 1.2.7.21 oh 0.0600 89,500.00 5,370.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Baja Profil 2.2.4.6 kg 1.1500 15,400.00 17,710.00
10,324.50 17,710.00 - 28,034.50
Overhead dan profit 0.1400 1,445.43 2,479.40 - 3,924.83
11,769.93 20,189.40 - 31,959.33

A.4.2.1.3 100 kg Pengerjaan Pekerjaan perakitan


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang las 1.2.7.21 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0010 93,500.00 93.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Solar 2.2.1.66 liter 1.0000 6,200.00 6,200.00
Minyak pelumas 2.2.6.30 liter 0.1000 37,500.00 3,750.00
Peralatan
1. Sewa alat jam 0.8000 18,000.00 14,400.00
16,366.00 9,950.00 14,400.00 40,716.00
Overhead dan profit 0.1400 2,291.24 1,393.00 2,016.00 5,700.24
18,657.24 11,343.00 16,416.00 46,416.24

A.4.2.1.4 1 m2 Pembuatan besi plat baja tebal 2 mm rangkap, rangka baja siku
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0500 68,500.00 71,925.00
Tukang las 1.2.7.21 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0520 94,500.00 4,914.00
Bahan
Baja siku L 30.30.3 2.2.4.7 kg 15.0000 19,300.00 289,500.00
Besi plat 2.2.4.13 kg 32.8000 17,900.00 587,120.00
kawat las listrik biasa 2.2.4.34 kg 0.0500 75,000.00 3,750.00
180,631.50 880,370.00 - 1,061,001.50
Overhead dan profit 0.1400 25,288.41 123,251.80 - 148,540.21
205,919.91 1,003,621.80 - 1,209,541.71

A.4.2.1.5 10 cm Pengerjaan pengelasan dengan las listrik


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0400 68,500.00 2,740.00
Tukang las 1.2.7.21 oh 0.0200 89,500.00 1,790.00
Kepala Tukang 1.2.7.3 oh 0.0020 93,500.00 187.00
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan
kawat las listrik biasa 2.2.4.34 kg 0.4000 75,000.00 30,000.00
Solar 2.2.1.66 liter 0.3000 6,200.00 1,860.00
Minyak pelumas 2.2.6.30 liter 0.0400 37,500.00 1,500.00
Peralatan
Mesin Las jam 0.1700 20,000.00 3,400.00
4,906.00 33,360.00 3,400.00 41,666.00
Overhead dan profit 0.1400 686.84 4,670.40 476.00 5,833.24
5,592.84 38,030.40 3,876.00 47,499.24
A.4.2.1.6 1 m2 Pemasangan rangka jendela besi scuare tube ( 25 x 5 ) cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6500 68,500.00 44,525.00
Tukang las 1.2.7.21 oh 0.6500 89,500.00 58,175.00
Kepala Tukang 1.2.7.3 oh 0.0650 93,500.00 6,077.50
Mandor 1.2.7.5 oh 0.0320 94,500.00 3,024.00
Bahan
Besi Square tube 2.2.4.16 m 4.7600 6,400.00 30,464.00
Besi lis kaca (1 x 1) cm 2.2.4.11 m 4.5220 17,600.00 79,587.20
Las besi / baja 2.2.4.55 cm 20.0000 2,300.00 46,000.00
111,801.50 156,051.20 - 267,852.70
Overhead dan profit 0.1400 15,652.21 21,847.17 - 37,499.38
127,453.71 177,898.37 - 305,352.08

A.4.2.1.7 1 m2 Pemasangan pintu rolling door besi


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.2000 68,500.00 82,200.00
Tukang las 1.2.7.21 oh 1.2000 89,500.00 107,400.00
Kepala Tukang 1.2.7.3 oh 0.1200 93,500.00 11,220.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Pintu Roling Door besi 2.2.4.68 m2 1.0000 548,700.00 548,700.00
201,387.00 548,700.00 - 750,087.00
Overhead dan profit 0.1400 28,194.18 76,818.00 - 105,012.18
229,581.18 625,518.00 - 855,099.18

21
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
A.4.2.1.8 1 m2 Pemasangan pintu lipat ( Folding door ) bahan plastik/PVC
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4400 68,500.00 30,140.00
Tukang las 1.2.7.21 oh 0.4400 89,500.00 39,380.00
Kepala Tukang 1.2.7.3 oh 0.0440 93,500.00 4,114.00
Mandor 1.2.7.5 oh 0.0220 94,500.00 2,079.00
Bahan
Pintu besi lipat ( Bukan Harmonika) 2.2.4.56 m2 1.0000 447,000.00 447,000.00
75,713.00 447,000.00 - 522,713.00
Overhead dan profit 0.1400 10,599.82 62,580.00 - 73,179.82
86,312.82 509,580.00 - 595,892.82

A.4.2.1.9 1 m2 Pemasangan sunscreen aluminium


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0800 68,500.00 5,480.00
Tukang las 1.2.7.21 oh 0.8000 89,500.00 71,600.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Sun Screen Aluminium 2.2.4.107 m2 1.0000 630,100.00 630,100.00
84,938.00 630,100.00 - 715,038.00
Overhead dan profit 0.1400 11,891.32 88,214.00 - 100,105.32
96,829.32 718,314.00 - 815,143.32

A.4.2.1.10 1 m2 Pemasangan rolling door aluminium


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang las 1.2.7.21 oh 1.0000 89,500.00 89,500.00
Kepala Tukang 1.2.7.3 oh 0.1000 93,500.00 9,350.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Pintu Roling Door aluminium 2.2.4.67 m2 1.0000 378,800.00 378,800.00
172,075.00 378,800.00 - 550,875.00
Overhead dan profit 0.1400 24,090.50 53,032.00 - 77,122.50
196,165.50 431,832.00 - 627,997.50

A.4.2.1.11 1m Pemasangan kusen pintu aluminium


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0430 68,500.00 2,945.50
Tukang las 1.2.7.21 oh 0.0430 89,500.00 3,848.50
Kepala Tukang 1.2.7.3 oh 0.0043 93,500.00 402.05
Mandor 1.2.7.5 oh 0.0021 94,500.00 198.45
Bahan
Profil kusen aluminium 4" 2.2.4.100 m 1.1000 90,300.00 99,330.00
Skrup fixer 2.2.12.15 buah 2.0000 800.00 1,600.00
Sealant 2.2.9.30 Tube 0.0600 19,000.00 1,140.00
7,394.50 102,070.00 - 109,464.50
Overhead dan profit 0.1400 1,035.23 14,289.80 - 15,325.03
8,429.73 116,359.80 - 124,789.53

A.4.2.1.12 1 m2 Pemasangan pintu aluminium strip lebar 8 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0850 68,500.00 5,822.50
Tukang las 1.2.7.21 oh 0.0850 89,500.00 7,607.50
Kepala Tukang 1.2.7.3 oh 0.0085 93,500.00 794.75
Mandor 1.2.7.5 oh 0.0042 94,500.00 396.90
Bahan
Profil kusen aluminium 4" 2.2.4.100 m 4.4000 90,300.00 397,320.00
Aluminium strip ( l = 5 - 10 cm) 2.2.4.1 m 14.6000 16,500.00 240,900.00
14,621.65 638,220.00 - 652,841.65
Overhead dan profit 0.1400 2,047.03 89,350.80 - 91,397.83
16,668.68 727,570.80 - 744,239.48

A.4.2.1.13 1 m2 Pemasangan pintu kaca alumunium


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0850 68,500.00 5,822.50
Tukang las 1.2.7.21 oh 0.0850 89,500.00 7,607.50
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Profil kusen aluminium 4" 2.2.4.100 m 4.4000 90,300.00 397,320.00
Kaca Bening t= 5 mm 2.2.9.9 m 4.5000 106,300.00 478,350.00
Sealant 2.2.9.30 Tube 0.2700 19,000.00 5,130.00
14,744.00 880,800.00 - 895,544.00
Overhead dan profit 0.1400 2,064.16 123,312.00 - 125,376.16
16,808.16 1,004,112.00 - 1,020,920.16

A.4.2.1.14 1 m2 Pemasangan venetions blinds dan vertical blinds


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00

22
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang las 1.2.7.21 oh 0.3500 89,500.00 31,325.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Venetion Blinds And Vertical Blinds (Tirai) 2.2.13.28 m2 1.0000 109,500.00 109,500.00
60,273.50 109,500.00 - 169,773.50
Overhead dan profit 0.1400 8,438.29 15,330.00 - 23,768.29
68,711.79 124,830.00 - 193,541.79

A.4.2.1.15 1 m2 Pemasangan terali besi strip ( 2x3 ) mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6700 68,500.00 114,395.00
Tukang las 1.2.7.21 oh 1.6700 89,500.00 149,465.00
Kepala Tukang 1.2.7.3 oh 0.1670 93,500.00 15,614.50
Mandor 1.2.7.5 oh 0.0830 94,500.00 7,843.50
Bahan
Besi strip + Mur Baut 2.2.4.17 kg 6.1770 18,700.00 115,509.90
Las besi / baja 2.2.4.55 cm 27.0800 2,300.00 62,284.00
287,318.00 177,793.90 - 465,111.90
Overhead dan profit 0.1400 40,224.52 24,891.15 - 65,115.67
327,542.52 202,685.05 - 530,227.57

A.4.2.1.16 1 m2 Pemasangan kawat nyamuk


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang las 1.2.7.21 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kawat Nyamuk aluminium 2.2.4.35 m2 1.1000 25,300.00 27,830.00
Las besi / baja 2.2.4.55 cm 11.1100 2,300.00 25,553.00
Besi strip + Mur Baut 2.2.4.17 kg 1.7160 18,700.00 32,089.20
17,207.50 85,472.20 - 102,679.70
Overhead dan profit 0.1400 2,409.05 11,966.11 - 14,375.16
19,616.55 97,438.31 - 117,054.86

A.4.2.1.16a 1 m2 Pemasangan kawat harmonika


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang las 1.2.7.21 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kawat Harmonika 2.2.4.32 m2 1.1000 31,400.00 34,540.00
Las besi / baja 2.2.4.55 cm 11.1100 2,300.00 25,553.00
Besi strip + Mur Baut 2.2.4.17 kg 1.7160 18,700.00 32,089.20
17,207.50 92,182.20 - 109,389.70
Overhead dan profit 0.1400 2,409.05 12,905.51 - 15,314.56
19,616.55 105,087.71 - 124,704.26

A.4.2.1.16b 1 m2 Pemasangan kawat kassa


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang las 1.2.7.21 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kawat Nyamuk kasa plastik 2.2.4.36 m2 1.1000 18,700.00 20,570.00
Las besi / baja 2.2.4.55 cm 11.1100 2,300.00 25,553.00
Besi strip + Mur Baut 2.2.4.17 kg 1.7160 18,700.00 32,089.20
17,207.50 78,212.20 - 95,419.70
Overhead dan profit 0.1400 2,409.05 10,949.71 - 13,358.76
19,616.55 89,161.91 - 108,778.46

A.4.2.1.16c 1 m2 Pemasangan kawat burung


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang las 1.2.7.21 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kawat Ayakan Pasir (untuk pasang) 2.2.4.26 m2 1.1000 18,200.00 20,020.00
Las besi / baja 2.2.4.55 cm 11.1100 2,300.00 25,553.00
Besi strip + Mur Baut 2.2.4.17 kg 1.7160 18,700.00 32,089.20
17,207.50 77,662.20 - 94,869.70
Overhead dan profit 0.1400 2,409.05 10,872.71 - 13,281.76
19,616.55 88,534.91 - 108,151.46

A.4.2.1.17 1 m2 Pemasangan jendela nako dan tralis


Tenaga

23
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang las 1.2.7.21 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan
Naco (Kerangka dan Daun ) 2.2.9.29 m2 1.1000 264,600.00 291,060.00
Paku Sekrup 2.2.12.12 buah 10.0000 600.00 6,000.00
Besi strip + Mur Baut 2.2.4.17 m2 7.0000 18,700.00 130,900.00
33,564.50 427,960.00 - 461,524.50
Overhead dan profit 0.1400 4,699.03 59,914.40 - 64,613.43
38,263.53 487,874.40 - 526,137.93

A.4.2.1.18 1 m' Pemasangan talang datar/jurai seng bjls 28 lebar 90 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang las 1.2.7.21 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan
Seng Plat BJLS 30 lebar 0,90 m 2.2.3.229 m 1.0500 42,400.00 44,520.00
Paku biasa 2.2.12.1 kg 0.0150 16,200.00 243.00
Kayu Meranti Papan 2.2.2.33 m3 0.0190 6,050,000.00 114,950.00
33,564.50 159,713.00 - 193,277.50
Overhead dan profit 0.1400 4,699.03 22,359.82 - 27,058.85
38,263.53 182,072.82 - 220,336.35

A.4.2.1.19 1m Pemasangan talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang las 1.2.7.21 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Seng Plat BJLS 30 lebar 0,90 m 2.2.3.229 m 1.0500 42,400.00 44,520.00
Paku biasa 2.2.12.1 kg 0.0100 16,200.00 162.00
Besi strip + Mur Baut 2.2.4.17 kg 0.5000 18,700.00 9,350.00
40,686.00 54,032.00 - 94,718.00
Overhead dan profit 0.1400 5,696.04 7,564.48 - 13,260.52
46,382.04 61,596.48 - 107,978.52

A.4.2.1.20 1 m2 Pemasangan rangka besi hollow 1x40.40.2, modul 60x120 cm, dinding partisi
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang besi 1.2.7.17 oh 0.2500 84,000.00 21,000.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Pipa Besi  4/4 Tebal= 1.4 mm 2.2.4.73 m1 3.5000 17,400.00 60,900.00
Assesoris (perkuatan,las dll) ls 1.0000 17,400.00 17,400.00
41,691.00 78,300.00 - 119,991.00
Overhead dan profit 0.1400 5,836.74 10,962.00 - 16,798.74
47,527.74 89,262.00 - 136,789.74

A.4.2.1.21 1 m2 Pemasangan rangka besi hollow 1x40.40.2, modul 60x60 cm, plafon
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang besi 1.2.7.17 oh 0.3500 84,000.00 29,400.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Pipa Besi  4/4 Tebal= 1.4 mm 2.2.4.73 m1 4.0000 17,400.00 69,600.00
Assesoris (perkuatan,las dll) ls 1.0000 17,400.00 17,400.00
58,348.50 87,000.00 - 145,348.50
Overhead dan profit 0.1400 8,168.79 12,180.00 - 20,348.79
66,517.29 99,180.00 - 165,697.29

A.4.4.1 PEKERJAAN PASANGAN DINDING

A.4.4.1.1 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 2 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Batu Bata / Merah 2.2.1.14 m3 140.0000 900.00 126,000.00
PC / Portland cement 2.2.1.52 kg 43.5000 1,400.00 60,900.00
Pasir pasang / beton 2.2.1.50 m3 0.0800 264,000.00 21,120.00
61,605.00 208,020.00 - 269,625.00

24
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 8,624.70 29,122.80 - 37,747.50
70,229.70 237,142.80 - 307,372.50

A.4.4.1.2 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Batu Bata / Merah 2.2.1.14 m3 140.0000 900.00 126,000.00
PC / Portland cement 2.2.1.52 kg 32.9500 1,400.00 46,130.00
Pasir pasang / beton 2.2.1.50 m3 0.0910 264,000.00 24,024.00
61,605.00 196,154.00 - 257,759.00
Overhead dan profit 0.1400 8,624.70 27,461.56 - 36,086.26
70,229.70 223,615.56 - 293,845.26

A.4.4.1.3 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 4 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Batu Bata / Merah 2.2.1.14 m3 140.0000 900.00 126,000.00
PC / Portland cement 2.2.1.52 kg 26.5500 1,400.00 37,170.00
Pasir pasang / beton 2.2.1.50 m3 0.0930 264,000.00 24,552.00
61,605.00 187,722.00 - 249,327.00
Overhead dan profit 0.1400 8,624.70 26,281.08 - 34,905.78
70,229.70 214,003.08 - 284,232.78

A.4.4.1.4 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 5 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Batu Bata / Merah 2.2.1.14 m3 140.0000 900.00 126,000.00
PC / Portland cement 2.2.1.52 kg 22.2000 1,400.00 31,080.00
Pasir pasang / beton 2.2.1.50 m3 0.1020 264,000.00 26,928.00
61,605.00 184,008.00 - 245,613.00
Overhead dan profit 0.1400 8,624.70 25,761.12 - 34,385.82
70,229.70 209,769.12 - 279,998.82

A.4.4.1.5 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 6 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Batu Bata / Merah 2.2.1.14 m3 140.0000 900.00 126,000.00
PC / Portland cement 2.2.1.52 kg 18.5000 1,400.00 25,900.00
Pasir pasang / beton 2.2.1.50 m3 0.1220 264,000.00 32,208.00
61,605.00 184,108.00 - 245,713.00
Overhead dan profit 0.1400 8,624.70 25,775.12 - 34,399.82
70,229.70 209,883.12 - 280,112.82

A.4.4.1.6 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 3 kp : 10 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Batu Bata / Merah 2.2.1.14 m3 140.0000 900.00 126,000.00
PC / Portland cement 2.2.1.52 kg 10.8000 1,400.00 15,120.00
Kapur Batu 2.2.1.46 m3 0.0275 1,270,500.00 34,938.75
Pasir pasang / beton 2.2.1.50 m3 0.0925 264,000.00 24,420.00
61,605.00 200,478.75 - 262,083.75
Overhead dan profit 0.1400 8,624.70 28,067.03 - 36,691.73
70,229.70 228,545.78 - 298,775.48

A.4.4.1.7 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 2 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50

25
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Bahan
Batu Bata / Merah 2.2.1.14 m3 70.0000 900.00 63,000.00
PC / Portland cement 2.2.1.52 kg 18.9500 1,400.00 26,530.00
Pasir pasang / beton 2.2.1.50 m3 0.0380 264,000.00 10,032.00
30,802.50 99,562.00 - 130,364.50
Overhead dan profit 0.1400 4,312.35 13,938.68 - 18,251.03
35,114.85 113,500.68 - 148,615.53

A.4.4.1.8 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Batu Bata / Merah 2.2.1.14 m3 70.0000 900.00 63,000.00
PC / Portland cement 2.2.1.52 kg 14.3700 1,400.00 20,118.00
Pasir pasang / beton 2.2.1.50 m3 0.0400 264,000.00 10,560.00
30,802.50 93,678.00 - 124,480.50
Overhead dan profit 0.1400 4,312.35 13,114.92 - 17,427.27
35,114.85 106,792.92 - 141,907.77

A.4.4.1.9 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 4 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Batu Bata / Merah 2.2.1.14 m3 70.0000 900.00 63,000.00
PC / Portland cement 2.2.1.52 kg 11.5000 1,400.00 16,100.00
Pasir pasang / beton 2.2.1.50 m3 0.0430 264,000.00 11,352.00
30,802.50 90,452.00 - 121,254.50
Overhead dan profit 0.1400 4,312.35 12,663.28 - 16,975.63
35,114.85 103,115.28 - 138,230.13

A.4.4.1.10 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 5 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Batu Bata / Merah 2.2.1.14 m3 70.0000 900.00 63,000.00
PC / Portland cement 2.2.1.52 kg 9.6800 1,400.00 13,552.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
30,802.50 88,432.00 - 119,234.50
Overhead dan profit 0.1400 4,312.35 12,380.48 - 16,692.83
35,114.85 100,812.48 - 135,927.33

A.4.4.1.11 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 6 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Batu Bata / Merah 2.2.1.14 m3 70.0000 900.00 63,000.00
PC / Portland cement 2.2.1.52 kg 8.3200 1,400.00 11,648.00
Pasir pasang / beton 2.2.1.50 m3 0.0490 264,000.00 12,936.00
30,802.50 87,584.00 - 118,386.50
Overhead dan profit 0.1400 4,312.35 12,261.76 - 16,574.11
35,114.85 99,845.76 - 134,960.61

A.4.4.1.12 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 8 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Batu Bata / Merah 2.2.1.14 m3 70.0000 900.00 63,000.00
PC / Portland cement 2.2.1.52 kg 6.5000 1,400.00 9,100.00
Pasir pasang / beton 2.2.1.50 m3 0.0500 264,000.00 13,200.00
30,802.50 85,300.00 - 116,102.50
Overhead dan profit 0.1400 4,312.35 11,942.00 - 16,254.35
35,114.85 97,242.00 - 132,356.85

A.4.4.1.13 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 3 kp : 8 pp


Tenaga

26
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Batu Bata / Merah 2.2.1.14 m3 70.0000 900.00 63,000.00
PC / Portland cement 2.2.1.52 kg 4.5000 1,400.00 6,300.00
Kapur Batu 2.2.1.46 m3 0.0150 1,270,500.00 19,057.50
Pasir pasang / beton 2.2.1.50 m3 0.0500 264,000.00 13,200.00
30,802.50 101,557.50 - 132,360.00
Overhead dan profit 0.1400 4,312.35 14,218.05 - 18,530.40
35,114.85 115,775.55 - 150,890.40

A.4.4.1.14 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sm : 1 kp : 1 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Batu Bata / Merah 2.2.1.14 m3 70.0000 900.00 63,000.00
PC / Portland cement 2.2.1.52 kg 0.0180 1,400.00 25.20
Kapur Batu 2.2.1.46 m3 0.0180 1,270,500.00 22,869.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
30,802.50 90,646.20 - 121,448.70
Overhead dan profit 0.1400 4,312.35 12,690.47 - 17,002.82
35,114.85 103,336.67 - 138,451.52

A.4.4.1.15 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sm : 1 kp : 2 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Batu Bata / Merah 2.2.1.14 m3 70.0000 900.00 63,000.00
PC / Portland cement 2.2.1.52 kg 0.0140 1,400.00 19.60
Kapur Batu 2.2.1.46 m3 0.0140 1,270,500.00 17,787.00
Pasir pasang / beton 2.2.1.50 m3 0.0280 264,000.00 7,392.00
30,802.50 88,198.60 - 119,001.10
Overhead dan profit 0.1400 4,312.35 12,347.80 - 16,660.15
35,114.85 100,546.40 - 135,661.25

A.4.4.1.16 1 m3 Pemasangan dinding HB20 campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Hollow Block 20 2.2.10.30 m3 12.5000 79,100.00 988,750.00
PC / Portland cement 2.2.1.52 kg 30.3200 1,400.00 42,448.00
Pasir pasang / beton 2.2.1.50 m3 0.7280 264,000.00 192,192.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
38,928.50 1,228,626.00 - 1,267,554.50
Overhead dan profit 0.1400 5,449.99 172,007.64 - 177,457.63
44,378.49 1,400,633.64 - 1,445,012.13

A.4.4.1.16a 1 m3 Pemasangan dinding CB20 campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Concrete Block 20 2.2.10.21 m3 12.5000 57,200.00 715,000.00
PC / Portland cement 2.2.1.52 kg 30.3200 1,400.00 42,448.00
Pasir pasang / beton 2.2.1.50 m3 0.7280 264,000.00 192,192.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
38,928.50 954,876.00 - 993,804.50
Overhead dan profit 0.1400 5,449.99 133,682.64 - 139,132.63
44,378.49 1,088,558.64 - 1,132,937.13

A.4.4.1.17 1 m3 Pemasangan dinding HB20 campuran 1 sp : 4 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan

27
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Hollow Block 20 2.2.10.30 m3 12.5000 79,100.00 988,750.00
PC / Portland cement 2.2.1.52 kg 24.2600 1,400.00 33,964.00
Pasir pasang / beton 2.2.1.50 m3 0.7720 264,000.00 203,808.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
38,928.50 1,231,758.00 - 1,270,686.50
Overhead dan profit 0.1400 5,449.99 172,446.12 - 177,896.11
44,378.49 1,404,204.12 - 1,448,582.61

A.4.4.1.17a 1 m3 Pemasangan dinding CB20 campuran 1 sp : 4 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Concrete Block 20 2.2.10.21 m3 12.5000 57,200.00 715,000.00
PC / Portland cement 2.2.1.52 kg 24.2600 1,400.00 33,964.00
Pasir pasang / beton 2.2.1.50 m3 0.7720 264,000.00 203,808.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
38,928.50 958,008.00 - 996,936.50
Overhead dan profit 0.1400 5,449.99 134,121.12 - 139,571.11
44,378.49 1,092,129.12 - 1,136,507.61

A.4.4.1.18 1 m3 Pemasangan dinding HB15 campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3200 68,500.00 21,920.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Hollow Block 15 2.2.10.31 m3 12.5000 56,700.00 708,750.00
PC / Portland cement 2.2.1.52 kg 22.7400 1,400.00 31,836.00
Pasir pasang / beton 2.2.1.50 m3 0.5500 264,000.00 145,200.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
47,642.00 891,022.00 - 938,664.00
Overhead dan profit 0.1400 6,669.88 124,743.08 - 131,412.96
54,311.88 1,015,765.08 - 1,070,076.96

A.4.4.1.18a 1 m3 Pemasangan dinding CB15 campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3200 68,500.00 21,920.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Concrete Block 15 2.2.10.22 m3 12.5000 46,800.00 585,000.00
PC / Portland cement 2.2.1.52 kg 22.7400 1,400.00 31,836.00
Pasir pasang / beton 2.2.1.50 m3 0.5500 264,000.00 145,200.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
47,642.00 767,272.00 - 814,914.00
Overhead dan profit 0.1400 6,669.88 107,418.08 - 114,087.96
54,311.88 874,690.08 - 929,001.96

A.4.4.1.19 1 m3 Pemasangan dinding HB15 campuran 1 sp : 4 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3200 68,500.00 21,920.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Hollow Block 15 2.2.10.31 m3 12.5000 56,700.00 708,750.00
PC / Portland cement 2.2.1.52 kg 18.2000 1,400.00 25,480.00
Pasir pasang / beton 2.2.1.50 m3 0.5820 264,000.00 153,648.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
47,642.00 893,114.00 - 940,756.00
Overhead dan profit 0.1400 6,669.88 125,035.96 - 131,705.84
54,311.88 1,018,149.96 - 1,072,461.84

A.4.4.1.19a 1 m3 Pemasangan dinding CB15 campuran 1 sp : 4 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3200 68,500.00 21,920.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Concrete Block 15 2.2.10.22 m3 12.5000 46,800.00 585,000.00
PC / Portland cement 2.2.1.52 kg 18.2000 1,400.00 25,480.00
Pasir pasang / beton 2.2.1.50 m3 0.5820 264,000.00 153,648.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
47,642.00 769,364.00 - 817,006.00

28
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 6,669.88 107,710.96 - 114,380.84
54,311.88 877,074.96 - 931,386.84

A.4.4.1.20 1 m3 Pemasangan dinding HB10 campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Hollow Block 10 2.2.10.32 m3 12.5000 35,200.00 440,000.00
PC / Portland cement 2.2.1.52 kg 15.1600 1,400.00 21,224.00
Pasir pasang / beton 2.2.1.50 m3 0.3640 264,000.00 96,096.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
30,802.50 562,556.00 - 593,358.50
Overhead dan profit 0.1400 4,312.35 78,757.84 - 83,070.19
35,114.85 641,313.84 - 676,428.69

A.4.4.1.20a 1 m3 Pemasangan dinding CB10 campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Concrete Block 10 2.2.10.23 m3 12.5000 35,200.00 440,000.00
PC / Portland cement 2.2.1.52 kg 15.1600 1,400.00 21,224.00
Pasir pasang / beton 2.2.1.50 m3 0.3640 264,000.00 96,096.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
30,802.50 562,556.00 - 593,358.50
Overhead dan profit 0.1400 4,312.35 78,757.84 - 83,070.19
35,114.85 641,313.84 - 676,428.69

A.4.4.1.21 1 m3 Pemasangan dinding HB10 campuran 1 sp : 4 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Hollow Block 10 2.2.10.32 m3 12.5000 35,200.00 440,000.00
PC / Portland cement 2.2.1.52 kg 12.1300 1,400.00 16,982.00
Pasir pasang / beton 2.2.1.50 m3 0.3880 264,000.00 102,432.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
30,802.50 564,650.00 - 595,452.50
Overhead dan profit 0.1400 4,312.35 79,051.00 - 83,363.35
35,114.85 643,701.00 - 678,815.85

A.4.4.1.21a 1 m3 Pemasangan dinding CB10 campuran 1 sp : 4 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Concrete Block 10 2.2.10.23 m3 12.5000 35,200.00 440,000.00
PC / Portland cement 2.2.1.52 kg 12.1300 1,400.00 16,982.00
Pasir pasang / beton 2.2.1.50 m3 0.3880 264,000.00 102,432.00
Besi Beugel/Baut 2.2.4.10 kg 0.2800 18,700.00 5,236.00
30,802.50 564,650.00 - 595,452.50
Overhead dan profit 0.1400 4,312.35 79,051.00 - 83,363.35
35,114.85 643,701.00 - 678,815.85

A.4.4.1.22 1 m2 Pemasangan dinding terawang (rooster)12x11x24 campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Rooster Lokal Bata Merah Uk. 20 x 20 cm 2.2.5.288 m3 30.0000 19,700.00 591,000.00
PC / Portland cement 2.2.1.52 kg 11.0000 1,400.00 15,400.00
Pasir pasang / beton 2.2.1.50 m3 0.0350 264,000.00 9,240.00
30,802.50 615,640.00 - 646,442.50
Overhead dan profit 0.1400 4,312.35 86,189.60 - 90,501.95
35,114.85 701,829.60 - 736,944.45

A.4.4.1.23 1 m2 Pemasangan dinding terawang (rooster)12x11x24 campuran 1 sp : 4 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00

29
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Bata berongga expose 2.2.5.1 m3 30.0000 8,500.00 255,000.00
PC / Portland cement 2.2.1.52 kg 11.0000 1,400.00 15,400.00
Pasir pasang / beton 2.2.1.50 m3 0.0350 264,000.00 9,240.00
30,802.50 279,640.00 - 310,442.50
Overhead dan profit 0.1400 4,312.35 39,149.60 - 43,461.95
35,114.85 318,789.60 - 353,904.45

A.4.4.1.24 1 m2 Pemasangan dinding bata berongga ekspose 12x11x24 campuran 1 sp : 3 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Bata berongga expose 2.2.5.1 m3 70.0000 8,500.00 595,000.00
PC / Portland cement 2.2.1.52 kg 14.0000 1,400.00 19,600.00
Pasir pasang / beton 2.2.1.50 m3 0.0320 264,000.00 8,448.00
35,220.00 623,048.00 - 658,268.00
Overhead dan profit 0.1400 4,930.80 87,226.72 - 92,157.52
40,150.80 710,274.72 - 750,425.52

A.4.4.1.24a 1 m2 Pasangan bataco 1 Pc : 3 Psr


Tenaga
Tukang batu 1.2.7.16 Oh 1.0000 79,000.00 79,000.00
Kepala Tukang 1.2.7.3 Oh 0.1000 93,500.00 9,350.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 3.0000 68,500.00 205,500.00
Mandor 1.2.7.5 Oh 0.1250 94,500.00 11,812.50
Bahan
Batako (30x25x10)cm 2.2.5.4 Bj 130.0000 3,900.00 507,000.00
PC / Portland cement 2.2.1.52 Kg 157.5000 1,400.00 220,500.00
Pasir pasang / beton 2.2.1.50 M3 0.3800 264,000.00 100,320.00
305,662.50 827,820.00 - 1,133,482.50
/m2 0.1000 30,566.25 82,782.00 - 113,348.25
Overhead dan profit 0.1400 4,279.28 11,589.48 - 15,868.76
34,845.53 94,371.48 - 129,217.01

A.4.4.2 PEKERJAAN PLESTERAN

A.4.4.2.1 1 m2 Pemasangan plesteran 1 sp : 1 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
PC / Portland cement 2.2.1.52 kg 15.5040 1,400.00 21,705.60
Pasir pasang / beton 2.2.1.50 m3 0.0160 264,000.00 4,224.00
35,220.00 25,929.60 - 61,149.60
Overhead dan profit 0.1400 4,930.80 3,630.14 - 8,560.94
40,150.80 29,559.74 - 69,710.54

A.4.4.2.2 1 m2 Pemasangan plesteran 1 sp : 2 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
PC / Portland cement 2.2.1.52 kg 10.2240 1,400.00 14,313.60
Pasir pasang / beton 2.2.1.50 m3 0.0200 264,000.00 5,280.00
35,220.00 19,593.60 - 54,813.60
Overhead dan profit 0.1400 4,930.80 2,743.10 - 7,673.90
40,150.80 22,336.70 - 62,487.50

A.4.4.2.3 1 m2 Pemasangan plesteran 1 sp : 3 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
PC / Portland cement 2.2.1.52 kg 7.7760 1,400.00 10,886.40
Pasir pasang / beton 2.2.1.50 m3 0.0230 264,000.00 6,072.00
35,220.00 16,958.40 - 52,178.40
Overhead dan profit 0.1400 4,930.80 2,374.18 - 7,304.98
40,150.80 19,332.58 - 59,483.38

30
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.4.4.2.4 1 m2 Pemasangan plesteran 1 sp : 4 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
PC / Portland cement 2.2.1.52 kg 6.2400 1,400.00 8,736.00
Pasir pasang / beton 2.2.1.50 m3 0.0240 264,000.00 6,336.00
35,220.00 15,072.00 - 50,292.00
Overhead dan profit 0.1400 4,930.80 2,110.08 - 7,040.88
40,150.80 17,182.08 - 57,332.88

A.4.4.2.5 1 m2 Pemasangan plesteran 1 sp : 5 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
PC / Portland cement 2.2.1.52 kg 5.1840 1,400.00 7,257.60
Pasir pasang / beton 2.2.1.50 m3 0.0260 264,000.00 6,864.00
35,220.00 14,121.60 - 49,341.60
Overhead dan profit 0.1400 4,930.80 1,977.02 - 6,907.82
40,150.80 16,098.62 - 56,249.42

A.4.4.2.6 1 m2 Pemasangan plesteran 1 sp : 6 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
PC / Portland cement 2.2.1.52 kg 4.4160 1,400.00 6,182.40
Pasir pasang / beton 2.2.1.50 m3 0.0270 264,000.00 7,128.00
35,220.00 13,310.40 - 48,530.40
Overhead dan profit 0.1400 4,930.80 1,863.46 - 6,794.26
40,150.80 15,173.86 - 55,324.66

A.4.4.2.7 1 m2 Pemasangan plesteran 1 sp : 7 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
PC / Portland cement 2.2.1.52 kg 3.9360 1,400.00 5,510.40
Pasir pasang / beton 2.2.1.50 m3 0.0280 264,000.00 7,392.00
35,220.00 12,902.40 - 48,122.40
Overhead dan profit 0.1400 4,930.80 1,806.34 - 6,737.14
40,150.80 14,708.74 - 54,859.54

A.4.4.2.8 1 m2 Pemasangan plesteran 1 sp : 8 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
PC / Portland cement 2.2.1.52 kg 3.4560 1,400.00 4,838.40
Pasir pasang / beton 2.2.1.50 m3 0.0290 264,000.00 7,656.00
35,220.00 12,494.40 - 47,714.40
Overhead dan profit 0.1400 4,930.80 1,749.22 - 6,680.02
40,150.80 14,243.62 - 54,394.42

A.4.4.2.9 1 m2 Pemasangan plesteran 1 sp : 1/2 kp : 3 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3600 68,500.00 24,660.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
PC / Portland cement 2.2.1.52 kg 5.7600 1,400.00 8,064.00
Kapur Batu 2.2.1.46 m3 0.0030 1,270,500.00 3,811.50
Pasir pasang / beton 2.2.1.50 m3 0.0130 264,000.00 3,432.00
36,963.00 15,307.50 - 52,270.50
Overhead dan profit 0.1400 5,174.82 2,143.05 - 7,317.87
42,137.82 17,450.55 - 59,588.37

31
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
A.4.4.2.10 1 m2 Pemasangan plesteran 1 sp : 2 kp : 8 pp tebal 15 mm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3600 68,500.00 24,660.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
PC / Portland cement 2.2.1.52 kg 3.0000 1,400.00 4,200.00
Kapur Batu 2.2.1.46 m3 0.0050 1,270,500.00 6,352.50
Pasir pasang / beton 2.2.1.50 m3 0.0200 264,000.00 5,280.00
36,963.00 15,832.50 - 52,795.50
Overhead dan profit 0.1400 5,174.82 2,216.55 - 7,391.37
42,137.82 18,049.05 - 60,186.87

A.4.4.2.11 1 m2 Pemasangan plesteran 1 sm : 1 kp : 1 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3600 68,500.00 24,660.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Semen Merah 2.2.1.53 m3 0.0090 150,200.00 1,351.80
Kapur Batu 2.2.1.46 m3 0.0090 1,270,500.00 11,434.50
Pasir pasang / beton 2.2.1.50 m3 0.0090 264,000.00 2,376.00
36,963.00 15,162.30 - 52,125.30
Overhead dan profit 0.1400 5,174.82 2,122.72 - 7,297.54
42,137.82 17,285.02 - 59,422.84

A.4.4.2.12 1 m2 Pemasangan plesteran 1 sm : 1 kp : 2 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3600 68,500.00 24,660.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Semen Merah 2.2.1.53 m3 0.0070 150,200.00 1,051.40
Kapur Batu 2.2.1.46 m3 0.0070 1,270,500.00 8,893.50
Pasir pasang / beton 2.2.1.50 m3 0.0150 264,000.00 3,960.00
36,963.00 13,904.90 - 50,867.90
Overhead dan profit 0.1400 5,174.82 1,946.69 - 7,121.51
42,137.82 15,851.59 - 57,989.41

A.4.4.2.13 1 m2 Pemasangan plesteran 1 sp : 1 pp tebal 20 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0220 94,500.00 2,079.00
Bahan
PC / Portland cement 2.2.1.52 kg 13.6320 1,400.00 19,084.80
Pasir pasang / beton 2.2.1.50 m3 0.0270 264,000.00 7,128.00
47,149.00 26,212.80 - 73,361.80
Overhead dan profit 0.1400 6,600.86 3,669.79 - 10,270.65
53,749.86 29,882.59 - 83,632.45

A.4.4.2.14 1 m2 Pemasangan plesteran 1 sp : 3 pp tebal 20 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2600 68,500.00 17,810.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
PC / Portland cement 2.2.1.52 kg 10.3680 1,400.00 14,515.20
Pasir pasang / beton 2.2.1.50 m3 0.0310 264,000.00 8,184.00
36,708.50 22,699.20 - 59,407.70
Overhead dan profit 0.1400 5,139.19 3,177.89 - 8,317.08
41,847.69 25,877.09 - 67,724.78

A.4.4.2.15 1 m2 Pemasangan plesteran 1 sp : 4 pp tebal 20 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0220 94,500.00 2,079.00
Bahan
PC / Portland cement 2.2.1.52 kg 8.3200 1,400.00 11,648.00
Pasir pasang / beton 2.2.1.50 m3 0.0320 264,000.00 8,448.00
47,149.00 20,096.00 - 67,245.00
Overhead dan profit 0.1400 6,600.86 2,813.44 - 9,414.30
53,749.86 22,909.44 - 76,659.30

32
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.4.4.2.16 1 m2 Pemasangan plesteran 1 sp : 5 pp tebal 20 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0220 94,500.00 2,079.00
Bahan
PC / Portland cement 2.2.1.52 kg 6.9120 1,400.00 9,676.80
Pasir pasang / beton 2.2.1.50 m3 0.0350 264,000.00 9,240.00
47,149.00 18,916.80 - 66,065.80
Overhead dan profit 0.1400 6,600.86 2,648.35 - 9,249.21
53,749.86 21,565.15 - 75,315.01

A.4.4.2.17 1 m2 Pemasangan plesteran 1 sp : 6 pp tebal 20 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0220 94,500.00 2,079.00
Bahan
PC / Portland cement 2.2.1.52 kg 5.8880 1,400.00 8,243.20
Pasir pasang / beton 2.2.1.50 m3 0.0360 264,000.00 9,504.00
47,149.00 17,747.20 - 64,896.20
Overhead dan profit 0.1400 6,600.86 2,484.61 - 9,085.47
53,749.86 20,231.81 - 73,981.67

A.4.4.2.18 1 m2 Pemasangan plesteran 1 sp : 1 kp : 2 pp tebal 20 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4400 68,500.00 30,140.00
Tukang batu 1.2.7.16 oh 0.2200 79,000.00 17,380.00
Kepala Tukang 1.2.7.3 oh 0.0220 93,500.00 2,057.00
Mandor 1.2.7.5 oh 0.0220 94,500.00 2,079.00
Bahan
Semen Merah 2.2.1.53 m3 0.0090 150,200.00 1,351.80
Kapur Batu 2.2.1.46 m3 0.0090 1,270,500.00 11,434.50
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
51,656.00 17,538.30 - 69,194.30
Overhead dan profit 0.1400 7,231.84 2,455.36 - 9,687.20
58,887.84 19,993.66 - 78,881.50

A.4.4.2.19 1 m2 Pemasangan berapen 1 sp : 5 pp tebal 15 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang batu 1.2.7.16 oh 0.0750 79,000.00 5,925.00
Kepala Tukang 1.2.7.3 oh 0.0080 93,500.00 748.00
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
PC / Portland cement 2.2.1.52 kg 5.1840 1,400.00 7,257.60
Pasir pasang / beton 2.2.1.50 m3 0.0260 264,000.00 6,864.00
17,704.00 14,121.60 - 31,825.60
Overhead dan profit 0.1400 2,478.56 1,977.02 - 4,455.58
20,182.56 16,098.62 - 36,281.18

A.4.4.2.20 1 m2 Pemasangan plesteran sconing 1 sp : 3 pp lebar 10 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0800 68,500.00 5,480.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
PC / Portland cement 2.2.1.52 kg 0.5000 1,400.00 700.00
Pasir pasang / beton 2.2.1.50 m3 0.0130 264,000.00 3,432.00
41,198.00 4,132.00 - 45,330.00
Overhead dan profit 0.1400 5,767.72 578.48 - 6,346.20
46,965.72 4,710.48 - 51,676.20

A.4.4.2.21 1 m2 Pemasangan plesteran granit 1 sp : 2 granit tebal 1 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4500 68,500.00 30,825.00
Tukang batu 1.2.7.16 oh 0.2250 79,000.00 17,775.00
Kepala Tukang 1.2.7.3 oh 0.0230 93,500.00 2,150.50
Mandor 1.2.7.5 oh 0.0230 94,500.00 2,173.50
Bahan
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Batu granit 2.2.5.5 kg 15.0000 4,200.00 63,000.00
52,924.00 77,000.00 - 129,924.00
Overhead dan profit 0.1400 7,409.36 10,780.00 - 18,189.36
60,333.36 87,780.00 - 148,113.36

33
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
A.4.4.2.22 1 m2 Pemasangan plesteran traso 1 sp : 2 traso tebal 1 cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4500 68,500.00 30,825.00
Tukang batu 1.2.7.16 oh 0.2250 79,000.00 17,775.00
Kepala Tukang 1.2.7.3 oh 0.0230 93,500.00 2,150.50
Mandor 1.2.7.5 oh 0.0230 94,500.00 2,173.50
Bahan
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Batu teraso 2.2.5.6 kg 15.0000 2,300.00 34,500.00
52,924.00 48,500.00 - 101,424.00
Overhead dan profit 0.1400 7,409.36 6,790.00 - 14,199.36
60,333.36 55,290.00 - 115,623.36

A.4.4.2.23 1 m2 Pemasangan plesteran ciprat 1 sp : 2 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
PC / Portland cement 2.2.1.52 kg 4.3200 1,400.00 6,048.00
Pasir pasang / beton 2.2.1.50 kg 0.0060 264,000.00 1,584.00
30,802.50 7,632.00 - 38,434.50
Overhead dan profit 0.1400 4,312.35 1,068.48 - 5,380.83
35,114.85 8,700.48 - 43,815.33

A.4.4.2.24 1 m2 Pemasangan finishing siar bata merah


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang batu 1.2.7.16 oh 0.0750 79,000.00 5,925.00
Kepala Tukang 1.2.7.3 oh 0.0080 93,500.00 748.00
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
PC / Portland cement 2.2.1.52 kg 3.1080 1,400.00 4,351.20
17,704.00 4,351.20 - 22,055.20
Overhead dan profit 0.1400 2,478.56 609.17 - 3,087.73
20,182.56 4,960.37 - 25,142.93

A.4.4.2.25 1 m2 Pemasangan finishing siar pasangan conblock ekspose


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0700 68,500.00 4,795.00
Tukang batu 1.2.7.16 oh 0.0350 79,000.00 2,765.00
Kepala Tukang 1.2.7.3 oh 0.0040 93,500.00 374.00
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
PC / Portland cement 2.2.1.52 kg 1.6000 1,400.00 2,240.00
8,312.00 2,240.00 - 10,552.00
Overhead dan profit 0.1400 1,163.68 313.60 - 1,477.28
9,475.68 2,553.60 - 12,029.28

A.4.4.2.26 1 m2 Pemasangan finishing siar pasangan batu kali, campuran 1 sp : 2 pp


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
PC / Portland cement 2.2.1.52 kg 6.3400 1,400.00 8,876.00
Pasir pasang / beton 2.2.1.50 m3 0.0120 264,000.00 3,168.00
35,220.00 12,044.00 - 47,264.00
Overhead dan profit 0.1400 4,930.80 1,686.16 - 6,616.96
40,150.80 13,730.16 - 53,880.96

A.4.4.2.27 1 m2 Pemasangan acian


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
PC / Portland cement 2.2.1.52 kg 3.2500 1,400.00 4,550.00
23,480.00 4,550.00 - 28,030.00
Overhead dan profit 0.1400 3,287.20 637.00 - 3,924.20
26,767.20 5,187.00 - 31,954.20

A.4.4.2.28 1 m' Benangan / Tali Air / Sudut Kol Kolan


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang batu 1.2.7.16 oh 0.0500 79,000.00 3,950.00
Bahan

34
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
PC / Portland cement 2.2.1.52 kg 3.7500 1,400.00 5,250.00
Pasir pasang / beton 2.2.1.50 m3 0.0300 264,000.00 7,920.00
4,977.50 13,170.00 - 18,147.50
Overhead dan profit 0.1400 696.85 1,843.80 - 2,540.65
5,674.35 15,013.80 - 20,688.15

A.4.4.3 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.1 1 m2 Pemasangan lantai ubin PC abu - abu ukuran 40 x 40 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang batu 1.2.7.16 oh 0.1250 79,000.00 9,875.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin Abu-abu m2 1.0608 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 9.8000 1,400.00 13,720.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
29,444.00 #N/A - #N/A
Overhead dan profit 0.1400 4,122.16 #N/A - #N/A
33,566.16 #N/A - #N/A

A.4.4.3.2 1 m2 Pemasangan lantai ubin PC abu - abu ukuran 30 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang batu 1.2.7.16 oh 0.1250 79,000.00 9,875.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin abu - abu m2 1.0683 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
29,444.00 #N/A - #N/A
Overhead dan profit 0.1400 4,122.16 #N/A - #N/A
33,566.16 #N/A - #N/A

A.4.4.3.3 1 m2 Pemasangan lantai ubin PC abu - abu ukuran 20 x 20 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2700 68,500.00 18,495.00
Tukang batu 1.2.7.16 oh 0.1350 79,000.00 10,665.00
Kepala Tukang 1.2.7.3 oh 0.0140 93,500.00 1,309.00
Mandor 1.2.7.5 oh 0.0140 94,500.00 1,323.00
Bahan
Ubin Abu-abu Uk. 20Cm x 20Cm 2.2.5.289 m2 1.0600 30,600.00 32,436.00
PC / Portland cement 2.2.1.52 kg 10.4000 1,400.00 14,560.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
31,792.00 58,876.00 - 90,668.00
Overhead dan profit 0.1400 4,450.88 8,242.64 - 12,693.52
36,242.88 67,118.64 - 103,361.52

A.4.4.3.4 1 m2 Pemasangan lantai ubin warna ukuran 40 x 40 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang batu 1.2.7.16 oh 0.1250 79,000.00 9,875.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin warna m2 1.0608 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 9.8000 1,400.00 13,720.00
Semen Putih / warna 2.2.1.54 kg 1.3000 3,000.00 3,900.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
29,444.00 #N/A - #N/A
Overhead dan profit 0.1400 4,122.16 #N/A - #N/A
33,566.16 #N/A - #N/A

A.4.4.3.5 1 m2 Pemasangan lantai ubin warna ukuran 30 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2600 68,500.00 17,810.00
Tukang batu 1.2.7.16 oh 0.1300 79,000.00 10,270.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin warna m2 1.0683 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
30,524.00 #N/A - #N/A
Overhead dan profit 0.1400 4,273.36 #N/A - #N/A
34,797.36 #N/A - #N/A

35
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.4.4.3.6 1 m2 Pemasangan lantai ubin warna ukuran 20 x 20 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2700 68,500.00 18,495.00
Tukang batu 1.2.7.16 oh 0.1350 79,000.00 10,665.00
Kepala Tukang 1.2.7.3 oh 0.0140 93,500.00 1,309.00
Mandor 1.2.7.5 oh 0.0140 94,500.00 1,323.00
Bahan
Ubin warna m2 1.0600 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 10.4000 1,400.00 14,560.00
Semen Putih / warna 2.2.1.54 kg 1.6200 3,000.00 4,860.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
31,792.00 #N/A - #N/A
Overhead dan profit 0.1400 4,450.88 #N/A - #N/A
36,242.88 #N/A - #N/A

A.4.4.3.7 1 m2 Pemasangan lantai ubin teraso ukuran 40 x 40 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang batu 1.2.7.16 oh 0.1250 79,000.00 9,875.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin teraso m2 1.0608 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 9.8000 1,400.00 13,720.00
Semen Putih / warna 2.2.1.54 kg 1.3000 3,000.00 3,900.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
29,444.00 #N/A - #N/A
Overhead dan profit 0.1400 4,122.16 #N/A - #N/A
33,566.16 #N/A - #N/A

A.4.4.3.8 1 m2 Pemasangan lantai ubin teraso ukuran 30 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2600 68,500.00 17,810.00
Tukang batu 1.2.7.16 oh 0.1300 79,000.00 10,270.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin Teraso Uk 30 Cm x 30 Cm 2.2.5.290 m2 1.0683 52,600.00 56,192.58
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
30,524.00 86,572.58 - 117,096.58
Overhead dan profit 0.1400 4,273.36 12,120.16 - 16,393.52
34,797.36 98,692.74 - 133,490.10

A.4.4.3.9 1 m2 Pemasangan lantai ubin Granit ukuran 40 x 40 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang batu 1.2.7.16 oh 0.1250 79,000.00 9,875.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Granit (ex Granito) tekstur Uk. 40x40 cm 2.2.5.9 m2 1.0608 161,700.00 171,531.36
PC / Portland cement 2.2.1.52 kg 9.8000 1,400.00 13,720.00
Semen Putih / warna 2.2.1.54 kg 1.3000 3,000.00 3,900.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
29,444.00 201,031.36 - 230,475.36
Overhead dan profit 0.1400 4,122.16 28,144.39 - 32,266.55
33,566.16 229,175.75 - 262,741.91

A.4.4.3.10 1 m2 Pemasangan lantai ubin Granit ukuran 30 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2600 68,500.00 17,810.00
Tukang batu 1.2.7.16 oh 0.1300 79,000.00 10,270.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin granit m2 1.0683 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
30,524.00 #N/A - #N/A
Overhead dan profit 0.1400 4,273.36 #N/A - #N/A
34,797.36 #N/A - #N/A

A.4.4.3.11 1 m2 Pemasangan lantai ubin teralux marmer ukuran 40 x 40 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang batu 1.2.7.16 oh 0.1250 79,000.00 9,875.00

36
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin teralux m2 1.0608 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 9.8000 1,400.00 13,720.00
Semen Putih / warna 2.2.1.54 kg 1.3000 3,000.00 3,900.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
29,444.00 #N/A - #N/A
Overhead dan profit 0.1400 4,122.16 #N/A - #N/A
33,566.16 #N/A - #N/A

A.4.4.3.12 1 m2 Pemasangan lantai ubin teralux marmer ukuran 30 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2600 68,500.00 17,810.00
Tukang batu 1.2.7.16 oh 0.1300 79,000.00 10,270.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin teralux m2 1.0683 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
30,524.00 #N/A - #N/A
Overhead dan profit 0.1400 4,273.36 #N/A - #N/A
34,797.36 #N/A - #N/A

A.4.4.3.13 1 m2 Pemasangan lantai ubin teralux marmer ukuran 60 x 60 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2400 68,500.00 16,440.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0120 94,500.00 1,134.00
Bahan
Ubin teralux marmer m2 1.1160 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 9.6000 1,400.00 13,440.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
28,176.00 #N/A - #N/A
Overhead dan profit 0.1400 3,944.64 #N/A - #N/A
32,120.64 #N/A - #N/A

A.4.4.3.14 1 m2 Pemasangan lantai ubin teralux marmer ukuran 40 x 40 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang batu 1.2.7.16 oh 0.1250 79,000.00 9,875.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin teralux marmer m2 1.0608 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 9.8000 1,400.00 13,720.00
Semen Putih / warna 2.2.1.54 kg 1.3000 3,000.00 3,900.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
29,444.00 #N/A - #N/A
Overhead dan profit 0.1400 4,122.16 #N/A - #N/A
33,566.16 #N/A - #N/A

A.4.4.3.15 1 m2 Pemasangan lantai ubin teralux marmer ukuran 30 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2600 68,500.00 17,810.00
Tukang batu 1.2.7.16 oh 0.1300 79,000.00 10,270.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Ubin teralux marmer m2 1.0683 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
30,524.00 #N/A - #N/A
Overhead dan profit 0.1400 4,273.36 #N/A - #N/A
34,797.36 #N/A - #N/A

A.4.4.3.16 1 m1 Pemasangan Plint ubin Pc abu - abu ukuran 15 x 20 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint ubin PC m2 0.2385 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.6500 1,400.00 2,310.00

37
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pasir pasang / beton 2.2.1.50 m3 0.0040 264,000.00 1,056.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A

A.4.4.3.17 1 m1 Pemasangan Plint ubin Pc abu - abu ukuran 10 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint ubin PC m' 1.0590 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.2400 1,400.00 1,736.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A
A.4.4.3.18 1 m1 Pemasangan Plint ubin Pc abu - abu ukuran 10 x 40 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint ubin PC m' 1.0600 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.2400 1,400.00 1,736.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A

A.4.4.3.19 1 m1 Pemasangan Plint ubin Warna ukuran 10 x 20 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint ubin warna m' 0.5300 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
#N/A 14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A
A.4.4.3.20 1 m1 Pemasangan Plint ubin Warna ukuran 10 x 30 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint ubin warna m' 1.0590 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A

A.4.4.3.21 1 m1 Pemasangan Plint ubin Warna ukuran 10 x 40 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint ubin warna m' 1.0600 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A

A.4.4.3.22 1 m1 Pemasangan Plint ubin traso ukuran 10 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00

38
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint ubin teraso m' 1.0590 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A
A.4.4.3.23 1 m1 Pemasangan Plint ubin teraso ukuran 10 x 40 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint ubin teraso m' 1.0600 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A

A.4.4.3.24 1 m1 Pemasangan Plint ubin granit ukuran 10 x 40 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint ubin granit m' 1.0600 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A
A.4.4.3.25 1 m1 Pemasangan Plint ubin granit ukuran 10 x 30 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint ubin granit m' 1.0590 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A

A.4.4.3.26 1 m1 Pemasangan Plint ubin teralux kerang ukuran 10 x 40 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint teralux kerang m' 1.0520 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A

A.4.4.3.27 1 m1 Pemasangan Plint ubin teralux kerang ukuran 10 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint teralux kerang m' 1.0590 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00

39
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A
A.4.4.3.28 1 m1 Pemasangan Plint ubin teralux marmer ukuran 10 x 60 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint teralux marmer m' 1.0200 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A

A.4.4.3.29 1 m1 Pemasangan Plint ubin teralux marmer ukuran 10 x 40 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint teralux marmer m' 1.0600 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A

A.4.4.3.30 1 m1 Pemasangan Plint ubin teralux marmer ukuran 10 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Plint teralux marmer m' 1.0590 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
14,589.00 #N/A - #N/A
Overhead dan profit 0.1400 2,042.46 #N/A - #N/A
16,631.46 #N/A - #N/A

A.4.4.3.31 1 m2 Pemasangan lantai teraso cor di tempat, tebal 3 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3600 68,500.00 24,660.00
Tukang batu 1.2.7.16 oh 0.1800 79,000.00 14,220.00
Kepala Tukang 1.2.7.3 oh 0.0180 93,500.00 1,683.00
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
teraso cor m3 0.0360 #N/A #N/A
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
42,264.00 #N/A - #N/A
Overhead dan profit 0.1400 #N/A 5,916.96 #N/A - #N/A
48,180.96 #N/A - #N/A
A.4.4.3.32 1 m2 Pemasangan lantai keramik artistik 10 x 20 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik Arstistik Uk. 10 x 20 cm 2.2.5.22 m2 1.0600 93,000.00 98,580.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 2.7500 3,000.00 8,250.00
82,180.00 130,176.00 - 212,356.00
Overhead dan profit 0.1400 11,505.20 18,224.64 - 29,729.84
93,685.20 148,400.64 - 242,085.84

A.4.4.3.33 1 m2 Pemasangan lantai keramik artistik 10 x 10 Cm / 5 Cm x 20 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50

40
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
ubin keramik m2 1.0600 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 3.2000 3,000.00 9,600.00
82,180.00 #N/A - #N/A
Overhead dan profit 0.1400 11,505.20 #N/A - #N/A
93,685.20 #N/A - #N/A

A.4.4.3.34 1 m2 Pemasangan lantai keramik 33 x 33 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
ubin keramik m2 1.0890 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.6200 3,000.00 4,860.00
82,180.00 #N/A - #N/A
Overhead dan profit 0.1400 11,505.20 #N/A - #N/A
93,685.20 #N/A - #N/A

A.4.4.3.35 1 m2 Pemasangan lantai keramik polos ukuran 30 x 30 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik putih Uk. 30 cm x 30 cm 2.2.5.243 m2 1.0683 47,400.00 50,637.42
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 81,017.42 - 163,197.42
Overhead dan profit 0.1400 11,505.20 11,342.44 - 22,847.64
93,685.20 92,359.86 - 186,045.06

A.4.4.3.35a 1 m2 Pemasangan lantai keramik motif ukuran 30 x 30 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik motif Uk. 30 cm x 30 cm 2.2.5.240 m2 1.0683 52,600.00 56,192.58
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 86,572.58 - 168,752.58
Overhead dan profit 0.1400 11,505.20 12,120.16 - 23,625.36
93,685.20 98,692.74 - 192,377.94

A.4.4.3.35b 1 m2 Pemasangan lantai keramik (eks Granito ) tekstur ukuran 40 x 40 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Granit (ex Granito) tekstur Uk. 40x40 cm 2.2.5.9 m2 1.0683 161,700.00 172,744.11
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 203,124.11 - 285,304.11
Overhead dan profit 0.1400 11,505.20 28,437.38 - 39,942.58
93,685.20 231,561.49 - 325,246.69

A.4.4.3.35c 1 m2 Pemasangan lantai keramik (eks Granito ) tekstur ukuran 60 x 60 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Granit (ex Granito) tekstur Uk. 60x60 cm 2.2.5.10 m2 1.0683 207,900.00 222,099.57
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00

41
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 252,479.57 - 334,659.57
Overhead dan profit 0.1400 11,505.20 35,347.14 - 46,852.34
93,685.20 287,826.71 - 381,511.91

A.4.4.3.35d 1 m2 Pemasangan lantai keramik (eks Granito ) warna gelap ukuran 40 x 40 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Granit (ex Granito) warna gelap Uk. 40x40 cm 2.2.5.13 m2 1.0683 225,300.00 240,687.99
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 271,067.99 - 353,247.99
Overhead dan profit 0.1400 11,505.20 37,949.52 - 49,454.72
93,685.20 309,017.51 - 402,702.71

A.4.4.3.35e 1 m2 Pemasangan lantai keramik (eks Granito ) warna gelap ukuran 60 x 60 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Granit (ex Granito) warna gelap Uk. 60x60 cm 2.2.5.14 m2 1.0683 323,400.00 345,488.22
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 375,868.22 - 458,048.22
Overhead dan profit 0.1400 11,505.20 52,621.55 - 64,126.75
93,685.20 428,489.77 - 522,174.97

A.4.4.3.35f 1 m2 Pemasangan lantai keramik (eks Granito ) warna terang ukuran 40 x 40 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Granit (ex Granito) warna terang Uk. 40x40 cm 2.2.5.15 m2 1.0683 146,700.00 156,719.61
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 187,099.61 - 269,279.61
Overhead dan profit 0.1400 11,505.20 26,193.95 - 37,699.15
93,685.20 213,293.56 - 306,978.76

A.4.4.3.35g 1 m2 Pemasangan lantai keramik (eks Granito ) warna terang ukuran 60 x 60 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Granit (ex Granito) warna terang Uk. 60x60 cm 2.2.5.16 m2 1.0683 85,000.00 90,805.50
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 121,185.50 - 203,365.50
Overhead dan profit 0.1400 11,505.20 16,965.97 - 28,471.17
93,685.20 138,151.47 - 231,836.67

A.4.4.3.35h 1 m2 Pemasangan lantai keramik cutting ukuran 30 x 50 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik cutting Uk. 30cm x 50 cm 2.2.5.23 m2 1.0683 79,100.00 84,502.53
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 114,882.53 - 197,062.53
Overhead dan profit 0.1400 11,505.20 16,083.55 - 27,588.75
93,685.20 130,966.08 - 224,651.28

42
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
A.4.4.3.35i 1 m2 Pemasangan lantai keramik cutting ukuran 31 x 63 cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik cutting Uk. 31cm x 63 cm 2.2.5.24 m2 1.0683 116,700.00 124,670.61
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 155,050.61 - 237,230.61
Overhead dan profit 0.1400 11,505.20 21,707.09 - 33,212.29
93,685.20 176,757.70 - 270,442.90

A.4.4.3.35j 1 m2 Pemasangan lantai keramik motif ukuran 40 x 40 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik motif Uk. 40 cm x 40 cm 2.2.5.241 m2 1.0608 57,200.00 60,677.76
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 91,057.76 - 173,237.76
Overhead dan profit 0.1400 11,505.20 12,748.09 - 24,253.29
93,685.20 103,805.85 - 197,491.05

A.4.4.3.35k 1 m2 Pemasangan lantai keramik polos ukuran 40 x 40 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik putih Uk. 40cm x 40 cm 2.2.5.244 m2 1.0608 54,300.00 57,601.44
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 87,981.44 - 170,161.44
Overhead dan profit 0.1400 11,505.20 12,317.40 - 23,822.60
93,685.20 100,298.84 - 193,984.04

A.4.4.3.35l 1 m2 Pemasangan lantai keramik tekstur cuttingukuran 31 x 63 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik tekstur cutting Uk. 31cm x 63 cm 2.2.5.250 m2 1.0683 123,600.00 132,041.88
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 162,421.88 - 244,601.88
Overhead dan profit 0.1400 11,505.20 22,739.06 - 34,244.26
93,685.20 185,160.94 - 278,846.14

A.4.4.3.35m 1 m2 Pemasangan lantai keramik tekstur ukuran 20 x 20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik tekstur Uk. 20cm x 20 cm 2.2.5.251 m2 1.0683 50,800.00 54,269.64
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 84,649.64 - 166,829.64
Overhead dan profit 0.1400 11,505.20 11,850.95 - 23,356.15
93,685.20 96,500.59 - 190,185.79

A.4.4.3.35n 1 m2 Pemasangan lantai keramik motif ukuran 30 x 30 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50

43
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik motif Uk. 30 cm x 30 cm 2.2.5.240 m2 1.0683 52,600.00 56,192.58
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 86,572.58 - 168,752.58
Overhead dan profit 0.1400 11,505.20 12,120.16 - 23,625.36
93,685.20 98,692.74 - 192,377.94

A.4.4.3.35o 1 m2 Pemasangan lantai keramik tekstur ukuran 30 x 30 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik tekstur Uk. 30cm x 30 cm 2.2.5.252 m2 1.0683 50,300.00 53,735.49
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 84,115.49 - 166,295.49
Overhead dan profit 0.1400 11,505.20 11,776.17 - 23,281.37
93,685.20 95,891.66 - 189,576.86

A.4.4.3.35p 1 m2 Pemasangan lantai keramik motif ukuran 50 x 50 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik motif Uk. 50 cm x 50 cm 2.2.5.242 m2 1.0683 63,600.00 67,943.88
PC / Portland cement 2.2.1.52 kg 10.0000 1,400.00 14,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
82,180.00 98,323.88 - 180,503.88
Overhead dan profit 0.1400 11,505.20 13,765.34 - 25,270.54
93,685.20 112,089.22 - 205,774.42

A.4.4.3.36 1 m2 Pemasangan lantai keramik ukuran 20 x 20 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Keramik Uk. 20Cm x 20Cm 2.2.5.253 m2 1.0600 50,800.00 53,848.00
PC / Portland cement 2.2.1.52 kg 10.4000 1,400.00 14,560.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 1.6200 3,000.00 4,860.00
82,180.00 85,148.00 - 167,328.00
Overhead dan profit 0.1400 11,505.20 11,920.72 - 23,425.92
93,685.20 97,068.72 - 190,753.92

A.4.4.3.37 1 m2 Pemasangan lantai keramik ukuran 20 x 33 Cm untuk variasi/ border


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0500 68,500.00 71,925.00
Tukang batu 1.2.7.16 oh 0.5250 79,000.00 41,475.00
Kepala Tukang 1.2.7.3 oh 0.0530 93,500.00 4,955.50
Mandor 1.2.7.5 oh 0.0530 94,500.00 5,008.50
Bahan
ubin keramik m2 2.1780 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 9.8000 1,400.00 13,720.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 4.3700 3,000.00 13,110.00
123,364.00 #N/A - #N/A
Overhead dan profit 0.1400 17,270.96 #N/A - #N/A
140,634.96 #N/A - #N/A

A.4.4.3.38 1 m2 Pemasangan lantai keramik mozaik ukuran 30 x 30 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
ubin keramik m2 1.0683 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 14.1500 1,400.00 19,810.00
Pasir pasang / beton 2.2.1.50 m3 0.0390 264,000.00 10,296.00

44
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Semen Putih / warna 2.2.1.54 kg 2.0000 3,000.00 6,000.00
82,180.00 #N/A - #N/A
Overhead dan profit 0.1400 11,505.20 #N/A - #N/A
93,685.20 #N/A - #N/A

A.4.4.3.39 1 m1 Pemasangan plint keramik artistik ukuran 10 x 20 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0530 93,500.00 4,955.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Keramik Arstistik Uk. 10 x 20 cm 2.2.5.22 m' 1.0600 93,000.00 98,580.00
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
Semen Putih / warna 2.2.1.54 kg 0.0250 3,000.00 75.00
18,703.00 101,043.00 - 119,746.00
Overhead dan profit 0.1400 2,618.42 14,146.02 - 16,764.44
21,321.42 115,189.02 - 136,510.44

A.4.4.3.40 1 m1 Pemasangan plint keramik ukuran 10 x 20 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
List Keramik (10x20)cm 2.2.5.260 m' 1.0600 17,400.00 18,444.00
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
Semen Putih / warna 2.2.1.54 kg 0.0500 3,000.00 150.00
17,020.00 20,982.00 - 38,002.00
Overhead dan profit 0.1400 2,382.80 2,937.48 - 5,320.28
19,402.80 23,919.48 - 43,322.28

A.4.4.3.41 1 m1 Pemasangan plint keramik ukuran 5 x 20 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0900 68,500.00 6,165.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
plint keramik m' 1.0600 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 0.5700 1,400.00 798.00
Pasir pasang / beton 2.2.1.50 m3 0.0015 264,000.00 396.00
Semen Putih / warna 2.2.1.54 kg 0.0130 3,000.00 39.00
17,020.00 #N/A - #N/A
Overhead dan profit 0.1400 2,382.80 #N/A - #N/A
19,402.80 #N/A - #N/A

A.4.4.3.42 1 m1 Pemasangan plint internal cove arsitek 5 cm x 5cm x 20 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7500 68,500.00 51,375.00
Tukang batu 1.2.7.16 oh 0.7500 79,000.00 59,250.00
Kepala Tukang 1.2.7.3 oh 0.0750 93,500.00 7,012.50
Mandor 1.2.7.5 oh 0.0380 94,500.00 3,591.00
Bahan
internal cove m' 1.0600 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 1.1400 1,400.00 1,596.00
Pasir pasang / beton 2.2.1.50 m3 0.0030 264,000.00 792.00
Semen Putih / warna 2.2.1.54 kg 0.1000 3,000.00 300.00
121,228.50 #N/A - #N/A
Overhead dan profit 0.1400 16,971.99 #N/A - #N/A
138,200.49 #N/A - #N/A

A.4.4.3.43 1 m2 Pemasangan lantai marmer bakar ukuran 100 x 100 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Marmer bakar 2.2.5.261 m2 1.0600 109,100.00 115,646.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 140,942.00 - 223,122.00
Overhead dan profit 0.1400 11,505.20 19,731.88 - 31,237.08
93,685.20 160,673.88 - 254,359.08

45
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
A.4.4.3.43a 1 m2 Pemasangan lantai marmer hitam ukuran 100 x 100 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Marmer Hitam 2.2.5.262 m2 1.0600 112,600.00 119,356.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 144,652.00 - 226,832.00
Overhead dan profit 0.1400 11,505.20 20,251.28 - 31,756.48
93,685.20 164,903.28 - 258,588.48

A.4.4.3.43b 1 m2 Pemasangan lantai marmer putih ukuran 100 x 100 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Marmer Putih 2.2.5.263 m2 1.0600 189,400.00 200,764.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 226,060.00 - 308,240.00
Overhead dan profit 0.1400 11,505.20 31,648.40 - 43,153.60
93,685.20 257,708.40 - 351,393.60

A.4.4.3.43c 1 m2 Pemasangan lantai batu andesit


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu andesit 2.2.1.5 m2 1.0600 163,700.00 173,522.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 198,818.00 - 280,998.00
Overhead dan profit 0.1400 11,505.20 27,834.52 - 39,339.72
93,685.20 226,652.52 - 320,337.72

A.4.4.3.43d 1 m2 Pemasangan lantai batu andesit hijau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu Andisit Hijau 2.2.1.11 m2 1.0600 196,400.00 208,184.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 233,480.00 - 315,660.00
Overhead dan profit 0.1400 11,505.20 32,687.20 - 44,192.40
93,685.20 266,167.20 - 359,852.40

A.4.4.3.43e 1 m2 Pemasangan lantai batu candi


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu candi 2.2.1.16 m2 1.0600 141,400.00 149,884.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 175,180.00 - 257,360.00
Overhead dan profit 0.1400 11,505.20 24,525.20 - 36,030.40
93,685.20 199,705.20 - 293,390.40

A.4.4.3.43f 1 m2 Pemasangan lantai batu candi hitam


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50

46
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu candi hitam 2.2.1.17 m2 1.0600 141,400.00 149,884.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 175,180.00 - 257,360.00
Overhead dan profit 0.1400 11,505.20 24,525.20 - 36,030.40
93,685.20 199,705.20 - 293,390.40

A.4.4.3.43g 1 m2 Pemasangan lantai batu granit black gold


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu granit black gold 2.2.1.18 m2 1.0600 2,310,000.00 2,448,600.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 2,473,896.00 - 2,556,076.00
Overhead dan profit 0.1400 11,505.20 346,345.44 - 357,850.64
93,685.20 2,820,241.44 - 2,913,926.64

A.4.4.3.43h 1 m2 Pemasangan lantai batu granit motif


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu granit motif 2.2.1.19 m2 1.0600 220,100.00 233,306.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 258,602.00 - 340,782.00
Overhead dan profit 0.1400 11,505.20 36,204.28 - 47,709.48
93,685.20 294,806.28 - 388,491.48

A.4.4.3.43i 1 m2 Pemasangan lantai batu lempeng


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu lempeng 2.2.1.24 m2 1.0600 111,000.00 117,660.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 142,956.00 - 225,136.00
Overhead dan profit 0.1400 11,505.20 20,013.84 - 31,519.04
93,685.20 162,969.84 - 256,655.04

A.4.4.3.43j 1 m2 Pemasangan lantai batu lempeng hijau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu lempeng hijau 2.2.1.25 m2 1.0600 109,800.00 116,388.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 141,684.00 - 223,864.00
Overhead dan profit 0.1400 11,505.20 19,835.76 - 31,340.96
93,685.20 161,519.76 - 255,204.96

A.4.4.3.43k 1 m2 Pemasangan lantai batu lempeng coklat


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu lempeng coklat 2.2.1.26 m2 1.0600 75,100.00 79,606.00
PC / Portland cement 2.2.1.52 kg 8.1900 1,400.00 11,466.00
Pasir pasang / beton 2.2.1.50 m3 0.0450 264,000.00 11,880.00

47
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Semen Putih / warna 2.2.1.54 kg 0.6500 3,000.00 1,950.00
82,180.00 104,902.00 - 187,082.00
Overhead dan profit 0.1400 11,505.20 14,686.28 - 26,191.48
93,685.20 119,588.28 - 213,273.48

A.4.4.3.44 1 m2 Lantai karpet


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1700 68,500.00 11,645.00
Tukang kayu 1.2.7.19 oh 0.1700 89,500.00 15,215.00
Kepala Tukang 1.2.7.3 oh 0.0170 93,500.00 1,589.50
Mandor 1.2.7.5 oh 0.0090 94,500.00 850.50
Bahan
karpet 2.2.5.21 m2 1.0500 27,300.00 28,665.00
Lem PVC 2.2.6.25 kg 0.3500 8,100.00 2,835.00
29,300.00 31,500.00 - 60,800.00
Overhead dan profit 0.1400 4,102.00 4,410.00 - 8,512.00
33,402.00 35,910.00 - 69,312.00

A.4.4.3.45 1 m2 underlayer ( pelapis bawah karpet )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
underlayer ( pelapis bawah karpet ) m2 1.0500 #N/A #N/A
Lem PVC 2.2.6.25 kg 0.3500 8,100.00 2,835.00
20,649.00 #N/A - #N/A
Overhead dan profit 0.1400 2,890.86 #N/A - #N/A
23,539.86 #N/A - #N/A
A.4.4.3.46 1 m2 Pemasang lantai parquet kayu
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang kayu 1.2.7.19 oh 0.3500 89,500.00 31,325.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Parquet m2 1.0500 #N/A #N/A
Lem PVC 2.2.6.25 kg 0.6000 8,100.00 4,860.00
85,855.00 #N/A - #N/A
Overhead dan profit 0.1400 12,019.70 #N/A - #N/A
97,874.70 #N/A - #N/A
A.4.4.3.47 1 m2 Pemasangan lantai kayu gymfloor
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang kayu 1.2.7.19 oh 0.3500 89,500.00 31,325.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
parquet m2 1.0500 #N/A #N/A
Lem PVC 2.2.6.25 kg 0.6000 8,100.00 4,860.00
85,855.00 #N/A - #N/A
Overhead dan profit 0.1400 12,019.70 #N/A - #N/A
97,874.70 #N/A - #N/A

A.4.4.3.48 1 m2 Pemasangan dinding porslen 11 cm x 11 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang batu 1.2.7.16 oh 0.5000 79,000.00 39,500.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
parsien m2 1.0406 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.5000 3,000.00 4,500.00
117,400.00 #N/A - #N/A
Overhead dan profit 0.1400 16,436.00 #N/A - #N/A
133,836.00 #N/A - #N/A

A.4.4.3.49 1 m2 Pemasangan dinding keramik 10 cm x 20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
List Keramik (10x20)cm 2.2.5.260 m2 1.0600 17,400.00 18,444.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00

48
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 2.7500 3,000.00 8,250.00
105,660.00 44,466.00 - 150,126.00
Overhead dan profit 0.1400 14,792.40 6,225.24 - 21,017.64
120,452.40 50,691.24 - 171,143.64

A.4.4.3.50 1 m2 Pemasangan dinding keramik tekture 20 cm x 20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik tekstur Uk. 20cm x 20 cm 2.2.5.251 m2 1.0400 50,800.00 52,832.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 76,424.00 - 182,084.00
Overhead dan profit 0.1400 14,792.40 10,699.36 - 25,491.76
120,452.40 87,123.36 - 207,575.76

A.4.4.3.51 1 m2 Pemasangan dinding keramik artistik 10 x 20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik Arstistik Uk. 10 x 20 cm 2.2.5.22 m2 1.0600 93,000.00 98,580.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 2.7500 3,000.00 8,250.00
105,660.00 124,602.00 - 230,262.00
Overhead dan profit 0.1400 14,792.40 17,444.28 - 32,236.68
120,452.40 142,046.28 - 262,498.68

A.4.4.3.52 1 m2 Pemasangan dinding keramik artistik 5 x 20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
keramik artistik m2 1.0600 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 2.9000 3,000.00 8,700.00
105,660.00 #N/A - #N/A
Overhead dan profit 0.1400 14,792.40 #N/A - #N/A
120,452.40 #N/A - #N/A

A.4.4.3.53 1 m2 Pemasangan dinding keramik artistik 10 x 20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik Arstistik Uk. 10 x 20 cm 2.2.5.22 m2 1.0600 93,000.00 98,580.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 2.7500 3,000.00 8,250.00
105,660.00 124,602.00 - 230,262.00
Overhead dan profit 0.1400 14,792.40 17,444.28 - 32,236.68
120,452.40 142,046.28 - 262,498.68

A.4.4.3.54 1 m2 Pemasangan dinding keramik 20 x 20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik Uk. 20Cm x 20Cm 2.2.5.253 m2 1.0600 50,800.00 53,848.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 77,440.00 - 183,100.00
Overhead dan profit 0.1400 14,792.40 10,841.60 - 25,634.00
120,452.40 88,281.60 - 208,734.00

49
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.4.4.3.54a 1 m2 Pemasangan dinding keramik motif 20 x 25 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik dinding motif Uk. 20cm x 25 cm 2.2.5.25 m2 1.0600 64,700.00 68,582.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 92,174.00 - 197,834.00
Overhead dan profit 0.1400 14,792.40 12,904.36 - 27,696.76
120,452.40 105,078.36 - 225,530.76

A.4.4.3.54b 1 m2 Pemasangan dinding keramik putih 20 x 25 cm


Tenaga #N/A
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik dinding putih ukuran 20/25 Cm 2.2.5.26 m2 1.0600 50,300.00 53,318.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 76,910.00 - 182,570.00
Overhead dan profit 0.1400 14,792.40 10,767.40 - 25,559.80
120,452.40 87,677.40 - 208,129.80

A.4.4.3.54c 1 m2 Pemasangan dinding keramik 20 x 33 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik dinding Uk. 20cm x 33 cm 2.2.5.27 m2 1.0600 54,300.00 57,558.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 81,150.00 - 186,810.00
Overhead dan profit 0.1400 14,792.40 11,361.00 - 26,153.40
120,452.40 92,511.00 - 212,963.40

A.4.4.3.54d 1 m2 Pemasangan dinding keramik 40 x 40 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik putih Uk. 40cm x 40 cm 2.2.5.244 m2 1.0600 54,300.00 57,558.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 81,150.00 - 186,810.00
Overhead dan profit 0.1400 14,792.40 11,361.00 - 26,153.40
120,452.40 92,511.00 - 212,963.40

A.4.4.3.54e 1 m2 Pemasangan dinding keramik tekstur cutting 31 x 63 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik tekstur cutting Uk. 31cm x 63 cm 2.2.5.250 m2 1.0600 123,600.00 131,016.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 154,608.00 - 260,268.00
Overhead dan profit 0.1400 14,792.40 21,645.12 - 36,437.52
120,452.40 176,253.12 - 296,705.52

A.4.4.3.54f 1 m2 Pemasangan dinding keramik tekstur 20 x 20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00

50
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik tekstur Uk. 20cm x 20 cm 2.2.5.251 m2 1.0600 50,800.00 53,848.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 77,440.00 - 183,100.00
Overhead dan profit 0.1400 14,792.40 10,841.60 - 25,634.00
120,452.40 88,281.60 - 208,734.00

A.4.4.3.54g 1 m2 Pemasangan dinding keramik tekstur 30 x 30 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Keramik tekstur Uk. 30cm x 30 cm 2.2.5.252 m2 1.0600 50,300.00 53,318.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 76,910.00 - 182,570.00
Overhead dan profit 0.1400 14,792.40 10,767.40 - 25,559.80
120,452.40 87,677.40 - 208,129.80

A.4.4.3.54h 1 m2 Pemasangan dinding batu marmo warna


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu marmo warna 2.2.1.3 m2 1.0600 117,800.00 124,868.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 148,460.00 - 254,120.00
Overhead dan profit 0.1400 14,792.40 20,784.40 - 35,576.80
120,452.40 169,244.40 - 289,696.80

A.4.4.3.54i 1 m2 Pemasangan dinding batu andesit


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu andesit 2.2.1.5 m2 1.0600 163,700.00 173,522.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 197,114.00 - 302,774.00
Overhead dan profit 0.1400 14,792.40 27,595.96 - 42,388.36
120,452.40 224,709.96 - 345,162.36

A.4.4.3.54j 1 m2 Pemasangan dinding batu andesit alur


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu Andesit alur 2.2.1.7 m2 1.0600 268,600.00 284,716.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 308,308.00 - 413,968.00
Overhead dan profit 0.1400 14,792.40 43,163.12 - 57,955.52
120,452.40 351,471.12 - 471,923.52

A.4.4.3.54k 1 m2 Pemasangan dinding batu andesit alur hitam


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu Andesit Alur hitam 2.2.1.8 m2 1.0600 274,600.00 291,076.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00

51
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 314,668.00 - 420,328.00
Overhead dan profit 0.1400 14,792.40 44,053.52 - 58,845.92
120,452.40 358,721.52 - 479,173.92

A.4.4.3.54l 1 m2 Pemasangan dinding batu andesit hitam bakar


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu andesit hitam bakar 2.2.1.9 m2 1.0600 264,100.00 279,946.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 303,538.00 - 409,198.00
Overhead dan profit 0.1400 14,792.40 42,495.32 - 57,287.72
120,452.40 346,033.32 - 466,485.72

A.4.4.3.54m 1 m2 Pemasangan dinding batu andesit hitam


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu andesit hitam 2.2.1.10 m2 1.0600 213,000.00 225,780.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 249,372.00 - 355,032.00
Overhead dan profit 0.1400 14,792.40 34,912.08 - 49,704.48
120,452.40 284,284.08 - 404,736.48

A.4.4.3.54n 1 m2 Pemasangan dinding batu andesit hijau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu Andisit Hijau 2.2.1.11 m2 1.0600 196,400.00 208,184.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 231,776.00 - 337,436.00
Overhead dan profit 0.1400 14,792.40 32,448.64 - 47,241.04
120,452.40 264,224.64 - 384,677.04

A.4.4.3.54o 1 m2 Pemasangan dinding batu bali green


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu Bali Green 2.2.1.13 m2 1.0600 129,600.00 137,376.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 160,968.00 - 266,628.00
Overhead dan profit 0.1400 14,792.40 22,535.52 - 37,327.92
120,452.40 183,503.52 - 303,955.92

A.4.4.3.54p 1 m2 Pemasangan dinding batu bobos


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu Bobos 2.2.1.15 m2 1.0600 146,100.00 154,866.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 178,458.00 - 284,118.00
Overhead dan profit 0.1400 14,792.40 24,984.12 - 39,776.52
120,452.40 203,442.12 - 323,894.52

52
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.4.4.3.54q 1 m2 Pemasangan dinding batu candi


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu candi 2.2.1.16 m2 1.0600 141,400.00 149,884.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 173,476.00 - 279,136.00
Overhead dan profit 0.1400 14,792.40 24,286.64 - 39,079.04
120,452.40 197,762.64 - 318,215.04

A.4.4.3.54r 1 m2 Pemasangan dinding batu candi hitam


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu candi hitam 2.2.1.17 m2 1.0600 141,400.00 149,884.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 173,476.00 - 279,136.00
Overhead dan profit 0.1400 14,792.40 24,286.64 - 39,079.04
120,452.40 197,762.64 - 318,215.04

A.4.4.3.54s 1 m2 Pemasangan dinding batu granit black gold


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu granit black gold 2.2.1.18 m2 1.0600 2,310,000.00 2,448,600.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 2,472,192.00 - 2,577,852.00
Overhead dan profit 0.1400 14,792.40 346,106.88 - 360,899.28
120,452.40 2,818,298.88 - 2,938,751.28

A.4.4.3.54t 1 m2 Pemasangan dinding batu granit motif


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu granit motif 2.2.1.19 m2 1.0600 220,100.00 233,306.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 256,898.00 - 362,558.00
Overhead dan profit 0.1400 14,792.40 35,965.72 - 50,758.12
120,452.40 292,863.72 - 413,316.12

A.4.4.3.54u 1 m2 Pemasangan dinding batu lempeng


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu lempeng 2.2.1.24 m2 1.0600 111,000.00 117,660.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 141,252.00 - 246,912.00
Overhead dan profit 0.1400 14,792.40 19,775.28 - 34,567.68
120,452.40 161,027.28 - 281,479.68

A.4.4.3.54v 1 m2 Pemasangan dinding batu marmo biasa


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00

53
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu marmo biasa 2.2.1.27 m2 1.0600 93,400.00 99,004.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 122,596.00 - 228,256.00
Overhead dan profit 0.1400 14,792.40 17,163.44 - 31,955.84
120,452.40 139,759.44 - 260,211.84

A.4.4.3.54w 1 m2 Pemasangan dinding batu paras putih


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu paras putih 2.2.1.28 m2 1.0600 127,100.00 134,726.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 158,318.00 - 263,978.00
Overhead dan profit 0.1400 14,792.40 22,164.52 - 36,956.92
120,452.40 180,482.52 - 300,934.92

A.4.4.3.54x 1 m2 Pemasangan dinding batu paras grobongan


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu paras grobongan 2.2.1.29 m2 1.0600 110,100.00 116,706.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 140,298.00 - 245,958.00
Overhead dan profit 0.1400 14,792.40 19,641.72 - 34,434.12
120,452.40 159,939.72 - 280,392.12

A.4.4.3.54y 1 m2 Pemasangan dinding batu susun sirih


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu susun sirih 2.2.1.40 m2 1.0600 451,000.00 478,060.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 501,652.00 - 607,312.00
Overhead dan profit 0.1400 14,792.40 70,231.28 - 85,023.68
120,452.40 571,883.28 - 692,335.68

A.4.4.3.54z 1 m2 Pemasangan dinding batu warna ( hias )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Batu warna ( hias ) 2.2.1.42 m2 1.0600 93,100.00 98,686.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 122,278.00 - 227,938.00
Overhead dan profit 0.1400 14,792.40 17,118.92 - 31,911.32
120,452.40 139,396.92 - 259,849.32

A.4.4.3.54aa 1 m2 Pemasangan dinding susun sirih, andesit hitam 3 x 20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Susun Sirih, andisit hitam uk. 3 x 20 cm 2.2.1.57 m2 1.0600 181,500.00 192,390.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00

54
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 215,982.00 - 321,642.00
Overhead dan profit 0.1400 14,792.40 30,237.48 - 45,029.88
120,452.40 246,219.48 - 366,671.88

A.4.4.3.54ab 1 m2 Pemasangan dinding susun sirih, andesit hitam 3 x 30 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Susun Sirih, andisit hitam uk. 3 x 30 cm 2.2.1.58 m2 1.0600 181,500.00 192,390.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 215,982.00 - 321,642.00
Overhead dan profit 0.1400 14,792.40 30,237.48 - 45,029.88
120,452.40 246,219.48 - 366,671.88

A.4.4.3.54ac 1 m2 Pemasangan dinding susun sirih, andesit hitam 3 x 40 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.9000 68,500.00 61,650.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0450 94,500.00 4,252.50
Bahan
Susun Sirih, andisit hitam uk. 3 x 40 cm 2.2.1.59 m2 1.0600 181,500.00 192,390.00
PC / Portland cement 2.2.1.52 kg 9.3000 1,400.00 13,020.00
Pasir pasang / beton 2.2.1.50 m3 0.0180 264,000.00 4,752.00
Semen Putih / warna 2.2.1.54 kg 1.9400 3,000.00 5,820.00
105,660.00 215,982.00 - 321,642.00
Overhead dan profit 0.1400 14,792.40 30,237.48 - 45,029.88
120,452.40 246,219.48 - 366,671.88

A.4.4.3.55 1 m2 Pemasangan dinding marmer bakar 100 x 100 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.3000 68,500.00 89,050.00
Tukang batu 1.2.7.16 oh 0.6500 79,000.00 51,350.00
Kepala Tukang 1.2.7.3 oh 0.0650 93,500.00 6,077.50
Mandor 1.2.7.5 oh 0.0650 94,500.00 6,142.50
Bahan
Marmer bakar 2.2.5.261 m2 1.0600 109,100.00 115,646.00
PC / Portland cement 2.2.1.52 kg 12.4400 1,400.00 17,416.00
Pasir pasang / beton 2.2.1.50 m3 0.6500 264,000.00 171,600.00
Semen Putih / warna 2.2.1.54 kg 3.0300 3,000.00 9,090.00
152,620.00 313,752.00 - 466,372.00
Overhead dan profit 0.1400 21,366.80 43,925.28 - 65,292.08
173,986.80 357,677.28 - 531,664.08

A.4.4.3.55a 1 m2 Pemasangan dinding marmer hitam 100 x 100 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.3000 68,500.00 89,050.00
Tukang batu 1.2.7.16 oh 0.6500 79,000.00 51,350.00
Kepala Tukang 1.2.7.3 oh 0.0650 93,500.00 6,077.50
Mandor 1.2.7.5 oh 0.0650 94,500.00 6,142.50
Bahan
Marmer Hitam 2.2.5.262 m2 1.0600 112,600.00 119,356.00
PC / Portland cement 2.2.1.52 kg 12.4400 1,400.00 17,416.00
Pasir pasang / beton 2.2.1.50 m3 0.6500 264,000.00 171,600.00
Semen Putih / warna 2.2.1.54 kg 3.0300 3,000.00 9,090.00
152,620.00 317,462.00 - 470,082.00
Overhead dan profit 0.1400 21,366.80 44,444.68 - 65,811.48
173,986.80 361,906.68 - 535,893.48

A.4.4.3.55b 1 m2 Pemasangan dinding marmer putih 100 x 100 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.3000 68,500.00 89,050.00
Tukang batu 1.2.7.16 oh 0.6500 79,000.00 51,350.00
Kepala Tukang 1.2.7.3 oh 0.0650 93,500.00 6,077.50
Mandor 1.2.7.5 oh 0.0650 94,500.00 6,142.50
Bahan
Marmer Putih 2.2.5.263 m2 1.0600 189,400.00 200,764.00
PC / Portland cement 2.2.1.52 kg 12.4400 1,400.00 17,416.00
Pasir pasang / beton 2.2.1.50 m3 0.6500 264,000.00 171,600.00
Semen Putih / warna 2.2.1.54 kg 3.0300 3,000.00 9,090.00
152,620.00 398,870.00 - 551,490.00
Overhead dan profit 0.1400 21,366.80 55,841.80 - 77,208.60
173,986.80 454,711.80 - 628,698.60

55
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.4.4.3.56 1 m2 Pemasangan dinding bata pelapis 3 x 7 x 24 Cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang batu 1.2.7.16 oh 0.5000 79,000.00 39,500.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan #N/A
bata pelapis buah 63.0000 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 12.4400 1,400.00 17,416.00
Pasir pasang / beton 2.2.1.50 m3 0.0250 264,000.00 6,600.00
Semen Putih / warna 2.2.1.54 kg 2.7500 3,000.00 8,250.00
117,400.00 #N/A - #N/A
Overhead dan profit 0.1400 16,436.00 #N/A - #N/A
133,836.00 #N/A - #N/A

A.4.4.3.57 1 m2 Pemasangan dinding batu paras putih


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu paras putih 2.2.1.28 m2 1.1000 127,100.00 139,810.00
PC / Portland cement 2.2.1.52 kg 11.7500 1,400.00 16,450.00
Pasir pasang / beton 2.2.1.50 m3 0.0350 264,000.00 9,240.00
82,180.00 165,500.00 - 247,680.00
Overhead dan profit 0.1400 11,505.20 23,170.00 - 34,675.20
93,685.20 188,670.00 - 282,355.20

A.4.4.3.57a 1 m2 Pemasangan dinding batu paras grobogan


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu paras grobongan 2.2.1.29 m2 1.1000 110,100.00 121,110.00
PC / Portland cement 2.2.1.52 kg 11.7500 1,400.00 16,450.00
Pasir pasang / beton 2.2.1.50 m3 0.0350 264,000.00 9,240.00
82,180.00 146,800.00 - 228,980.00
Overhead dan profit 0.1400 11,505.20 20,552.00 - 32,057.20
93,685.20 167,352.00 - 261,037.20

A.4.4.3.58 1 m2 Pemasangan dinding batu tempel hitam


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang batu 1.2.7.16 oh 0.3500 79,000.00 27,650.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Batu lempeng 2.2.1.24 m2 1.1000 111,000.00 122,100.00
PC / Portland cement 2.2.1.52 kg 11.7500 1,400.00 16,450.00
Pasir pasang / beton 2.2.1.50 m3 0.0350 264,000.00 9,240.00
82,180.00 147,790.00 - 229,970.00
Overhead dan profit 0.1400 11,505.20 20,690.60 - 32,195.80
93,685.20 168,480.60 - 262,165.80

A.4.4.3.59 1 m2 Pemasangan lantai vynil 30 x 30 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang batu 1.2.7.16 oh 0.1500 79,000.00 11,850.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
vynil buah 11.8700 #N/A #N/A
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3500 13,900.00 4,865.00
24,283.50 #N/A - #N/A
Overhead dan profit 0.1400 3,399.69 #N/A - #N/A
27,683.19 #N/A - #N/A

A.4.4.3.60 1 m2 Pemasangan wallpaper lebar 50 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang batu 1.2.7.16 oh 0.1750 79,000.00 13,825.00
Kepala Tukang 1.2.7.3 oh 0.0170 93,500.00 1,589.50
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan
Wallpaper ( standart ) 2.2.5.295 buah 2.2000 7,500.00 16,500.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.2500 13,900.00 3,475.00

56
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
39,578.50 19,975.00 - 59,553.50
Overhead dan profit 0.1400 5,540.99 2,796.50 - 8,337.49
45,119.49 22,771.50 - 67,890.99

A.4.4.3.61 1 m2 Pemasangan Floor harderner


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
floor harderner Kg 5.0000 #N/A #N/A
19,389.00 #N/A - #N/A
Overhead dan profit 0.1400 2,714.46 #N/A - #N/A
22,103.46 #N/A - #N/A

A.4.4.3.62 1 m1 Pemasangan plint vynil 15 x 30 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0800 68,500.00 5,480.00
Tukang batu 1.2.7.16 oh 0.0800 79,000.00 6,320.00
Kepala Tukang 1.2.7.3 oh 0.0080 93,500.00 748.00
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
vynil buah 1.7600 #N/A #N/A
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.0800 13,900.00 1,112.00
12,926.00 #N/A - #N/A
Overhead dan profit 0.1400 1,809.64 #N/A - #N/A
14,735.64 #N/A - #N/A

A.4.4.3.63 1 m1 Pemasangan plint kayu tebal 2 cm lebar 10 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang batu 1.2.7.16 oh 0.1200 79,000.00 9,480.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Kayu jati papan lokal 2.2.2.19 m3 0.0030 22,550,000.00 67,650.00
Paku Sekrup 2.2.12.12 kg 0.0500 600.00 30.00
19,389.00 67,680.00 - 87,069.00
Overhead dan profit 0.1400 2,714.46 9,475.20 - 12,189.66
22,103.46 77,155.20 - 99,258.66

A.4.4.3.63a 1 m2 Lantai Patlag 1 Lapis Bata merah camp. 1 Sm : 1 Kpr : 3 Psr


Tenaga
Tukang batu 1.2.7.16 oh 0.1600 79,000.00 12,640.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Mandor 1.2.7.5 oh 0.0250 94,500.00 2,362.50
Bahan
Batu Bata / Merah 2.2.1.14 Bj 30.0000 900.00 27,000.00
Kapur Batu 2.2.1.46 M3 0.0120 1,270,500.00 15,246.00
Semen Merah 2.2.1.53 M3 0.0120 150,200.00 1,802.40
Pasir pasang / beton 2.2.1.50 M3 0.0360 264,000.00 9,504.00
19,362.50 53,552.40 - 72,914.90
Overhead dan profit 0.1400 2,710.75 7,497.34 - 10,208.09
22,073.25 61,049.74 - 83,122.99

A.4.4.3.63b 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm K225


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone abu - abu t= 8 cm, K225 2.2.5.268 M2 1.1000 80,300.00 88,330.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 97,570.00 - 116,010.00
Overhead dan profit 0.1400 2,581.60 13,659.80 - 16,241.40
21,021.60 111,229.80 - 132,251.40

A.4.4.3.63c 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm K225


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone abu - abu t= 6 cm, K225 2.2.5.269 M2 1.1000 67,100.00 73,810.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 83,050.00 - 101,490.00
Overhead dan profit 0.1400 2,581.60 11,627.00 - 14,208.60
21,021.60 94,677.00 - 115,698.60

A.4.4.3.63d 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm K300

57
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone abu - abu t= 8 cm, K300 2.2.5.272 M2 1.1000 93,500.00 102,850.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 112,090.00 - 130,530.00
Overhead dan profit 0.1400 2,581.60 15,692.60 - 18,274.20
21,021.60 127,782.60 - 148,804.20

A.4.4.3.63e 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm K300


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone abu - abu t= 6 cm, K300 2.2.5.270 M2 1.1000 77,000.00 84,700.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 93,940.00 - 112,380.00
Overhead dan profit 0.1400 2,581.60 13,151.60 - 15,733.20
21,021.60 107,091.60 - 128,113.20

A.4.4.3.63f 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm K400


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone abu - abu t= 8 cm, K400 2.2.5.274 M2 1.1000 110,000.00 121,000.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 130,240.00 - 148,680.00
Overhead dan profit 0.1400 2,581.60 18,233.60 - 20,815.20
21,021.60 148,473.60 - 169,495.20

A.4.4.3.63g 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm K400


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone abu - abu t= 6 cm, K400 2.2.5.271 M2 1.1000 72,600.00 79,860.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 89,100.00 - 107,540.00
Overhead dan profit 0.1400 2,581.60 12,474.00 - 15,055.60
21,021.60 101,574.00 - 122,595.60

A.4.4.3.63h 1 m2 Pasang Paving Stone Warna Tebal 8 Cm K225


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone warna t= 8 cm, K225 2.2.5.282 M2 1.1000 88,000.00 96,800.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 106,040.00 - 124,480.00
Overhead dan profit 0.1400 2,581.60 14,845.60 - 17,427.20
21,021.60 120,885.60 - 141,907.20

A.4.4.3.63i 1 m2 Pasang Paving Stone Warna Tebal 6 Cm K225


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone warna t= 6 cm, K225 2.2.5.281 M2 1.1000 71,500.00 78,650.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 87,890.00 - 106,330.00
Overhead dan profit 0.1400 2,581.60 12,304.60 - 14,886.20
21,021.60 100,194.60 - 121,216.20

A.4.4.3.63j 1 m2 Pasang Paving Stone Segi 6 Warna Tebal 8 Cm K225


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone warna t= 8 cm, K225 2.2.5.282 M2 1.1000 88,000.00 96,800.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 106,040.00 - 124,480.00
Overhead dan profit 0.1400 2,581.60 14,845.60 - 17,427.20
21,021.60 120,885.60 - 141,907.20

A.4.4.3.63k 1 m2 Pasang Paving Stone Segi 6 Warna Tebal 6 Cm K225


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00

58
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Bahan
Paving Stone warna t= 6 cm, K225 2.2.5.281 M2 1.1000 71,500.00 78,650.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 87,890.00 - 106,330.00
Overhead dan profit 0.1400 2,581.60 12,304.60 - 14,886.20
21,021.60 100,194.60 - 121,216.20

A.4.4.3.63l 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone abu - abu t= 8 cm 2.2.5.276 M2 1.1000 73,700.00 81,070.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 90,310.00 - 108,750.00
Overhead dan profit 0.1400 2,581.60 12,643.40 - 15,225.00
21,021.60 102,953.40 - 123,975.00

A.4.4.3.63m 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone abu - abu t= 6 cm 2.2.5.275 M2 1.1000 60,500.00 66,550.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 75,790.00 - 94,230.00
Overhead dan profit 0.1400 2,581.60 10,610.60 - 13,192.20
21,021.60 86,400.60 - 107,422.20

A.4.4.3.63n 1 m2 Pasang Paving Stone Segi 6 abu abu Tebal 8 cm


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone segi 6 abu - abu t= 8 cm 2.2.5.278 M2 1.1000 60,500.00 66,550.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 75,790.00 - 94,230.00
Overhead dan profit 0.1400 2,581.60 10,610.60 - 13,192.20
21,021.60 86,400.60 - 107,422.20

A.4.4.3.63o 1 m2 Pasang Paving Stone Segi 6 abu abu Tebal 6 cm


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone segi 6 abu - abu t= 6 cm 2.2.5.277 M2 1.1000 55,000.00 60,500.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 69,740.00 - 88,180.00
Overhead dan profit 0.1400 2,581.60 9,763.60 - 12,345.20
21,021.60 79,503.60 - 100,525.20

A.4.4.3.63p 1 m2 Pasang Paving Stone Segi 6 Merah Tebal 8 Cm


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone segi 6 merah t= 8 cm 2.2.5.280 M2 1.1000 71,500.00 78,650.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 87,890.00 - 106,330.00
Overhead dan profit 0.1400 2,581.60 12,304.60 - 14,886.20
21,021.60 100,194.60 - 121,216.20

A.4.4.3.63q 1 m2 Pasang Paving Stone Segi 6 Merah Tebal 6 Cm


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan
Paving Stone segi 6 merah t= 6 cm 2.2.5.279 M2 1.1000 57,200.00 62,920.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00
18,440.00 72,160.00 - 90,600.00
Overhead dan profit 0.1400 2,581.60 10,102.40 - 12,684.00
21,021.60 82,262.40 - 103,284.00

A.4.4.3.63r 1 m2 Pasang Paving Stone (12 x 12) 5 warna Tebal 6 Cm


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 79,000.00 4,740.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 68,500.00 13,700.00
Bahan #N/A
Paving Stone (12x12) 5 warna tebal 6 cm 2.2.5.267 M2 1.1000 77,000.00 84,700.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 264,000.00 9,240.00

59
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
18,440.00 93,940.00 - 112,380.00
Overhead dan profit 0.1400 2,581.60 13,151.60 - 15,733.20
21,021.60 107,091.60 - 128,113.20

A.4.5.1 PEKERJAAN LANGIT - LANGIT ( PLAFOND )

A.4.5.1.1 1 m2 Pemasangan langit - langit Eternit Polos ( Asbes )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0300 68,500.00 2,055.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Eternit polos (Asbes) 2.2.3.63 m2 1.1000 14,300.00 15,730.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
9,352.50 16,002.00 - 25,354.50
Overhead dan profit 0.1400 1,309.35 2,240.28 - 3,549.63
10,661.85 18,242.28 - 28,904.13

A.4.5.1.1a 1 m2 Pemasangan langit - langit Eternit Kembang ( Asbes )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0300 68,500.00 2,055.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Eternit kembang 2.2.3.62 m2 1.1000 10,500.00 11,550.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
9,352.50 11,822.00 - 21,174.50
Overhead dan profit 0.1400 1,309.35 1,655.08 - 2,964.43
10,661.85 13,477.08 - 24,138.93

A.4.5.1.2 1 m2 Pemasangan langit - langit akustik ukuran ( 30 x 30 ) cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Langit-langit Akustik ex. Jayaboard (30x30)cm 2.2.3.195 lembar 12.0000 41,800.00 501,600.00
Paku Asbes 2.2.12.8 kg 0.0500 27,200.00 1,360.00
20,649.00 502,960.00 - 523,609.00
Overhead dan profit 0.1400 2,890.86 70,414.40 - 73,305.26
23,539.86 573,374.40 - 596,914.26

A.4.5.1.3 1 m2 Pemasangan langit - langit akustik ukuran ( 30 x 60 ) cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Langit-langit Akustik ex. Jayaboard (30x60)cm 2.2.3.196 lembar 5.8000 47,300.00 274,340.00
Paku Asbes 2.2.12.8 kg 0.0500 27,200.00 1,360.00
20,649.00 275,700.00 - 296,349.00
Overhead dan profit 0.1400 2,890.86 38,598.00 - 41,488.86
23,539.86 314,298.00 - 337,837.86

A.4.5.1.4 1 m2 Pemasangan langit - langit akustik ukuran ( 60 x 120 ) cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.1000 68,500.00 75,350.00
Tukang kayu 1.2.7.19 oh 1.1000 89,500.00 98,450.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Langit-langit Akustik ex. Jayaboard (60x120)cm 2.2.3.197 lembar 1.5000 52,800.00 79,200.00
Paku Asbes 2.2.12.8 kg 0.0500 27,200.00 1,360.00
175,207.50 80,560.00 - 255,767.50
Overhead dan profit 0.1400 24,529.05 11,278.40 - 35,807.45
199,736.55 91,838.40 - 291,574.95

A.4.5.1.5 1 m2 Pemasangan langit - langit akustik ukuran ( 120 x 240 ) cm, tebal 3 mm,4mm & 6 mm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.1000 68,500.00 75,350.00
Tukang kayu 1.2.7.19 oh 1.1000 89,500.00 98,450.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Tripleks tebal 4 mm ( 1.20 x 2.40 ) m 2.2.3.246 lembar 0.3750 77,000.00 28,875.00
Paku Asbes 2.2.12.8 kg 0.0300 27,200.00 816.00

60
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
175,207.50 29,691.00 - 204,898.50
Overhead dan profit 0.1400 24,529.05 4,156.74 - 28,685.79
199,736.55 33,847.74 - 233,584.29

A.4.5.1.6 1 m2 Pemasangan langit - langit lambrisering kayu jati eks bojonegoro, tebal 9 mm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 0.8000 89,500.00 71,600.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0150 36,850,000.00 552,750.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
137,660.00 553,022.00 - 690,682.00
Overhead dan profit 0.1400 19,272.40 77,423.08 - 96,695.48
156,932.40 630,445.08 - 787,377.48

A.4.5.1.6a 1 m2 Pemasangan langit - langit lambrisering kayu jati lokal, tebal 9 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 0.8000 89,500.00 71,600.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0150 22,550,000.00 338,250.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
137,660.00 338,522.00 - 476,182.00
Overhead dan profit 0.1400 19,272.40 47,393.08 - 66,665.48
156,932.40 385,915.08 - 542,847.48

A.4.5.1.6b 1 m2 Pemasangan langit - langit lambrisering kayu kamfer, tebal 9 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 0.8000 89,500.00 71,600.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0150 11,550,000.00 173,250.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
137,660.00 173,522.00 - 311,182.00
Overhead dan profit 0.1400 19,272.40 24,293.08 - 43,565.48
156,932.40 197,815.08 - 354,747.48

A.4.5.1.6c 1 m2 Pemasangan langit - langit lambrisering kayu balau, tebal 9 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 0.8000 89,500.00 71,600.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0150 11,825,000.00 177,375.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
137,660.00 177,647.00 - 315,307.00
Overhead dan profit 0.1400 19,272.40 24,870.58 - 44,142.98
156,932.40 202,517.58 - 359,449.98

A.4.5.1.6d 1 m2 Pemasangan langit - langit lambrisering kayu kempas, tebal 9 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 0.8000 89,500.00 71,600.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0150 8,525,000.00 127,875.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
137,660.00 128,147.00 - 265,807.00
Overhead dan profit 0.1400 19,272.40 17,940.58 - 37,212.98
156,932.40 146,087.58 - 303,019.98

A.4.5.1.6e 1 m2 Pemasangan langit - langit lambrisering kayu kruing, tebal 9 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 0.8000 89,500.00 71,600.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0150 7,975,000.00 119,625.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
137,660.00 119,897.00 - 257,557.00
Overhead dan profit 0.1400 19,272.40 16,785.58 - 36,057.98

61
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
156,932.40 136,682.58 - 293,614.98

A.4.5.1.6f 1 m2 Pemasangan langit - langit lambrisering kayu meranti, tebal 9 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 0.8000 89,500.00 71,600.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0150 6,050,000.00 90,750.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
137,660.00 91,022.00 - 228,682.00
Overhead dan profit 0.1400 19,272.40 12,743.08 - 32,015.48
156,932.40 103,765.08 - 260,697.48

A.4.5.1.6g 1 m2 Pemasangan langit - langit lambrisering kayu tahun ( mauni / akasia ), tebal 9 mm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 0.8000 89,500.00 71,600.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0150 5,225,000.00 78,375.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
137,660.00 78,647.00 - 216,307.00
Overhead dan profit 0.1400 19,272.40 11,010.58 - 30,282.98
156,932.40 89,657.58 - 246,589.98

A.4.5.1.7 1 m2 Pemasangan langit - langit gypsum board ukuran ( 120 x 240 x 9 ) 9 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Gypsum board tebal 9mm ( 1,2 x 2,4 m ) 2.2.3.85 lembar 0.3640 76,500.00 27,846.00
Paku Asbes 2.2.12.8 kg 0.1100 27,200.00 2,992.00
12,265.00 30,838.00 - 43,103.00
Overhead dan profit 0.1400 1,717.10 4,317.32 - 6,034.42
13,982.10 35,155.32 - 49,137.42

A.4.5.1.8 1 m2 Pemasangan langit - langit akustik ukuran ( 60 x 240 ) Cm rangka Alluminium


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.5000 68,500.00 34,250.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0250 94,500.00 2,362.50
Bahan
Profil kusen aluminium 4" 2.2.4.100 m 3.6000 90,300.00 325,080.00
Kawat Beton / bendraat 2.2.4.30 kg 0.1500 17,600.00 2,640.00
Paku Ramset / dinabolt 2.2.12.11 buah 1.0500 2,900.00 3,045.00
Langit-langit Akustik ex. Jayaboard (60x120)cm 2.2.3.197 lembar 1.5000 52,800.00 79,200.00
86,037.50 409,965.00 - 496,002.50
Overhead dan profit 0.1400 12,045.25 57,395.10 - 69,440.35
98,082.75 467,360.10 - 565,442.85

A.4.5.1.9 1 m' Pemasangan list langit - langit kayu profil


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
List Eternit ( kayu ) 2.2.3.198 m 1.0500 3,000.00 3,150.00
Paku Asbes 2.2.12.8 kg 0.0100 27,200.00 272.00
8,651.00 3,422.00 - 12,073.00
Overhead dan profit 0.1400 1,211.14 479.08 - 1,690.22
9,862.14 3,901.08 - 13,763.22

A.4.5.1.10 1 m2 Pemasangan rangka besi hollow 1x40.40.2, modul 60x60 cm, plafon
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang besi 1.2.7.17 oh 0.3500 84,000.00 29,400.00
Kepala Tukang 1.2.7.3 oh 0.0350 93,500.00 3,272.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Pipa Besi  4/4 Tebal= 1.4 mm 2.2.4.73 m1 4.0000 17,400.00 69,600.00
Assesoris (perkuatan,las dll) ls 1.0000 17,400.00 17,400.00
58,348.50 87,000.00 - 145,348.50

62
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 8,168.79 12,180.00 - 20,348.79
66,517.29 99,180.00 - 165,697.29

A.4.5.1.10a 1 m' List Plafond Gypsum Kecil


Tenaga
Tukang kayu 1.2.7.19 Oh 0.0210 89,500.00 1,879.50
Kepala Tukang 1.2.7.3 Oh 0.0020 93,500.00 187.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.0210 68,500.00 1,438.50
Mandor 1.2.7.5 Oh 0.0010 94,500.00 94.50
Bahan
List Profil kecil ( gypsum ) 2.2.3.200 M' 1.0500 17,400.00 18,270.00
Plamur Tembok 2.2.6.38 Kg 0.2000 15,600.00 3,120.00
3,599.50 21,390.00 - 24,989.50
Overhead dan profit 0.1400 503.93 2,994.60 - 3,498.53
4,103.43 24,384.60 - 28,488.03

A.4.5.1.10b 1 m' List Plafond Gypsum Besar


Tenaga
Tukang kayu 1.2.7.19 Oh 0.0210 89,500.00 1,879.50
Kepala Tukang 1.2.7.3 Oh 0.0020 93,500.00 187.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.0210 68,500.00 1,438.50
Mandor 1.2.7.5 Oh 0.0010 94,500.00 94.50
Bahan
List Profil besar ( gypsum ) 2.2.3.199 M' 1.0500 23,100.00 24,255.00
Plamur Tembok 2.2.6.38 Kg 0.2000 15,600.00 3,120.00
3,599.50 27,375.00 - 30,974.50
Overhead dan profit 0.1400 503.93 3,832.50 - 4,336.43
4,103.43 31,207.50 - 35,310.93

A.4.5.2 HARGA SATUAN PENUTUP ATAP

A.4.5.2.1 1 m2 Pemasangan atap genteng MKP lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0750 89,500.00 6,712.50
Kepala Tukang 1.2.7.3 oh 0.0075 93,500.00 701.25
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Genteng MKP 2.2.3.67 buah 25.0000 2,600.00 65,000.00
18,444.75 65,000.00 - 83,444.75
Overhead dan profit 0.1400 2,582.27 9,100.00 - 11,682.27
21,027.02 74,100.00 - 95,127.02

A.4.5.2.1a 1 m2 Pemasangan atap genteng Mantili


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0750 89,500.00 6,712.50
Kepala Tukang 1.2.7.3 oh 0.0075 93,500.00 701.25
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Genteng mantili 2.2.3.79 buah 25.0000 3,200.00 80,000.00
18,444.75 80,000.00 - 98,444.75
Overhead dan profit 0.1400 2,582.27 11,200.00 - 13,782.27
21,027.02 91,200.00 - 112,227.02

A.4.5.2.1b 1 m2 Pemasangan atap genteng Press biasa


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0750 89,500.00 6,712.50
Kepala Tukang 1.2.7.3 oh 0.0075 93,500.00 701.25
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Genteng pres biasa 2.2.3.82 buah 25.0000 2,300.00 57,500.00
18,444.75 57,500.00 - 75,944.75
Overhead dan profit 0.1400 2,582.27 8,050.00 - 10,632.27
21,027.02 65,550.00 - 86,577.02

A.4.5.2.1c 1 m2 Pemasangan atap genteng Prentul eks Trenggalek / Tulungagung


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0750 89,500.00 6,712.50
Kepala Tukang 1.2.7.3 oh 0.0075 93,500.00 701.25
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Genteng bubung Prentul ex. Trenggalek / Tulungagung 2.2.3.72 buah 25.0000 5,000.00 125,000.00
18,444.75 125,000.00 - 143,444.75
Overhead dan profit 0.1400 2,582.27 17,500.00 - 20,082.27
21,027.02 142,500.00 - 163,527.02

A.4.5.2.1d 1 m2 Pemasangan atap genteng Kaca ( model karangpilang)

63
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0750 89,500.00 6,712.50
Kepala Tukang 1.2.7.3 oh 0.0075 93,500.00 701.25
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Genteng Kaca (model Karang Pilang) 2.2.3.77 buah 25.0000 11,400.00 285,000.00
18,444.75 285,000.00 - 303,444.75
Overhead dan profit 0.1400 2,582.27 39,900.00 - 42,482.27
21,027.02 324,900.00 - 345,927.02

A.4.5.2.2 1 m2 Pemasangan atap genteng glazuur eks Kanmuri


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0750 89,500.00 6,712.50
Kepala Tukang 1.2.7.3 oh 0.0080 93,500.00 748.00
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Genteng Glasur ex. Kanmuri 2.2.3.76 buah 25.0000 10,000.00 250,000.00
18,491.50 250,000.00 - 268,491.50
Overhead dan profit 0.1400 2,588.81 35,000.00 - 37,588.81
21,080.31 285,000.00 - 306,080.31

A.4.5.2.3 1 m2 Pemasangan atap genteng palentong besar / super


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0750 89,500.00 6,712.50
Kepala Tukang 1.2.7.3 oh 0.0080 93,500.00 748.00
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
genteng kodok buah 12.0000 #N/A #N/A
18,491.50 #N/A - #N/A
Overhead dan profit 0.1400 2,588.81 #N/A - #N/A
21,080.31 #N/A - #N/A

A.4.5.2.4 1 m2 Pemasangan bubung genteng MKP lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan
Genteng Bubung MKP 2.2.3.66 buah 5.0000 5,800.00 29,000.00
PC / Portland cement 2.2.1.52 Kg 8.0000 1,400.00 11,200.00
Pasir pasang / beton 2.2.1.50 m3 0.0320 264,000.00 8,448.00
47,359.00 48,648.00 - 96,007.00
Overhead dan profit 0.1400 6,630.26 6,810.72 - 13,440.98
53,989.26 55,458.72 - 109,447.98

A.4.5.2.5 1 m2 Pemasangan bubung genteng glazuur eks Kanmuri


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan
Bubungan Glasur ex. Kanmuri 2.2.3.56 buah 5.0000 20,200.00 101,000.00
PC / Portland cement 2.2.1.52 Kg 8.0000 1,400.00 11,200.00
Pasir pasang / beton 2.2.1.50 m3 0.0320 264,000.00 8,448.00
47,359.00 120,648.00 - 168,007.00
Overhead dan profit 0.1400 6,630.26 16,890.72 - 23,520.98
53,989.26 137,538.72 - 191,527.98

A.4.5.2.6 1 m2 Pemasangan bubung genteng palentong besar


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan #N/A
Genteng bubung buah 4.0000 #N/A #N/A
PC / Portland cement 2.2.1.52 Kg 8.0000 1,400.00 11,200.00
Pasir pasang / beton 2.2.1.50 m3 0.0320 264,000.00 8,448.00
47,359.00 #N/A - #N/A
Overhead dan profit 0.1400 6,630.26 #N/A - #N/A
53,989.26 #N/A - #N/A

A.4.5.2.6a 1 m2 Pemasangan bubung genteng bubung mantili


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00

64
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang batu 1.2.7.16 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan
Genteng bubung Mantili ex. Trenggalek / Tulungagung 2.2.3.71 buah 4.0000 6,400.00 25,600.00
PC / Portland cement 2.2.1.52 Kg 8.0000 1,400.00 11,200.00
Pasir pasang / beton 2.2.1.50 m3 0.0320 264,000.00 8,448.00
45,259.00 45,248.00 - 90,507.00
Overhead dan profit 0.1400 6,336.26 6,334.72 - 12,670.98
51,595.26 51,582.72 - 103,177.98

A.4.5.2.6b 1 m2 Pemasangan bubung genteng bubung Prentul eks Trenggalek / Tulungagung


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan
Genteng bubung Prentul ex. Trenggalek / Tulungagung 2.2.3.72 buah 4.0000 5,000.00 20,000.00
PC / Portland cement 2.2.1.52 Kg 8.0000 1,400.00 11,200.00
Pasir pasang / beton 2.2.1.50 m3 0.0320 264,000.00 8,448.00
47,359.00 39,648.00 - 87,007.00
Overhead dan profit 0.1400 6,630.26 5,550.72 - 12,180.98
53,989.26 45,198.72 - 99,187.98

A.4.5.2.6c 1 m2 Pemasangan bubung genteng bubung Press


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan
Genteng bubung Press 2.2.3.73 buah 4.0000 4,800.00 19,200.00
PC / Portland cement 2.2.1.52 Kg 8.0000 1,400.00 11,200.00
Pasir pasang / beton 2.2.1.50 m3 0.0320 264,000.00 8,448.00
47,359.00 38,848.00 - 86,207.00
Overhead dan profit 0.1400 6,630.26 5,438.72 - 12,068.98
53,989.26 44,286.72 - 98,275.98
A.4.5.2.7 1 m2 Pemasangan roof light fibreglass 90 x 180
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0670 89,500.00 5,996.50
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Atap Skylight / fiber 2.2.3.51 buah 0.6000 242,000.00 145,200.00
Paku biasa 2.2.12.1 Kg 0.0500 16,200.00 810.00
16,902.50 146,010.00 - 162,912.50
Overhead dan profit 0.1400 2,366.35 20,441.40 - 22,807.75
19,268.85 166,451.40 - 185,720.25

A.4.5.2.8 1 m2 Pemasangan atap asbes gelombang 0,92 m x 2,50 m x 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0750 89,500.00 6,712.50
Kepala Tukang 1.2.7.3 oh 0.0080 93,500.00 748.00
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Asbes Gelombang besar 92 x 250 tbl = 5 mm 2.2.3.13 Lembar 0.5000 115,500.00 57,750.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,806.50 57,894.00 - 75,700.50
Overhead dan profit 0.1400 2,492.91 8,105.16 - 10,598.07
20,299.41 65,999.16 - 86,298.57

A.4.5.2.9 1 m2 Pemasangan atap asbes gelombang 0,92 m x 2,25 m x 5 mm


Tenaga #N/A
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0750 89,500.00 6,712.50
Kepala Tukang 1.2.7.3 oh 0.0080 93,500.00 748.00
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Asbes Gelombang nok kecil 92 x 225 tbl = 5 mm 2.2.3.35 Lembar 0.6000 101,300.00 60,780.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,806.50 60,924.00 - 78,730.50
Overhead dan profit 0.1400 2,492.91 8,529.36 - 11,022.27
20,299.41 69,453.36 - 89,752.77

A.4.5.2.10 1 m2 Pemasangan atap asbes gelombang 0,92 m x 2,00 m x 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00

65
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang kecil 92 x 200 tbl = 5 mm 2.2.3.31 Lembar 0.6000 111,000.00 66,600.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 66,744.00 - 83,915.00
Overhead dan profit 0.1400 2,403.94 9,344.16 - 11,748.10
19,574.94 76,088.16 - 95,663.10

A.4.5.2.11 1 m2 Pemasangan atap asbes gelombang 0,92 m x 1,80 m x 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang nok kecil 92 x 180 tbl = 5 mm 2.2.3.33 Lembar 0.7500 71,200.00 53,400.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 53,544.00 - 70,715.00
Overhead dan profit 0.1400 2,403.94 7,496.16 - 9,900.10
19,574.94 61,040.16 - 80,615.10

A.4.5.2.12 1 m2 Pemasangan atap asbes gelombang 1,05 m x 3,00 m x 4 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang kecil 105 x 300 tbl = 4 mm 2.2.3.24 Lembar 0.3500 62,900.00 22,015.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 22,159.00 - 39,330.00
Overhead dan profit 0.1400 2,403.94 3,102.26 - 5,506.20
19,574.94 25,261.26 - 44,836.20

A.4.5.2.13 1 m2 Pemasangan atap asbes gelombang 1,05 m x 2,70 m x 4 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang kecil 105 x 270 tbl = 4 mm 2.2.3.22 Lembar 0.4200 75,700.00 31,794.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 31,938.00 - 49,109.00
Overhead dan profit 0.1400 2,403.94 4,471.32 - 6,875.26
19,574.94 36,409.32 - 55,984.26

A.4.5.2.14 1 m2 Pemasangan atap asbes gelombang 1,05 m x 2,50 m x 4 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang kecil 105 x 240 tbl = 4 mm 2.2.3.20 Lembar 0.4400 67,800.00 29,832.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 29,976.00 - 47,147.00
Overhead dan profit 0.1400 2,403.94 4,196.64 - 6,600.58
19,574.94 34,172.64 - 53,747.58

A.4.5.2.15 1 m2 Pemasangan atap asbes gelombang 1,05 m x 2,25 m x 4 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang kecil 105 x 225 tbl = 4 mm 2.2.3.19 Lembar 0.5100 83,600.00 42,636.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 42,780.00 - 59,951.00
Overhead dan profit 0.1400 2,403.94 5,989.20 - 8,393.14
19,574.94 48,769.20 - 68,344.14

A.4.5.2.16 1 m2 Pemasangan atap asbes gelombang 1,05 m x 1,50 m x 4 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50

66
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang kecil 105 x 150 tbl = 4 mm 2.2.3.18 Lembar 0.8000 50,400.00 40,320.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 40,464.00 - 57,635.00
Overhead dan profit 0.1400 2,403.94 5,664.96 - 8,068.90
19,574.94 46,128.96 - 65,703.90

A.4.5.2.17 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 3,00 m x 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang besar 110 x 300 tbl = 5 mm 2.2.3.11 Lembar 0.3700 109,500.00 40,515.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 40,659.00 - 57,830.00
Overhead dan profit 0.1400 2,403.94 5,692.26 - 8,096.20
19,574.94 46,351.26 - 65,926.20

A.4.5.2.18 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 2,50 m x 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang besar 110 x 250 tbl = 5 mm 2.2.3.10 Lembar 0.3800 115,500.00 43,890.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 44,034.00 - 61,205.00
Overhead dan profit 0.1400 2,403.94 6,164.76 - 8,568.70
19,574.94 50,198.76 - 69,773.70

A.4.5.2.19 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 2,25 m x 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang besar 110 x 225 tbl = 5 mm 2.2.3.9 Lembar 0.4600 105,200.00 48,392.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 48,536.00 - 65,707.00
Overhead dan profit 0.1400 2,403.94 6,795.04 - 9,198.98
19,574.94 55,331.04 - 74,905.98

A.4.5.2.20 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 2,00 m x 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang besar 110 x 200 tbl = 5 mm 2.2.3.8 Lembar 0.4900 99,300.00 48,657.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 48,801.00 - 65,972.00
Overhead dan profit 0.1400 2,403.94 6,832.14 - 9,236.08
19,574.94 55,633.14 - 75,208.08

A.4.5.2.21 1 m2 Pemasangan atap asbes gelombang besar 0,92 x 2,50 m x 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Asbes Gelombang besar 92 x 250 tbl = 5 mm 2.2.3.13 Lembar 0.5700 115,500.00 65,835.00
Paku Kait ( pancing ) 2.2.12.10 Kg 0.1200 1,200.00 144.00
17,171.00 65,979.00 - 83,150.00
Overhead dan profit 0.1400 2,403.94 9,237.06 - 11,641.00
19,574.94 75,216.06 - 94,791.00

A.4.5.2.22 1 m1 Pemasangan bumbungan stel gelombang 0,92 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0840 68,500.00 5,754.00
Tukang kayu 1.2.7.19 oh 0.1250 89,500.00 11,187.50
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan

67
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Bubung asbes gel kecil (Ardek 1Stel 2 Lmbr) 2.2.3.55 Lembar 2.4000 34,700.00 83,280.00
Paku Sekrup 2.2.12.12 Kg 6.0000 600.00 3,600.00
18,535.00 86,880.00 - 105,415.00
Overhead dan profit 0.1400 2,594.90 12,163.20 - 14,758.10
21,129.90 99,043.20 - 120,173.10

A.4.5.2.23 1 m1 Pemasangan bumbungan stel gelombang 1,05 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0840 68,500.00 5,754.00
Tukang kayu 1.2.7.19 oh 0.1250 89,500.00 11,187.50
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Nok Stel Asbes Gelombang kecil 105 2.2.3.207 Lembar 2.1000 39,700.00 83,370.00
Paku Sekrup 2.2.12.12 Kg 6.0000 600.00 3,600.00
18,535.00 86,970.00 - 105,505.00
Overhead dan profit 0.1400 2,594.90 12,175.80 - 14,770.70
21,129.90 99,145.80 - 120,275.70

A.4.5.2.24 1 m1 Pemasangan bumbungan stel gelombang 1,08 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0840 68,500.00 5,754.00
Tukang kayu 1.2.7.19 oh 0.1250 89,500.00 11,187.50
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Nok Stel Asbes Gelombang besar 108 2.2.3.206 Lembar 2.0500 60,500.00 124,025.00
Paku Sekrup 2.2.12.12 Kg 6.0000 600.00 3,600.00
18,535.00 127,625.00 - 146,160.00
Overhead dan profit 0.1400 2,594.90 17,867.50 - 20,462.40
21,129.90 145,492.50 - 166,622.40

A.4.5.2.25 1 m1 Pemasangan nok paten 0,92 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0840 68,500.00 5,754.00
Tukang kayu 1.2.7.19 oh 0.1250 89,500.00 11,187.50
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Asbes Nok 92 2.2.3.37 Lembar 1.2000 32,200.00 38,640.00
Paku Sekrup 2.2.12.12 Kg 6.0000 600.00 3,600.00
18,535.00 42,240.00 - 60,775.00
Overhead dan profit 0.1400 2,594.90 5,913.60 - 8,508.50
21,129.90 48,153.60 - 69,283.50

A.4.5.2.26 1 m1 Pemasangan nok paten 1,05 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0840 68,500.00 5,754.00
Tukang kayu 1.2.7.19 oh 0.1250 89,500.00 11,187.50
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Asbes Nok 105 2.2.3.36 Lembar 1.2000 38,700.00 46,440.00
Paku Sekrup 2.2.12.12 Kg 6.0000 600.00 3,600.00
18,535.00 50,040.00 - 68,575.00
Overhead dan profit 0.1400 2,594.90 7,005.60 - 9,600.50
21,129.90 57,045.60 - 78,175.50

A.4.5.2.27 1 m1 Pemasangan nok paten 1,08 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0840 68,500.00 5,754.00
Tukang kayu 1.2.7.19 oh 0.1250 89,500.00 11,187.50
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Nok paten 92 cm Lembar 1.2000 #N/A #N/A
Paku Sekrup 2.2.12.12 Kg 6.0000 600.00 3,600.00
18,535.00 #N/A - #N/A
Overhead dan profit 0.1400 2,594.90 #N/A - #N/A
21,129.90 #N/A - #N/A

A.4.5.2.28 1 m1 Pemasangan nok stel rata 0,92 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Asbes Nok Gelombang kecil 2.2.3.39 Lembar 1.1000 37,500.00 41,250.00
Paku Sekrup 2.2.12.12 Kg 6.0000 600.00 3,600.00

68
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
21,868.50 44,850.00 - 66,718.50
Overhead dan profit 0.1400 3,061.59 6,279.00 - 9,340.59
24,930.09 51,129.00 - 76,059.09

A.4.5.2.29 1 m1 Pemasangan nok stel rata 1,05 m


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0840 68,500.00 5,754.00
Tukang kayu 1.2.7.19 oh 0.1250 89,500.00 11,187.50
Kepala Tukang 1.2.7.3 oh 0.0130 93,500.00 1,215.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Asbes Nok Gelombang besar 2.2.3.38 Lembar 1.1000 69,300.00 76,230.00
Paku Sekrup 2.2.12.12 Kg 6.0000 600.00 3,600.00
18,535.00 79,830.00 - 98,365.00
Overhead dan profit 0.1400 2,594.90 11,176.20 - 13,771.10
21,129.90 91,006.20 - 112,136.10

A.4.5.2.30 1 m2 Pemasangan genteng beton


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Genteng Beton 2.2.3.68 Lembar 11.0000 5,000.00 55,000.00
Paku Sekrup 2.2.12.12 Kg 0.0300 600.00 18.00
24,530.00 55,018.00 - 79,548.00
Overhead dan profit 0.1400 3,434.20 7,702.52 - 11,136.72
27,964.20 62,720.52 - 90,684.72

A.4.5.2.31 1 m2 Pemasangan genteng aspal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0030 93,500.00 280.50
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Genteng aspal Lembar 6.9000 #N/A #N/A
Plywood 6 mm Kg 0.3500 #N/A #N/A
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Plastik aerator bh 0.5000 #N/A #N/A
41,775.50 #N/A - #N/A
Overhead dan profit 0.1400 5,848.57 #N/A - #N/A
47,624.07 #N/A - #N/A

A.4.5.2.32 1 m2 Pemasangan genteng metal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan
Genteng metal 2.2.3.80 buah 1.0200 65,200.00 66,504.00
Paku biasa 2.2.12.1 Kg 0.2000 16,200.00 3,240.00
23,679.50 69,744.00 - 93,423.50
Overhead dan profit 0.1400 3,315.13 9,764.16 - 13,079.29
26,994.63 79,508.16 - 106,502.79

A.4.5.2.33 1 m2 Pemasangan atap sirap kayu


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1660 68,500.00 11,371.00
Tukang kayu 1.2.7.19 oh 0.2500 89,500.00 22,375.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Atap sirap 2.2.3.50 m2 1.0000 220,000.00 220,000.00
Paku biasa 2.2.12.1 Kg 0.2000 16,200.00 3,240.00
36,839.50 223,240.00 - 260,079.50
Overhead dan profit 0.1400 5,157.53 31,253.60 - 36,411.13
41,997.03 254,493.60 - 296,490.63

A.4.5.2.34 1 m1 Pemasangan nok genteng beton


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0200 94,500.00 1,890.00
Bahan
Genteng bubung beton 2.2.3.69 buah 3.5000 4,800.00 16,800.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00

69
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
PC / Portland cement 2.2.1.52 kg 10.8000 1,400.00 15,120.00
Pasir pasang / beton 2.2.1.50 m3 0.0320 264,000.00 8,448.00
Semen Putih / warna 2.2.1.54 Kg 1.0000 3,000.00 3,000.00
49,060.00 44,178.00 - 93,238.00
Overhead dan profit 0.1400 6,868.40 6,184.92 - 13,053.32
55,928.40 50,362.92 - 106,291.32

A.4.5.2.35 1 m1 Pemasangan nok genteng aspal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1250 68,500.00 8,562.50
Tukang kayu 1.2.7.19 oh 0.2500 89,500.00 22,375.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Nok genteng aspal buah 2.0000 #N/A #N/A
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
Kayu Kruing Balok 2.2.2.30 m3 0.0035 6,875,000.00 24,062.50
33,842.00 #N/A - #N/A
Overhead dan profit 0.1400 4,737.88 #N/A - #N/A
38,579.88 #N/A - #N/A

A.4.5.2.36 1 m1 Pemasangan nok genteng metal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0130 94,500.00 1,228.50
Bahan
Nok atap genteng metal 2.2.3.204 bh 1.1000 36,900.00 40,590.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
33,181.00 41,400.00 - 74,581.00
Overhead dan profit 0.1400 4,645.34 5,796.00 - 10,441.34
37,826.34 47,196.00 - 85,022.34

A.4.5.2.37 1 m1 Pemasangan nok sirap


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1250 68,500.00 8,562.50
Tukang kayu 1.2.7.19 oh 0.2500 89,500.00 22,375.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Seng Plat BJLS 30 lebar 0,90 m 2.2.3.229 lbr 0.4000 42,400.00 16,960.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
33,842.00 18,580.00 - 52,422.00
Overhead dan profit 0.1400 4,737.88 2,601.20 - 7,339.08
38,579.88 21,181.20 - 59,761.08

A.4.5.2.38 1 m2 Pemasangan atap seng gelombang BJLS 30 Uk 180 x 90 x 0,03 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.0600 89,500.00 5,370.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Seng Gelombang Bjls 30 uk 180x90x0,03 cm 2.2.3.221 lbr 0.7000 74,300.00 52,010.00
Paku biasa 2.2.12.1 kg 0.0200 16,200.00 324.00
14,718.00 52,334.00 - 67,052.00
Overhead dan profit 0.1400 2,060.52 7,326.76 - 9,387.28
16,778.52 59,660.76 - 76,439.28

A.4.5.2.38a 1 m2 Pemasangan atap seng gelombang BJLS 20 Uk 180 x 90 x 0,02 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.0600 89,500.00 5,370.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Seng Gelombang Bjls 20 uk. 180x90x0,02 cm 2.2.3.219 lbr 0.7000 55,600.00 38,920.00
Paku biasa 2.2.12.1 kg 0.0200 16,200.00 324.00
14,718.00 39,244.00 - 53,962.00
Overhead dan profit 0.1400 2,060.52 5,494.16 - 7,554.68
16,778.52 44,738.16 - 61,516.68

A.4.5.2.38b 1 m2 Pemasangan atap seng gelombang BJLS 30 Uk 305 x 90 x 0,03 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.0600 89,500.00 5,370.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00

70
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Bahan
Seng gelombang Bjls 30 uk. 305x90x0,03 cm 2.2.3.223 lbr 0.4000 123,800.00 49,520.00
Paku biasa 2.2.12.1 kg 0.0200 16,200.00 324.00
14,718.00 49,844.00 - 64,562.00
Overhead dan profit 0.1400 2,060.52 6,978.16 - 9,038.68
16,778.52 56,822.16 - 73,600.68

A.4.5.2.38c 1 m2 Pemasangan atap seng gelombang BJLS 20 Uk 305 x 90 x 0,02 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.0600 89,500.00 5,370.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Seng gelombang Bjls 20 uk. 305x90x0,02 cm 2.2.3.220 lbr 0.4000 89,100.00 35,640.00
Paku biasa 2.2.12.1 kg 0.0200 16,200.00 324.00
14,718.00 35,964.00 - 50,682.00
Overhead dan profit 0.1400 2,060.52 5,034.96 - 7,095.48
16,778.52 40,998.96 - 57,777.48

A.4.5.2.39 1 m2 Pemasangan atap seng BJLS 20


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Seng Plat BJLS 20 lebar 0,90 m 2.2.3.224 lbr 0.3000 75,400.00 22,620.00
Paku Seng ( Paku payung ) 2.2.12.13 kg 0.0400 26,000.00 1,040.00
17,761.50 23,660.00 - 41,421.50
Overhead dan profit 0.1400 2,486.61 3,312.40 - 5,799.01
20,248.11 26,972.40 - 47,220.51

A.4.5.2.39a 1 m2 Pemasangan atap seng BJLS 27


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Seng Plat BJLS 27 lebar 0,90 m 2.2.3.226 lbr 0.3000 39,100.00 11,730.00
Paku Seng ( Paku payung ) 2.2.12.13 kg 0.0400 26,000.00 1,040.00
#N/A 17,761.50 12,770.00 - 30,531.50
Overhead dan profit #N/A 0.1400 2,486.61 1,787.80 - 4,274.41
#N/A 20,248.11 14,557.80 - 34,805.91
#N/A
A.4.5.2.39b 1 m2 Pemasangan atap seng BJLS 30 #N/A
Tenaga #N/A
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0700 89,500.00 6,265.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Seng Plat BJLS 30 lebar 0,90 m 2.2.3.229 lbr 0.3000 42,400.00 12,720.00
Paku Seng ( Paku payung ) 2.2.12.13 kg 0.0400 26,000.00 1,040.00
17,761.50 13,760.00 - 31,521.50
Overhead dan profit 0.1400 2,486.61 1,926.40 - 4,413.01
20,248.11 15,686.40 - 35,934.51

A.4.5.2.40 1 m2 Pemasangan atap alumunium tebal 0,25 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.7500 89,500.00 67,125.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Atap galvalum tebal 0,25 2.2.3.43 bh 1.0500 50,800.00 53,340.00
Paku Seng ( Paku payung ) 2.2.12.13 kg 0.0200 26,000.00 520.00
85,447.00 53,860.00 - 139,307.00
Overhead dan profit 0.1400 11,962.58 7,540.40 - 19,502.98
97,409.58 61,400.40 - 158,809.98

A.4.5.2.40a 1 m2 Pemasangan atap alumunium tebal 0,30 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.7500 89,500.00 67,125.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Atap galvalum tebal 0,30 2.2.3.44 bh 1.0500 59,500.00 62,475.00

71
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Paku Seng ( Paku payung ) 2.2.12.13 kg 0.0200 26,000.00 520.00
85,447.00 62,995.00 - 148,442.00
Overhead dan profit 0.1400 11,962.58 8,819.30 - 20,781.88
97,409.58 71,814.30 - 169,223.88

A.4.5.2.40b 1 m2 Pemasangan atap alumunium tebal 0,35 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.7500 89,500.00 67,125.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Atap galvalum tebal 0,35 2.2.3.45 bh 1.0500 68,200.00 71,610.00
Paku Seng ( Paku payung ) 2.2.12.13 kg 0.0200 26,000.00 520.00
85,447.00 72,130.00 - 157,577.00
Overhead dan profit 0.1400 11,962.58 10,098.20 - 22,060.78
97,409.58 82,228.20 - 179,637.78

A.4.5.2.40c 1 m2 Pemasangan atap alumunium tebal 0,40 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.7500 89,500.00 67,125.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Atap galvalum tebal 0,40 2.2.3.46 bh 1.0500 76,200.00 80,010.00
Paku Seng ( Paku payung ) 2.2.12.13 kg 0.0200 26,000.00 520.00
85,447.00 80,530.00 - 165,977.00
Overhead dan profit 0.1400 11,962.58 11,274.20 - 23,236.78
97,409.58 91,804.20 - 189,213.78

A.4.5.2.41 1 m2 Pemasangan nok alumunium


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.1000 93,500.00 9,350.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Aluminium strip ( l = 5 - 10 cm) 2.2.4.1 bh 1.2000 16,500.00 19,800.00
Paku Seng ( Paku payung ) 2.2.12.13 kg 0.0400 26,000.00 1,040.00
29,875.00 20,840.00 - 50,715.00
Overhead dan profit 0.1400 4,182.50 2,917.60 - 7,100.10
34,057.50 23,757.60 - 57,815.10

A.4.5.2.42 1 m2 Pemasangan alumunium foil / sisalation


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Alumunium foil 2.2.4.3 bh 1.0500 11,000.00 11,550.00
15,973.50 11,550.00 - 27,523.50
Overhead dan profit 0.1400 2,236.29 1,617.00 - 3,853.29
18,209.79 13,167.00 - 31,376.79

A.4.6.1 PEKERJAAN KAYU

A.4.6.1.1 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 7.0000 68,500.00 479,500.00
Tukang kayu 1.2.7.19 oh 21.0000 89,500.00 1,879,500.00
Kepala Tukang 1.2.7.3 oh 2.1000 93,500.00 196,350.00
Mandor 1.2.7.5 oh 0.3500 94,500.00 33,075.00
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 1.1000 30,800,000.00 33,880,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,588,425.00 33,914,150.00 - 36,502,575.00
Overhead dan profit 0.1400 362,379.50 4,747,981.00 - 5,110,360.50
2,950,804.50 38,662,131.00 - 41,612,935.50

A.4.6.1.1a 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu jati lokal
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 7.0000 68,500.00 479,500.00
Tukang kayu 1.2.7.19 oh 21.0000 89,500.00 1,879,500.00
Kepala Tukang 1.2.7.3 oh 2.1000 93,500.00 196,350.00
Mandor 1.2.7.5 oh 0.3500 94,500.00 33,075.00
Bahan

72
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Kayu Jati Balok lokal 2.2.2.17 m3 1.1000 20,900,000.00 22,990,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,588,425.00 23,024,150.00 - 25,612,575.00
Overhead dan profit 0.1400 362,379.50 3,223,381.00 - 3,585,760.50
2,950,804.50 26,247,531.00 - 29,198,335.50

A.4.6.1.1b 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu kamfer
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 7.0000 68,500.00 479,500.00
Tukang kayu 1.2.7.19 oh 21.0000 89,500.00 1,879,500.00
Kepala Tukang 1.2.7.3 oh 2.1000 93,500.00 196,350.00
Mandor 1.2.7.5 oh 0.3500 94,500.00 33,075.00
Bahan
Kayu Kamper Balok 2.2.2.20 m3 1.1000 10,450,000.00 11,495,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,588,425.00 11,529,150.00 - 14,117,575.00
Overhead dan profit 0.1400 362,379.50 1,614,081.00 - 1,976,460.50
2,950,804.50 13,143,231.00 - 16,094,035.50

A.4.6.1.1c 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu balau
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 7.0000 68,500.00 479,500.00
Tukang kayu 1.2.7.19 oh 21.0000 89,500.00 1,879,500.00
Kepala Tukang 1.2.7.3 oh 2.1000 93,500.00 196,350.00
Mandor 1.2.7.5 oh 0.3500 94,500.00 33,075.00
Bahan
Kayu Balau Balok 2.2.2.13 m3 1.1000 10,725,000.00 11,797,500.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,588,425.00 11,831,650.00 - 14,420,075.00
Overhead dan profit 0.1400 362,379.50 1,656,431.00 - 2,018,810.50
2,950,804.50 13,488,081.00 - 16,438,885.50

A.4.6.1.1d 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu kempas
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 7.0000 68,500.00 479,500.00
Tukang kayu 1.2.7.19 oh 21.0000 89,500.00 1,879,500.00
Kepala Tukang 1.2.7.3 oh 2.1000 93,500.00 196,350.00
Mandor 1.2.7.5 oh 0.3500 94,500.00 33,075.00
Bahan
Kayu Kempas Balok 2.2.2.28 m3 1.1000 7,425,000.00 8,167,500.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,588,425.00 8,201,650.00 - 10,790,075.00
Overhead dan profit 0.1400 362,379.50 1,148,231.00 - 1,510,610.50
2,950,804.50 9,349,881.00 - 12,300,685.50

A.4.6.1.1e 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu kruing
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 7.0000 68,500.00 479,500.00
Tukang kayu 1.2.7.19 oh 21.0000 89,500.00 1,879,500.00
Kepala Tukang 1.2.7.3 oh 2.1000 93,500.00 196,350.00
Mandor 1.2.7.5 oh 0.3500 94,500.00 33,075.00
Bahan
Kayu Kruing Balok 2.2.2.30 m3 1.1000 6,875,000.00 7,562,500.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,588,425.00 7,596,650.00 - 10,185,075.00
Overhead dan profit 0.1400 362,379.50 1,063,531.00 - 1,425,910.50
2,950,804.50 8,660,181.00 - 11,610,985.50

A.4.6.1.1f 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu meranti
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 7.0000 68,500.00 479,500.00
Tukang kayu 1.2.7.19 oh 21.0000 89,500.00 1,879,500.00
Kepala Tukang 1.2.7.3 oh 2.1000 93,500.00 196,350.00
Mandor 1.2.7.5 oh 0.3500 94,500.00 33,075.00
Bahan
Kayu Meranti Balok 2.2.2.32 m3 1.1000 5,500,000.00 6,050,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,588,425.00 6,084,150.00 - 8,672,575.00
Overhead dan profit 0.1400 362,379.50 851,781.00 - 1,214,160.50
2,950,804.50 6,935,931.00 - 9,886,735.50

A.4.6.1.1g 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu tahun ( mahuni/akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 7.0000 68,500.00 479,500.00

73
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang kayu 1.2.7.19 oh 21.0000 89,500.00 1,879,500.00
Kepala Tukang 1.2.7.3 oh 2.1000 93,500.00 196,350.00
Mandor 1.2.7.5 oh 0.3500 94,500.00 33,075.00
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 1.1000 4,950,000.00 5,445,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,588,425.00 5,479,150.00 - 8,067,575.00
Overhead dan profit 0.1400 362,379.50 767,081.00 - 1,129,460.50
2,950,804.50 6,246,231.00 - 9,197,035.50

A.4.6.1.2 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.0000 68,500.00 411,000.00
Tukang kayu 1.2.7.19 oh 18.0000 89,500.00 1,611,000.00
Kepala Tukang 1.2.7.3 oh 1.8000 93,500.00 168,300.00
Mandor 1.2.7.5 oh 0.3000 94,500.00 28,350.00
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 1.2000 30,800,000.00 36,960,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,218,650.00 36,994,150.00 - 39,212,800.00
Overhead dan profit 0.1400 310,611.00 5,179,181.00 - 5,489,792.00
2,529,261.00 42,173,331.00 - 44,702,592.00

A.4.6.1.2a 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu jati lokal
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.0000 68,500.00 411,000.00
Tukang kayu 1.2.7.19 oh 18.0000 89,500.00 1,611,000.00
Kepala Tukang 1.2.7.3 oh 1.8000 93,500.00 168,300.00
Mandor 1.2.7.5 oh 0.3000 94,500.00 28,350.00
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 1.2000 20,900,000.00 25,080,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,218,650.00 25,114,150.00 - 27,332,800.00
Overhead dan profit 0.1400 310,611.00 3,515,981.00 - 3,826,592.00
2,529,261.00 28,630,131.00 - 31,159,392.00

A.4.6.1.2b 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu kamfer
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.0000 68,500.00 411,000.00
Tukang kayu 1.2.7.19 oh 18.0000 89,500.00 1,611,000.00
Kepala Tukang 1.2.7.3 oh 1.8000 93,500.00 168,300.00
Mandor 1.2.7.5 oh 0.3000 94,500.00 28,350.00
Bahan
Kayu Kamper Balok 2.2.2.20 m3 1.2000 10,450,000.00 12,540,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,218,650.00 12,574,150.00 - 14,792,800.00
Overhead dan profit 0.1400 310,611.00 1,760,381.00 - 2,070,992.00
2,529,261.00 14,334,531.00 - 16,863,792.00

A.4.6.1.2c 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu balau
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.0000 68,500.00 411,000.00
Tukang kayu 1.2.7.19 oh 18.0000 89,500.00 1,611,000.00
Kepala Tukang 1.2.7.3 oh 1.8000 93,500.00 168,300.00
Mandor 1.2.7.5 oh 0.3000 94,500.00 28,350.00
Bahan
Kayu Balau Balok 2.2.2.13 m3 1.2000 10,725,000.00 12,870,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,218,650.00 12,904,150.00 - 15,122,800.00
Overhead dan profit 0.1400 310,611.00 1,806,581.00 - 2,117,192.00
2,529,261.00 14,710,731.00 - 17,239,992.00

A.4.6.1.2d 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu kempas
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.0000 68,500.00 411,000.00
Tukang kayu 1.2.7.19 oh 18.0000 89,500.00 1,611,000.00
Kepala Tukang 1.2.7.3 oh 1.8000 93,500.00 168,300.00
Mandor 1.2.7.5 oh 0.3000 94,500.00 28,350.00
Bahan
Kayu Kempas Balok 2.2.2.28 m3 1.2000 7,425,000.00 8,910,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,218,650.00 8,944,150.00 - 11,162,800.00
Overhead dan profit 0.1400 310,611.00 1,252,181.00 - 1,562,792.00

74
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
2,529,261.00 10,196,331.00 - 12,725,592.00

A.4.6.1.2e 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu kruing
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.0000 68,500.00 411,000.00
Tukang kayu 1.2.7.19 oh 18.0000 89,500.00 1,611,000.00
Kepala Tukang 1.2.7.3 oh 1.8000 93,500.00 168,300.00
Mandor 1.2.7.5 oh 0.3000 94,500.00 28,350.00
Bahan
Kayu Kruing Balok 2.2.2.30 m3 1.2000 6,875,000.00 8,250,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,218,650.00 8,284,150.00 - 10,502,800.00
Overhead dan profit 0.1400 310,611.00 1,159,781.00 - 1,470,392.00
2,529,261.00 9,443,931.00 - 11,973,192.00

A.4.6.1.2f 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu meranti
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.0000 68,500.00 411,000.00
Tukang kayu 1.2.7.19 oh 18.0000 89,500.00 1,611,000.00
Kepala Tukang 1.2.7.3 oh 1.8000 93,500.00 168,300.00
Mandor 1.2.7.5 oh 0.3000 94,500.00 28,350.00
Bahan
Kayu Meranti Balok 2.2.2.32 m3 1.2000 5,500,000.00 6,600,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,218,650.00 6,634,150.00 - 8,852,800.00
Overhead dan profit 0.1400 310,611.00 928,781.00 - 1,239,392.00
2,529,261.00 7,562,931.00 - 10,092,192.00

A.4.6.1.2g 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.0000 68,500.00 411,000.00
Tukang kayu 1.2.7.19 oh 18.0000 89,500.00 1,611,000.00
Kepala Tukang 1.2.7.3 oh 1.8000 93,500.00 168,300.00
Mandor 1.2.7.5 oh 0.3000 94,500.00 28,350.00
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 1.2000 4,950,000.00 5,940,000.00
Paku biasa 2.2.12.1 kg 1.2500 16,200.00 20,250.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 1.0000 13,900.00 13,900.00
2,218,650.00 5,974,150.00 - 8,192,800.00
Overhead dan profit 0.1400 310,611.00 836,381.00 - 1,146,992.00
2,529,261.00 6,810,531.00 - 9,339,792.00

A.4.6.1.3 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0400 36,850,000.00 1,474,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 1,474,810.00 - 1,604,278.50
Overhead dan profit 0.1400 18,125.59 206,473.40 - 224,598.99
147,594.09 1,681,283.40 - 1,828,877.49

A.4.6.1.3a 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu Jati


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu jati papan lokal 2.2.2.19 m3 0.0400 22,550,000.00 902,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 902,810.00 - 1,032,278.50
Overhead dan profit 0.1400 18,125.59 126,393.40 - 144,518.99
147,594.09 1,029,203.40 - 1,176,797.49

A.4.6.1.3b 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0400 11,550,000.00 462,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 462,810.00 - 592,278.50

75
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 18,125.59 64,793.40 - 82,918.99
147,594.09 527,603.40 - 675,197.49

A.4.6.1.3c 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0400 11,825,000.00 473,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 473,810.00 - 603,278.50
Overhead dan profit 0.1400 18,125.59 66,333.40 - 84,458.99
147,594.09 540,143.40 - 687,737.49

A.4.6.1.3d 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0400 8,525,000.00 341,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 341,810.00 - 471,278.50
Overhead dan profit 0.1400 18,125.59 47,853.40 - 65,978.99
147,594.09 389,663.40 - 537,257.49

A.4.6.1.3e 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0400 7,975,000.00 319,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 319,810.00 - 449,278.50
Overhead dan profit 0.1400 18,125.59 44,773.40 - 62,898.99
147,594.09 364,583.40 - 512,177.49

A.4.6.1.3f 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0400 6,050,000.00 242,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 242,810.00 - 372,278.50
Overhead dan profit 0.1400 18,125.59 33,993.40 - 52,118.99
147,594.09 276,803.40 - 424,397.49

A.4.6.1.3g 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0400 5,225,000.00 209,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 209,810.00 - 339,278.50
Overhead dan profit 0.1400 18,125.59 29,373.40 - 47,498.99
147,594.09 239,183.40 - 386,777.49

A.4.6.1.4 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0400 36,850,000.00 1,474,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 1,474,810.00 - 1,604,278.50
Overhead dan profit 0.1400 18,125.59 206,473.40 - 224,598.99
147,594.09 1,681,283.40 - 1,828,877.49

76
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.4.6.1.4a 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu Jati


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu jati papan lokal 2.2.2.19 m3 0.0400 22,550,000.00 902,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 902,810.00 - 1,032,278.50
Overhead dan profit 0.1400 18,125.59 126,393.40 - 144,518.99
147,594.09 1,029,203.40 - 1,176,797.49

A.4.6.1.4b 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0400 11,550,000.00 462,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 462,810.00 - 592,278.50
Overhead dan profit 0.1400 18,125.59 64,793.40 - 82,918.99
147,594.09 527,603.40 - 675,197.49

A.4.6.1.4c 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0400 11,825,000.00 473,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 473,810.00 - 603,278.50
Overhead dan profit 0.1400 18,125.59 66,333.40 - 84,458.99
147,594.09 540,143.40 - 687,737.49

A.4.6.1.4d 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0400 8,525,000.00 341,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 341,810.00 - 471,278.50
Overhead dan profit 0.1400 18,125.59 47,853.40 - 65,978.99
147,594.09 389,663.40 - 537,257.49

A.4.6.1.4e 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0400 7,975,000.00 319,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 319,810.00 - 449,278.50
Overhead dan profit 0.1400 18,125.59 44,773.40 - 62,898.99
147,594.09 364,583.40 - 512,177.49

A.4.6.1.4f 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0400 6,050,000.00 242,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 242,810.00 - 372,278.50
Overhead dan profit 0.1400 18,125.59 33,993.40 - 52,118.99
147,594.09 276,803.40 - 424,397.49

A.4.6.1.4g 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu tahun ( mauni / akasia )

77
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3500 68,500.00 23,975.00
Tukang kayu 1.2.7.19 oh 1.0500 89,500.00 93,975.00
Kepala Tukang 1.2.7.3 oh 0.1050 93,500.00 9,817.50
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0400 5,225,000.00 209,000.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
129,468.50 209,810.00 - 339,278.50
Overhead dan profit 0.1400 18,125.59 29,373.40 - 47,498.99
147,594.09 239,183.40 - 386,777.49

A.4.6.1.5 1 m2 Pembuatan dan pemasangan pintu panel, kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0400 36,850,000.00 1,474,000.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.0500 13,900.00 695.00
369,775.00 1,474,695.00 - 1,844,470.00
Overhead dan profit 0.1400 51,768.50 206,457.30 - 258,225.80
421,543.50 1,681,152.30 - 2,102,695.80

A.4.6.1.5a 1 m2 Pembuatan dan pemasangan pintu panel, kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0400 22,550,000.00 902,000.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.0500 13,900.00 695.00
369,775.00 902,695.00 - 1,272,470.00
Overhead dan profit 0.1400 51,768.50 126,377.30 - 178,145.80
421,543.50 1,029,072.30 - 1,450,615.80

A.4.6.1.5b 1 m2 Pembuatan dan pemasangan pintu panel, kayu kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0400 11,550,000.00 462,000.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.0500 13,900.00 695.00
369,775.00 462,695.00 - 832,470.00
Overhead dan profit 0.1400 51,768.50 64,777.30 - 116,545.80
421,543.50 527,472.30 - 949,015.80

A.4.6.1.5c 1 m2 Pembuatan dan pemasangan pintu panel, kayu balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0400 11,825,000.00 473,000.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.0500 13,900.00 695.00
369,775.00 473,695.00 - 843,470.00
Overhead dan profit 0.1400 51,768.50 66,317.30 - 118,085.80
421,543.50 540,012.30 - 961,555.80

A.4.6.1.5d 1 m2 Pembuatan dan pemasangan pintu panel, kayu kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0400 8,525,000.00 341,000.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.0500 13,900.00 695.00
369,775.00 341,695.00 - 711,470.00
Overhead dan profit 0.1400 51,768.50 47,837.30 - 99,605.80
421,543.50 389,532.30 - 811,075.80

A.4.6.1.5e 1 m2 Pembuatan dan pemasangan pintu panel, kayu kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00

78
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0400 7,975,000.00 319,000.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.0500 13,900.00 695.00
369,775.00 319,695.00 - 689,470.00
Overhead dan profit 0.1400 51,768.50 44,757.30 - 96,525.80
421,543.50 364,452.30 - 785,995.80

A.4.6.1.5f 1 m2 Pembuatan dan pemasangan pintu panel, kayu meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0400 6,050,000.00 242,000.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.0500 13,900.00 695.00
369,775.00 242,695.00 - 612,470.00
Overhead dan profit 0.1400 51,768.50 33,977.30 - 85,745.80
421,543.50 276,672.30 - 698,215.80

A.4.6.1.5g 1 m2 Pembuatan dan pemasangan pintu panel, kayu tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0400 5,225,000.00 209,000.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.0500 13,900.00 695.00
369,775.00 209,695.00 - 579,470.00
Overhead dan profit 0.1400 51,768.50 29,357.30 - 81,125.80
421,543.50 239,052.30 - 660,595.80

A.4.6.1.6 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0240 36,850,000.00 884,400.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
295,820.00 888,570.00 - 1,184,390.00
Overhead dan profit 0.1400 41,414.80 124,399.80 - 165,814.60
337,234.80 1,012,969.80 - 1,350,204.60

A.4.6.1.6a 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu Jati lokal
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0240 22,550,000.00 541,200.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
295,820.00 545,370.00 - 841,190.00
Overhead dan profit 0.1400 41,414.80 76,351.80 - 117,766.60
337,234.80 621,721.80 - 958,956.60

A.4.6.1.6b 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu kamfer
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0240 11,550,000.00 277,200.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
295,820.00 281,370.00 - 577,190.00
Overhead dan profit 0.1400 41,414.80 39,391.80 - 80,806.60
337,234.80 320,761.80 - 657,996.60

A.4.6.1.6c 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu balau
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00

79
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0240 11,825,000.00 283,800.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
295,820.00 287,970.00 - 583,790.00
Overhead dan profit 0.1400 41,414.80 40,315.80 - 81,730.60
337,234.80 328,285.80 - 665,520.60

A.4.6.1.6d 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu kempas
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0240 8,525,000.00 204,600.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
295,820.00 208,770.00 - 504,590.00
Overhead dan profit 0.1400 41,414.80 29,227.80 - 70,642.60
337,234.80 237,997.80 - 575,232.60

A.4.6.1.6e 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu kruing
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0240 7,975,000.00 191,400.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
295,820.00 195,570.00 - 491,390.00
Overhead dan profit 0.1400 41,414.80 27,379.80 - 68,794.60
337,234.80 222,949.80 - 560,184.60

A.4.6.1.6f 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu meranti
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0240 6,050,000.00 145,200.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
295,820.00 149,370.00 - 445,190.00
Overhead dan profit 0.1400 41,414.80 20,911.80 - 62,326.60
337,234.80 170,281.80 - 507,516.60

A.4.6.1.6g 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu Tahun papan ( Mauni/akasia)
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0240 5,225,000.00 125,400.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
295,820.00 129,570.00 - 425,390.00
Overhead dan profit 0.1400 41,414.80 18,139.80 - 59,554.60
337,234.80 147,709.80 - 484,944.60

A.4.6.1.7 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu Jati papan eks. Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0640 36,850,000.00 2,358,400.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
369,775.00 2,365,350.00 - 2,735,125.00
Overhead dan profit 0.1400 51,768.50 331,149.00 - 382,917.50
421,543.50 2,696,499.00 - 3,118,042.50

A.4.6.1.7a 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu jati papan lokal
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan

80
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Kayu Jati Papan lokal 2.2.2.19 m3 0.0640 22,550,000.00 1,443,200.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
369,775.00 1,450,150.00 - 1,819,925.00
Overhead dan profit 0.1400 51,768.50 203,021.00 - 254,789.50
421,543.50 1,653,171.00 - 2,074,714.50

A.4.6.1.7b 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu kanfer
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0640 11,550,000.00 739,200.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
369,775.00 746,150.00 - 1,115,925.00
Overhead dan profit 0.1400 51,768.50 104,461.00 - 156,229.50
421,543.50 850,611.00 - 1,272,154.50

A.4.6.1.7c 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu balau
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0640 11,825,000.00 756,800.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
369,775.00 763,750.00 - 1,133,525.00
Overhead dan profit 0.1400 51,768.50 106,925.00 - 158,693.50
421,543.50 870,675.00 - 1,292,218.50

A.4.6.1.7d 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu kempas
Tenaga #N/A
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0640 8,525,000.00 545,600.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
369,775.00 552,550.00 - 922,325.00
Overhead dan profit 0.1400 51,768.50 77,357.00 - 129,125.50
421,543.50 629,907.00 - 1,051,450.50

A.4.6.1.7e 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu kruing
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0640 7,975,000.00 510,400.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
369,775.00 517,350.00 - 887,125.00
Overhead dan profit 0.1400 51,768.50 72,429.00 - 124,197.50
421,543.50 589,779.00 - 1,011,322.50

A.4.6.1.7f 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu meranti
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0640 6,050,000.00 387,200.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
369,775.00 394,150.00 - 763,925.00
Overhead dan profit 0.1400 51,768.50 55,181.00 - 106,949.50
421,543.50 449,331.00 - 870,874.50

A.4.6.1.7g 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang kayu 1.2.7.19 oh 3.0000 89,500.00 268,500.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0640 5,225,000.00 334,400.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00

81
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
369,775.00 341,350.00 - 711,125.00
Overhead dan profit 0.1400 51,768.50 47,789.00 - 99,557.50
421,543.50 389,139.00 - 810,682.50

A.4.6.1.8 1 m2 Pembuatan daun pintu plywood rangka kayu Jati eks Bojonegoro tertutup lebar sampai 90 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang kayu 1.2.7.19 oh 2.1000 89,500.00 187,950.00
Kepala Tukang 1.2.7.3 oh 0.2100 93,500.00 19,635.00
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0250 36,850,000.00 921,250.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
258,842.50 990,886.00 - 1,249,728.50
Overhead dan profit 0.1400 36,237.95 138,724.04 - 174,961.99
295,080.45 1,129,610.04 - 1,424,690.49

A.4.6.1.8a 1 m2 Pembuatan daun pintu plywood rangka kayu Jati lokal tertutup lebar sampai 90 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang kayu 1.2.7.19 oh 2.1000 89,500.00 187,950.00
Kepala Tukang 1.2.7.3 oh 0.2100 93,500.00 19,635.00
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0250 22,550,000.00 563,750.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
258,842.50 633,386.00 - 892,228.50
Overhead dan profit 0.1400 36,237.95 88,674.04 - 124,911.99
295,080.45 722,060.04 - 1,017,140.49

A.4.6.1.8b 1 m2 Pembuatan daun pintu plywood rangka kayu kamfer tertutup lebar sampai 90 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang kayu 1.2.7.19 oh 2.1000 89,500.00 187,950.00
Kepala Tukang 1.2.7.3 oh 0.2100 93,500.00 19,635.00
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0250 11,550,000.00 288,750.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
258,842.50 358,386.00 - 617,228.50
Overhead dan profit 0.1400 36,237.95 50,174.04 - 86,411.99
295,080.45 408,560.04 - 703,640.49

A.4.6.1.8c 1 m2 Pembuatan daun pintu plywood rangka kayu balau tertutup lebar sampai 90 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang kayu 1.2.7.19 oh 2.1000 89,500.00 187,950.00
Kepala Tukang 1.2.7.3 oh 0.2100 93,500.00 19,635.00
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0250 11,825,000.00 295,625.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
258,842.50 365,261.00 - 624,103.50
Overhead dan profit 0.1400 36,237.95 51,136.54 - 87,374.49
295,080.45 416,397.54 - 711,477.99

A.4.6.1.8d 1 m2 Pembuatan daun pintu plywood rangka kayu kempas tertutup lebar sampai 90 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang kayu 1.2.7.19 oh 2.1000 89,500.00 187,950.00
Kepala Tukang 1.2.7.3 oh 0.2100 93,500.00 19,635.00
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0250 8,525,000.00 213,125.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
258,842.50 282,761.00 - 541,603.50
Overhead dan profit 0.1400 36,237.95 39,586.54 - 75,824.49
295,080.45 322,347.54 - 617,427.99

A.4.6.1.8e 1 m2 Pembuatan daun pintu plywood rangka kayu kruing tertutup lebar sampai 90 Cm

82
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang kayu 1.2.7.19 oh 2.1000 89,500.00 187,950.00
Kepala Tukang 1.2.7.3 oh 0.2100 93,500.00 19,635.00
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0250 7,975,000.00 199,375.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
258,842.50 269,011.00 - 527,853.50
Overhead dan profit 0.1400 36,237.95 37,661.54 - 73,899.49
295,080.45 306,672.54 - 601,752.99

A.4.6.1.8f 1 m2 Pembuatan daun pintu plywood rangka kayu meranti tertutup lebar sampai 90 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang kayu 1.2.7.19 oh 2.1000 89,500.00 187,950.00
Kepala Tukang 1.2.7.3 oh 0.2100 93,500.00 19,635.00
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0250 6,050,000.00 151,250.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
258,842.50 220,886.00 - 479,728.50
Overhead dan profit 0.1400 36,237.95 30,924.04 - 67,161.99
295,080.45 251,810.04 - 546,890.49

A.4.6.1.8g 1 m2 Pembuatan daun pintu plywood rangka kayu tahun ( mauni / akasia ) tertutup lebar sampai 90 Cm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.7000 68,500.00 47,950.00
Tukang kayu 1.2.7.19 oh 2.1000 89,500.00 187,950.00
Kepala Tukang 1.2.7.3 oh 0.2100 93,500.00 19,635.00
Mandor 1.2.7.5 oh 0.0350 94,500.00 3,307.50
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0250 5,225,000.00 130,625.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
258,842.50 200,261.00 - 459,103.50
Overhead dan profit 0.1400 36,237.95 28,036.54 - 64,274.49
295,080.45 228,297.54 - 523,377.99

A.4.6.1.9 1 m2 Pembuatan daun pintu plywood rangka expose kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0560 36,850,000.00 2,063,600.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
295,820.00 2,133,236.00 - 2,429,056.00
Overhead dan profit 0.1400 41,414.80 298,653.04 - 340,067.84
337,234.80 2,431,889.04 - 2,769,123.84

A.4.6.1.9a 1 m2 Pembuatan daun pintu plywood rangka expose kayu Jati lokal
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0560 22,550,000.00 1,262,800.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
295,820.00 1,332,436.00 - 1,628,256.00
Overhead dan profit 0.1400 41,414.80 186,541.04 - 227,955.84
337,234.80 1,518,977.04 - 1,856,211.84

A.4.6.1.9b 1 m2 Pembuatan daun pintu plywood rangka expose kayu kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00

83
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0560 11,550,000.00 646,800.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
295,820.00 716,436.00 - 1,012,256.00
Overhead dan profit 0.1400 41,414.80 100,301.04 - 141,715.84
337,234.80 816,737.04 - 1,153,971.84

A.4.6.1.9c 1 m2 Pembuatan daun pintu plywood rangka expose kayu balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0560 11,825,000.00 662,200.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
295,820.00 731,836.00 - 1,027,656.00
Overhead dan profit 0.1400 41,414.80 102,457.04 - 143,871.84
337,234.80 834,293.04 - 1,171,527.84

A.4.6.1.9d 1 m2 Pembuatan daun pintu plywood rangka expose kayu kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0560 8,525,000.00 477,400.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
295,820.00 547,036.00 - 842,856.00
Overhead dan profit 0.1400 41,414.80 76,585.04 - 117,999.84
337,234.80 623,621.04 - 960,855.84

A.4.6.1.9e 1 m2 Pembuatan daun pintu plywood rangka expose kayu kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0560 7,975,000.00 446,600.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
295,820.00 516,236.00 - 812,056.00
Overhead dan profit 0.1400 41,414.80 72,273.04 - 113,687.84
337,234.80 588,509.04 - 925,743.84

A.4.6.1.9f 1 m2 Pembuatan daun pintu plywood rangka expose kayu meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0560 6,050,000.00 338,800.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00
295,820.00 408,436.00 - 704,256.00
Overhead dan profit 0.1400 41,414.80 57,181.04 - 98,595.84
337,234.80 465,617.04 - 802,851.84

A.4.6.1.9g 1 m2 Pembuatan daun pintu plywood rangka expose kayu tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0560 5,225,000.00 292,600.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5000 13,900.00 6,950.00
Plywood ( 90 x 220 ) cm, tbl. 4 mm 2.2.3.214 lbr 1.0000 62,200.00 62,200.00

84
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
295,820.00 362,236.00 - 658,056.00
Overhead dan profit 0.1400 41,414.80 50,713.04 - 92,127.84
337,234.80 412,949.04 - 750,183.84

A.4.6.1.10 1 m2 Pemasangan jalusi kusen, kayu Jati eks Bojonegoro


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6700 68,500.00 45,895.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.2000 93,500.00 18,700.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0600 36,850,000.00 2,211,000.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
275,252.50 2,213,430.00 - 2,488,682.50
Overhead dan profit 0.1400 38,535.35 309,880.20 - 348,415.55
313,787.85 2,523,310.20 - 2,837,098.05

A.4.6.1.10a 1 m2 Pemasangan jalusi kusen, kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6700 68,500.00 45,895.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.2000 93,500.00 18,700.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0600 22,550,000.00 1,353,000.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
275,252.50 1,355,430.00 - 1,630,682.50
Overhead dan profit 0.1400 38,535.35 189,760.20 - 228,295.55
313,787.85 1,545,190.20 - 1,858,978.05

A.4.6.1.10b 1 m2 Pemasangan jalusi kusen, kayu kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6700 68,500.00 45,895.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.2000 93,500.00 18,700.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0600 11,550,000.00 693,000.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
275,252.50 695,430.00 - 970,682.50
Overhead dan profit 0.1400 38,535.35 97,360.20 - 135,895.55
313,787.85 792,790.20 - 1,106,578.05

A.4.6.1.10c 1 m2 Pemasangan jalusi kusen, kayu balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6700 68,500.00 45,895.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.2000 93,500.00 18,700.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0600 11,825,000.00 709,500.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
275,252.50 711,930.00 - 987,182.50
Overhead dan profit 0.1400 38,535.35 99,670.20 - 138,205.55
313,787.85 811,600.20 - 1,125,388.05

A.4.6.1.10d 1 m2 Pemasangan jalusi kusen, kayu kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6700 68,500.00 45,895.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.2000 93,500.00 18,700.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0600 8,525,000.00 511,500.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
275,252.50 513,930.00 - 789,182.50
Overhead dan profit 0.1400 38,535.35 71,950.20 - 110,485.55
313,787.85 585,880.20 - 899,668.05

A.4.6.1.10e 1 m2 Pemasangan jalusi kusen, kayu kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6700 68,500.00 45,895.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.2000 93,500.00 18,700.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0600 7,975,000.00 478,500.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
275,252.50 480,930.00 - 756,182.50
Overhead dan profit 0.1400 38,535.35 67,330.20 - 105,865.55

85
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
313,787.85 548,260.20 - 862,048.05

A.4.6.1.10f 1 m2 Pemasangan jalusi kusen, kayu meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6700 68,500.00 45,895.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.2000 93,500.00 18,700.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0600 6,050,000.00 363,000.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
275,252.50 365,430.00 - 640,682.50
Overhead dan profit 0.1400 38,535.35 51,160.20 - 89,695.55
313,787.85 416,590.20 - 730,378.05

A.4.6.1.10g 1 m2 Pemasangan jalusi kusen, kayu tahun ( mauni / akasia )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6700 68,500.00 45,895.00
Tukang kayu 1.2.7.19 oh 2.0000 89,500.00 179,000.00
Kepala Tukang 1.2.7.3 oh 0.2000 93,500.00 18,700.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0600 5,225,000.00 313,500.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
275,252.50 315,930.00 - 591,182.50
Overhead dan profit 0.1400 38,535.35 44,230.20 - 82,765.55
313,787.85 360,160.20 - 673,948.05

A.4.6.1.11 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0250 36,850,000.00 921,250.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
295,820.00 1,006,206.00 - 1,302,026.00
Overhead dan profit 0.1400 41,414.80 140,868.84 - 182,283.64
337,234.80 1,147,074.84 - 1,484,309.64

A.4.6.1.11a 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0250 22,550,000.00 563,750.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
295,820.00 648,706.00 - 944,526.00
Overhead dan profit 0.1400 41,414.80 90,818.84 - 132,233.64
337,234.80 739,524.84 - 1,076,759.64

A.4.6.1.11b 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0250 11,550,000.00 288,750.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
295,820.00 373,706.00 - 669,526.00
Overhead dan profit 0.1400 41,414.80 52,318.84 - 93,733.64
337,234.80 426,024.84 - 763,259.64

A.4.6.1.11c 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan

86
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Kayu Balau Papan 2.2.2.14 m3 0.0250 11,825,000.00 295,625.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
295,820.00 380,581.00 - 676,401.00
Overhead dan profit 0.1400 41,414.80 53,281.34 - 94,696.14
337,234.80 433,862.34 - 771,097.14

A.4.6.1.11d 1 m2 Pemasangan teakwood rangkap, rangka expose kayu kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0250 8,525,000.00 213,125.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
295,820.00 298,081.00 - 593,901.00
Overhead dan profit 0.1400 41,414.80 41,731.34 - 83,146.14
337,234.80 339,812.34 - 677,047.14

A.4.6.1.11e 1 m2 Pemasangan teakwood rangkap, rangka expose kayu kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0250 7,975,000.00 199,375.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
295,820.00 284,331.00 - 580,151.00
Overhead dan profit 0.1400 41,414.80 39,806.34 - 81,221.14
337,234.80 324,137.34 - 661,372.14

A.4.6.1.11f 1 m2 Pemasangan teakwood rangkap, rangka expose kayu meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0250 6,050,000.00 151,250.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
295,820.00 236,206.00 - 532,026.00
Overhead dan profit 0.1400 41,414.80 33,068.84 - 74,483.64
337,234.80 269,274.84 - 606,509.64

A.4.6.1.11g 1 m2 Pemasangan teakwood rangkap, rangka expose kayu tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8000 68,500.00 54,800.00
Tukang kayu 1.2.7.19 oh 2.4000 89,500.00 214,800.00
Kepala Tukang 1.2.7.3 oh 0.2400 93,500.00 22,440.00
Mandor 1.2.7.5 oh 0.0400 94,500.00 3,780.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0250 5,225,000.00 130,625.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.3000 13,900.00 4,170.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
295,820.00 215,581.00 - 511,401.00
Overhead dan profit 0.1400 41,414.80 30,181.34 - 71,596.14
337,234.80 245,762.34 - 582,997.14
A.4.6.1.12 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8500 68,500.00 58,225.00
Tukang kayu 1.2.7.19 oh 2.5500 89,500.00 228,225.00
Kepala Tukang 1.2.7.3 oh 0.2550 93,500.00 23,842.50
Mandor 1.2.7.5 oh 0.0430 94,500.00 4,063.50
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0250 36,850,000.00 921,250.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.8000 13,900.00 11,120.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
Formika (120x240)cm 2.2.3.65 lbr 0.5000 275,000.00 137,500.00
314,356.00 1,150,656.00 - 1,465,012.00

87
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 44,009.84 161,091.84 - 205,101.68
358,365.84 1,311,747.84 - 1,670,113.68

A.4.6.1.12a 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Jati lokal
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8500 68,500.00 58,225.00
Tukang kayu 1.2.7.19 oh 2.5500 89,500.00 228,225.00
Kepala Tukang 1.2.7.3 oh 0.2550 93,500.00 23,842.50
Mandor 1.2.7.5 oh 0.0430 94,500.00 4,063.50
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0250 22,550,000.00 563,750.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.8000 13,900.00 11,120.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
Formika (120x240)cm 2.2.3.65 lbr 0.5000 275,000.00 137,500.00
314,356.00 793,156.00 - 1,107,512.00
Overhead dan profit 0.1400 44,009.84 111,041.84 - 155,051.68
358,365.84 904,197.84 - 1,262,563.68

A.4.6.1.12b 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Kamfer
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8500 68,500.00 58,225.00
Tukang kayu 1.2.7.19 oh 2.5500 89,500.00 228,225.00
Kepala Tukang 1.2.7.3 oh 0.2550 93,500.00 23,842.50
Mandor 1.2.7.5 oh 0.0430 94,500.00 4,063.50
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0250 11,550,000.00 288,750.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.8000 13,900.00 11,120.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
Formika (120x240)cm 2.2.3.65 lbr 0.5000 275,000.00 137,500.00
314,356.00 518,156.00 - 832,512.00
Overhead dan profit 0.1400 44,009.84 72,541.84 - 116,551.68
358,365.84 590,697.84 - 949,063.68

A.4.6.1.12c 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Balau
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8500 68,500.00 58,225.00
Tukang kayu 1.2.7.19 oh 2.5500 89,500.00 228,225.00
Kepala Tukang 1.2.7.3 oh 0.2550 93,500.00 23,842.50
Mandor 1.2.7.5 oh 0.0430 94,500.00 4,063.50
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0250 11,825,000.00 295,625.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.8000 13,900.00 11,120.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
Formika (120x240)cm 2.2.3.65 lbr 0.5000 275,000.00 137,500.00
314,356.00 525,031.00 - 839,387.00
Overhead dan profit 0.1400 44,009.84 73,504.34 - 117,514.18
358,365.84 598,535.34 - 956,901.18

A.4.6.1.12d 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Kempas
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8500 68,500.00 58,225.00
Tukang kayu 1.2.7.19 oh 2.5500 89,500.00 228,225.00
Kepala Tukang 1.2.7.3 oh 0.2550 93,500.00 23,842.50
Mandor 1.2.7.5 oh 0.0430 94,500.00 4,063.50
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0250 8,525,000.00 213,125.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.8000 13,900.00 11,120.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
Formika (120x240)cm 2.2.3.65 lbr 0.5000 275,000.00 137,500.00
314,356.00 442,531.00 - 756,887.00
Overhead dan profit 0.1400 44,009.84 61,954.34 - 105,964.18
358,365.84 504,485.34 - 862,851.18

A.4.6.1.12e 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Kruing
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8500 68,500.00 58,225.00
Tukang kayu 1.2.7.19 oh 2.5500 89,500.00 228,225.00
Kepala Tukang 1.2.7.3 oh 0.2550 93,500.00 23,842.50
Mandor 1.2.7.5 oh 0.0430 94,500.00 4,063.50
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0250 7,975,000.00 199,375.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.8000 13,900.00 11,120.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
Formika (120x240)cm 2.2.3.65 lbr 0.5000 275,000.00 137,500.00
314,356.00 428,781.00 - 743,137.00

88
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 44,009.84 60,029.34 - 104,039.18
358,365.84 488,810.34 - 847,176.18

A.4.6.1.12f 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Meranti
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8500 68,500.00 58,225.00
Tukang kayu 1.2.7.19 oh 2.5500 89,500.00 228,225.00
Kepala Tukang 1.2.7.3 oh 0.2550 93,500.00 23,842.50
Mandor 1.2.7.5 oh 0.0430 94,500.00 4,063.50
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0250 6,050,000.00 151,250.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.8000 13,900.00 11,120.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
Formika (120x240)cm 2.2.3.65 lbr 0.5000 275,000.00 137,500.00
314,356.00 380,656.00 - 695,012.00
Overhead dan profit 0.1400 44,009.84 53,291.84 - 97,301.68
358,365.84 433,947.84 - 792,313.68

A.4.6.1.12g 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.8500 68,500.00 58,225.00
Tukang kayu 1.2.7.19 oh 2.5500 89,500.00 228,225.00
Kepala Tukang 1.2.7.3 oh 0.2550 93,500.00 23,842.50
Mandor 1.2.7.5 oh 0.0430 94,500.00 4,063.50
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0250 5,225,000.00 130,625.00
Paku biasa 2.2.12.1 kg 0.0300 16,200.00 486.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.8000 13,900.00 11,120.00
Teakwood tebal 3mm (90 x 210) Cm 2.2.3.234 lbr 1.0000 80,300.00 80,300.00
Formika (120x240)cm 2.2.3.65 lbr 0.5000 275,000.00 137,500.00
314,356.00 360,031.00 - 674,387.00
Overhead dan profit 0.1400 44,009.84 50,404.34 - 94,414.18
358,365.84 410,435.34 - 768,801.18

A.4.6.1.13 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Jati Eks Bojonegoro bentang 6 meter
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 4.0000 68,500.00 274,000.00
Tukang kayu 1.2.7.19 oh 12.0000 89,500.00 1,074,000.00
Kepala Tukang 1.2.7.3 oh 1.2000 93,500.00 112,200.00
Mandor 1.2.7.5 oh 0.2000 94,500.00 18,900.00
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 1.1000 30,800,000.00 33,880,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
1,479,100.00 34,251,220.00 - 35,730,320.00
Overhead dan profit 0.1400 207,074.00 4,795,170.80 - 5,002,244.80
1,686,174.00 39,046,390.80 - 40,732,564.80

A.4.6.1.13a 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu lokal bentang 6 meter
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 4.0000 68,500.00 274,000.00
Tukang kayu 1.2.7.19 oh 12.0000 89,500.00 1,074,000.00
Kepala Tukang 1.2.7.3 oh 1.2000 93,500.00 112,200.00
Mandor 1.2.7.5 oh 0.2000 94,500.00 18,900.00
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 1.1000 20,900,000.00 22,990,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
1,479,100.00 23,361,220.00 - 24,840,320.00
Overhead dan profit 0.1400 207,074.00 3,270,570.80 - 3,477,644.80
1,686,174.00 26,631,790.80 - 28,317,964.80

A.4.6.1.13b 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Jati Kamfer bentang 6 meter
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 4.0000 68,500.00 274,000.00
Tukang kayu 1.2.7.19 oh 12.0000 89,500.00 1,074,000.00
Kepala Tukang 1.2.7.3 oh 1.2000 93,500.00 112,200.00
Mandor 1.2.7.5 oh 0.2000 94,500.00 18,900.00
Bahan
Kayu Kamper papan 2.2.2.21 m3 1.1000 11,550,000.00 12,705,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
1,479,100.00 13,076,220.00 - 14,555,320.00
Overhead dan profit 0.1400 207,074.00 1,830,670.80 - 2,037,744.80
1,686,174.00 14,906,890.80 - 16,593,064.80

A.4.6.1.13c 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Balau bentang 6 meter
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 4.0000 68,500.00 274,000.00

89
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang kayu 1.2.7.19 oh 12.0000 89,500.00 1,074,000.00
Kepala Tukang 1.2.7.3 oh 1.2000 93,500.00 112,200.00
Mandor 1.2.7.5 oh 0.2000 94,500.00 18,900.00
Bahan
Kayu Balau Balok 2.2.2.13 m3 1.1000 10,725,000.00 11,797,500.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
1,479,100.00 12,168,720.00 - 13,647,820.00
Overhead dan profit 0.1400 207,074.00 1,703,620.80 - 1,910,694.80
1,686,174.00 13,872,340.80 - 15,558,514.80

A.4.6.1.13d 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Kempas bentang 6 meter
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 4.0000 68,500.00 274,000.00
Tukang kayu 1.2.7.19 oh 12.0000 89,500.00 1,074,000.00
Kepala Tukang 1.2.7.3 oh 1.2000 93,500.00 112,200.00
Mandor 1.2.7.5 oh 0.2000 94,500.00 18,900.00
Bahan
Kayu Kempas Balok 2.2.2.28 m3 1.1000 7,425,000.00 8,167,500.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
1,479,100.00 8,538,720.00 - 10,017,820.00
Overhead dan profit 0.1400 207,074.00 1,195,420.80 - 1,402,494.80
1,686,174.00 9,734,140.80 - 11,420,314.80

A.4.6.1.13e 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Kruing bentang 6 meter
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 4.0000 68,500.00 274,000.00
Tukang kayu 1.2.7.19 oh 12.0000 89,500.00 1,074,000.00
Kepala Tukang 1.2.7.3 oh 1.2000 93,500.00 112,200.00
Mandor 1.2.7.5 oh 0.2000 94,500.00 18,900.00
Bahan
Kayu Kruing Balok 2.2.2.30 m3 1.1000 6,875,000.00 7,562,500.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
1,479,100.00 7,933,720.00 - 9,412,820.00
Overhead dan profit 0.1400 207,074.00 1,110,720.80 - 1,317,794.80
1,686,174.00 9,044,440.80 - 10,730,614.80

A.4.6.1.13f 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Meranti bentang 6 meter
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 4.0000 68,500.00 274,000.00
Tukang kayu 1.2.7.19 oh 12.0000 89,500.00 1,074,000.00
Kepala Tukang 1.2.7.3 oh 1.2000 93,500.00 112,200.00
Mandor 1.2.7.5 oh 0.2000 94,500.00 18,900.00
Bahan
Kayu Meranti Balok 2.2.2.32 m3 1.1000 5,500,000.00 6,050,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
1,479,100.00 6,421,220.00 - 7,900,320.00
Overhead dan profit 0.1400 207,074.00 898,970.80 - 1,106,044.80
1,686,174.00 7,320,190.80 - 9,006,364.80

A.4.6.1.13g 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu tahun ( mauni / akasia ) bentang 6 meter
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 4.0000 68,500.00 274,000.00
Tukang kayu 1.2.7.19 oh 12.0000 89,500.00 1,074,000.00
Kepala Tukang 1.2.7.3 oh 1.2000 93,500.00 112,200.00
Mandor 1.2.7.5 oh 0.2000 94,500.00 18,900.00
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 1.1000 4,950,000.00 5,445,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
1,479,100.00 5,816,220.00 - 7,295,320.00
Overhead dan profit 0.1400 207,074.00 814,270.80 - 1,021,344.80
1,686,174.00 6,630,490.80 - 8,316,664.80

A.4.6.1.14 1 m3 Pemasangan konstruksi kuda kuda expose kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 1.2000 30,800,000.00 36,960,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
2,477,492.50 37,331,220.00 - 39,808,712.50
Overhead dan profit 0.1400 346,848.95 5,226,370.80 - 5,573,219.75
2,824,341.45 42,557,590.80 - 45,381,932.25

90
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.4.6.1.14a 1 m3 Pemasangan konstruksi kuda kuda expose kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 1.2000 20,900,000.00 25,080,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
2,477,492.50 25,451,220.00 - 27,928,712.50
Overhead dan profit 0.1400 346,848.95 3,563,170.80 - 3,910,019.75
2,824,341.45 29,014,390.80 - 31,838,732.25

A.4.6.1.14b 1 m3 Pemasangan konstruksi kuda kuda expose kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Kamper Balok 2.2.2.20 m3 1.2000 10,450,000.00 12,540,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
2,477,492.50 12,911,220.00 - 15,388,712.50
Overhead dan profit 0.1400 346,848.95 1,807,570.80 - 2,154,419.75
2,824,341.45 14,718,790.80 - 17,543,132.25

A.4.6.1.14c 1 m3 Pemasangan konstruksi kuda kuda expose kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Balau Balok 2.2.2.13 m3 1.2000 10,725,000.00 12,870,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
2,477,492.50 13,241,220.00 - 15,718,712.50
Overhead dan profit 0.1400 346,848.95 1,853,770.80 - 2,200,619.75
2,824,341.45 15,094,990.80 - 17,919,332.25

A.4.6.1.14d 1 m3 Pemasangan konstruksi kuda kuda expose kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Kempas Balok 2.2.2.28 m3 1.2000 7,425,000.00 8,910,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
2,477,492.50 9,281,220.00 - 11,758,712.50
Overhead dan profit 0.1400 346,848.95 1,299,370.80 - 1,646,219.75
2,824,341.45 10,580,590.80 - 13,404,932.25

A.4.6.1.14e 1 m3 Pemasangan konstruksi kuda kuda expose kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Kruing Balok 2.2.2.30 m3 1.2000 6,875,000.00 8,250,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
2,477,492.50 8,621,220.00 - 11,098,712.50
Overhead dan profit 0.1400 346,848.95 1,206,970.80 - 1,553,819.75
2,824,341.45 9,828,190.80 - 12,652,532.25

A.4.6.1.14f 1 m3 Pemasangan konstruksi kuda kuda expose kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Meranti Balok 2.2.2.32 m3 1.2000 5,500,000.00 6,600,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00

91
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
2,477,492.50 6,971,220.00 - 9,448,712.50
Overhead dan profit 0.1400 346,848.95 975,970.80 - 1,322,819.75
2,824,341.45 7,947,190.80 - 10,771,532.25

A.4.6.1.14g 1 m3 Pemasangan konstruksi kuda kuda expose kayu Tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 1.2000 4,950,000.00 5,940,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 5.6000 16,200.00 90,720.00
2,477,492.50 6,311,220.00 - 8,788,712.50
Overhead dan profit 0.1400 346,848.95 883,570.80 - 1,230,419.75
2,824,341.45 7,194,790.80 - 10,019,132.25

A.4.6.1.15 1 m3 Pemasangan konstruksi gordeng, kayu Jati eks Bojonegoro


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 1.1000 30,800,000.00 33,880,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 3.0000 16,200.00 48,600.00
2,477,492.50 34,209,100.00 - 36,686,592.50
Overhead dan profit 0.1400 346,848.95 4,789,274.00 - 5,136,122.95
2,824,341.45 38,998,374.00 - 41,822,715.45

A.4.6.1.15a 1 m3 Pemasangan konstruksi gordeng, kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 1.1000 20,900,000.00 22,990,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 3.0000 16,200.00 48,600.00
2,477,492.50 23,319,100.00 - 25,796,592.50
Overhead dan profit 0.1400 346,848.95 3,264,674.00 - 3,611,522.95
2,824,341.45 26,583,774.00 - 29,408,115.45

A.4.6.1.15b 1 m3 Pemasangan konstruksi gordeng, kayu kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Kamper Balok 2.2.2.20 m3 1.1000 10,450,000.00 11,495,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 3.0000 16,200.00 48,600.00
2,477,492.50 11,824,100.00 - 14,301,592.50
Overhead dan profit 0.1400 346,848.95 1,655,374.00 - 2,002,222.95
2,824,341.45 13,479,474.00 - 16,303,815.45

A.4.6.1.15c 1 m3 Pemasangan konstruksi gordeng, kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Balau Balok 2.2.2.13 m3 1.1000 10,725,000.00 11,797,500.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 3.0000 16,200.00 48,600.00
2,477,492.50 12,126,600.00 - 14,604,092.50
Overhead dan profit 0.1400 346,848.95 1,697,724.00 - 2,044,572.95
2,824,341.45 13,824,324.00 - 16,648,665.45

A.4.6.1.15d 1 m3 Pemasangan konstruksi gordeng, kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00

92
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Kempas Balok 2.2.2.28 m3 1.1000 7,425,000.00 8,167,500.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 3.0000 16,200.00 48,600.00
2,477,492.50 8,496,600.00 - 10,974,092.50
Overhead dan profit 0.1400 346,848.95 1,189,524.00 - 1,536,372.95
2,824,341.45 9,686,124.00 - 12,510,465.45

A.4.6.1.15e 1 m3 Pemasangan konstruksi gordeng, kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Kruing Balok 2.2.2.30 m3 1.1000 6,875,000.00 7,562,500.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 3.0000 16,200.00 48,600.00
2,477,492.50 7,891,600.00 - 10,369,092.50
Overhead dan profit 0.1400 346,848.95 1,104,824.00 - 1,451,672.95
2,824,341.45 8,996,424.00 - 11,820,765.45

A.4.6.1.15f 1 m3 Pemasangan konstruksi gordeng, kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Meranti Balok 2.2.2.32 m3 1.1000 5,500,000.00 6,050,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 3.0000 16,200.00 48,600.00
2,477,492.50 6,379,100.00 - 8,856,592.50
Overhead dan profit 0.1400 346,848.95 893,074.00 - 1,239,922.95
2,824,341.45 7,272,174.00 - 10,096,515.45

A.4.6.1.15g 1 m3 Pemasangan konstruksi gordeng, kayu Tahun ( mauni / akasia )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.7000 68,500.00 458,950.00
Tukang kayu 1.2.7.19 oh 20.1000 89,500.00 1,798,950.00
Kepala Tukang 1.2.7.3 oh 2.0100 93,500.00 187,935.00
Mandor 1.2.7.5 oh 0.3350 94,500.00 31,657.50
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 1.1000 4,950,000.00 5,445,000.00
Besi strip + Mur Baut 2.2.4.17 kg 15.0000 18,700.00 280,500.00
Paku biasa 2.2.12.1 kg 3.0000 16,200.00 48,600.00
2,477,492.50 5,774,100.00 - 8,251,592.50
Overhead dan profit 0.1400 346,848.95 808,374.00 - 1,155,222.95
2,824,341.45 6,582,474.00 - 9,406,815.45

A.4.6.1.16 1 m2 Pemasangan rangka atap genteng keramik, kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0140 30,800,000.00 431,200.00
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0036 30,800,000.00 110,880.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 546,130.00 - 563,337.50
Overhead dan profit 0.1400 2,409.05 76,458.20 - 78,867.25
19,616.55 622,588.20 - 642,204.75

A.4.6.1.16a 1 m2 Pemasangan rangka atap genteng keramik, kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 0.0140 20,900,000.00 292,600.00
Kayu Jati Balok lokal 2.2.2.17 m3 0.0036 20,900,000.00 75,240.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 371,890.00 - 389,097.50
Overhead dan profit 0.1400 2,409.05 52,064.60 - 54,473.65
19,616.55 423,954.60 - 443,571.15

A.4.6.1.16b 1 m2 Pemasangan rangka atap genteng keramik, kayu Kamfer

93
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kamper Balok 2.2.2.20 m3 0.0140 10,450,000.00 146,300.00
Kayu Kamper Balok 2.2.2.20 m3 0.0036 10,450,000.00 37,620.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 187,970.00 - 205,177.50
Overhead dan profit 0.1400 2,409.05 26,315.80 - 28,724.85
19,616.55 214,285.80 - 233,902.35

A.4.6.1.16c 1 m2 Pemasangan rangka atap genteng keramik, kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Balau Balok 2.2.2.13 m3 0.0140 10,725,000.00 150,150.00
Kayu Balau Balok 2.2.2.13 m3 0.0036 10,725,000.00 38,610.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 192,810.00 - 210,017.50
Overhead dan profit 0.1400 2,409.05 26,993.40 - 29,402.45
19,616.55 219,803.40 - 239,419.95

A.4.6.1.16d 1 m2 Pemasangan rangka atap genteng keramik, kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kempas Balok 2.2.2.28 m3 0.0140 7,425,000.00 103,950.00
Kayu Kempas Balok 2.2.2.28 m3 0.0036 7,425,000.00 26,730.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 134,730.00 - 151,937.50
Overhead dan profit 0.1400 2,409.05 18,862.20 - 21,271.25
19,616.55 153,592.20 - 173,208.75

A.4.6.1.16e 1 m2 Pemasangan rangka atap genteng keramik, kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kruing Balok 2.2.2.30 m3 0.0140 6,875,000.00 96,250.00
Kayu Kruing Balok 2.2.2.30 m3 0.0036 6,875,000.00 24,750.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 125,050.00 - 142,257.50
Overhead dan profit 0.1400 2,409.05 17,507.00 - 19,916.05
19,616.55 142,557.00 - 162,173.55

A.4.6.1.16f 1 m2 Pemasangan rangka atap genteng keramik, kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Meranti Balok 2.2.2.32 m3 0.0140 5,500,000.00 77,000.00
Kayu Meranti Balok 2.2.2.32 m3 0.0036 5,500,000.00 19,800.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 100,850.00 - 118,057.50
Overhead dan profit 0.1400 2,409.05 14,119.00 - 16,528.05
19,616.55 114,969.00 - 134,585.55

A.4.6.1.16g 1 m2 Pemasangan rangka atap genteng keramik, kayu Tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0140 4,950,000.00 69,300.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0036 4,950,000.00 17,820.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 91,170.00 - 108,377.50

94
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 2,409.05 12,763.80 - 15,172.85
19,616.55 103,933.80 - 123,550.35

A.4.6.1.17 1 m2 Pemasangan rangka atap genteng beton, kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0140 30,800,000.00 431,200.00
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0057 30,800,000.00 175,560.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 610,810.00 - 628,017.50
Overhead dan profit 0.1400 2,409.05 85,513.40 - 87,922.45
19,616.55 696,323.40 - 715,939.95

A.4.6.1.17a 1 m2 Pemasangan rangka atap genteng beton, kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 0.0140 20,900,000.00 292,600.00
Kayu Jati Balok lokal 2.2.2.17 m3 0.0057 20,900,000.00 119,130.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 415,780.00 - 432,987.50
Overhead dan profit 0.1400 2,409.05 58,209.20 - 60,618.25
19,616.55 473,989.20 - 493,605.75

A.4.6.1.17b 1 m2 Pemasangan rangka atap genteng beton, kayu Kamper


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kamper Balok 2.2.2.20 m3 0.0140 10,450,000.00 146,300.00
Kayu Kamper Balok 2.2.2.20 m3 0.0057 10,450,000.00 59,565.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 209,915.00 - 227,122.50
Overhead dan profit 0.1400 2,409.05 29,388.10 - 31,797.15
19,616.55 239,303.10 - 258,919.65

A.4.6.1.17c 1 m2 Pemasangan rangka atap genteng beton, kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Balau Balok 2.2.2.13 m3 0.0140 10,725,000.00 150,150.00
Kayu Balau Balok 2.2.2.13 m3 0.0057 10,725,000.00 61,132.50
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 215,332.50 - 232,540.00
Overhead dan profit 0.1400 2,409.05 30,146.55 - 32,555.60
19,616.55 245,479.05 - 265,095.60

A.4.6.1.17d 1 m2 Pemasangan rangka atap genteng beton, kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kempas Balok 2.2.2.28 m3 0.0140 7,425,000.00 103,950.00
Kayu Kempas Balok 2.2.2.28 m3 0.0057 7,425,000.00 42,322.50
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 150,322.50 - 167,530.00
Overhead dan profit 0.1400 2,409.05 21,045.15 - 23,454.20
19,616.55 171,367.65 - 190,984.20

A.4.6.1.17e 1 m2 Pemasangan rangka atap genteng beton, kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan

95
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Kayu Kruing Balok 2.2.2.30 m3 0.0140 6,875,000.00 96,250.00
Kayu Kruing Balok 2.2.2.30 m3 0.0057 6,875,000.00 39,187.50
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 139,487.50 - 156,695.00
Overhead dan profit 0.1400 2,409.05 19,528.25 - 21,937.30
19,616.55 159,015.75 - 178,632.30

A.4.6.1.17f 1 m2 Pemasangan rangka atap genteng beton, kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Meranti Balok 2.2.2.32 m3 0.0140 5,500,000.00 77,000.00
Kayu Meranti Balok 2.2.2.32 m3 0.0057 5,500,000.00 31,350.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 112,400.00 - 129,607.50
Overhead dan profit 0.1400 2,409.05 15,736.00 - 18,145.05
19,616.55 128,136.00 - 147,752.55

A.4.6.1.17g 1 m2 Pemasangan rangka atap genteng beton, kayu Tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0140 4,950,000.00 69,300.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0057 4,950,000.00 28,215.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
17,207.50 101,565.00 - 118,772.50
Overhead dan profit 0.1400 2,409.05 14,219.10 - 16,628.15
19,616.55 115,784.10 - 135,400.65

A.4.6.1.18 1 m2 Pemasangan rangka atap sirap, kayu Jati eks Bojonegoro


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0140 30,800,000.00 431,200.00
Paku biasa 2.2.12.1 m3 0.0570 16,200.00 923.40
20,649.00 432,123.40 - 452,772.40
Overhead dan profit 0.1400 2,890.86 60,497.28 - 63,388.14
23,539.86 492,620.68 - 516,160.54

A.4.6.1.18a 1 m2 Pemasangan rangka atap sirap, kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 0.0140 20,900,000.00 292,600.00
Paku biasa 2.2.12.1 m3 0.0570 16,200.00 923.40
20,649.00 293,523.40 - 314,172.40
Overhead dan profit 0.1400 2,890.86 41,093.28 - 43,984.14
23,539.86 334,616.68 - 358,156.54

A.4.6.1.18b 1 m2 Pemasangan rangka atap sirap, kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Kayu Kamper Balok 2.2.2.20 m3 0.0140 10,450,000.00 146,300.00
Paku biasa 2.2.12.1 m3 0.0570 16,200.00 923.40
20,649.00 147,223.40 - 167,872.40
Overhead dan profit 0.1400 2,890.86 20,611.28 - 23,502.14
23,539.86 167,834.68 - 191,374.54

A.4.6.1.18c 1 m2 Pemasangan rangka atap sirap, kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00

96
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Bahan
Kayu Balau Balok 2.2.2.13 m3 0.0140 10,725,000.00 150,150.00
Paku biasa 2.2.12.1 m3 0.0570 16,200.00 923.40
20,649.00 151,073.40 - 171,722.40
Overhead dan profit 0.1400 2,890.86 21,150.28 - 24,041.14
23,539.86 172,223.68 - 195,763.54

A.4.6.1.18d 1 m2 Pemasangan rangka atap sirap, kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Kayu Kempas Balok 2.2.2.28 m3 0.0140 7,425,000.00 103,950.00
Paku biasa 2.2.12.1 m3 0.0570 16,200.00 923.40
20,649.00 104,873.40 - 125,522.40
Overhead dan profit 0.1400 2,890.86 14,682.28 - 17,573.14
23,539.86 119,555.68 - 143,095.54

A.4.6.1.18e 1 m2 Pemasangan rangka atap sirap, kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Kayu Kruing Balok 2.2.2.30 m3 0.0140 6,875,000.00 96,250.00
Paku biasa 2.2.12.1 m3 0.0570 16,200.00 923.40
20,649.00 97,173.40 - 117,822.40
Overhead dan profit 0.1400 2,890.86 13,604.28 - 16,495.14
23,539.86 110,777.68 - 134,317.54

A.4.6.1.18f 1 m2 Pemasangan rangka atap sirap, kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Kayu Meranti Balok 2.2.2.32 m3 0.0140 5,500,000.00 77,000.00
Paku biasa 2.2.12.1 m3 0.0570 16,200.00 923.40
20,649.00 77,923.40 - 98,572.40
Overhead dan profit 0.1400 2,890.86 10,909.28 - 13,800.14
23,539.86 88,832.68 - 112,372.54

A.4.6.1.18g 1 m2 Pemasangan rangka atap sirap, kayu Tahun ( mauni / akasia )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1200 68,500.00 8,220.00
Tukang kayu 1.2.7.19 oh 0.1200 89,500.00 10,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0140 4,950,000.00 69,300.00
Paku biasa 2.2.12.1 m3 0.0570 16,200.00 923.40
20,649.00 70,223.40 - 90,872.40
Overhead dan profit 0.1400 2,890.86 9,831.28 - 12,722.14
23,539.86 80,054.68 - 103,594.54

A.4.6.1.19 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0154 30,800,000.00 474,320.00
Paku biasa 2.2.12.1 kg 0.2000 16,200.00 3,240.00
47,017.50 477,560.00 - 524,577.50
Overhead dan profit 0.1400 6,582.45 66,858.40 - 73,440.85
53,599.95 544,418.40 - 598,018.35

A.4.6.1.19a 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 0.0154 20,900,000.00 321,860.00

97
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Paku biasa 2.2.12.1 kg 0.2000 16,200.00 3,240.00
47,017.50 325,100.00 - 372,117.50
Overhead dan profit 0.1400 6,582.45 45,514.00 - 52,096.45
53,599.95 370,614.00 - 424,213.95

A.4.6.1.19b 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Kayu Kamper Balok 2.2.2.20 m3 0.0154 10,450,000.00 160,930.00
Paku biasa 2.2.12.1 kg 0.2000 16,200.00 3,240.00
47,017.50 164,170.00 - 211,187.50
Overhead dan profit 0.1400 6,582.45 22,983.80 - 29,566.25
53,599.95 187,153.80 - 240,753.75

A.4.6.1.19c 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Kayu Balau Balok 2.2.2.13 m3 0.0154 10,725,000.00 165,165.00
Paku biasa 2.2.12.1 kg 0.2000 16,200.00 3,240.00
47,017.50 168,405.00 - 215,422.50
Overhead dan profit 0.1400 6,582.45 23,576.70 - 30,159.15
53,599.95 191,981.70 - 245,581.65

A.4.6.1.19d 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Kayu Kempas Balok 2.2.2.28 m3 0.0154 7,425,000.00 114,345.00
Paku biasa 2.2.12.1 kg 0.2000 16,200.00 3,240.00
47,017.50 117,585.00 - 164,602.50
Overhead dan profit 0.1400 6,582.45 16,461.90 - 23,044.35
53,599.95 134,046.90 - 187,646.85

A.4.6.1.19e 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Kayu Kruing Balok 2.2.2.30 m3 0.0154 6,875,000.00 105,875.00
Paku biasa 2.2.12.1 kg 0.2000 16,200.00 3,240.00
47,017.50 109,115.00 - 156,132.50
Overhead dan profit 0.1400 6,582.45 15,276.10 - 21,858.55
53,599.95 124,391.10 - 177,991.05

A.4.6.1.19f 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Kayu Meranti Balok 2.2.2.32 m3 0.0154 5,500,000.00 84,700.00
Paku biasa 2.2.12.1 kg 0.2000 16,200.00 3,240.00
47,017.50 87,940.00 - 134,957.50
Overhead dan profit 0.1400 6,582.45 12,311.60 - 18,894.05
53,599.95 100,251.60 - 153,851.55

A.4.6.1.19g 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0750 94,500.00 7,087.50
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0154 4,950,000.00 76,230.00
Paku biasa 2.2.12.1 kg 0.2000 16,200.00 3,240.00
47,017.50 79,470.00 - 126,487.50

98
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 6,582.45 11,125.80 - 17,708.25
53,599.95 90,595.80 - 144,195.75

A.4.6.1.20 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Jati eks Bojonegoro


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0163 30,800,000.00 502,040.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
44,300.00 506,090.00 - 550,390.00
Overhead dan profit 0.1400 6,202.00 70,852.60 - 77,054.60
50,502.00 576,942.60 - 627,444.60

A.4.6.1.20a 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 0.0163 20,900,000.00 340,670.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
44,300.00 344,720.00 - 389,020.00
Overhead dan profit 0.1400 6,202.00 48,260.80 - 54,462.80
50,502.00 392,980.80 - 443,482.80

A.4.6.1.20b 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Kayu Kamper Balok 2.2.2.20 m3 0.0163 10,450,000.00 170,335.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
44,300.00 174,385.00 - 218,685.00
Overhead dan profit 0.1400 6,202.00 24,413.90 - 30,615.90
50,502.00 198,798.90 - 249,300.90

A.4.6.1.20c 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Kayu Balau Balok 2.2.2.13 m3 0.0163 10,725,000.00 174,817.50
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
44,300.00 178,867.50 - 223,167.50
Overhead dan profit 0.1400 6,202.00 25,041.45 - 31,243.45
50,502.00 203,908.95 - 254,410.95

A.4.6.1.20d 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Kayu Kempas Balok 2.2.2.28 m3 0.0163 7,425,000.00 121,027.50
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
44,300.00 125,077.50 - 169,377.50
Overhead dan profit 0.1400 6,202.00 17,510.85 - 23,712.85
50,502.00 142,588.35 - 193,090.35

A.4.6.1.20e 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Kayu Kruing Balok 2.2.2.30 m3 0.0163 6,875,000.00 112,062.50
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
44,300.00 116,112.50 - 160,412.50
Overhead dan profit 0.1400 6,202.00 16,255.75 - 22,457.75
50,502.00 132,368.25 - 182,870.25

99
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.4.6.1.20f 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Kayu Meranti Balok 2.2.2.32 m3 0.0163 5,500,000.00 89,650.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
44,300.00 93,700.00 - 138,000.00
Overhead dan profit 0.1400 6,202.00 13,118.00 - 19,320.00
50,502.00 106,818.00 - 157,320.00

A.4.6.1.20g 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Tahun 9 mauni / akasia )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.3000 89,500.00 26,850.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00
Mandor 1.2.7.5 oh 0.0100 94,500.00 945.00
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0163 4,950,000.00 80,685.00
Paku biasa 2.2.12.1 kg 0.2500 16,200.00 4,050.00
44,300.00 84,735.00 - 129,035.00
Overhead dan profit 0.1400 6,202.00 11,862.90 - 18,064.90
50,502.00 96,597.90 - 147,099.90

A.4.6.1.21 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Jati eks Bojonegoro


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0108 36,850,000.00 397,980.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
27,092.50 399,600.00 - 426,692.50
Overhead dan profit 0.1400 3,792.95 55,944.00 - 59,736.95
30,885.45 455,544.00 - 486,429.45

A.4.6.1.21a 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0108 22,550,000.00 243,540.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
27,092.50 245,160.00 - 272,252.50
Overhead dan profit 0.1400 3,792.95 34,322.40 - 38,115.35
30,885.45 279,482.40 - 310,367.85

A.4.6.1.21b 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0108 11,550,000.00 124,740.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
27,092.50 126,360.00 - 153,452.50
Overhead dan profit 0.1400 3,792.95 17,690.40 - 21,483.35
30,885.45 144,050.40 - 174,935.85

A.4.6.1.21c 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0108 11,825,000.00 127,710.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
27,092.50 129,330.00 - 156,422.50
Overhead dan profit 0.1400 3,792.95 18,106.20 - 21,899.15
30,885.45 147,436.20 - 178,321.65

A.4.6.1.21d 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Jati Kempas

100
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0108 8,525,000.00 92,070.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
27,092.50 93,690.00 - 120,782.50
Overhead dan profit 0.1400 3,792.95 13,116.60 - 16,909.55
30,885.45 106,806.60 - 137,692.05

A.4.6.1.21e 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0108 7,975,000.00 86,130.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
27,092.50 87,750.00 - 114,842.50
Overhead dan profit 0.1400 3,792.95 12,285.00 - 16,077.95
30,885.45 100,035.00 - 130,920.45

A.4.6.1.21f 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0108 6,050,000.00 65,340.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
27,092.50 66,960.00 - 94,052.50
Overhead dan profit 0.1400 3,792.95 9,374.40 - 13,167.35
30,885.45 76,334.40 - 107,219.85

A.4.6.1.21g 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Tahun ( mauni / akasia )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0108 5,225,000.00 56,430.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
27,092.50 58,050.00 - 85,142.50
Overhead dan profit 0.1400 3,792.95 8,127.00 - 11,919.95
30,885.45 66,177.00 - 97,062.45

A.4.6.1.22 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Jati eks Bojonegoro


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0110 36,850,000.00 405,350.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
27,092.50 406,160.00 - 433,252.50
Overhead dan profit 0.1400 3,792.95 56,862.40 - 60,655.35
30,885.45 463,022.40 - 493,907.85

A.4.6.1.22a 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0110 22,550,000.00 248,050.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
27,092.50 248,860.00 - 275,952.50
Overhead dan profit 0.1400 3,792.95 34,840.40 - 38,633.35
30,885.45 283,700.40 - 314,585.85

A.4.6.1.22b 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00

101
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0110 11,550,000.00 127,050.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
27,092.50 127,860.00 - 154,952.50
Overhead dan profit 0.1400 3,792.95 17,900.40 - 21,693.35
30,885.45 145,760.40 - 176,645.85

A.4.6.1.22c 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0110 11,825,000.00 130,075.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
27,092.50 130,885.00 - 157,977.50
Overhead dan profit 0.1400 3,792.95 18,323.90 - 22,116.85
30,885.45 149,208.90 - 180,094.35

A.4.6.1.22d 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0110 8,525,000.00 93,775.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
27,092.50 94,585.00 - 121,677.50
Overhead dan profit 0.1400 3,792.95 13,241.90 - 17,034.85
30,885.45 107,826.90 - 138,712.35

A.4.6.1.22e 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0110 7,975,000.00 87,725.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
27,092.50 88,535.00 - 115,627.50
Overhead dan profit 0.1400 3,792.95 12,394.90 - 16,187.85
30,885.45 100,929.90 - 131,815.35

A.4.6.1.22f 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0110 6,050,000.00 66,550.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
27,092.50 67,360.00 - 94,452.50
Overhead dan profit 0.1400 3,792.95 9,430.40 - 13,223.35
30,885.45 76,790.40 - 107,675.85

A.4.6.1.22g 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Tahun ( mauni / akasia )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0110 5,225,000.00 57,475.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
27,092.50 58,285.00 - 85,377.50
Overhead dan profit 0.1400 3,792.95 8,159.90 - 11,952.85
30,885.45 66,444.90 - 97,330.35

A.4.6.1.23 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50

102
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0280 36,850,000.00 1,031,800.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
55,513.50 1,034,230.00 - 1,089,743.50
Overhead dan profit 0.1400 7,771.89 144,792.20 - 152,564.09
63,285.39 1,179,022.20 - 1,242,307.59

A.4.6.1.23a 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Jati lokal
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0280 22,550,000.00 631,400.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
55,513.50 633,830.00 - 689,343.50
Overhead dan profit 0.1400 7,771.89 88,736.20 - 96,508.09
63,285.39 722,566.20 - 785,851.59

A.4.6.1.23b 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0280 11,550,000.00 323,400.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
55,513.50 325,830.00 - 381,343.50
Overhead dan profit 0.1400 7,771.89 45,616.20 - 53,388.09
63,285.39 371,446.20 - 434,731.59

A.4.6.1.23c 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0280 11,825,000.00 331,100.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
55,513.50 333,530.00 - 389,043.50
Overhead dan profit 0.1400 7,771.89 46,694.20 - 54,466.09
63,285.39 380,224.20 - 443,509.59

A.4.6.1.23d 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0280 8,525,000.00 238,700.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
55,513.50 241,130.00 - 296,643.50
Overhead dan profit 0.1400 7,771.89 33,758.20 - 41,530.09
63,285.39 274,888.20 - 338,173.59

A.4.6.1.23e 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0280 7,975,000.00 223,300.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
55,513.50 225,730.00 - 281,243.50
Overhead dan profit 0.1400 7,771.89 31,602.20 - 39,374.09
63,285.39 257,332.20 - 320,617.59

A.4.6.1.23f 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan

103
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Kayu Meranti Papan 2.2.2.33 m3 0.0280 6,050,000.00 169,400.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
55,513.50 171,830.00 - 227,343.50
Overhead dan profit 0.1400 7,771.89 24,056.20 - 31,828.09
63,285.39 195,886.20 - 259,171.59

A.4.6.1.23g 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0280 5,225,000.00 146,300.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
55,513.50 148,730.00 - 204,243.50
Overhead dan profit 0.1400 7,771.89 20,822.20 - 28,594.09
63,285.39 169,552.20 - 232,837.59

A.4.6.1.24 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0280 30,800,000.00 862,400.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Teakwood tebal 4mm (120 x 240) Cm 2.2.3.236 lbr 0.8600 83,700.00 71,982.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
55,513.50 944,596.00 - 1,000,109.50
Overhead dan profit 0.1400 7,771.89 132,243.44 - 140,015.33
63,285.39 1,076,839.44 - 1,140,124.83

A.4.6.1.24a 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 0.0280 20,900,000.00 585,200.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Teakwood tebal 4mm (120 x 240) Cm 2.2.3.236 lbr 0.8600 83,700.00 71,982.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
55,513.50 667,396.00 - 722,909.50
Overhead dan profit 0.1400 7,771.89 93,435.44 - 101,207.33
63,285.39 760,831.44 - 824,116.83

A.4.6.1.24b 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Kamper Balok 2.2.2.20 m3 0.0280 10,450,000.00 292,600.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Teakwood tebal 4mm (120 x 240) Cm 2.2.3.236 lbr 0.8600 83,700.00 71,982.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
55,513.50 374,796.00 - 430,309.50
Overhead dan profit 0.1400 7,771.89 52,471.44 - 60,243.33
63,285.39 427,267.44 - 490,552.83

A.4.6.1.24c 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Balau Balok 2.2.2.13 m3 0.0280 10,725,000.00 300,300.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Teakwood tebal 4mm (120 x 240) Cm 2.2.3.236 lbr 0.8600 83,700.00 71,982.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
55,513.50 382,496.00 - 438,009.50
Overhead dan profit 0.1400 7,771.89 53,549.44 - 61,321.33
63,285.39 436,045.44 - 499,330.83

A.4.6.1.24d 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Kempas

104
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Kempas Balok 2.2.2.28 m3 0.0280 7,425,000.00 207,900.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Teakwood tebal 4mm (120 x 240) Cm 2.2.3.236 lbr 0.8600 83,700.00 71,982.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
55,513.50 290,096.00 - 345,609.50
Overhead dan profit 0.1400 7,771.89 40,613.44 - 48,385.33
63,285.39 330,709.44 - 393,994.83

A.4.6.1.24e 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Kruing Balok 2.2.2.30 m3 0.0280 6,875,000.00 192,500.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Teakwood tebal 4mm (120 x 240) Cm 2.2.3.236 lbr 0.8600 83,700.00 71,982.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
55,513.50 274,696.00 - 330,209.50
Overhead dan profit 0.1400 7,771.89 38,457.44 - 46,229.33
63,285.39 313,153.44 - 376,438.83

A.4.6.1.24f 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Meranti Balok 2.2.2.32 m3 0.0280 5,500,000.00 154,000.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Teakwood tebal 4mm (120 x 240) Cm 2.2.3.236 lbr 0.8600 83,700.00 71,982.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
55,513.50 236,196.00 - 291,709.50
Overhead dan profit 0.1400 7,771.89 33,067.44 - 40,839.33
63,285.39 269,263.44 - 332,548.83

A.4.6.1.24g 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang kayu 1.2.7.19 oh 0.4500 89,500.00 40,275.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0280 4,950,000.00 138,600.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Teakwood tebal 4mm (120 x 240) Cm 2.2.3.236 lbr 0.8600 83,700.00 71,982.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
55,513.50 220,796.00 - 276,309.50
Overhead dan profit 0.1400 7,771.89 30,911.44 - 38,683.33
63,285.39 251,707.44 - 314,992.83

A.4.6.1.25 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Jati eks Bojonegoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00
Bahan
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0280 30,800,000.00 862,400.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 lbr 0.8600 99,000.00 85,140.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
82,460.00 957,754.00 - 1,040,214.00
Overhead dan profit 0.1400 11,544.40 134,085.56 - 145,629.96
94,004.40 1,091,839.56 - 1,185,843.96

A.4.6.1.25a 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00

105
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Bahan
Kayu Jati Balok lokal 2.2.2.17 m3 0.0280 20,900,000.00 585,200.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 lbr 0.8600 99,000.00 85,140.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
82,460.00 680,554.00 - 763,014.00
Overhead dan profit 0.1400 11,544.40 95,277.56 - 106,821.96
94,004.40 775,831.56 - 869,835.96

A.4.6.1.25b 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00
Bahan
Kayu Kamper Balok 2.2.2.20 m3 0.0280 10,450,000.00 292,600.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 lbr 0.8600 99,000.00 85,140.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
82,460.00 387,954.00 - 470,414.00
Overhead dan profit 0.1400 11,544.40 54,313.56 - 65,857.96
94,004.40 442,267.56 - 536,271.96

A.4.6.1.25c 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00
Bahan
Kayu Balau Balok 2.2.2.13 m3 0.0280 10,725,000.00 300,300.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 lbr 0.8600 99,000.00 85,140.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
82,460.00 395,654.00 - 478,114.00
Overhead dan profit 0.1400 11,544.40 55,391.56 - 66,935.96
94,004.40 451,045.56 - 545,049.96

A.4.6.1.25d 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00
Bahan
Kayu Kempas Balok 2.2.2.28 m3 0.0280 7,425,000.00 207,900.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 lbr 0.8600 99,000.00 85,140.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
82,460.00 303,254.00 - 385,714.00
Overhead dan profit 0.1400 11,544.40 42,455.56 - 53,999.96
94,004.40 345,709.56 - 439,713.96

A.4.6.1.25e 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00
Bahan
Kayu Kruing Balok 2.2.2.30 m3 0.0280 6,875,000.00 192,500.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 lbr 0.8600 99,000.00 85,140.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
82,460.00 287,854.00 - 370,314.00
Overhead dan profit 0.1400 11,544.40 40,299.56 - 51,843.96
94,004.40 328,153.56 - 422,157.96

A.4.6.1.25f 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00
Bahan
Kayu Meranti Balok 2.2.2.32 m3 0.0280 5,500,000.00 154,000.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 lbr 0.8600 99,000.00 85,140.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00

106
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
82,460.00 249,354.00 - 331,814.00
Overhead dan profit 0.1400 11,544.40 34,909.56 - 46,453.96
94,004.40 284,263.56 - 378,267.96

A.4.6.1.25g 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.1000 94,500.00 9,450.00
Bahan
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0280 4,950,000.00 138,600.00
Paku biasa 2.2.12.1 kg 0.1500 16,200.00 2,430.00
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 lbr 0.8600 99,000.00 85,140.00
Lem ( Kayu + Tembok ) 2.2.6.24 kg 0.5600 13,900.00 7,784.00
82,460.00 233,954.00 - 316,414.00
Overhead dan profit 0.1400 11,544.40 32,753.56 - 44,297.96
94,004.40 266,707.56 - 360,711.96

A.4.6.1.26 1 m2 Pemasangan dinding lambrisering dari papan kayu Jati eks Bojoneoro
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang kayu 1.2.7.19 oh 1.8000 89,500.00 161,100.00
Kepala Tukang 1.2.7.3 oh 0.1800 93,500.00 16,830.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Kayu Jati Papan eks. Bojonegoro 2.2.2.18 m3 0.0070 36,850,000.00 257,950.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
Paku Sekrup 2.2.12.12 kg 0.1500 600.00 90.00
221,865.00 259,660.00 - 481,525.00
Overhead dan profit 0.1400 31,061.10 36,352.40 - 67,413.50
252,926.10 296,012.40 - 548,938.50

A.4.6.1.26a 1 m2 Pemasangan dinding lambrisering dari papan kayu Jati lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang kayu 1.2.7.19 oh 1.8000 89,500.00 161,100.00
Kepala Tukang 1.2.7.3 oh 0.1800 93,500.00 16,830.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Kayu Jati Papan lokal 2.2.2.19 m3 0.0070 22,550,000.00 157,850.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
Paku Sekrup 2.2.12.12 kg 0.1500 600.00 90.00
221,865.00 159,560.00 - 381,425.00
Overhead dan profit 0.1400 31,061.10 22,338.40 - 53,399.50
252,926.10 181,898.40 - 434,824.50

A.4.6.1.26b 1 m2 Pemasangan dinding lambrisering dari papan kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang kayu 1.2.7.19 oh 1.8000 89,500.00 161,100.00
Kepala Tukang 1.2.7.3 oh 0.1800 93,500.00 16,830.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Kayu Kamper papan 2.2.2.21 m3 0.0070 11,550,000.00 80,850.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
Paku Sekrup 2.2.12.12 kg 0.1500 600.00 90.00
221,865.00 82,560.00 - 304,425.00
Overhead dan profit 0.1400 31,061.10 11,558.40 - 42,619.50
252,926.10 94,118.40 - 347,044.50

A.4.6.1.26c 1 m2 Pemasangan dinding lambrisering dari papan kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang kayu 1.2.7.19 oh 1.8000 89,500.00 161,100.00
Kepala Tukang 1.2.7.3 oh 0.1800 93,500.00 16,830.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Kayu Balau Papan 2.2.2.14 m3 0.0070 11,825,000.00 82,775.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
Paku Sekrup 2.2.12.12 kg 0.1500 600.00 90.00
221,865.00 84,485.00 - 306,350.00
Overhead dan profit 0.1400 31,061.10 11,827.90 - 42,889.00
252,926.10 96,312.90 - 349,239.00

A.4.6.1.26d 1 m2 Pemasangan dinding lambrisering dari papan kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang kayu 1.2.7.19 oh 1.8000 89,500.00 161,100.00
Kepala Tukang 1.2.7.3 oh 0.1800 93,500.00 16,830.00

107
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Kayu Kempas Papan 2.2.2.29 m3 0.0070 8,525,000.00 59,675.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
Paku Sekrup 2.2.12.12 kg 0.1500 600.00 90.00
221,865.00 61,385.00 - 283,250.00
Overhead dan profit 0.1400 31,061.10 8,593.90 - 39,655.00
252,926.10 69,978.90 - 322,905.00

A.4.6.1.26e 1 m2 Pemasangan dinding lambrisering dari papan kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang kayu 1.2.7.19 oh 1.8000 89,500.00 161,100.00
Kepala Tukang 1.2.7.3 oh 0.1800 93,500.00 16,830.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Kayu Kruing Papan 2.2.2.31 m3 0.0070 7,975,000.00 55,825.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
Paku Sekrup 2.2.12.12 kg 0.1500 600.00 90.00
221,865.00 57,535.00 - 279,400.00
Overhead dan profit 0.1400 31,061.10 8,054.90 - 39,116.00
252,926.10 65,589.90 - 318,516.00

A.4.6.1.26f 1 m2 Pemasangan dinding lambrisering dari papan kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang kayu 1.2.7.19 oh 1.8000 89,500.00 161,100.00
Kepala Tukang 1.2.7.3 oh 0.1800 93,500.00 16,830.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Kayu Meranti Papan 2.2.2.33 m3 0.0070 6,050,000.00 42,350.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
Paku Sekrup 2.2.12.12 kg 0.1500 600.00 90.00
221,865.00 44,060.00 - 265,925.00
Overhead dan profit 0.1400 31,061.10 6,168.40 - 37,229.50
252,926.10 50,228.40 - 303,154.50

A.4.6.1.26g 1 m2 Pemasangan dinding lambrisering dari papan kayu Tahun ( mauni / akasia )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.6000 68,500.00 41,100.00
Tukang kayu 1.2.7.19 oh 1.8000 89,500.00 161,100.00
Kepala Tukang 1.2.7.3 oh 0.1800 93,500.00 16,830.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Kayu Tahun papan ( Mauni/akasia) 2.2.2.35 m3 0.0070 5,225,000.00 36,575.00
Paku biasa 2.2.12.1 kg 0.1000 16,200.00 1,620.00
Paku Sekrup 2.2.12.12 kg 0.1500 600.00 90.00
221,865.00 38,285.00 - 260,150.00
Overhead dan profit 0.1400 31,061.10 5,359.90 - 36,421.00
252,926.10 43,644.90 - 296,571.00

A.4.6.1.27 1 m2 Pemasangan dinding lambrisering dari plywood ukuran 120 x 240 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0250 68,500.00 1,712.50
Tukang kayu 1.2.7.19 oh 0.0750 89,500.00 6,712.50
Kepala Tukang 1.2.7.3 oh 0.0080 93,500.00 748.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan
Plywood ( 120 x 240 ) cm, tbl. 4 mm 2.2.3.212 m3 0.4000 99,000.00 39,600.00
Paku biasa 2.2.12.1 kg 0.0500 16,200.00 810.00
9,267.50 40,410.00 - 49,677.50
Overhead dan profit 0.1400 1,297.45 5,657.40 - 6,954.85
10,564.95 46,067.40 - 56,632.35

A.4.6.1.28 1 m2 Pemasangan dinding bilik, rangka kayu Jati eks Bojonegoro


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Bilik bambu Uk. 2m x 3m 2.2.2.7 m2 1.5000 30,000.00 45,000.00
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0140 30,800,000.00 431,200.00
Paku biasa 2.2.12.1 kg 0.0120 16,200.00 194.40
Kayu Jati Balok eks. Bojonegoro 2.2.2.16 m3 0.0030 30,800,000.00 92,400.00
12,265.00 568,794.40 - 581,059.40
Overhead dan profit 0.1400 1,717.10 79,631.22 - 81,348.32
13,982.10 648,425.62 - 662,407.72

A.4.6.1.28a 1 m2 Pemasangan dinding bilik, rangka kayu Jati lokal

108
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Bilik bambu Uk. 2m x 3m 2.2.2.7 m2 1.5000 30,000.00 45,000.00
Kayu Jati Balok lokal 2.2.2.17 m3 0.0140 20,900,000.00 292,600.00
Paku biasa 2.2.12.1 kg 0.0120 16,200.00 194.40
Kayu Jati Balok lokal 2.2.2.17 m3 0.0030 20,900,000.00 62,700.00
12,265.00 400,494.40 - 412,759.40
Overhead dan profit 0.1400 1,717.10 56,069.22 - 57,786.32
13,982.10 456,563.62 - 470,545.72

A.4.6.1.28b 1 m2 Pemasangan dinding bilik, rangka kayu Kamfer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Bilik bambu Uk. 2m x 3m 2.2.2.7 m2 1.5000 30,000.00 45,000.00
Kayu Kamper Balok 2.2.2.20 m3 0.0140 10,450,000.00 146,300.00
Paku biasa 2.2.12.1 kg 0.0120 16,200.00 194.40
Kayu Kamper Balok 2.2.2.20 m3 0.0030 10,450,000.00 31,350.00
12,265.00 222,844.40 - 235,109.40
Overhead dan profit 0.1400 1,717.10 31,198.22 - 32,915.32
13,982.10 254,042.62 - 268,024.72

A.4.6.1.28c 1 m2 Pemasangan dinding bilik, rangka kayu Balau


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Bilik bambu Uk. 2m x 3m 2.2.2.7 m2 1.5000 30,000.00 45,000.00
Kayu Balau Balok 2.2.2.13 m3 0.0140 10,725,000.00 150,150.00
Paku biasa 2.2.12.1 kg 0.0120 16,200.00 194.40
Kayu Balau Balok 2.2.2.13 m3 0.0030 10,725,000.00 32,175.00
12,265.00 227,519.40 - 239,784.40
Overhead dan profit 0.1400 1,717.10 31,852.72 - 33,569.82
13,982.10 259,372.12 - 273,354.22

A.4.6.1.28d 1 m2 Pemasangan dinding bilik, rangka kayu Kempas


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Bilik bambu Uk. 2m x 3m 2.2.2.7 m2 1.5000 30,000.00 45,000.00
Kayu Kempas Balok 2.2.2.28 m3 0.0140 7,425,000.00 103,950.00
Paku biasa 2.2.12.1 kg 0.0120 16,200.00 194.40
Kayu Kempas Balok 2.2.2.28 m3 0.0030 7,425,000.00 22,275.00
12,265.00 171,419.40 - 183,684.40
Overhead dan profit 0.1400 1,717.10 23,998.72 - 25,715.82
13,982.10 195,418.12 - 209,400.22

A.4.6.1.28e 1 m2 Pemasangan dinding bilik, rangka kayu Kruing


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Bilik bambu Uk. 2m x 3m 2.2.2.7 m2 1.5000 30,000.00 45,000.00
Kayu Kruing Balok 2.2.2.30 m3 0.0140 6,875,000.00 96,250.00
Paku biasa 2.2.12.1 kg 0.0120 16,200.00 194.40
Kayu Kruing Balok 2.2.2.30 m3 0.0030 6,875,000.00 20,625.00
12,265.00 162,069.40 - 174,334.40
Overhead dan profit 0.1400 1,717.10 22,689.72 - 24,406.82
13,982.10 184,759.12 - 198,741.22

A.4.6.1.28f 1 m2 Pemasangan dinding bilik, rangka kayu Meranti


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50

109
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Bahan
Bilik bambu Uk. 2m x 3m 2.2.2.7 m2 1.5000 30,000.00 45,000.00
Kayu Meranti Balok 2.2.2.32 m3 0.0140 5,500,000.00 77,000.00
Paku biasa 2.2.12.1 kg 0.0120 16,200.00 194.40
Kayu Meranti Balok 2.2.2.32 m3 0.0030 5,500,000.00 16,500.00
12,265.00 138,694.40 - 150,959.40
Overhead dan profit 0.1400 1,717.10 19,417.22 - 21,134.32
13,982.10 158,111.62 - 172,093.72

A.4.6.1.28g 1 m2 Pemasangan dinding bilik, rangka kayu Tahun ( mauni / akasia )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.0500 89,500.00 4,475.00
Kepala Tukang 1.2.7.3 oh 0.0050 93,500.00 467.50
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Bilik bambu Uk. 2m x 3m 2.2.2.7 m2 1.5000 30,000.00 45,000.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0140 4,950,000.00 69,300.00
Paku biasa 2.2.12.1 kg 0.0120 16,200.00 194.40
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 m3 0.0030 4,950,000.00 14,850.00
12,265.00 129,344.40 - 141,609.40
Overhead dan profit 0.1400 1,717.10 18,108.22 - 19,825.32
13,982.10 147,452.62 - 161,434.72

A.4.6.2 PEKERJAAN KUNCI DAN KACA

A.4.6.2.1 1 bh Pemasangan kunci tanam antik eks Miler


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0600 68,500.00 4,110.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Kunci Tanam Pintu Antik ex. Miler 2.2.7.51 bh 1.0000 236,800.00 236,800.00
63,703.50 236,800.00 - 300,503.50
Overhead dan profit 0.1400 8,918.49 33,152.00 - 42,070.49
72,621.99 269,952.00 - 342,573.99

A.4.6.2.1a 1 bh Pemasangan kunci tanam ( SES )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0600 68,500.00 4,110.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Kunci tanam merk SES ( pelor ) 2.2.7.50 bh 1.0000 217,100.00 217,100.00
63,703.50 217,100.00 - 280,803.50
Overhead dan profit 0.1400 8,918.49 30,394.00 - 39,312.49
72,621.99 247,494.00 - 320,115.99

A.4.6.2.2 1 bh Pemasangan kunci tanam biasa


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kunci tanam Slot ex.Kuda (2x Putaran) 2.2.7.52 bh 1.0000 70,500.00 70,500.00
50,582.50 70,500.00 - 121,082.50
Overhead dan profit 0.1400 7,081.55 9,870.00 - 16,951.55
57,664.05 80,370.00 - 138,034.05

A.4.6.2.2a 1 bh Pemasangan kunci tanam slot tanam eks Kuda 2x putaran


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kunci tanam Slot ex.Kuda (2x Putaran) 2.2.7.52 bh 1.0000 70,500.00 70,500.00
50,582.50 70,500.00 - 121,082.50
Overhead dan profit 0.1400 7,081.55 9,870.00 - 16,951.55
57,664.05 80,370.00 - 138,034.05

A.4.6.2.3 1 bh Pemasangan kunci Slot tanam kamar mandi eks Miler


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0050 68,500.00 342.50
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00

110
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Kunci Slot Tanam Kamar Mandi ex.Miller 2.2.7.49 bh 1.0000 72,800.00 72,800.00
50,051.00 72,800.00 - 122,851.00
Overhead dan profit 0.1400 7,007.14 10,192.00 - 17,199.14
57,058.14 82,992.00 - 140,050.14

A.4.6.2.3a 1 bh Pemasangan kunci Slot tanam kamar mandi


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0050 68,500.00 342.50
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Slot Tanam Kamar Mandi 2.2.7.59 bh 1.0000 138,600.00 138,600.00
50,051.00 138,600.00 - 188,651.00
Overhead dan profit 0.1400 7,007.14 19,404.00 - 26,411.14
57,058.14 158,004.00 - 215,062.14

A.4.6.2.4 1 bh Pemasangan kunci silinder


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0050 68,500.00 342.50
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Kunci silinder bh 1.0000 #N/A #N/A
50,051.00 #N/A - #N/A
Overhead dan profit 0.1400 7,007.14 #N/A - #N/A
57,058.14 #N/A - #N/A

A.4.6.2.5 1 bh Pemasangan engsel pintu kupu - kupu


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan
Engsel pintu kupu - kupu 2.2.7.3 bh 1.0000 41,000.00 41,000.00
15,930.60 41,000.00 - 56,930.60
Overhead dan profit 0.1400 2,230.28 5,740.00 - 7,970.28
18,160.88 46,740.00 - 64,900.88

A.4.6.2.5a 1 bh Pemasangan engsel kuningan Arc Asli eks Elitech 4"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan
Engsel kuningan Arc Asli ex. Elitech 4" 2.2.7.8 bh 1.0000 79,100.00 79,100.00
#N/A 15,930.60 79,100.00 - 95,030.60
Overhead dan profit 0.1400 2,230.28 11,074.00 - 13,304.28
18,160.88 90,174.00 - 108,334.88

A.4.6.2.5b 1 bh Pemasangan engsel pintu ( H )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan
Engsel Pintu ( H ) 2.2.7.9 bh 1.0000 14,400.00 14,400.00
15,930.60 14,400.00 - 30,330.60
Overhead dan profit 0.1400 2,230.28 2,016.00 - 4,246.28
18,160.88 16,416.00 - 34,576.88

A.4.6.2.5c 1 bh Pemasangan engsel pintu ( Arc ) nylon


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan
Engsel Pintu (Arch ) nylon 2.2.7.10 bh 1.0000 9,800.00 9,800.00
15,930.60 9,800.00 - 25,730.60
Overhead dan profit 0.1400 2,230.28 1,372.00 - 3,602.28
18,160.88 11,172.00 - 29,332.88

A.4.6.2.5d 1 bh Pemasangan engsel pintu eks Union 4"

111
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan
Engsel pintu ex. Union 4" 2.2.7.11 bh 1.0000 47,400.00 47,400.00
15,930.60 47,400.00 - 63,330.60
Overhead dan profit 0.1400 2,230.28 6,636.00 - 8,866.28
18,160.88 54,036.00 - 72,196.88

A.4.6.2.5e 1 bh Pemasangan engsel Stainlesstel Dekson 3"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan
Engsel Stainlesstel Dekson 3" 2.2.7.19 bh 1.0000 53,100.00 53,100.00
15,930.60 53,100.00 - 69,030.60
Overhead dan profit 0.1400 2,230.28 7,434.00 - 9,664.28
18,160.88 60,534.00 - 78,694.88

A.4.6.2.5f 1 bh Pemasangan engsel Stainlesstel Dekson 4"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan
Engsel Stainlesstel Dekson 4" 2.2.7.20 bh 1.0000 124,700.00 124,700.00
15,930.60 124,700.00 - 140,630.60
Overhead dan profit 0.1400 2,230.28 17,458.00 - 19,688.28
18,160.88 142,158.00 - 160,318.88

A.4.6.2.5g 1 bh Pemasangan engsel Stainlesstel Dekson 5"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan
Engsel Stainlesstel Dekson 5" 2.2.7.21 bh 1.0000 142,700.00 142,700.00
15,930.60 142,700.00 - 158,630.60
Overhead dan profit 0.1400 2,230.28 19,978.00 - 22,208.28
18,160.88 162,678.00 - 180,838.88

A.4.6.2.5h 1 bh Pemasangan engsel Sendok


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan
Engsel sendok 2.2.7.12 bh 1.0000 12,100.00 12,100.00
15,930.60 12,100.00 - 28,030.60
Overhead dan profit 0.1400 2,230.28 1,694.00 - 3,924.28
18,160.88 13,794.00 - 31,954.88

A.4.6.2.6 1 bh Pemasangan engsel jendela kupu kupu


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Engsel jendela (kupu-kupu) 3" 2.2.7.6 bh 1.0000 20,200.00 20,200.00
10,617.25 20,200.00 - 30,817.25
Overhead dan profit 0.1400 1,486.42 2,828.00 - 4,314.42
12,103.67 23,028.00 - 35,131.67

A.4.6.2.6a 1 bh Pemasangan engsel jendela eks Union 3"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Engsel jendela ex. Union 3" 2.2.7.7 bh 1.0000 35,900.00 35,900.00
10,617.25 35,900.00 - 46,517.25

112
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 1,486.42 5,026.00 - 6,512.42
12,103.67 40,926.00 - 53,029.67

A.4.6.2.6b 1 bh Pemasangan engsel jendela ( H )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Engsel Jendela ( H ) 2.2.7.4 bh 1.0000 16,700.00 16,700.00
10,617.25 16,700.00 - 27,317.25
Overhead dan profit 0.1400 1,486.42 2,338.00 - 3,824.42
12,103.67 19,038.00 - 31,141.67

A.4.6.2.6c 1 bh Pemasangan engsel jendela ( Arch )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Engsel Jendela (Arch ) 2.2.7.5 bh 1.0000 17,400.00 17,400.00
10,617.25 17,400.00 - 28,017.25
Overhead dan profit 0.1400 1,486.42 2,436.00 - 3,922.42
12,103.67 19,836.00 - 31,939.67

A.4.6.2.6d 1 bh Pemasangan grendel biasa ( besar ) 8"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Grendel biasa (Besar) 8" 2.2.7.22 bh 1.0000 14,400.00 14,400.00
10,617.25 14,400.00 - 25,017.25
Overhead dan profit 0.1400 1,486.42 2,016.00 - 3,502.42
12,103.67 16,416.00 - 28,519.67

A.4.6.2.6e 1 bh Pemasangan grendel biasa ( kecil ) 3"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Grendel biasa (Kecil) 3" 2.2.7.17 bh 1.0000 6,900.00 6,900.00
#N/A 10,617.25 6,900.00 - 17,517.25
Overhead dan profit 0.1400 1,486.42 966.00 - 2,452.42
12,103.67 7,866.00 - 19,969.67

A.4.6.2.6f 1 bh Pemasangan grendel eks AEG


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Grendel ex. AEG 2.2.7.24 bh 1.0000 32,300.00 32,300.00
10,617.25 32,300.00 - 42,917.25
Overhead dan profit 0.1400 1,486.42 4,522.00 - 6,008.42
12,103.67 36,822.00 - 48,925.67

A.4.6.2.6g 1 bh Pemasangan grendel jendela merk SES


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Grendel jendela merk SES 2.2.7.25 bh 1.0000 23,700.00 23,700.00
10,617.25 23,700.00 - 34,317.25
Overhead dan profit 0.1400 1,486.42 3,318.00 - 4,804.42
12,103.67 27,018.00 - 39,121.67

A.4.6.2.6h 1 bh Pemasangan grendel pintu panjang ( sespen )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00

113
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Grendel Pintu Panjang ( sespen ) 2.2.7.26 bh 1.0000 52,000.00 52,000.00
10,617.25 52,000.00 - 62,617.25
Overhead dan profit 0.1400 1,486.42 7,280.00 - 8,766.42
12,103.67 59,280.00 - 71,383.67

A.4.6.2.6i 1 bh Pemasangan grendel pintu ganda Dekson 40 cm komplit


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Grendel pintu ganda Dekson 40 cm komplit 2.2.7.27 bh 1.0000 184,800.00 184,800.00
10,617.25 184,800.00 - 195,417.25
Overhead dan profit 0.1400 1,486.42 25,872.00 - 27,358.42
12,103.67 210,672.00 - 222,775.67

A.4.6.2.6j 1 bh Pemasangan grendel tanam kuningan besar eks Cavel 60 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Grendel Tanam Kuningan Besar ex. Cavel 60mm 2.2.7.28 bh 1.0000 268,000.00 268,000.00
10,617.25 268,000.00 - 278,617.25
Overhead dan profit 0.1400 1,486.42 37,520.00 - 39,006.42
12,103.67 305,520.00 - 317,623.67

A.4.6.2.6k 1 bh Pemasangan grendel tanam kuningan kecil eks beluci 4"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Grendel Tanam Kuningan Kecil ex. Beluci 4" 2.2.7.30 bh 1.0000 156,000.00 156,000.00
10,617.25 156,000.00 - 166,617.25
Overhead dan profit 0.1400 1,486.42 21,840.00 - 23,326.42
12,103.67 177,840.00 - 189,943.67

A.4.6.2.6l 1 bh Pemasangan grendel tanam merk SES


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Grendel tanam merk SES 2.2.7.31 bh 1.0000 41,000.00 41,000.00
10,617.25 41,000.00 - 51,617.25
Overhead dan profit 0.1400 1,486.42 5,740.00 - 7,226.42
12,103.67 46,740.00 - 58,843.67

A.4.6.2.7 1 bh Pemasangan hak angin


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Hak Angin 2.2.7.32 bh 1.0000 17,400.00 17,400.00
26,667.25 17,400.00 - 44,067.25
Overhead dan profit 0.1400 3,733.42 2,436.00 - 6,169.42
30,400.67 19,836.00 - 50,236.67

A.4.6.2.7a 1 bh Pemasangan hak angin ( Sikutan ) biasa


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Hak angin (Sikutan) biasa 2.2.7.33 bh 1.0000 21,300.00 21,300.00
26,667.25 21,300.00 - 47,967.25
Overhead dan profit 0.1400 3,733.42 2,982.00 - 6,715.42
30,400.67 24,282.00 - 54,682.67

A.4.6.2.7b 1 bh Pemasangan hak angin 4 mm lurus / plat 4 x 150 mm

114
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Hak angin 4mm Lurus/plat 4x150mm 2.2.7.34 bh 1.0000 18,500.00 18,500.00
26,667.25 18,500.00 - 45,167.25
Overhead dan profit 0.1400 3,733.42 2,590.00 - 6,323.42
30,400.67 21,090.00 - 51,490.67

A.4.6.2.7c 1 bh Pemasangan hak angin lurus


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Hak angin lurus 2.2.7.35 bh 1.0000 36,400.00 36,400.00
26,667.25 36,400.00 - 63,067.25
Overhead dan profit 0.1400 3,733.42 5,096.00 - 8,829.42
30,400.67 41,496.00 - 71,896.67

A.4.6.2.7d 1 bh Pemasangan hak angin merk SES


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0005 94,500.00 47.25
Bahan
Hak angin Merk SES 2.2.7.36 bh 1.0000 33,600.00 33,600.00
26,667.25 33,600.00 - 60,267.25
Overhead dan profit 0.1400 3,733.42 4,704.00 - 8,437.42
30,400.67 38,304.00 - 68,704.67

A.4.6.2.8 1 bh Pemasangan spring knip


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Spring knip #N/A bh 1.0000 #N/A #N/A
16,611.00 #N/A - #N/A
Overhead dan profit 0.1400 2,325.54 #N/A - #N/A
18,936.54 #N/A - #N/A

A.4.6.2.9 1 bh Pemasangan kait angin


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Hak Angin 2.2.7.32 bh 1.0000 17,400.00 17,400.00
16,611.00 17,400.00 - 34,011.00
Overhead dan profit 0.1400 2,325.54 2,436.00 - 4,761.54
18,936.54 19,836.00 - 38,772.54

A.4.6.2.10 1 bh Pemasangan door closer


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Door Closer ex. Beluci 2.2.7.1 bh 1.0000 216,600.00 216,600.00
53,133.50 216,600.00 - 269,733.50
Overhead dan profit 0.1400 7,438.69 30,324.00 - 37,762.69
60,572.19 246,924.00 - 307,496.19

A.4.6.2.11 1 bh Pemasangan kunci sloot 2 putaran eks CAVEL ( dengan handle )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan -
Kunci Slot 2 Putaran ex.CAVEL (dengan handle) 2.2.7.46 bh 1.0000 209,700.00 209,700.00
21,234.50 209,700.00 - 230,934.50

115
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 2,972.83 29,358.00 - 32,330.83
24,207.33 239,058.00 - 263,265.33

A.4.6.2.11a 1 bh Pemasangan kunci sloot 2 putaran eks kodai


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan -
Kunci Slot 2 Putaran ex.Kodai 2.2.7.47 bh 1.0000 107,500.00 107,500.00
21,234.50 107,500.00 - 128,734.50
Overhead dan profit 0.1400 2,972.83 15,050.00 - 18,022.83
24,207.33 122,550.00 - 146,757.33

A.4.6.2.11b 1 bh Pemasangan kunci sloot 2 putaran eks YALE ( dengan handle )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan -
Kunci Slot 2 Putaran ex.YALE (dengan handle) 2.2.7.48 bh 1.0000 123,600.00 123,600.00
21,234.50 123,600.00 - 144,834.50
Overhead dan profit 0.1400 2,972.83 17,304.00 - 20,276.83
24,207.33 140,904.00 - 165,111.33

A.4.6.2.11c 1 bh Pemasangan kunci sloot ( kunci pintu ) merk SES


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan -
Selot ( kunci pintu ) merk SES 2.2.7.56 bh 1.0000 283,000.00 283,000.00
21,234.50 283,000.00 - 304,234.50
Overhead dan profit 0.1400 2,972.83 39,620.00 - 42,592.83
24,207.33 322,620.00 - 346,827.33

A.4.6.2.11d 1 bh Pemasangan kunci sloot ( kunci pintu ) merk SES


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan -
Selot ( kunci pintu ) merk SES 2.2.7.56 bh 1.0000 283,000.00 283,000.00
21,234.50 283,000.00 - 304,234.50
Overhead dan profit 0.1400 2,972.83 39,620.00 - 42,592.83
24,207.33 322,620.00 - 346,827.33

A.4.6.2.11e 1 bh Pemasangan kunci sloot Rossete Dekson


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan -
Selot Rossete Dekson 2.2.7.57 bh 1.0000 314,700.00 314,700.00
21,234.50 314,700.00 - 335,934.50
Overhead dan profit 0.1400 2,972.83 44,058.00 - 47,030.83
24,207.33 358,758.00 - 382,965.33

A.4.6.2.11f 1 bh Pemasangan kunci sloot ( kunci pintu ) lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang kayu 1.2.7.19 oh 0.2000 89,500.00 17,900.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0010 94,500.00 94.50
Bahan -
Slot ( Kunci-kunci pintu ) lokal 2.2.7.58 bh 1.0000 95,900.00 95,900.00
21,234.50 95,900.00 - 117,134.50
Overhead dan profit 0.1400 2,972.83 13,426.00 - 16,398.83
24,207.33 109,326.00 - 133,533.33

A.4.6.2.12 1 bh Pemasangan Door holder


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00

116
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan -
Dooor holder bh 1.0000 #N/A #N/A
53,133.50 #N/A - #N/A
Overhead dan profit 0.1400 7,438.69 #N/A - #N/A
60,572.19 #N/A - #N/A

A.4.6.2.12a 1 bh Pemasangan Handle


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan -
Handle 2.2.7.37 bh 1.0000 84,400.00 84,400.00
53,133.50 84,400.00 - 137,533.50
Overhead dan profit 0.1400 7,438.69 11,816.00 - 19,254.69
60,572.19 96,216.00 - 156,788.19

A.4.6.2.12b 1 bh Pemasangan Handle pintu ganda Dekson 30 cm komplit


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan -
Handle pintu ganda Dekson 30 cm komplit 2.2.7.38 bh 1.0000 114,400.00 114,400.00
53,133.50 114,400.00 - 167,533.50
Overhead dan profit 0.1400 7,438.69 16,016.00 - 23,454.69
60,572.19 130,416.00 - 190,988.19

A.4.6.2.12c 1 bh Pemasangan Handle pintu ganda Dekson 40 cm komplit


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan -
Handle pintu ganda Dekson 40 cm komplit 2.2.7.39 bh 1.0000 270,300.00 270,300.00
53,133.50 270,300.00 - 323,433.50
Overhead dan profit 0.1400 7,438.69 37,842.00 - 45,280.69
60,572.19 308,142.00 - 368,714.19

A.4.6.2.12d 1 bh Pemasangan Handle ointu stainless steel besar


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan -
Handle pintu stanless steel besar 2.2.7.40 bh 1.0000 510,500.00 510,500.00
53,133.50 510,500.00 - 563,633.50
Overhead dan profit 0.1400 7,438.69 71,470.00 - 78,908.69
60,572.19 581,970.00 - 642,542.19

A.4.6.2.12e 1 bh Pemasangan Handle ointu stainless steel kecil


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan -
Handle pintu stanless steel kecil 2.2.7.41 bh 1.0000 201,000.00 201,000.00
53,133.50 201,000.00 - 254,133.50
Overhead dan profit 0.1400 7,438.69 28,140.00 - 35,578.69
60,572.19 229,140.00 - 289,712.19

A.4.6.2.12f 1 bh Pemasangan Pegangan pintu handle marmer kecil


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan -
Pegangan pintu handle Marmer kecil bh 1.0000 #N/A #N/A
53,133.50 #N/A - #N/A
Overhead dan profit 0.1400 7,438.69 #N/A - #N/A
60,572.19 #N/A - #N/A

A.4.6.2.12g 1 bh Pemasangan Pegangan pintu handle marmer besar

117
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan -
Pegangan pintu handle Marmer besar bh 1.0000 #N/A #N/A
53,133.50 #N/A - #N/A
Overhead dan profit 0.1400 7,438.69 #N/A - #N/A
60,572.19 #N/A - #N/A

A.4.6.2.12h 1 bh Pemasangan Pegangan pintu P=20


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang kayu 1.2.7.19 oh 0.5000 89,500.00 44,750.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan -
Pegangan pintu P=20 2.2.7.55 bh 1.0000 69,900.00 69,900.00
53,133.50 69,900.00 - 123,033.50
Overhead dan profit 0.1400 7,438.69 9,786.00 - 17,224.69
60,572.19 79,686.00 - 140,258.19

A.4.6.2.13 1 bh Pemasangan Door stoper Stainlees


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang kayu 1.2.7.19 oh 0.1000 89,500.00 8,950.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan -
Door Stoper Stainless 2.2.7.2 bh 1.0000 50,300.00 50,300.00
11,042.50 50,300.00 - 61,342.50
Overhead dan profit 0.1400 1,545.95 7,042.00 - 8,587.95
12,588.45 57,342.00 - 69,930.45

A.4.6.2.14 1 bh Pemasangan Rel pintu dorong


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0600 68,500.00 4,110.00
Tukang kayu 1.2.7.19 oh 0.6000 89,500.00 53,700.00
Kepala Tukang 1.2.7.3 oh 0.0600 93,500.00 5,610.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan -
Rel pintu dorong 2.2.4.104 bh 1.0000 270,800.00 270,800.00
63,703.50 270,800.00 - 334,503.50
Overhead dan profit 0.1400 8,918.49 37,912.00 - 46,830.49
72,621.99 308,712.00 - 381,333.99

A.4.6.2.15 1 bh Pemasangan Kunci lemari


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0250 68,500.00 1,712.50
Tukang kayu 1.2.7.19 oh 0.2500 89,500.00 22,375.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0013 94,500.00 122.85
Bahan -
Kunci lemari 2.2.7.45 bh 1.0000 14,400.00 14,400.00
26,547.85 14,400.00 - 40,947.85
Overhead dan profit 0.1400 3,716.70 2,016.00 - 5,732.70
30,264.55 16,416.00 - 46,680.55

A.4.6.2.15a 1 bh Pemasangan Kunci laci ( 808 )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0250 68,500.00 1,712.50
Tukang kayu 1.2.7.19 oh 0.2500 89,500.00 22,375.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0013 94,500.00 122.85
Bahan -
Kunci laci (088) 2.2.7.44 bh 1.0000 15,100.00 15,100.00
26,547.85 15,100.00 - 41,647.85
Overhead dan profit 0.1400 3,716.70 2,114.00 - 5,830.70
30,264.55 17,214.00 - 47,478.55

A.4.6.2.15b 1 bh Pemasangan Kunci gembok besar stainless 40 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0250 68,500.00 1,712.50
Tukang kayu 1.2.7.19 oh 0.2500 89,500.00 22,375.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0013 94,500.00 122.85
Bahan -
Kunci gembok besar stainless 40mm 2.2.7.42 bh 1.0000 32,900.00 32,900.00
26,547.85 32,900.00 - 59,447.85

118
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 3,716.70 4,606.00 - 8,322.70
30,264.55 37,506.00 - 67,770.55

A.4.6.2.15c 1 bh Pemasangan Kunci gembok besar stainless 30 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0250 68,500.00 1,712.50
Tukang kayu 1.2.7.19 oh 0.2500 89,500.00 22,375.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0013 94,500.00 122.85
Bahan -
Kunci gembok sedang stainless 30mm 2.2.7.43 bh 1.0000 35,200.00 35,200.00
26,547.85 35,200.00 - 61,747.85
Overhead dan profit 0.1400 3,716.70 4,928.00 - 8,644.70
30,264.55 40,128.00 - 70,392.55

A.4.6.2.16 1 m2 Pemasangan kaca bening tebal 3 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan -
Kaca Bening t= 3 mm 2.2.9.8 bh 1.1000 62,900.00 69,190.00
Sealant 2.2.9.30 kg 0.0500 19,000.00 950.00
15,930.60 70,140.00 - 86,070.60
Overhead dan profit 0.1400 2,230.28 9,819.60 - 12,049.88
18,160.88 79,959.60 - 98,120.48

A.4.6.2.16a 1 m2 Pemasangan kaca buram tebal 3 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan -
Kaca Buram t=3mm 2.2.9.12 bh 1.1000 112,600.00 123,860.00
Sealant 2.2.9.30 kg 0.0500 19,000.00 950.00
15,930.60 124,810.00 - 140,740.60
Overhead dan profit 0.1400 2,230.28 17,473.40 - 19,703.68
18,160.88 142,283.40 - 160,444.28

A.4.6.2.16b 1 m2 Pemasangan kaca Es tebal 3 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan -
Kaca Es t=3mm 2.2.9.15 bh 1.1000 115,500.00 127,050.00
Sealant 2.2.9.30 kg 0.0500 19,000.00 950.00
15,930.60 128,000.00 - 143,930.60
Overhead dan profit 0.1400 2,230.28 17,920.00 - 20,150.28
18,160.88 145,920.00 - 164,080.88

A.4.6.2.17 1 bh Pemasangan kaca bening tebal 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan -
Kaca Bening t= 5 mm 2.2.9.9 bh 1.1000 106,300.00 116,930.00
Sealant 2.2.9.30 kg 0.0500 19,000.00 950.00
15,930.60 117,880.00 - 133,810.60
Overhead dan profit 0.1400 2,230.28 16,503.20 - 18,733.48
18,160.88 134,383.20 - 152,544.08

A.4.6.2.17a 1 bh Pemasangan kaca Ray band tebal 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0008 94,500.00 75.60
Bahan -
Kaca Ray-band t= 5 mm 2.2.9.17 bh 1.1000 113,200.00 124,520.00
Sealant 2.2.9.30 kg 0.0500 19,000.00 950.00
15,930.60 125,470.00 - 141,400.60
Overhead dan profit 0.1400 2,230.28 17,565.80 - 19,796.08
18,160.88 143,035.80 - 161,196.68

119
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
A.4.6.2.18 1 m2 Pemasangan kaca bening tebal 7 mm
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0170 68,500.00 1,164.50
Tukang kayu 1.2.7.19 oh 0.1700 89,500.00 15,215.00
Kepala Tukang 1.2.7.3 oh 0.0170 93,500.00 1,589.50
Mandor 1.2.7.5 oh 0.0009 94,500.00 85.05
Bahan -
Kaca Bening t= 7 mm 2.2.9.10 bh 1.1000 150,700.00 165,770.00
Sealant 2.2.9.30 kg 0.0700 19,000.00 1,330.00
18,054.05 167,100.00 - 185,154.05
Overhead dan profit 0.1400 2,527.57 23,394.00 - 25,921.57
20,581.62 190,494.00 - 211,075.62

A.4.6.2.18a 1 m2 Pemasangan kaca Ray band tebal 7 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0170 68,500.00 1,164.50
Tukang kayu 1.2.7.19 oh 0.1700 89,500.00 15,215.00
Kepala Tukang 1.2.7.3 oh 0.0170 93,500.00 1,589.50
Mandor 1.2.7.5 oh 0.0009 94,500.00 85.05
Bahan -
Kaca Ray-band t= 7 mm 2.2.9.18 bh 1.1000 176,100.00 193,710.00
Sealant 2.2.9.30 kg 0.0700 19,000.00 1,330.00
18,054.05 195,040.00 - 213,094.05
Overhead dan profit 0.1400 2,527.57 27,305.60 - 29,833.17
20,581.62 222,345.60 - 242,927.22

A.4.6.2.19 1 m2 Pemasangan kaca tebal 10 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0250 68,500.00 1,712.50
Tukang kayu 1.2.7.19 oh 0.2500 89,500.00 22,375.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0013 94,500.00 122.85
Bahan -
Kaca Bening t= 10 mm 2.2.9.11 bh 1.1000 231,000.00 254,100.00
Sealant 2.2.9.30 kg 0.0700 19,000.00 1,330.00
26,547.85 255,430.00 - 281,977.85
Overhead dan profit 0.1400 3,716.70 35,760.20 - 39,476.90
30,264.55 291,190.20 - 321,454.75

A.4.6.2.20 1 m2 Pemasangan kaca cermin tebal 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan -
Kaca Cermin t=5mm 2.2.9.14 bh 1.1000 144,400.00 158,840.00
16,611.00 158,840.00 - 175,451.00
Overhead dan profit 0.1400 2,325.54 22,237.60 - 24,563.14
18,936.54 181,077.60 - 200,014.14

A.4.6.2.21 1 m2 Pemasangan kaca cermin tebal 3 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0170 68,500.00 1,164.50
Tukang kayu 1.2.7.19 oh 0.1700 89,500.00 15,215.00
Kepala Tukang 1.2.7.3 oh 0.0170 93,500.00 1,589.50
Mandor 1.2.7.5 oh 0.0090 94,500.00 850.50
Bahan -
Kaca Cermin t=3mm 2.2.9.13 bh 1.1000 126,000.00 138,600.00
18,819.50 138,600.00 - 157,419.50
Overhead dan profit 0.1400 2,634.73 19,404.00 - 22,038.73
21,454.23 158,004.00 - 179,458.23

A.4.6.2.22 1 m2 Pemasangan kaca Stained glass tebal 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan -
Kaca Stained Glass 2.2.9.20 bh 1.1000 1,253,200.00 1,378,520.00
16,611.00 1,378,520.00 - 1,395,131.00
Overhead dan profit 0.1400 2,325.54 192,992.80 - 195,318.34
18,936.54 1,571,512.80 - 1,590,449.34

A.4.6.2.22a 1 m2 Pemasangan kaca air tebal 5 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50

120
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan -
Kaca air 5 Cm 2.2.9.5 bh 1.1000 94,700.00 104,170.00
16,611.00 104,170.00 - 120,781.00
Overhead dan profit 0.1400 2,325.54 14,583.80 - 16,909.34
18,936.54 118,753.80 - 137,690.34

A.4.6.2.22b 1 m2 Pemasangan kaca bluegreen tebal 8 mm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan -
Kaca bluegreen t=8mm 2.2.9.6 bh 1.1000 752,000.00 827,200.00
16,611.00 827,200.00 - 843,811.00
Overhead dan profit 0.1400 2,325.54 115,808.00 - 118,133.54
18,936.54 943,008.00 - 961,944.54

A.4.6.2.22c 1 m2 Pemasangan kaca profil ( bevel / moulding )


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0150 68,500.00 1,027.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan -
Kaca profil (Bevel / moulding) 2.2.9.16 bh 1.1000 7,500.00 8,250.00
16,611.00 8,250.00 - 24,861.00
Overhead dan profit 0.1400 2,325.54 1,155.00 - 3,480.54
18,936.54 9,405.00 - 28,341.54

A.4.6.2.23 1 m2 Pemasangan kaca patri


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0750 68,500.00 5,137.50
Tukang kayu 1.2.7.19 oh 0.1500 89,500.00 13,425.00
Kepala Tukang 1.2.7.3 oh 0.0150 93,500.00 1,402.50
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan -
Kaca patry 2.2.9.7 bh 1.1000 2,505,800.00 2,756,380.00
Sealant 2.2.9.30 bh 0.0500 19,000.00 950.00
20,343.00 2,757,330.00 - 2,777,673.00
Overhead dan profit 0.1400 2,848.02 386,026.20 - 388,874.22
23,191.02 3,143,356.20 - 3,166,547.22

A.4.7.1 PEKERJAAN PENGECATAN

A.4.7.1.1 1 m2 Pengikisan / pengerokan permukaan cat lama


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Soda Api 2.2.6.44 Kg 0.0500 17,400.00 870.00
10,558.50 870.00 - 11,428.50
Overhead dan profit 0.1400 1,478.19 121.80 - 1,599.99
12,036.69 991.80 - 13,028.49

A.4.7.1.2 1 m2 Pencucian Bidang permukaan tembok yang pernah dicat


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Sabun 2.2.6.42 Kg 0.0500 11,600.00 580.00
10,558.50 580.00 - 11,138.50
Overhead dan profit 0.1400 1,478.19 81.20 - 1,559.39
12,036.69 661.20 - 12,697.89

A.4.7.1.3 1 m2 Pengerokan karat pada permukaan baja cara manual


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Mandor 1.2.7.5 oh 0.0080 94,500.00 756.00
Bahan
Sabun 2.2.6.42 Kg 0.0500 11,600.00 580.00
11,031.00 580.00 - 11,611.00
Overhead dan profit 0.1400 1,544.34 81.20 - 1,625.54
12,575.34 661.20 - 13,236.54

A.4.7.1.4 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur , 1 lapis cat dasar , 2 lapis cat penutup)
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0700 68,500.00 4,795.00

121
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang cat 1.2.7.18 oh 0.0090 79,000.00 711.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Cat Meny kayu 2.2.6.11 kg 0.2000 27,200.00 5,440.00
Plamur kayu 2.2.6.37 kg 0.1500 27,200.00 4,080.00
Cat Dasar Kayu 2.2.6.6 kg 0.1700 30,600.00 5,202.00
Cat Kayu 2.2.6.8 kg 0.2600 64,100.00 16,666.00
Kuas 3 " 2.2.6.22 Bh 0.0100 15,100.00 151.00
Minyak Cat / Thiner B 2.2.6.29 kg 0.0300 16,200.00 486.00
Kertas gosok ( rempelas ) 2.2.6.21 Lbr 0.2000 3,500.00 700.00
6,350.50 32,725.00 - 39,075.50
Overhead dan profit 0.1400 889.07 4,581.50 - 5,470.57
7,239.57 37,306.50 - 44,546.07

A.4.7.1.5 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur , 1 lapis cat dasar , 3 lapis cat penutup)
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0700 68,500.00 4,795.00
Tukang cat 1.2.7.18 oh 0.1050 79,000.00 8,295.00
Kepala Tukang 1.2.7.3 oh 0.0040 93,500.00 374.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Cat Meny kayu 2.2.6.11 kg 0.2000 27,200.00 5,440.00
Plamur kayu 2.2.6.37 kg 0.1500 27,200.00 4,080.00
Cat Dasar Kayu 2.2.6.6 kg 0.1700 30,600.00 5,202.00
Cat Kayu 2.2.6.8 kg 0.3500 64,100.00 22,435.00
Kuas 3 " 2.2.6.22 Bh 0.0100 15,100.00 151.00
Minyak Cat / Thiner B 2.2.6.29 kg 0.0300 16,200.00 486.00
Kertas gosok ( rempelas ) 2.2.6.21 Lbr 0.2000 3,500.00 700.00
13,747.50 38,494.00 - 52,241.50
Overhead dan profit 0.1400 1,924.65 5,389.16 - 7,313.81
15,672.15 43,883.16 - 59,555.31

A.4.7.1.6 1 m2 Pelaburan bidang kayu dengan teak oil


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0400 68,500.00 2,740.00
Tukang cat 1.2.7.18 oh 0.0630 79,000.00 4,977.00
Kepala Tukang 1.2.7.3 oh 0.0630 93,500.00 5,890.50
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Teak oil 2.2.6.47 ltr 0.3600 8,100.00 2,916.00
13,891.00 2,916.00 - 16,807.00
Overhead dan profit 0.1400 1,944.74 408.24 - 2,352.98
15,835.74 3,324.24 - 19,159.98

A.4.7.1.7 1 m2 Pelaburan bidang kayu dengan pelitur


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0400 68,500.00 2,740.00
Tukang cat 1.2.7.18 oh 0.0600 79,000.00 4,740.00
Kepala Tukang 1.2.7.3 oh 0.0160 93,500.00 1,496.00
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Politur jadi 2.2.6.39 L 0.1500 55,400.00 8,310.00
Politur jadi 2.2.6.39 L 0.3720 55,400.00 20,608.80
Kertas gosok ( rempelas ) 2.2.6.21 Lbr 2.0000 3,500.00 7,000.00
9,259.50 35,918.80 - 45,178.30
Overhead dan profit 0.1400 1,296.33 5,028.63 - 6,324.96
10,555.83 40,947.43 - 51,503.26

A.4.7.1.8 1 m2 Pelaburan bidang kayu dengan cat residu dan ter


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1000 68,500.00 6,850.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Residu ( Ter ) 2.2.6.40 L 0.3500 5,800.00 2,030.00
7,417.00 2,030.00 - 9,447.00
Overhead dan profit 0.1400 1,038.38 284.20 - 1,322.58
8,455.38 2,314.20 - 10,769.58

A.4.7.1.9 1 m2 Pelaburan bidang kayu dengan vernis


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0160 68,500.00 1,096.00
Tukang cat 1.2.7.18 oh 0.0030 79,000.00 237.00
Kepala Tukang 1.2.7.3 oh 0.0160 93,500.00 1,496.00
Mandor 1.2.7.5 oh 0.0060 94,500.00 567.00
Bahan
Vernis 2.2.6.48 L 0.1500 40,500.00 6,075.00
Dempul Kayu 2.2.6.18 Kg 0.0500 32,300.00 1,615.00
Kertas gosok ( rempelas ) 2.2.6.21 Lbr 0.1000 3,500.00 350.00
3,396.00 8,040.00 - 11,436.00

122
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 475.44 1,125.60 - 1,601.04
3,871.44 9,165.60 - 13,037.04

A.4.7.1.10 1 m2 Pengecatan tembok baru (1 lapis plamuur , 1 lapis dasar , 2 lapis cat penutup)
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang cat 1.2.7.18 oh 0.0630 79,000.00 4,977.00
Kepala Tukang 1.2.7.3 oh 0.0063 93,500.00 589.05
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Plamur Tembok 2.2.6.38 Kg 0.1000 15,600.00 1,560.00
Cat Tembok 2.2.6.12 Kg 0.1000 24,300.00 2,430.00
Cat Tembok 2.2.6.12 Kg 0.2600 24,300.00 6,318.00
7,219.55 10,308.00 - 17,527.55
Overhead dan profit 0.1400 1,010.74 1,443.12 - 2,453.86
8,230.29 11,751.12 - 19,981.41

A.4.7.1.10a 1 m2 Pengecatan tembok Eksterior


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang cat 1.2.7.18 oh 0.0630 79,000.00 4,977.00
Kepala Tukang 1.2.7.3 oh 0.0063 93,500.00 589.05
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Plamur Tembok 2.2.6.38 Kg 0.1000 15,600.00 1,560.00
Cat Tembok exterior wheathershield 2.2.6.13 Kg 0.1000 121,300.00 12,130.00
Cat Tembok exterior wheathershield 2.2.6.13 Kg 0.2600 121,300.00 31,538.00
7,219.55 45,228.00 - 52,447.55
Overhead dan profit 0.1400 1,010.74 6,331.92 - 7,342.66
8,230.29 51,559.92 - 59,790.21

A.4.7.1.10b 1 m2 Pengecatan tembok Interior


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang cat 1.2.7.18 oh 0.0630 79,000.00 4,977.00
Kepala Tukang 1.2.7.3 oh 0.0063 93,500.00 589.05
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Plamur Tembok 2.2.6.38 Kg 0.1000 15,600.00 1,560.00
Cat Tembok interior premium 2.2.6.14 Kg 0.1000 54,900.00 5,490.00
Cat Tembok interior premium 2.2.6.14 Kg 0.2600 54,900.00 14,274.00
7,219.55 21,324.00 - 28,543.55
Overhead dan profit 0.1400 1,010.74 2,985.36 - 3,996.10
8,230.29 24,309.36 - 32,539.65

A.4.7.1.11 1 m2 Pengecatan tembok lama (1 lapis cat dasar ,2 lapis cat penutup)
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0280 68,500.00 1,918.00
Tukang cat 1.2.7.18 oh 0.0420 79,000.00 3,318.00
Kepala Tukang 1.2.7.3 oh 0.0042 93,500.00 392.70
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Cat Tembok 2.2.6.12 Kg 0.1200 24,300.00 2,916.00
Cat Tembok 2.2.6.12 Kg 0.1800 24,300.00 4,374.00
5,912.20 7,290.00 - 13,202.20
Overhead dan profit 0.1400 827.71 1,020.60 - 1,848.31
6,739.91 8,310.60 - 15,050.51

A.4.7.1.12 1 m2 Pelaburan tembok dengan kalkarium


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0280 68,500.00 1,918.00
Tukang cat 1.2.7.18 oh 0.0420 79,000.00 3,318.00
Kepala Tukang 1.2.7.3 oh 0.0042 93,500.00 392.70
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Kalkarium Kg 0.1000 #N/A #N/A
5,912.20 #N/A - #N/A
Overhead dan profit 0.1400 827.71 #N/A - #N/A
6,739.91 #N/A - #N/A

A.4.7.1.13 1 m2 Pelaburan tembok dengan kapur sirih


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1500 68,500.00 10,275.00
Tukang cat 1.2.7.18 oh 0.0010 79,000.00 79.00
Kepala Tukang 1.2.7.3 oh 0.0001 93,500.00 9.35
Mandor 1.2.7.5 oh 0.0025 94,500.00 236.25
Bahan
Kapur Batu ( sirih ) 2.2.1.45 Kg 0.1500 1,800.00 270.00
Kertas gosok ( rempelas ) 2.2.6.21 Lbr 0.1000 3,500.00 350.00
Kuas 3 " 2.2.6.22 Ikat 0.2500 15,100.00 3,775.00

123
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
10,599.60 4,395.00 - 14,994.60
Overhead dan profit 0.1400 1,483.94 615.30 - 2,099.24
12,083.54 5,010.30 - 17,093.84

A.4.7.1.14 1 m2 Pelaburan tembok lama dengan kapur sirih


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0400 68,500.00 2,740.00
Tukang cat 1.2.7.18 oh 0.0050 79,000.00 395.00
Kepala Tukang 1.2.7.3 oh 0.0005 93,500.00 46.75
Mandor 1.2.7.5 oh 0.0025 94,500.00 236.25
Bahan
Kapur Batu ( sirih ) 2.2.1.45 Kg 0.3000 1,800.00 540.00
Kertas gosok ( rempelas ) 2.2.6.21 Lbr 0.2000 3,500.00 700.00
Kuas 3 " 2.2.6.22 Ikat 0.2500 15,100.00 3,775.00
3,418.00 5,015.00 - 8,433.00
Overhead dan profit 0.1400 478.52 702.10 - 1,180.62
3,896.52 5,717.10 - 9,613.62

A.4.7.1.15 1 m2 Pemasangan wallpaper


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang cat 1.2.7.18 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0025 94,500.00 236.25
Bahan
Wallpaper ( standart ) 2.2.5.295 M2 1.2000 7,500.00 9,000.00
Lem ( Kayu + Tembok ) 2.2.6.24 Kg 0.2000 13,900.00 2,780.00
19,276.25 11,780.00 - 31,056.25
Overhead dan profit 0.1400 2,698.68 1,649.20 - 4,347.88
21,974.93 13,429.20 - 35,404.13

A.4.7.1.16 1 m2 Pengecatan permukaan baja dengan menie besi


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0200 68,500.00 1,370.00
Tukang cat 1.2.7.18 oh 0.2000 79,000.00 15,800.00
Kepala Tukang 1.2.7.3 oh 0.0200 93,500.00 1,870.00
Mandor 1.2.7.5 oh 0.0025 94,500.00 236.25
Bahan
Meni besi 2.2.6.26 M2 0.1000 34,700.00 3,470.00
Lem ( Kayu + Tembok ) 2.2.6.24 Kg 0.0100 13,900.00 139.00
19,276.25 3,609.00 - 22,885.25
Overhead dan profit 0.1400 2,698.68 505.26 - 3,203.94
21,974.93 4,114.26 - 26,089.19

A.4.7.1.17 1 m2 Pengecatan permukaan baja dengan menie besi dengan perancah


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang cat 1.2.7.18 oh 0.2250 79,000.00 17,775.00
Kepala Tukang 1.2.7.3 oh 0.0225 93,500.00 2,103.75
Mandor 1.2.7.5 oh 0.0075 94,500.00 708.75
Bahan
Meni besi 2.2.6.26 Kg 0.1000 34,700.00 3,470.00
Minyak Cat / Thiner B 2.2.6.29 L 0.0100 16,200.00 162.00
Kuas 3 " 2.2.6.22 Bh 0.0100 15,100.00 151.00
Kayu Tahun Balok ( Mauni/ Akasia ) 2.2.2.34 M3 0.0020 4,950,000.00 9,900.00
37,712.50 13,683.00 - 51,395.50
Overhead dan profit 0.1400 5,279.75 1,915.62 - 7,195.37
42,992.25 15,598.62 - 58,590.87

A.4.7.1.18 1 m2 Pengecatan permukaan baja galvanis secara manual 4 lapis


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 68,500.00 17,125.00
Tukang cat 1.2.7.18 oh 0.2500 79,000.00 19,750.00
Kepala Tukang 1.2.7.3 oh 0.0250 93,500.00 2,337.50
Mandor 1.2.7.5 oh 0.0013 94,500.00 122.85
Bahan
Minyak Cat / Thiner A 2.2.6.28 Kg 0.1000 30,000.00 3,000.00
Minyak Cat / Thiner B 2.2.6.29 Kg 0.1000 16,200.00 1,620.00
Cat besi 2.2.6.3 Kg 0.0800 59,500.00 4,760.00
Kuas 3 " 2.2.6.22 Bh 0.0100 15,100.00 151.00
Minyak Cat / Thiner B 2.2.6.29 l 0.0100 16,200.00 162.00
39,335.35 9,693.00 - 49,028.35
Overhead dan profit 0.1400 5,506.95 1,357.02 - 6,863.97
44,842.30 11,050.02 - 55,892.32

A.4.7.1.19 1 m2 Pengecatan permukaan baja galvanis secara manual sistem 1 lapis cat terakhir
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0600 68,500.00 4,110.00
Tukang cat 1.2.7.18 oh 0.0600 79,000.00 4,740.00
Kepala Tukang 1.2.7.3 oh 0.0120 93,500.00 1,122.00

124
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Cat besi 2.2.6.3 Kg 0.3000 59,500.00 17,850.00
Kuas 3 " 2.2.6.22 Bh 0.0100 15,100.00 151.00
Minyak Cat / Thiner B 2.2.6.29 l 0.0100 16,200.00 162.00
10,255.50 18,163.00 - 28,418.50
Overhead dan profit 0.1400 1,435.77 2,542.82 - 3,978.59
11,691.27 20,705.82 - 32,397.09

A.4.7.1.20 1 m2 Pengecatan permukaan baja galvanis secara manual sistem 3 lapis


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang cat 1.2.7.18 oh 0.8000 79,000.00 63,200.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0200 94,500.00 1,890.00
Bahan
Cat besi 2.2.6.3 Kg 0.1100 59,500.00 6,545.00
Cat besi 2.2.6.3 Kg 0.1700 59,500.00 10,115.00
Cat besi 2.2.6.3 Kg 0.0800 59,500.00 4,760.00
Kuas 3 " 2.2.6.22 Bh 0.0100 15,100.00 151.00
Minyak Cat / Thiner B 2.2.6.29 l 0.0100 16,200.00 162.00
99,970.00 21,733.00 - 121,703.00
Overhead dan profit 0.1400 13,995.80 3,042.62 - 17,038.42
113,965.80 24,775.62 - 138,741.42

A.4.7.1.21 1 m2 Pengecatan permukaan baja galvanis secara semprot sistem 3 lapis cat terakhir
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.4000 68,500.00 27,400.00
Tukang cat 1.2.7.18 oh 0.7000 79,000.00 55,300.00
Kepala Tukang 1.2.7.3 oh 0.0700 93,500.00 6,545.00
Mandor 1.2.7.5 oh 0.0200 94,500.00 1,890.00
Bahan
Cat besi 2.2.6.3 Kg 0.3000 59,500.00 17,850.00
Minyak Cat / Thiner A 2.2.6.28 l 0.0100 30,000.00 300.00
91,135.00 18,150.00 - 109,285.00
Overhead dan profit 0.1400 12,758.90 2,541.00 - 15,299.90
103,893.90 20,691.00 - 124,584.90

A.4.7.1.21a 1 m2 Pengecatan langit-langit (plafond)


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.0200 68,500.00 1,370.00
Tukang cat 1.2.7.18 Oh 0.0630 79,000.00 4,977.00
Kepala Tukang 1.2.7.3 Oh 0.0063 93,500.00 589.05
Mandor 1.2.7.5 Oh 0.0030 94,500.00 283.50
Bahan
Cat Tembok 2.2.6.12 Kg 0.1000 24,300.00 2,430.00
Cat Tembok 2.2.6.12 Kg 0.2600 24,300.00 6,318.00
7,219.55 8,748.00 - 15,967.55
Overhead dan profit 0.1400 1,010.74 1,224.72 - 2,235.46
8,230.29 9,972.72 - 18,203.01

A.4.7.1.21b 1 m2 Couttting ( Glasur batu alam )


Tenaga
Tukang cat 1.2.7.18 Oh 0.0750 79,000.00 5,925.00
Kepala Tukang 1.2.7.3 Oh 0.0080 93,500.00 748.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.0500 68,500.00 3,425.00
Mandor 1.2.7.5 Oh 0.0030 94,500.00 283.50
Bahan
Coatting 2.2.6.17 Ltr 0.3500 75,100.00 26,285.00
HCL / air keras 2.2.6.19 Ltr 0.1600 12,100.00 1,936.00
10,381.50 28,221.00 - 38,602.50
Overhead dan profit 0.1400 1,453.41 3,950.94 - 5,404.35
11,834.91 32,171.94 - 44,006.85

A.4.7.1.21c 1 m2 Pengecatan genteng ( 1 lapis cat dasar, 2 lapis cat penutup)


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.0280 68,500.00 1,918.00
Tukang cat 1.2.7.18 Oh 0.0420 79,000.00 3,318.00
Kepala Tukang 1.2.7.3 Oh 0.0042 93,500.00 392.70
Mandor 1.2.7.5 Oh 0.0025 94,500.00 236.25
Bahan
Cat genteng 2.2.6.4 Kg 0.1200 52,000.00 6,240.00
Cat genteng 2.2.6.4 Kg 0.1800 52,000.00 9,360.00
5,864.95 15,600.00 - 21,464.95
Overhead dan profit 0.1400 821.09 2,184.00 - 3,005.09
6,686.04 17,784.00 - 24,470.04

A.4.7.1.21d 1 m2 Sending impra ( melamine) 2.2.6.43


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2000 68,500.00 13,700.00

125
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tukang cat 1.2.7.18 oh 0.3000 79,000.00 23,700.00
Kepala Tukang 1.2.7.3 oh 0.0800 93,500.00 7,480.00
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Wood filler impra ( dempul jati ) 2.2.6.51 kg 0.2500 37,000.00 9,250.00
Sending impra ( melamine) 2.2.6.43 kg 0.2500 67,000.00 16,750.00
Clear melamin impra dof / gloos 2.2.6.16 kg 0.2500 63,600.00 15,900.00
Wood stain impra ( Pewarna melamine) 2.2.6.52 kg 0.2500 69,300.00 17,325.00
Minyak Cat / Thiner A 2.2.6.28 ltr 0.3750 30,000.00 11,250.00
Kertas gosok ( rempelas ) 180 lbr 1.0000 2,500.00 2,500.00
Kertas gosok ( rempelas ) 320 lbr 1.0000 2,500.00 2,500.00
Peralatan
Air Kompressor 0.0500 7,000.00 350.00
46,297.50 75,475.00 350.00 122,122.50
Overhead dan profit 0.1400 6,481.65 10,566.50 49.00 17,097.15
52,779.15 86,041.50 399.00 139,219.65

A.5.1.1 PEKERJAAN SANITASI DALAM GEDUNG

A.5.1.1.1 1 Bh Pemasangan closet duduk keramik


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.3000 68,500.00 226,050.00
Tukang batu 1.2.7.16 oh 1.1000 79,000.00 86,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Kloset Duduk Keramik 2.2.8.11 Unit 1.0000 601,800.00 601,800.00
Perlengkapan Ls 0.0600 601,800.00 36,108.00
329,005.00 637,908.00 - 966,913.00
Overhead dan profit 0.1400 46,060.70 89,307.12 - 135,367.82
375,065.70 727,215.12 - 1,102,280.82

A.5.1.1.1a 1 Bh Pemasangan closet duduk keramik komplit eks AMSTAD


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.3000 68,500.00 226,050.00
Tukang batu 1.2.7.16 oh 1.1000 79,000.00 86,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Kloset Duduk Keramik Komplit ex.AMSTAD 2.2.8.12 Unit 1.0000 2,086,500.00 2,086,500.00
Perlengkapan Ls 0.0600 2,086,500.00 125,190.00
329,005.00 2,211,690.00 - 2,540,695.00
Overhead dan profit 0.1400 46,060.70 309,636.60 - 355,697.30
375,065.70 2,521,326.60 - 2,896,392.30

A.5.1.1.1b 1 Bh Pemasangan closet duduk keramik komplit eks INA


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.3000 68,500.00 226,050.00
Tukang batu 1.2.7.16 oh 1.1000 79,000.00 86,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Kloset Duduk Keramik Komplit ex.INA 2.2.8.13 Unit 1.0000 1,376,800.00 1,376,800.00
Perlengkapan Ls 0.0600 1,376,800.00 82,608.00
329,005.00 1,459,408.00 - 1,788,413.00
Overhead dan profit 0.1400 46,060.70 204,317.12 - 250,377.82
375,065.70 1,663,725.12 - 2,038,790.82

A.5.1.1.1c 1 Bh Pemasangan closet duduk keramik komplit eks TOTO


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.3000 68,500.00 226,050.00
Tukang batu 1.2.7.16 oh 1.1000 79,000.00 86,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Kloset Duduk Keramik Komplit ex.TOTO 2.2.8.14 Unit 1.0000 2,673,200.00 2,673,200.00
Perlengkapan Ls 0.0600 2,673,200.00 160,392.00
329,005.00 2,833,592.00 - 3,162,597.00
Overhead dan profit 0.1400 46,060.70 396,702.88 - 442,763.58
375,065.70 3,230,294.88 - 3,605,360.58

A.5.1.1.1d 1 Bh Pemasangan closet monoblock lokal


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.3000 68,500.00 226,050.00
Tukang batu 1.2.7.16 oh 1.1000 79,000.00 86,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Kloset Monoblok Lokal 2.2.8.18 Unit 1.0000 974,300.00 974,300.00

126
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Perlengkapan Ls 0.0600 974,300.00 58,458.00
329,005.00 1,032,758.00 - 1,361,763.00
Overhead dan profit 0.1400 46,060.70 144,586.12 - 190,646.82
375,065.70 1,177,344.12 - 1,552,409.82

A.5.1.1.2 1 Bh Pemasangan closet jongkok keramik eks AMSTAD


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang batu 1.2.7.16 oh 1.5000 79,000.00 118,500.00
Kepala Tukang 1.2.7.3 oh 0.1500 93,500.00 14,025.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Kloset Jongkok Keramik ex.AMSTAD 2.2.8.15 Unit 1.0000 237,900.00 237,900.00
PC / Portland cement 2.2.1.52 Kg 6.0000 1,400.00 8,400.00
Pasir pasang / beton 2.2.1.50 Ls 0.1000 264,000.00 26,400.00
216,145.00 272,700.00 - 488,845.00
Overhead dan profit 0.1400 30,260.30 38,178.00 - 68,438.30
246,405.30 310,878.00 - 557,283.30

A.5.1.1.2a 1 Bh Pemasangan closet jongkok keramik eks INA


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang batu 1.2.7.16 oh 1.5000 79,000.00 118,500.00
Kepala Tukang 1.2.7.3 oh 0.1500 93,500.00 14,025.00
Mandor 1.2.7.5 oh 0.1600 94,500.00 15,120.00
Bahan
Kloset Jongkok Keramik ex.INA 2.2.8.16 Unit 1.0000 142,700.00 142,700.00
PC / Portland cement 2.2.1.52 Kg 6.0000 1,400.00 8,400.00
Pasir pasang / beton 2.2.1.50 Ls 0.1000 264,000.00 26,400.00
216,145.00 177,500.00 - 393,645.00
Overhead dan profit 0.1400 30,260.30 24,850.00 - 55,110.30
246,405.30 202,350.00 - 448,755.30

A.5.1.1.3 1 Bh Pemasangan closet duduk jongkok teraso


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang batu 1.2.7.16 oh 1.5000 79,000.00 118,500.00
Kepala Tukang 1.2.7.3 oh 0.1500 93,500.00 14,025.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Kloset Jongkok teraso 2.2.8.17 Unit 1.0000 140,900.00 140,900.00
PC / Portland cement 2.2.1.52 Kg 6.0000 1,400.00 8,400.00
Pasir pasang / beton 2.2.1.50 Ls 0.0100 264,000.00 2,640.00
Batu Bata / Merah 2.2.1.14 Bh 7.0000 900.00 6,300.00
205,750.00 158,240.00 - 363,990.00
Overhead dan profit 0.1400 28,805.00 22,153.60 - 50,958.60
234,555.00 180,393.60 - 414,948.60

A.5.1.1.4 1 Bh Pemasangan urinoir


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.0000 68,500.00 68,500.00
Tukang batu 1.2.7.16 oh 1.0000 79,000.00 79,000.00
Kepala Tukang 1.2.7.3 oh 0.1000 93,500.00 9,350.00
Mandor 1.2.7.5 oh 0.0500 94,500.00 4,725.00
Bahan
Urinoir 2.2.8.137 Unit 1.0000 1,148,100.00 1,148,100.00
PC / Portland cement 2.2.1.52 Kg 6.0000 1,400.00 8,400.00
Pasir pasang / beton 2.2.1.50 M3 0.0100 264,000.00 2,640.00
Perlengkapan % 0.3000 1,148,100.00 344,430.00
161,575.00 1,503,570.00 - 1,665,145.00
Overhead dan profit 0.1400 22,620.50 210,499.80 - 233,120.30
184,195.50 1,714,069.80 - 1,898,265.30

A.5.1.1.5 1 Bh Pemasangan wastafel besar warna muda eks INA


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.2000 68,500.00 82,200.00
Tukang batu 1.2.7.16 oh 1.4500 79,000.00 114,550.00
Kepala Tukang 1.2.7.3 oh 0.1500 93,500.00 14,025.00
Mandor 1.2.7.5 oh 0.0600 94,500.00 5,670.00
Bahan
Wastafel Besar Warna Muda ex.INA 2.2.8.138 Unit 1.2000 269,500.00 323,400.00
PC / Portland cement 2.2.1.52 Kg 6.0000 1,400.00 8,400.00
Pasir pasang / beton 2.2.1.50 M3 0.0100 264,000.00 2,640.00
Perlengkapan % 0.1200 269,500.00 32,340.00
216,445.00 366,780.00 - 583,225.00
Overhead dan profit 0.1400 30,302.30 51,349.20 - 81,651.50
246,747.30 418,129.20 - 664,876.50

A.5.1.1.5a 1 Bh Pemasangan wastafel besar warna tua eks INA


Tenaga

127
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.2000 68,500.00 82,200.00
Tukang batu 1.2.7.16 oh 1.4500 79,000.00 114,550.00
Kepala Tukang 1.2.7.3 oh 0.1500 93,500.00 14,025.00

128
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0600 94,500.00 5,670.00
Bahan
Wastafel Besar Warna Tua ex.INA 2.2.8.139 Unit 1.2000 298,700.00 358,440.00
PC / Portland cement 2.2.1.52 Kg 6.0000 1,400.00 8,400.00
Pasir pasang / beton 2.2.1.50 M3 0.0100 264,000.00 2,640.00
Perlengkapan % 0.1200 298,700.00 35,844.00
216,445.00 405,324.00 - 621,769.00
Overhead dan profit 0.1400 30,302.30 56,745.36 - 87,047.66
246,747.30 462,069.36 - 708,816.66

A.5.1.1.6 1 Bh Pemasangan bathcuip porselen


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0750 68,500.00 5,137.50
Tukang batu 1.2.7.16 oh 0.7500 79,000.00 59,250.00
Kepala Tukang 1.2.7.3 oh 0.0750 93,500.00 7,012.50
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Bak Kip 2.2.8.5 Unit 1.0000 1,991,200.00 1,991,200.00
Perlengkapan % 0.2000 1,991,200.00 398,240.00
71,683.50 2,389,440.00 - 2,461,123.50
Overhead dan profit 0.1400 10,035.69 334,521.60 - 344,557.29
81,719.19 2,723,961.60 - 2,805,680.79

A.5.1.1.7 1 Bh Pemasangan bak fiberglass vol 1 m3


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.0000 68,500.00 205,500.00
Tukang batu 1.2.7.16 oh 4.5000 79,000.00 355,500.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.9000 94,500.00 85,050.00
Bahan
Bak Mandi Fiber glass, 1.00 m x 1.00 m 2.2.8.7 Unit 1.0000 300,900.00 300,900.00
Perlengkapan % 0.1200 300,900.00 36,108.00
650,725.00 337,008.00 - 987,733.00
Overhead dan profit 0.1400 91,101.50 47,181.12 - 138,282.62
741,826.50 384,189.12 - 1,126,015.62

A.5.1.1.8 1 Bh Pemasangan bak mandi batu vol 0,30 m3


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 6.0000 68,500.00 411,000.00
Tukang batu 1.2.7.16 oh 3.0000 79,000.00 237,000.00
Kepala Tukang 1.2.7.3 oh 0.3000 93,500.00 28,050.00
Mandor 1.2.7.5 oh 0.0300 94,500.00 2,835.00
Bahan
Batu Bata / Merah 2.2.1.14 m3 150.0000 900.00 135,000.00
PC / Portland cement 2.2.1.52 Kg 120.0000 1,400.00 168,000.00
Pasir pasang / beton 2.2.1.50 m3 0.3000 264,000.00 79,200.00
Keramik putih Uk. 30 cm x 30 cm 2.2.5.243 bh 4.3560 47,400.00 206,474.40
Semen Putih / warna 2.2.1.54 Kg 6.0000 3,000.00 18,000.00
678,885.00 606,674.40 - 1,285,559.40
Overhead dan profit 0.1400 95,043.90 84,934.42 - 179,978.32
773,928.90 691,608.82 - 1,465,537.72

A.5.1.1.9 1 Bh Pemasangan bak mandi teraso vol 0,30 m3


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.0000 68,500.00 205,500.00
Tukang batu 1.2.7.16 oh 4.5000 79,000.00 355,500.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.9000 94,500.00 85,050.00
Bahan
Bak Mandi teraso 2.2.8.8 Unit 1.0000 110,300.00 110,300.00
Perlengkapan % 0.1200 110,300.00 13,236.00
650,725.00 123,536.00 - 774,261.00
Overhead dan profit 0.1400 91,101.50 17,295.04 - 108,396.54
741,826.50 140,831.04 - 882,657.54

A.5.1.1.10 1 Bh Pemasangan bak mandi fiberglass vol 1 m3


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 68,500.00 20,550.00
Tukang batu 1.2.7.16 oh 0.4500 79,000.00 35,550.00
Kepala Tukang 1.2.7.3 oh 0.0450 93,500.00 4,207.50
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Bak Mandi Fiber glass, 1.00 m x 1.00 m 2.2.8.7 Unit 1.0000 300,900.00 300,900.00
Perlengkapan % 0.1200 300,900.00 36,108.00
61,725.00 337,008.00 - 398,733.00
Overhead dan profit 0.1400 8,641.50 47,181.12 - 55,822.62
70,366.50 384,189.12 - 454,555.62

A.5.1.1.11 1 Bh Pemasangan bak mandi beton vol 1 m3


Tenaga

129
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.5000 68,500.00 239,750.00
Tukang batu 1.2.7.16 oh 4.5000 79,000.00 355,500.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0180 94,500.00 1,701.00
Bahan
Beton 1:2:3 m3 0.9000 995,097.10 895,587.39
Besi Beton / tulangan beton 2.2.4.9 Kg 180.0000 10,500.00 1,890,000.00
Kayu Bekisting 2.2.2.15 m2 0.0800 3,465,000.00 277,200.00
Keramik putih Uk. 30 cm x 30 cm 2.2.5.243 m2 6.0500 47,400.00 286,770.00
Perlengkapan % 0.1000 995,097.10 99,509.71
601,626.00 3,449,067.10 - 4,050,693.10
Overhead dan profit 0.1400 84,227.64 482,869.39 - 567,097.03
685,853.64 3,931,936.49 - 4,617,790.13

A.5.1.1.12 1 Bh Pemasangan bak cuci piring stainlessteel


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0300 68,500.00 2,055.00
Tukang batu 1.2.7.16 oh 0.3000 79,000.00 23,700.00
Kepala Tukang 1.2.7.3 oh 0.0300 93,500.00 2,805.00

130
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Mandor 1.2.7.5 oh 0.0150 94,500.00 1,417.50
Bahan
Bak Cuci Stainlesstel (Royal) 2.2.8.4 Unit 1.0000 253,000.00 253,000.00
Kran cucian dia 3/4" 2.2.8.29 Bh 1.0000 75,700.00 75,700.00
29,977.50 328,700.00 - 358,677.50
Overhead dan profit 0.1400 4,196.85 46,018.00 - 50,214.85
34,174.35 374,718.00 - 408,892.35

A.5.1.1.13 1 Bh Pemasangan bak cuci piring teraso


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0500 68,500.00 3,425.00
Tukang batu 1.2.7.16 oh 0.5000 79,000.00 39,500.00
Kepala Tukang 1.2.7.3 oh 0.0500 93,500.00 4,675.00
Mandor 1.2.7.5 oh 0.0250 94,500.00 2,362.50
Bahan
Bak cuci traso 2.2.8.3 Unit 1.0000 205,000.00 205,000.00
Kran cucian dia 3/4" 2.2.8.29 Bh 1.0000 75,700.00 75,700.00
PC / Portland cement 2.2.1.52 Kg 20.0000 1,400.00 28,000.00
Pasir pasang / beton 2.2.1.50 m3 0.0500 264,000.00 13,200.00
49,962.50 321,900.00 - 371,862.50
Overhead dan profit 0.1400 6,994.75 45,066.00 - 52,060.75
56,957.25 366,966.00 - 423,923.25

A.5.1.1.14 1 Bh Pemasangan floor drain plastik


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Avor plastik / floor drain 2.2.8.1 Unit 1.0000 11,200.00 11,200.00
9,992.50 11,200.00 - 21,192.50
Overhead dan profit 0.1400 1,398.95 1,568.00 - 2,966.95
11,391.45 12,768.00 - 24,159.45

A.5.1.1.14a 1 Bh Pemasangan floor drain staninlees steel


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.1000 79,000.00 7,900.00
Kepala Tukang 1.2.7.3 oh 0.0100 93,500.00 935.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Avor staninlees steel 2.2.8.2 Unit 1.0000 47,400.00 47,400.00
9,992.50 47,400.00 - 57,392.50
Overhead dan profit 0.1400 1,398.95 6,636.00 - 8,034.95
11,391.45 54,036.00 - 65,427.45

A.5.1.1.15 1 Bh Pemasangan bak kontrol pasangan bata 30x30 tinggi 35cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 2.1600 68,500.00 147,960.00
Tukang batu 1.2.7.16 oh 0.7200 79,000.00 56,880.00
Kepala Tukang 1.2.7.3 oh 0.0720 93,500.00 6,732.00
Mandor 1.2.7.5 oh 0.0011 94,500.00 103.95
Bahan
Batu Bata / Merah 2.2.1.14 bh 40.0000 900.00 36,000.00
PC / Portland cement 2.2.1.52 Kg 44.0000 1,400.00 61,600.00
Pasir pasang / beton 2.2.1.50 m3 0.0700 264,000.00 18,480.00
Pasir pasang / beton 2.2.1.50 m3 0.0600 264,000.00 15,840.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0700 300,000.00 21,000.00
Besi Beton / tulangan beton 2.2.4.9 Kg 1.6000 10,500.00 16,800.00
211,675.95 169,720.00 - 381,395.95
Overhead dan profit 0.1400 29,634.63 23,760.80 - 53,395.43
241,310.58 193,480.80 - 434,791.38

A.5.1.1.16 1 Bh Pemasangan bak kontrol pasangan bata 45x45 tinggi 50cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.2000 68,500.00 219,200.00
Tukang batu 1.2.7.16 oh 1.1500 79,000.00 90,850.00
Kepala Tukang 1.2.7.3 oh 0.0110 93,500.00 1,028.50
Mandor 1.2.7.5 oh 0.0160 94,500.00 1,512.00
Bahan
Batu Bata / Merah 2.2.1.14 bh 70.0000 900.00 63,000.00
PC / Portland cement 2.2.1.52 Kg 77.0000 1,400.00 107,800.00
Pasir pasang / beton 2.2.1.50 m3 0.1300 264,000.00 34,320.00
Pasir pasang / beton 2.2.1.50 m3 0.0900 264,000.00 23,760.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0200 300,000.00 6,000.00
Besi Beton / tulangan beton 2.2.4.9 Kg 2.6000 10,500.00 27,300.00
312,590.50 262,180.00 - 574,770.50
Overhead dan profit 0.1400 43,762.67 36,705.20 - 80,467.87
356,353.17 298,885.20 - 655,238.37

131
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.5.1.1.17 1 Bh Pemasangan bak kontrol pasangan bata 60x60 tinggi 65cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 3.2000 68,500.00 219,200.00
Tukang batu 1.2.7.16 oh 1.1500 79,000.00 90,850.00
Kepala Tukang 1.2.7.3 oh 0.0110 93,500.00 1,028.50
Mandor 1.2.7.5 oh 0.0160 94,500.00 1,512.00
Bahan
Batu Bata / Merah 2.2.1.14 bh 123.0000 900.00 110,700.00
PC / Portland cement 2.2.1.52 Kg 114.0000 1,400.00 159,600.00
Pasir pasang / beton 2.2.1.50 m3 0.1840 264,000.00 48,576.00
Pasir pasang / beton 2.2.1.50 m3 0.1200 264,000.00 31,680.00
Batu pecah 2-3 cm 2.2.1.32 m3 0.0330 300,000.00 9,900.00
Besi Beton / tulangan beton 2.2.4.9 Kg 4.8500 10,500.00 50,925.00
312,590.50 411,381.00 - 723,971.50
Overhead dan profit 0.1400 43,762.67 57,593.34 - 101,356.01
356,353.17 468,974.34 - 825,327.51

A.5.1.1.18 1 m' Pemasangan pipa galvanis diameter 1/2"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0540 68,500.00 3,699.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0270 94,500.00 2,551.50
Bahan
Pipa GI Med. Ø 0,5" (SNI 0039:2013) 2.2.11.2.1 M 1.2000 22,900.00 27,480.00
Perlengkapan Ls 0.3500 22,900.00 8,015.00
14,202.00 35,495.00 - 49,697.00
Overhead dan profit 0.1400 1,988.28 4,969.30 - 6,957.58
16,190.28 40,464.30 - 56,654.58

A.5.1.1.19 1 m' Pemasangan kran diameter 1/2"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kran Dia 1/2 " 2.2.8.30 M 1.0000 27,700.00 27,700.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 27,757.75 - 64,255.25
Overhead dan profit 0.1400 5,109.65 3,886.09 - 8,995.74
41,607.15 31,643.84 - 73,250.99

A.5.1.1.19a 1 m' Pemasangan kran diameter 3/4"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kran Dia 3/4 " 2.2.8.31 M 1.0000 32,900.00 32,900.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 32,957.75 - 69,455.25
Overhead dan profit 0.1400 5,109.65 4,614.09 - 9,723.74
41,607.15 37,571.84 - 79,178.99

A.5.1.1.19b 1 m' Pemasangan kran dupon


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kran Dupon 2.2.8.32 M 1.0000 159,900.00 159,900.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 159,957.75 - 196,455.25
Overhead dan profit 0.1400 5,109.65 22,394.09 - 27,503.74
41,607.15 182,351.84 - 223,958.99

A.5.1.1.19c 1 m' Pemasangan kran Toto 1/2"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Kran Toto 1/2" 2.2.8.33 M 1.0000 306,700.00 306,700.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 306,757.75 - 343,255.25

132
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Overhead dan profit 0.1400 5,109.65 42,946.09 - 48,055.74
41,607.15 349,703.84 - 391,310.99

A.5.1.1.19d 1 m' Pemasangan stop kran diameter 1"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Stop Kran Dia 1 " 2.2.8.116 M 1.0000 23,700.00 23,700.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 23,757.75 - 60,255.25
Overhead dan profit 0.1400 5,109.65 3,326.09 - 8,435.74
41,607.15 27,083.84 - 68,690.99

A.5.1.1.19e 1 m' Pemasangan stop kran diameter 1/2"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Stop Kran Dia 1/2 " 2.2.8.117 M 1.0000 31,200.00 31,200.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 31,257.75 - 67,755.25
Overhead dan profit 0.1400 5,109.65 4,376.09 - 9,485.74
41,607.15 35,633.84 - 77,240.99

A.5.1.1.19f 1 m' Pemasangan stop kran diameter 3/4"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Stop Kran Dia 3/4 " 2.2.8.118 M 1.0000 20,200.00 20,200.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 20,257.75 - 56,755.25
Overhead dan profit 0.1400 5,109.65 2,836.09 - 7,945.74
41,607.15 23,093.84 - 64,700.99

A.5.1.1.19g 1 m' Pemasangan stop kran diameter 1" kuningan


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Stop kran dia 1" kuningan 2.2.8.119 M 1.0000 80,900.00 80,900.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 80,957.75 - 117,455.25
Overhead dan profit 0.1400 5,109.65 11,334.09 - 16,443.74
41,607.15 92,291.84 - 133,898.99

A.5.1.1.19h 1 m' Pemasangan stop kran diameter 1/2" kuningan


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Stop kran dia 1/2" kuningan 2.2.8.121 M 1.0000 76,800.00 76,800.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 76,857.75 - 113,355.25
Overhead dan profit 0.1400 5,109.65 10,760.09 - 15,869.74
41,607.15 87,617.84 - 129,224.99

A.5.1.1.19i 1 m' Pemasangan stop kran diameter 3/4" kuningan


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Stop kran dia 3/4" kuningan 2.2.8.122 M 1.0000 59,500.00 59,500.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 59,557.75 - 96,055.25
Overhead dan profit 0.1400 5,109.65 8,338.09 - 13,447.74
41,607.15 67,895.84 - 109,502.99

133
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.5.1.1.19j 1 m' Pemasangan stop kran diameter 1" plastik


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Stop kran dia 1" plastik 2.2.8.120 M 1.0000 20,800.00 20,800.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 20,857.75 - 57,355.25
Overhead dan profit 0.1400 5,109.65 2,920.09 - 8,029.74
41,607.15 23,777.84 - 65,384.99

A.5.1.1.19k 1 m' Pemasangan stop kran diameter 1/2"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0100 68,500.00 685.00
Tukang batu 1.2.7.16 oh 0.4000 79,000.00 31,600.00
Kepala Tukang 1.2.7.3 oh 0.0400 93,500.00 3,740.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Stop Kran Ǿ 1/2" 2.2.8.123 M 1.0000 26,000.00 26,000.00
Seal Tape 2.2.8.115 Buah 0.0025 23,100.00 57.75
36,497.50 26,057.75 - 62,555.25
Overhead dan profit 0.1400 5,109.65 3,648.09 - 8,757.74
41,607.15 29,705.84 - 71,312.99

A.5.1.1.20 1 m' Pemasangan pipa galvanis diameter 3/4"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0540 68,500.00 3,699.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0270 94,500.00 2,551.50
Bahan #N/A
Pipa GI Med. Ø 0,75" (SNI 0039:2013) 2.2.11.2.2 M 1.2000 29,400.00 35,280.00
Perlengkapan % 0.3500 29,400.00 10,290.00
14,202.00 45,570.00 - 59,772.00
Overhead dan profit 0.1400 1,988.28 6,379.80 - 8,368.08
16,190.28 51,949.80 - 68,140.08

A.5.1.1.21 1 m' Pemasangan pipa galvanis diameter 1"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0540 68,500.00 3,699.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0270 94,500.00 2,551.50
Bahan #N/A
Pipa GI Med. Ø 1" (SNI 0039:2013) 2.2.11.2.3 M 1.2000 45,000.00 54,000.00
Perlengkapan % 0.3500 45,000.00 15,750.00
14,202.00 69,750.00 - 83,952.00
Overhead dan profit 0.1400 1,988.28 9,765.00 - 11,753.28
16,190.28 79,515.00 - 95,705.28

A.5.1.1.22 1 m' Pemasangan pipa galvanis diameter 1 1/2"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1080 68,500.00 7,398.00
Tukang batu 1.2.7.16 oh 0.1800 79,000.00 14,220.00
Kepala Tukang 1.2.7.3 oh 0.0180 93,500.00 1,683.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Pipa GI Med. Ø 1,5" (SNI 0039:2013) 2.2.11.2.4 M 1.2000 68,200.00 81,840.00
Perlengkapan % 0.3500 68,200.00 23,870.00
23,773.50 105,710.00 - 129,483.50
Overhead dan profit 0.1400 3,328.29 14,799.40 - 18,127.69
27,101.79 120,509.40 - 147,611.19

A.5.1.1.22a 1 m' Pemasangan pipa galvanis diameter 2"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1080 68,500.00 7,398.00
Tukang batu 1.2.7.16 oh 0.1800 79,000.00 14,220.00
Kepala Tukang 1.2.7.3 oh 0.0180 93,500.00 1,683.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Pipa GI Med. Ø 2" (SNI 0039:2013) 2.2.11.2.5 M 1.2000 93,100.00 111,720.00
Perlengkapan % 0.3500 93,100.00 32,585.00
23,773.50 144,305.00 - 168,078.50
Overhead dan profit 0.1400 3,328.29 20,202.70 - 23,530.99
27,101.79 164,507.70 - 191,609.49

A.5.1.1.22b 1 m' Pemasangan pipa galvanis diameter 2 1/2"

134
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1080 68,500.00 7,398.00
Tukang batu 1.2.7.16 oh 0.1800 79,000.00 14,220.00
Kepala Tukang 1.2.7.3 oh 0.0180 93,500.00 1,683.00
Mandor 1.2.7.5 oh 0.0050 94,500.00 472.50
Bahan
Pipa GI Med. Ø 2,5" (SNI 0039:2013) 2.2.11.2.6 M 1.2000 118,800.00 142,560.00
Perlengkapan % 0.3500 118,800.00 41,580.00
23,773.50 184,140.00 - 207,913.50
Overhead dan profit 0.1400 3,328.29 25,779.60 - 29,107.89
27,101.79 209,919.60 - 237,021.39

A.5.1.1.23 1 m' Pemasangan pipa galvanis diameter 3"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1350 68,500.00 9,247.50
Tukang batu 1.2.7.16 oh 0.2250 79,000.00 17,775.00
Kepala Tukang 1.2.7.3 oh 0.0230 93,500.00 2,150.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Pipa GI Med. Ø 3" (SNI 0039:2013) 2.2.11.2.7 M 1.2000 153,500.00 184,200.00
Perlengkapan % 0.3500 153,500.00 53,725.00
29,834.50 237,925.00 - 267,759.50
Overhead dan profit 0.1400 4,176.83 33,309.50 - 37,486.33
34,011.33 271,234.50 - 305,245.83

A.5.1.1.24 1 m' Pemasangan pipa galvanis diameter 4"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1350 68,500.00 9,247.50
Tukang batu 1.2.7.16 oh 0.2250 79,000.00 17,775.00
Kepala Tukang 1.2.7.3 oh 0.0230 93,500.00 2,150.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Pipa GI Med. Ø 4" (SNI 0039:2013) 2.2.11.2.8 M 1.2000 222,100.00 266,520.00
Perlengkapan % 0.3500 222,100.00 77,735.00
29,834.50 344,255.00 - 374,089.50
Overhead dan profit 0.1400 4,176.83 48,195.70 - 52,372.53
34,011.33 392,450.70 - 426,462.03

A.5.1.1.25 1 m' Pemasangan pipa PVC tipe AW diameter 1/2"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0360 68,500.00 2,466.00
Tukang batu 1.2.7.16 oh 0.0600 79,000.00 4,740.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan
PVC AW Dia 0.5 " ( abu - abu ) 2.2.8.57 M 1.2000 2,900.00 3,480.00
Perlengkapan % 0.3500 2,900.00 1,015.00
7,956.00 4,495.00 - 12,451.00
Overhead dan profit 0.1400 1,113.84 629.30 - 1,743.14
9,069.84 5,124.30 - 14,194.14

A.5.1.1.26 1 m' Pemasangan pipa PVC tipe AW diameter 3/4"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0360 68,500.00 2,466.00
Tukang batu 1.2.7.16 oh 0.0600 79,000.00 4,740.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan
PVC AW Dia 0.75 " ( abu - abu ) 2.2.8.58 M 1.2000 8,700.00 10,440.00
Perlengkapan % 0.3500 8,700.00 3,045.00
7,956.00 13,485.00 - 21,441.00
Overhead dan profit 0.1400 1,113.84 1,887.90 - 3,001.74
9,069.84 15,372.90 - 24,442.74

A.5.1.1.27 1 m' Pemasangan pipa PVC tipe AW diameter 1"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0360 68,500.00 2,466.00
Tukang batu 1.2.7.16 oh 0.0600 79,000.00 4,740.00
Kepala Tukang 1.2.7.3 oh 0.0060 93,500.00 561.00
Mandor 1.2.7.5 oh 0.0020 94,500.00 189.00
Bahan
PVC AW Dia 1 " ( abu - abu ) 2.2.8.59 M 1.2000 11,000.00 13,200.00
Perlengkapan % 0.3500 11,000.00 3,850.00
7,956.00 17,050.00 - 25,006.00
Overhead dan profit 0.1400 1,113.84 2,387.00 - 3,500.84
9,069.84 19,437.00 - 28,506.84

A.5.1.1.28 1 m' Pemasangan pipa PVC tipe AW diameter 11/2"

135
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0540 68,500.00 3,699.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
PVC AW Dia 1,5 " ( abu - abu ) 2.2.8.61 M 1.2000 17,400.00 20,880.00
Perlengkapan % 0.3500 17,400.00 6,090.00
11,934.00 26,970.00 - 38,904.00
Overhead dan profit 0.1400 1,670.76 3,775.80 - 5,446.56
13,604.76 30,745.80 - 44,350.56

A.5.1.1.29 1 m' Pemasangan pipa PVC tipe AW diameter 2"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0540 68,500.00 3,699.00
Tukang batu 1.2.7.16 oh 0.0900 79,000.00 7,110.00
Kepala Tukang 1.2.7.3 oh 0.0090 93,500.00 841.50
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
PVC AW Dia 2 " ( abu - abu ) 2.2.8.62 M 1.2000 20,200.00 24,240.00
Perlengkapan % 0.3500 20,200.00 7,070.00
11,934.00 31,310.00 - 43,244.00
Overhead dan profit 0.1400 1,670.76 4,383.40 - 6,054.16
13,604.76 35,693.40 - 49,298.16

A.5.1.1.30 1 m' Pemasangan pipa PVC tipe AW diameter 21/2"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0810 68,500.00 5,548.50
Tukang batu 1.2.7.16 oh 0.1350 79,000.00 10,665.00
Kepala Tukang 1.2.7.3 oh 0.0135 93,500.00 1,262.25
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
PVC AW Dia 2 ,5" ( abu - abu ) 2.2.8.63 M 1.2000 28,900.00 34,680.00
Perlengkapan % 0.3500 28,900.00 10,115.00
17,853.75 44,795.00 - 62,648.75
Overhead dan profit 0.1400 2,499.53 6,271.30 - 8,770.83
20,353.28 51,066.30 - 71,419.58

A.5.1.1.31 1 m' Pemasangan pipa PVC tipe AW diameter 3"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0810 68,500.00 5,548.50
Tukang batu 1.2.7.16 oh 0.1350 79,000.00 10,665.00
Kepala Tukang 1.2.7.3 oh 0.0135 93,500.00 1,262.25
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
PVC AW Dia 3 " ( abu - abu ) 2.2.8.64 M 1.2000 34,700.00 41,640.00
Perlengkapan % 0.3500 34,700.00 12,145.00
17,853.75 53,785.00 - 71,638.75
Overhead dan profit 0.1400 2,499.53 7,529.90 - 10,029.43
20,353.28 61,314.90 - 81,668.18

A.5.1.1.32 1 m' Pemasangan pipa PVC tipe AW diameter 4"


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0810 68,500.00 5,548.50
Tukang batu 1.2.7.16 oh 0.1350 79,000.00 10,665.00
Kepala Tukang 1.2.7.3 oh 0.0135 93,500.00 1,262.25
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
PVC AW Dia 4 " ( abu - abu ) 2.2.8.65 M 1.2000 52,000.00 62,400.00
Perlengkapan % 0.3500 52,000.00 18,200.00
17,853.75 80,600.00 - 98,453.75
Overhead dan profit 0.1400 2,499.53 11,284.00 - 13,783.53
20,353.28 91,884.00 - 112,237.28

A.5.1.1.33 1 m' Pemasangan pipa air limbah jenis pipa tanah Ø 20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0800 68,500.00 5,480.00
Tukang batu 1.2.7.16 oh 0.0400 79,000.00 3,160.00
Kepala Tukang 1.2.7.3 oh 0.0040 93,500.00 374.00
Mandor 1.2.7.5 oh 0.0040 94,500.00 378.00
Bahan
Buis Beton ø 20 Cm 2.2.10.15 Bh 1.6000 63,600.00 101,760.00
PC / Portland cement 2.2.1.52 Kg 35.0000 1,400.00 49,000.00
Pasir pasang / beton 2.2.1.50 M3 0.0140 264,000.00 3,696.00
Pasir Urug 2.2.1.51 M3 0.0140 173,300.00 2,426.20
9,392.00 156,882.20 - 166,274.20
Overhead dan profit 0.1400 1,314.88 21,963.51 - 23,278.39
10,706.88 178,845.71 - 189,552.59

A.5.1.1.34 1 m' Pemasangan pipa air limbah jenis pipa tanah Ø 15 cm

136
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.0600 68,500.00 4,110.00
Tukang batu 1.2.7.16 oh 0.0300 79,000.00 2,370.00
Kepala Tukang 1.2.7.3 oh 0.0030 93,500.00 280.50
Mandor 1.2.7.5 oh 0.0030 94,500.00 283.50
Bahan
Pipa tanah dia 15 Bh 1.6000 #N/A #N/A
PC / Portland cement 2.2.1.52 kg 0.6800 1,400.00 952.00
Pasir pasang / beton 2.2.1.50 m3 0.0130 264,000.00 3,432.00
Pasir Urug 2.2.1.51 M3 0.0110 173,300.00 1,906.30
7,044.00 #N/A - #N/A
Overhead dan profit 0.1400 986.16 #N/A - #N/A
8,030.16 #N/A - #N/A

A.5.1.1.35 1 m' Pemasangan pipa beton diameter 15-20 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.1400 68,500.00 9,590.00
Tukang batu 1.2.7.16 oh 0.0700 79,000.00 5,530.00
Kepala Tukang 1.2.7.3 oh 0.0070 93,500.00 654.50
Mandor 1.2.7.5 oh 0.0070 94,500.00 661.50
Bahan
Buis Beton ø 20 Cm 2.2.10.15 Bh 1.1000 63,600.00 69,960.00
Batu Bata / Merah 2.2.1.14 M3 21.0000 900.00 18,900.00
PC / Portland cement 2.2.1.52 Kg 3.9200 1,400.00 5,488.00
Pasir pasang / beton 2.2.1.50 M3 0.0560 264,000.00 14,784.00
Pasir Urug 2.2.1.51 M3 0.0240 173,300.00 4,159.20
16,436.00 113,291.20 - 129,727.20
Overhead dan profit 0.1400 2,301.04 15,860.77 - 18,161.81
18,737.04 129,151.97 - 147,889.01

A.5.1.1.36 1 m' Pemasangan pipa beton diameter 30 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3800 68,500.00 26,030.00
Tukang batu 1.2.7.16 oh 0.1900 79,000.00 15,010.00
Kepala Tukang 1.2.7.3 oh 0.0190 93,500.00 1,776.50
Mandor 1.2.7.5 oh 0.0190 94,500.00 1,795.50
Bahan
Buis Beton ø 30 Cm 2.2.10.16 Bh 1.1000 86,700.00 95,370.00
Batu Bata / Merah 2.2.1.14 M3 42.0000 900.00 37,800.00
PC / Portland cement 2.2.1.52 Kg 10.3000 1,400.00 14,420.00
Pasir pasang / beton 2.2.1.50 M3 0.0610 264,000.00 16,104.00
Pasir Urug 2.2.1.51 M3 0.0690 173,300.00 11,957.70
44,612.00 175,651.70 - 220,263.70
Overhead dan profit 0.1400 6,245.68 24,591.24 - 30,836.92
50,857.68 200,242.94 - 251,100.62

A.5.1.1.36a 1 m' Pemasangan pipa beton diameter 40 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3800 68,500.00 26,030.00
Tukang batu 1.2.7.16 oh 0.1900 79,000.00 15,010.00
Kepala Tukang 1.2.7.3 oh 0.0190 93,500.00 1,776.50
Mandor 1.2.7.5 oh 0.0190 94,500.00 1,795.50
Bahan
Buis Beton ø 40 Cm 2.2.10.17 Bh 1.1000 115,500.00 127,050.00
Batu Bata / Merah 2.2.1.14 M3 42.0000 900.00 37,800.00
PC / Portland cement 2.2.1.52 Kg 10.3000 1,400.00 14,420.00
Pasir pasang / beton 2.2.1.50 M3 0.0610 264,000.00 16,104.00
Pasir Urug 2.2.1.51 M3 0.0690 173,300.00 11,957.70
44,612.00 207,331.70 - 251,943.70
Overhead dan profit 0.1400 6,245.68 29,026.44 - 35,272.12
50,857.68 236,358.14 - 287,215.82

A.5.1.1.36b 1 m' Pemasangan pipa beton diameter 50 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3800 68,500.00 26,030.00
Tukang batu 1.2.7.16 oh 0.1900 79,000.00 15,010.00
Kepala Tukang 1.2.7.3 oh 0.0190 93,500.00 1,776.50
Mandor 1.2.7.5 oh 0.0190 94,500.00 1,795.50
Bahan
Buis Beton ø 50 Cm 2.2.10.18 Bh 1.1000 173,300.00 190,630.00
Batu Bata / Merah 2.2.1.14 M3 42.0000 900.00 37,800.00
PC / Portland cement 2.2.1.52 Kg 10.3000 1,400.00 14,420.00
Pasir pasang / beton 2.2.1.50 M3 0.0610 264,000.00 16,104.00
Pasir Urug 2.2.1.51 M3 0.0690 173,300.00 11,957.70
44,612.00 270,911.70 - 315,523.70
Overhead dan profit 0.1400 6,245.68 37,927.64 - 44,173.32
50,857.68 308,839.34 - 359,697.02

A.5.1.1.36c 1 m' Pemasangan pipa beton diameter 60 cm


Tenaga

137
HARGA JUMLAH HARGA
NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3800 68,500.00 26,030.00
Tukang batu 1.2.7.16 oh 0.1900 79,000.00 15,010.00
Kepala Tukang 1.2.7.3 oh 0.0190 93,500.00 1,776.50
Mandor 1.2.7.5 oh 0.0190 94,500.00 1,795.50
Bahan
Buis Beton ø 60 Cm 2.2.10.19 Bh 1.1000 184,800.00 203,280.00
Batu Bata / Merah 2.2.1.14 M3 42.0000 900.00 37,800.00
PC / Portland cement 2.2.1.52 Kg 10.3000 1,400.00 14,420.00
Pasir pasang / beton 2.2.1.50 M3 0.0610 264,000.00 16,104.00
Pasir Urug 2.2.1.51 M3 0.0690 173,300.00 11,957.70
44,612.00 283,561.70 - 328,173.70
Overhead dan profit 0.1400 6,245.68 39,698.64 - 45,944.32
50,857.68 323,260.34 - 374,118.02

A.5.1.1.36d 1 m' Pemasangan pipa beton diameter 80 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3800 68,500.00 26,030.00
Tukang batu 1.2.7.16 oh 0.1900 79,000.00 15,010.00
Kepala Tukang 1.2.7.3 oh 0.0190 93,500.00 1,776.50
Mandor 1.2.7.5 oh 0.0190 94,500.00 1,795.50
Bahan
Buis Beton ø 80 Cm 2.2.10.20 Bh 1.1000 231,000.00 254,100.00
Batu Bata / Merah 2.2.1.14 M3 42.0000 900.00 37,800.00
PC / Portland cement 2.2.1.52 Kg 10.3000 1,400.00 14,420.00
Pasir pasang / beton 2.2.1.50 M3 0.0610 264,000.00 16,104.00
Pasir Urug 2.2.1.51 M3 0.0690 173,300.00 11,957.70
44,612.00 334,381.70 - 378,993.70
Overhead dan profit 0.1400 6,245.68 46,813.44 - 53,059.12
50,857.68 381,195.14 - 432,052.82

A.5.1.1.36e 1 m' Pemasangan pipa beton diameter 100 cm


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3800 68,500.00 26,030.00
Tukang batu 1.2.7.16 oh 0.1900 79,000.00 15,010.00
Kepala Tukang 1.2.7.3 oh 0.0190 93,500.00 1,776.50
Mandor 1.2.7.5 oh 0.0190 94,500.00 1,795.50
Bahan
Buis Beton ø 100 Cm 2.2.10.14 Bh 1.1000 404,300.00 444,730.00
Batu Bata / Merah 2.2.1.14 M3 42.0000 900.00 37,800.00
PC / Portland cement 2.2.1.52 Kg 10.3000 1,400.00 14,420.00
Pasir pasang / beton 2.2.1.50 M3 0.0610 264,000.00 16,104.00
Pasir Urug 2.2.1.51 M3 0.0690 173,300.00 11,957.70
44,612.00 525,011.70 - 569,623.70
Overhead dan profit 0.1400 6,245.68 73,501.64 - 79,747.32
50,857.68 598,513.34 - 649,371.02

138
REKAPITULASI
ANALISA HARGA SATUAN PEKERJAAN ( AHSP )
BIDANG PEKERJAAN UMUM
KABUPATEN : TULUNGAGUNG
SISTEM : KONTRAK
HARGA : BAWAH OVERHEAD DAN PROFIT

HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3

A.2.2.1 PEKERJAAN PERSIAPAN

A.2.2.1.1 1 m2 Pembuatan Pagar sementara dari kayu tinggi 2 meter 55,928.40


A.2.2.1.2 1 m2 Pembuatan Pagar Sementara dari seng gelombang tinggi 2m 60,716.40
A.2.2.1.3 1 m2 Pembuatan Pagar sementara dari kawat duri tinggi 1.8 M 50,513.40
A.2.2.1.4 1 m' Pengukuran dan pemasangan Bowplank 19,616.55
A.2.2.1.5 1 m2 Pembuatan kantor sementara lantai plesteran 487,663.50
A.2.2.1.6 1 m2 Pembuatan Rumah Jaga ( Kontrusi Kayu ) 252,510.00
A.2.2.1.7 1 m2 Pembuatan Gudang Semen dan Peralatan 289,668.30
A.2.2.1.8 1 m2 Pembuatan Bedeng Pekerja 289,668.30
A.2.2.1.9 1 m2 Pembersihan Lapangan dan perataan 13,195.50
A.2.2.1.10 1 m2 Pembuatan Steger/Perancah dari bambu 289,668.30
A.2.2.1.11 1 bh Pembuatan Kotak adukan ukuran 40 cm x 50 cm x25 cm 33,806.70
A.2.2.1.12 1 m2 Pembuatan Jalan Sementara 78,628.65
A.2.2.1.13 1 m3 Pembongkaran Beton bertulang 1,113,000.24
A.2.2.1.14 1 m3 Pembongkaran Dinding Tembok bata 556,500.12
A.2.2.1.15 1 m2 Pemasangan pagar kawat jaring galvanis panjang 240 Cm 8,425.74
A.2.2.1.16 1 m2 Pemasangan panel Beton pracetak 5 x 50 x 213 Cm 55,378.92
A.2.2.1.17 10 m2 Membongkar lantai lama, berikut membersihkan bata-bata lama atau ubin-ubin yang dibongkar 88,863.00
A.2.2.1.17a 10 m2 Menghapus plesteran yang lama 41,738.25
A.2.2.1.17b 10 m2 Menurunkan atap genteng atau sirap (jika atap genteng atau sirap akan dipakai lagi) 26,391.00
A.2.2.1.17c 10 m2 Menurunkan atap genteng atau sirap (jika atap genteng atau sirap tidak dipakai lagi) 26,391.00
A.2.2.1.17d 10 m2 Menurunkan rangka atap dari kayu (jika kayu bongkaran hendak dipakai lagi) 135,631.50
A.2.2.1.17e 10 m2 Menurunkan rangka atap dari kayu (jika kayu bongkaran tidak dipakai lagi) 83,476.50
A.2.2.1.17f 1 m3 Membongkar kuda-kuda jika dipakai lagi 1,010,040.00

1
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.2.2.1.17g 1 m3 Membongkar kuda-kuda jika tidak dipakai lagi 676,134.00

A.2.3.1 PEKERJAAN TANAH

A.2.3.1.1 1 m3 Penggalian Tanah biasa sedalam 1 m 61,260.75


A.2.3.1.2 1 m3 Penggalian Tanah biasa sedalam 2 m 75,128.85
A.2.3.1.3 1 m3 Penggalian Tanah biasa sedalam 3 m 89,212.41
A.2.3.1.4 1 m3 Penggalian Tanah keras sedalam 1 m 81,537.36
A.2.3.1.5 1 m3 Penggalian Tanah cadas sedalam 1 m 123,598.80
A.2.3.1.6 1 m3 Penggalian Tanah lumpur sedalam 1 m 98,555.85
A.2.3.1.7 1 m2 Pengerjaan stripping tanah tebing setinngi 1 meter 4,443.15
A.2.3.1.8 1 m3 Pembuangan tanah sejauh 30 meter 26,847.00
A.2.3.1.9 1 m3 Pengurugan kembali galian tanah 44,431.50
A.2.3.1.10 1 m3 Pemadatan tanah ( per 20 cm ) 44,431.50
A.2.3.1.11 1 m3 Pengurugan dengan pasir urug 24,504.30
A.2.3.1.12 1 m3 Pemasangan lapisan pudel campuran 1 kp : 3 pp : 7 tl 111,378.00
A.2.3.1.13 1 m2 Pemasangan lapisan ijuk tebal 10 cm untuk bidang resapan 13,329.45
A.2.3.1.14 1 m3 Pengurugan sirtu padat 22,215.75
A.2.3.1.14a 1 m3 Pengurugan tanah 22,215.75

A.3.2.1 PEKERJAAN PONDASI

A.3.2.1.1 1 m3 Pasangan pondasi batu belah campuran 1 sp : 3 pp 200,754.00


A.3.2.1.2 1 m3 Pasangan pondasi batu belah campuran 1 sp : 4 pp 200,754.00
A.3.2.1.3 1 m3 Pasangan pondasi batu belah campuran 1 sp : 5 pp 200,754.00
A.3.2.1.4 1 m3 Pasangan pondasi batu belah campuran 1 sp : 6 pp 200,754.00
A.3.2.1.5 1 m3 Pasangan pondasi batu belah campuran 1 sp : 8 pp 200,754.00
A.3.2.1.6 1 m3 Pasangan pondasi batu belah campuran 1 sp : 1 kp : 2 pp 200,754.00
A.3.2.1.7 1 m3 Pasangan pondasi batu belah campuran 1 sp : 3 kp : 10 pp 200,754.00
A.3.2.1.8 1 m3 Pasangan pondasi batu belah campuran 1/4 sp : 1 kp : 4 pp 200,754.00
A.3.2.1.9 1 m3 Pasangan pondasi batu kosong ( anstamping ) 104,392.08
A.3.2.1.10 1 m3 Pasangan pondasi siklop 60 % beton campuran 1 sp : 2 pb : 3 kr dan 40% batu belah 369,862.17
A.3.2.1.11 1 m3 Pasangan pondasi sumuran diameter 100 cm 280,811.07
A.3.2.1.11a 1 m' Pembuatan tiang pancang (40 X 40) Cm, beton bertulang 150,958.23
A.3.2.1.11b 1 m' Pembuatan tiang pancang (35 X 35) Cm, beton bertulang 117,140.70

2
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3

A.4.1.1 PEKERJAAN BETON

A.4.1.1.1 1 m3 Membuat Beton mutu fc=7,4 Mpa (K100), Slump (12±2) cm, w/c = 0,87 165,541.11
A.4.1.1.2 1 m3 Membuat Beton mutu fc=9,8 Mpa (K125), Slump (12±2) cm, w/c = 0,78 165,541.11
A.4.1.1.3 1 m3 Membuat Beton mutu fc=12,2 Mpa (K150), Slump (12±2) cm, w/c = 0,72 165,541.11
A.4.1.1.4 1 m3 Membuat lantai kerja beton mutu f'c=7,4 Mpa ( K100) Slump (3-6) cm, w/c = 0,87 120,315.60
A.4.1.1.5 1 m3 Membuat Beton mutu fc=14,5 Mpa (K175), Slump (12±2) cm, w/c = 0,66 165,541.11
A.4.1.1.6 1 m3 Membuat Beton mutu fc=15,9 Mpa (K200), Slump (12±2) cm, w/c = 0,61 165,541.11
A.4.1.1.7 1 m3 Membuat Beton mutu fc=19,3 Mpa (K225), Slump (12±2) cm, w/c = 0,58 165,541.11
A.4.1.1.8 1 m3 Membuat Beton mutu fc=21,7 Mpa (K250), Slump (12±2) cm, w/c = 0,56 165,541.11
A.4.1.1.9 1 m3 Membuat Beton mutu fc=24,0 Mpa (K275), Slump (12±2) cm, w/c = 0,53 165,541.11
A.4.1.1.10 1 m3 Membuat Beton mutu fc=26,4 Mpa (K300), Slump (12±2) cm, w/c = 0,52 165,541.11
A.4.1.1.11 1 m3 Membuat Beton mutu fc=28,8 Mpa (K325), Slump (12±2) cm, w/c = 0,49 210,552.30
A.4.1.1.12 1 m3 Membuat Beton mutu fc=31,2 Mpa (K350), Slump (12±2) cm, w/c = 0,48 244,128.15
A.4.1.1.13 1 m3 Membuat Beton kedap air dengan strorox - 100 210,552.30
A.4.1.1.14 1 m' Pasang PVC waterstop lebar 150 mm 8,030.16
A.4.1.1.15 1 m' Pasang PVC waterstop lebar 200 mm 9,798.87
A.4.1.1.16 1 m' Pasang PVC waterstop lebar 230 - 320 mm 10,706.88
A.4.1.1.17 10 kg Pembesian dengan besi polos atau ulir 13,346.55
A.4.1.1.18 10 kg Pemasangan kabel presstressed polos / strands 9,263.64
A.4.1.1.19 10 kg Pemasangan jaring kawat baja ( wiremesh ) 6,976.23
A.4.1.1.20 1 m2 Pemasangan bekisting untuk pondasi 72,706.92
A.4.1.1.21 1 m2 Pemasangan bekisting untuk sloof 72,706.92
A.4.1.1.22 1 m2 Pemasangan bekisting untuk kolom 92,281.86
A.4.1.1.23 1 m2 Pemasangan bekisting untuk balok 92,281.86
A.4.1.1.24 1 m2 Pemasangan bekisting untuk lantai 92,281.86
A.4.1.1.25 1 m2 Pemasangan bekisting untuk dinding 92,281.86
A.4.1.1.26 1 m2 Pemasangan bekisting untuk tangga 92,281.86
A.4.1.1.27 1 m2 Pemasangan jembatan untuk pengecoran beton 18,209.79
A.4.1.1.28 1 m3 Membuat pondasi beton bertulang ( 150 kg besi + bekisting ) 728,305.53
A.4.1.1.29 1 m3 Membuat sloof beton bertulang ( 200 kg besi + bekisting ) 824,121.96
A.4.1.1.30 1 m3 Membuat kolom beton bertulang ( 300 kg besi + bekisting ) 1,025,730.96
A.4.1.1.31 1 m3 Membuat balok beton bertulang (200 kg besi + bekisting ) 892,804.11
A.4.1.1.32 1 m3 Membuat kolom beton bertulang (150 kg besi + bekisting ) 728,625.30
A.4.1.1.33 1 m3 Membuat dinding beton bertulang (150 kg besi + bekisting ) 728,305.53
A.4.1.1.34 1 m3 Membuat dinding beton bertulang (200 kg besi + bekisting ) 824,121.96
A.4.1.1.35 1 m' Membuat kolom praktis beton bertulang (11 x 11 ) cm 21,422.31
A.4.1.1.36 1 m' Membuat ring balok beton bertulang (10 x 15 ) cm 35,373.63
A.4.1.1.37 1 m3 Membongkar bekisting dan perawatan beton 312,360.00

A.4.1.2 PEKERJAAN BETON PRACETAK

A.4.1.2.1 1 m2 Pembuatan lahan produksi tebal 8 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm 13,256.49
A.4.1.2.2 1 m2 Pembuatan lahan produksi tebal 10 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm 16,588.14
A.4.1.2.3 1 m2 Pembuatan lahan produksi tebal 12 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm 19,830.87
A.4.1.2.4 1 m2 Pembuatan lahan produksi tebal 15 cm beton f'c 14,5 Mpa (K175) slump ( 12±2) cm 24,885.63
A.4.1.2.5 1 m2 Pembuatan bekisting untuk plat pracetak ( 5 kali pakai ) 8,351.64
A.4.1.2.6 1 m2 Pembuatan bekisting untuk balok beton pracetak ( 10-12 kali pakai ) 4,268.73
A.4.1.2.7 1 m2 Pembuatan bekisting untuk kolom beton pracetak ( 10-12 kali pakai ) 4,268.73
A.4.1.2.8 1 bh Pemasangan dan membuka bekisting komponen plat beton pracetak 5,975.31
A.4.1.2.9 1 bh Pemasangan dan membuka bekisting komponen balok beton pracetak 10,549.56

3
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.1.2.10 1 bh Pemasangan dan membuka bekisting komponen kolom beton pracetak 8,531.76
A.4.1.2.11 1 bh Penuangan/menebar beton untuk komponen plat beton pracetak 52,250.19
A.4.1.2.12 1 bh Penuangan/menebar beton untuk komponen balok beton pracetak 53,857.59
A.4.1.2.13 1 bh Penuangan/menebar beton untuk komponen balok beton pracetak 48,471.09
A.4.1.2.22 1 titik Upah melakukan grouting pada join pracetak 44,925.69
A.4.1.2.23 1 titik Pemasangan bekisting join pracetak 28,615.14
A.4.1.2.24 1 titik Upah join dengan sling 64,261.23

A.4.2.1 PEKERJAAN BESI DAN ALUMINIUM

A.4.2.1.1 1 kg Pemasangan besi profil 13,206.33


A.4.2.1.2 1 kg Pemasangan rangka kuda-kuda baja IWF 11,769.93
A.4.2.1.3 100 kg Pengerjaan Pekerjaan perakitan 18,657.24
A.4.2.1.4 1 m2 Pembuatan besi plat baja tebal 2 mm rangkap, rangka baja siku 205,919.91
A.4.2.1.5 10 cm Pengerjaan pengelasan dengan las listrik 5,592.84
A.4.2.1.6 1 m2 Pemasangan rangka jendela besi scuare tube ( 25 x 5 ) cm 127,453.71
A.4.2.1.7 1 m2 Pemasangan pintu rolling door besi 229,581.18
A.4.2.1.8 1 m2 Pemasangan pintu lipat ( Folding door ) bahan plastik/PVC 86,312.82
A.4.2.1.9 1 m2 Pemasangan sunscreen aluminium 96,829.32
A.4.2.1.10 1 m2 Pemasangan rolling door aluminium 196,165.50
A.4.2.1.11 1 m Pemasangan kusen pintu aluminium 8,429.73
A.4.2.1.12 1 m2 Pemasangan pintu aluminium strip lebar 8 cm 16,668.68
A.4.2.1.13 1 m2 Pemasangan pintu kaca alumunium 16,808.16
A.4.2.1.14 1 m2 Pemasangan venetions blinds dan vertical blinds 68,711.79
A.4.2.1.15 1 m2 Pemasangan terali besi strip ( 2x3 ) mm 327,542.52
A.4.2.1.16 1 m2 Pemasangan kawat nyamuk 19,616.55
A.4.2.1.16a 1 m2 Pemasangan kawat harmonika 19,616.55
A.4.2.1.16b 1 m2 Pemasangan kawat kassa 19,616.55
A.4.2.1.16c 1 m2 Pemasangan kawat burung 19,616.55
A.4.2.1.17 1 m2 Pemasangan jendela nako dan tralis 38,263.53
A.4.2.1.18 1 m' Pemasangan talang datar/jurai seng bjls 28 lebar 90 cm 38,263.53
A.4.2.1.19 1 m Pemasangan talang ½ lingkaran D-15 cm, seng plat bjls 30 lebar 45 cm 46,382.04
A.4.2.1.20 1 m2 Pemasangan rangka besi hollow 1x40.40.2, modul 60x120 cm, dinding partisi 47,527.74
A.4.2.1.21 1 m2 Pemasangan rangka besi hollow 1x40.40.2, modul 60x60 cm, plafon 66,517.29

A.4.4.1 PEKERJAAN PASANGAN DINDING

A.4.4.1.1 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 2 pp 70,229.70
A.4.4.1.2 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 3 pp 70,229.70
A.4.4.1.3 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 4 pp 70,229.70
A.4.4.1.4 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 5 pp 70,229.70
A.4.4.1.5 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 6 pp 70,229.70
A.4.4.1.6 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal 1 batu campuran 1 sp : 3 kp : 10 pp 70,229.70
A.4.4.1.7 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 2 pp 35,114.85
A.4.4.1.8 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 3 pp 35,114.85
A.4.4.1.9 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 4 pp 35,114.85
A.4.4.1.10 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 5 pp 35,114.85
A.4.4.1.11 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 6 pp 35,114.85
A.4.4.1.12 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 8 pp 35,114.85
A.4.4.1.13 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sp : 3 kp : 8 pp 35,114.85
A.4.4.1.14 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sm : 1 kp : 1 pp 35,114.85
A.4.4.1.15 1 m2 Pemasangan dinding bata merah ( 5x11x22 ) cm tebal ½ batu campuran 1 sm : 1 kp : 2 pp 35,114.85

4
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.4.1.16 1 m3 Pemasangan dinding HB20 campuran 1 sp : 3 pp 44,378.49
A.4.4.1.16a 1 m3 Pemasangan dinding CB20 campuran 1 sp : 3 pp 44,378.49
A.4.4.1.17 1 m3 Pemasangan dinding HB20 campuran 1 sp : 4 pp 44,378.49
A.4.4.1.17a 1 m3 Pemasangan dinding CB20 campuran 1 sp : 4 pp 44,378.49
A.4.4.1.18 1 m3 Pemasangan dinding HB15 campuran 1 sp : 3 pp 54,311.88
A.4.4.1.18a 1 m3 Pemasangan dinding CB15 campuran 1 sp : 3 pp 54,311.88
A.4.4.1.19 1 m3 Pemasangan dinding HB15 campuran 1 sp : 4 pp 54,311.88
A.4.4.1.19a 1 m3 Pemasangan dinding CB15 campuran 1 sp : 4 pp 54,311.88
A.4.4.1.20 1 m3 Pemasangan dinding HB10 campuran 1 sp : 3 pp 35,114.85
A.4.4.1.20a 1 m3 Pemasangan dinding CB10 campuran 1 sp : 3 pp 35,114.85
A.4.4.1.21 1 m3 Pemasangan dinding HB10 campuran 1 sp : 4 pp 35,114.85
A.4.4.1.21a 1 m3 Pemasangan dinding CB10 campuran 1 sp : 4 pp 35,114.85
A.4.4.1.22 1 m2 Pemasangan dinding terawang (rooster)12x11x24 campuran 1 sp : 3 pp 35,114.85
A.4.4.1.23 1 m2 Pemasangan dinding terawang (rooster)12x11x24 campuran 1 sp : 4 pp 35,114.85
A.4.4.1.24 1 m2 Pemasangan dinding bata berongga ekspose 12x11x24 campuran 1 sp : 3 pp 40,150.80
A.4.4.1.24a 1 m2 Pasangan bataco 1 Pc : 3 Psr 34,845.53

A.4.4.2 PEKERJAAN PLESTERAN

A.4.4.2.1 1 m2 Pemasangan plesteran 1 sp : 1 pp tebal 15 mm 40,150.80


A.4.4.2.2 1 m2 Pemasangan plesteran 1 sp : 2 pp tebal 15 mm 40,150.80
A.4.4.2.3 1 m2 Pemasangan plesteran 1 sp : 3 pp tebal 15 mm 40,150.80
A.4.4.2.4 1 m2 Pemasangan plesteran 1 sp : 4 pp tebal 15 mm 40,150.80
A.4.4.2.5 1 m2 Pemasangan plesteran 1 sp : 5 pp tebal 15 mm 40,150.80
A.4.4.2.6 1 m2 Pemasangan plesteran 1 sp : 6 pp tebal 15 mm 40,150.80
A.4.4.2.7 1 m2 Pemasangan plesteran 1 sp : 7 pp tebal 15 mm 40,150.80
A.4.4.2.8 1 m2 Pemasangan plesteran 1 sp : 8 pp tebal 15 mm 40,150.80
A.4.4.2.9 1 m2 Pemasangan plesteran 1 sp : 1/2 kp : 3 pp tebal 15 mm 42,137.82
A.4.4.2.10 1 m2 Pemasangan plesteran 1 sp : 2 kp : 8 pp tebal 15 mm 42,137.82
A.4.4.2.11 1 m2 Pemasangan plesteran 1 sm : 1 kp : 1 pp tebal 15 mm 42,137.82
A.4.4.2.12 1 m2 Pemasangan plesteran 1 sm : 1 kp : 2 pp tebal 15 mm 42,137.82
A.4.4.2.13 1 m2 Pemasangan plesteran 1 sp : 1 pp tebal 20 mm 53,749.86
A.4.4.2.14 1 m2 Pemasangan plesteran 1 sp : 3 pp tebal 20 mm 41,847.69
A.4.4.2.15 1 m2 Pemasangan plesteran 1 sp : 4 pp tebal 20 mm 53,749.86
A.4.4.2.16 1 m2 Pemasangan plesteran 1 sp : 5 pp tebal 20 mm 53,749.86
A.4.4.2.17 1 m2 Pemasangan plesteran 1 sp : 6 pp tebal 20 mm 53,749.86
A.4.4.2.18 1 m2 Pemasangan plesteran 1 sp : 1 kp : 2 pp tebal 20 mm 58,887.84
A.4.4.2.19 1 m2 Pemasangan berapen 1 sp : 5 pp tebal 15 mm 20,182.56
A.4.4.2.20 1 m2 Pemasangan plesteran sconing 1 sp : 3 pp lebar 10 mm 46,965.72
A.4.4.2.21 1 m2 Pemasangan plesteran granit 1 sp : 2 granit tebal 1 cm 60,333.36
A.4.4.2.22 1 m2 Pemasangan plesteran traso 1 sp : 2 traso tebal 1 cm 60,333.36
A.4.4.2.23 1 m2 Pemasangan plesteran ciprat 1 sp : 2 pp 35,114.85
A.4.4.2.24 1 m2 Pemasangan finishing siar bata merah 20,182.56
A.4.4.2.25 1 m2 Pemasangan finishing siar pasangan conblock ekspose 9,475.68
A.4.4.2.26 1 m2 Pemasangan finishing siar pasangan batu kali, campuran 1 sp : 2 pp 40,150.80
A.4.4.2.27 1 m2 Pemasangan acian 26,767.20
A.4.4.2.28 1 m' Benangan / Tali Air / Sudut Kol Kolan 5,674.35

A.4.4.3 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.3 1 m2 Pemasangan lantai ubin PC abu - abu ukuran 20 x 20 Cm 36,242.88


A.4.4.3.8 1 m2 Pemasangan lantai ubin teraso ukuran 30 x 30 Cm 34,797.36

5
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.4.3.9 1 m2 Pemasangan lantai ubin Granit ukuran 40 x 40 Cm 33,566.16
A.4.4.3.32 1 m2 Pemasangan lantai keramik artistik 10 x 20 Cm 93,685.20
A.4.4.3.35 1 m2 Pemasangan lantai keramik polos ukuran 30 x 30 cm 93,685.20
A.4.4.3.35a 1 m2 Pemasangan lantai keramik motif ukuran 30 x 30 cm 93,685.20
A.4.4.3.35b 1 m2 Pemasangan lantai keramik (eks Granito ) tekstur ukuran 40 x 40 cm 93,685.20
A.4.4.3.35c 1 m2 Pemasangan lantai keramik (eks Granito ) tekstur ukuran 60 x 60 cm 93,685.20
A.4.4.3.35d 1 m2 Pemasangan lantai keramik (eks Granito ) warna gelap ukuran 40 x 40 cm 93,685.20
A.4.4.3.35e 1 m2 Pemasangan lantai keramik (eks Granito ) warna gelap ukuran 60 x 60 cm 93,685.20
A.4.4.3.35f 1 m2 Pemasangan lantai keramik (eks Granito ) warna terang ukuran 40 x 40 cm 93,685.20
A.4.4.3.35g 1 m2 Pemasangan lantai keramik (eks Granito ) warna terang ukuran 60 x 60 cm 93,685.20
A.4.4.3.35h 1 m2 Pemasangan lantai keramik cutting ukuran 30 x 50 cm 93,685.20
A.4.4.3.35i 1 m2 Pemasangan lantai keramik cutting ukuran 31 x 63 cm 93,685.20
A.4.4.3.35j 1 m2 Pemasangan lantai keramik motif ukuran 40 x 40 cm 93,685.20
A.4.4.3.35k 1 m2 Pemasangan lantai keramik polos ukuran 40 x 40 cm 93,685.20
A.4.4.3.35l 1 m2 Pemasangan lantai keramik tekstur cuttingukuran 31 x 63 cm 93,685.20
A.4.4.3.35m 1 m2 Pemasangan lantai keramik tekstur ukuran 20 x 20 cm 93,685.20
A.4.4.3.35n 1 m2 Pemasangan lantai keramik motif ukuran 30 x 30 cm 93,685.20
A.4.4.3.35o 1 m2 Pemasangan lantai keramik tekstur ukuran 30 x 30 cm 93,685.20
A.4.4.3.35p 1 m2 Pemasangan lantai keramik motif ukuran 50 x 50 cm 93,685.20
A.4.4.3.36 1 m2 Pemasangan lantai keramik ukuran 20 x 20 Cm 93,685.20
A.4.4.3.39 1 m1 Pemasangan plint keramik artistik ukuran 10 x 20 Cm 21,321.42
A.4.4.3.40 1 m1 Pemasangan plint keramik ukuran 10 x 20 Cm 19,402.80
A.4.4.3.43 1 m2 Pemasangan lantai marmer bakar ukuran 100 x 100 Cm 93,685.20
A.4.4.3.43a 1 m2 Pemasangan lantai marmer hitam ukuran 100 x 100 Cm 93,685.20
A.4.4.3.43b 1 m2 Pemasangan lantai marmer putih ukuran 100 x 100 Cm 93,685.20
A.4.4.3.43c 1 m2 Pemasangan lantai batu andesit 93,685.20
A.4.4.3.43d 1 m2 Pemasangan lantai batu andesit hijau 93,685.20
A.4.4.3.43e 1 m2 Pemasangan lantai batu candi 93,685.20
A.4.4.3.43f 1 m2 Pemasangan lantai batu candi hitam 93,685.20
A.4.4.3.43g 1 m2 Pemasangan lantai batu granit black gold 93,685.20
A.4.4.3.43h 1 m2 Pemasangan lantai batu granit motif 93,685.20
A.4.4.3.43i 1 m2 Pemasangan lantai batu lempeng 93,685.20
A.4.4.3.43j 1 m2 Pemasangan lantai batu lempeng hijau 93,685.20
A.4.4.3.43k 1 m2 Pemasangan lantai batu lempeng coklat 93,685.20
A.4.4.3.44 1 m2 Lantai karpet 33,402.00
A.4.4.3.49 1 m2 Pemasangan dinding keramik 10 cm x 20 cm 120,452.40
A.4.4.3.50 1 m2 Pemasangan dinding keramik tekture 20 cm x 20 cm 120,452.40
A.4.4.3.51 1 m2 Pemasangan dinding keramik artistik 10 x 20 cm 120,452.40
A.4.4.3.53 1 m2 Pemasangan dinding keramik artistik 10 x 20 cm 120,452.40
A.4.4.3.54 1 m2 Pemasangan dinding keramik 20 x 20 cm 120,452.40
A.4.4.3.54a 1 m2 Pemasangan dinding keramik motif 20 x 25 cm 120,452.40
A.4.4.3.54b 1 m2 Pemasangan dinding keramik putih 20 x 25 cm 120,452.40
A.4.4.3.54c 1 m2 Pemasangan dinding keramik 20 x 33 cm 120,452.40
A.4.4.3.54d 1 m2 Pemasangan dinding keramik 40 x 40 cm 120,452.40
A.4.4.3.54e 1 m2 Pemasangan dinding keramik tekstur cutting 31 x 63 cm 120,452.40
A.4.4.3.54f 1 m2 Pemasangan dinding keramik tekstur 20 x 20 cm 120,452.40
A.4.4.3.54g 1 m2 Pemasangan dinding keramik tekstur 30 x 30 cm 120,452.40
A.4.4.3.54h 1 m2 Pemasangan dinding batu marmo warna 120,452.40
A.4.4.3.54i 1 m2 Pemasangan dinding batu andesit 120,452.40
A.4.4.3.54j 1 m2 Pemasangan dinding batu andesit alur 120,452.40
A.4.4.3.54k 1 m2 Pemasangan dinding batu andesit alur hitam 120,452.40
A.4.4.3.54l 1 m2 Pemasangan dinding batu andesit hitam bakar 120,452.40

6
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.4.3.54m 1 m2 Pemasangan dinding batu andesit hitam 120,452.40
A.4.4.3.54n 1 m2 Pemasangan dinding batu andesit hijau 120,452.40
A.4.4.3.54o 1 m2 Pemasangan dinding batu bali green 120,452.40
A.4.4.3.54p 1 m2 Pemasangan dinding batu bobos 120,452.40
A.4.4.3.54q 1 m2 Pemasangan dinding batu candi 120,452.40
A.4.4.3.54r 1 m2 Pemasangan dinding batu candi hitam 120,452.40
A.4.4.3.54s 1 m2 Pemasangan dinding batu granit black gold 120,452.40
A.4.4.3.54t 1 m2 Pemasangan dinding batu granit motif 120,452.40
A.4.4.3.54u 1 m2 Pemasangan dinding batu lempeng 120,452.40
A.4.4.3.54v 1 m2 Pemasangan dinding batu marmo biasa 120,452.40
A.4.4.3.54w 1 m2 Pemasangan dinding batu paras putih 120,452.40
A.4.4.3.54x 1 m2 Pemasangan dinding batu paras grobongan 120,452.40
A.4.4.3.54y 1 m2 Pemasangan dinding batu susun sirih 120,452.40
A.4.4.3.54z 1 m2 Pemasangan dinding batu warna ( hias ) 120,452.40
A.4.4.3.54aa 1 m2 Pemasangan dinding susun sirih, andesit hitam 3 x 20 cm 120,452.40
A.4.4.3.54ab 1 m2 Pemasangan dinding susun sirih, andesit hitam 3 x 30 cm 120,452.40
A.4.4.3.54ac 1 m2 Pemasangan dinding susun sirih, andesit hitam 3 x 40 cm 120,452.40
A.4.4.3.55 1 m2 Pemasangan dinding marmer bakar 100 x 100 cm 173,986.80
A.4.4.3.55a 1 m2 Pemasangan dinding marmer hitam 100 x 100 cm 173,986.80
A.4.4.3.55b 1 m2 Pemasangan dinding marmer putih 100 x 100 cm 173,986.80
A.4.4.3.57 1 m2 Pemasangan dinding batu paras putih 93,685.20
A.4.4.3.57a 1 m2 Pemasangan dinding batu paras grobogan 93,685.20
A.4.4.3.58 1 m2 Pemasangan dinding batu tempel hitam 93,685.20
A.4.4.3.60 1 m2 Pemasangan wallpaper lebar 50 cm 45,119.49
A.4.4.3.63 1 m1 Pemasangan plint kayu tebal 2 cm lebar 10 cm 22,103.46
A.4.4.3.63a 1 m2 Lantai Patlag 1 Lapis Bata merah camp. 1 Sm : 1 Kpr : 3 Psr 22,073.25
A.4.4.3.63b 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm K225 21,021.60
A.4.4.3.63c 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm K225 21,021.60
A.4.4.3.63d 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm K300 21,021.60
A.4.4.3.63e 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm K300 21,021.60
A.4.4.3.63f 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm K400 21,021.60
A.4.4.3.63g 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm K400 21,021.60
A.4.4.3.63h 1 m2 Pasang Paving Stone Warna Tebal 8 Cm K225 21,021.60
A.4.4.3.63i 1 m2 Pasang Paving Stone Warna Tebal 6 Cm K225 21,021.60
A.4.4.3.63j 1 m2 Pasang Paving Stone Segi 6 Warna Tebal 8 Cm K225 21,021.60
A.4.4.3.63k 1 m2 Pasang Paving Stone Segi 6 Warna Tebal 6 Cm K225 21,021.60
A.4.4.3.63l 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm 21,021.60
A.4.4.3.63m 1 m2 Pasang Paving Stone Abu abu Tebal 6 Cm 21,021.60
A.4.4.3.63n 1 m2 Pasang Paving Stone Segi 6 abu abu Tebal 8 cm 21,021.60
A.4.4.3.63o 1 m2 Pasang Paving Stone Segi 6 abu abu Tebal 6 cm 21,021.60
A.4.4.3.63p 1 m2 Pasang Paving Stone Segi 6 Merah Tebal 8 Cm 21,021.60
A.4.4.3.63q 1 m2 Pasang Paving Stone Segi 6 Merah Tebal 6 Cm 21,021.60
A.4.4.3.63r 1 m2 Pasang Paving Stone (12 x 12) 5 warna Tebal 6 Cm 21,021.60

A.4.5.1 PEKERJAAN LANGIT - LANGIT ( PLAFOND )

A.4.5.1.1 1 m2 Pemasangan langit - langit Eternit Polos ( Asbes ) 10,661.85


A.4.5.1.1a 1 m2 Pemasangan langit - langit Eternit Kembang ( Asbes ) 10,661.85
A.4.5.1.2 1 m2 Pemasangan langit - langit akustik ukuran ( 30 x 30 ) cm 23,539.86
A.4.5.1.3 1 m2 Pemasangan langit - langit akustik ukuran ( 30 x 60 ) cm 23,539.86
A.4.5.1.4 1 m2 Pemasangan langit - langit akustik ukuran ( 60 x 120 ) cm 199,736.55
A.4.5.1.5 1 m2 Pemasangan langit - langit akustik ukuran ( 120 x 240 ) cm, tebal 3 mm,4mm & 6 mm 199,736.55

7
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.5.1.6 1 m2 Pemasangan langit - langit lambrisering kayu jati eks bojonegoro, tebal 9 mm 156,932.40
A.4.5.1.6a 1 m2 Pemasangan langit - langit lambrisering kayu jati lokal, tebal 9 mm 156,932.40
A.4.5.1.6b 1 m2 Pemasangan langit - langit lambrisering kayu kamfer, tebal 9 mm 156,932.40
A.4.5.1.6c 1 m2 Pemasangan langit - langit lambrisering kayu balau, tebal 9 mm 156,932.40
A.4.5.1.6d 1 m2 Pemasangan langit - langit lambrisering kayu kempas, tebal 9 mm 156,932.40
A.4.5.1.6e 1 m2 Pemasangan langit - langit lambrisering kayu kruing, tebal 9 mm 156,932.40
A.4.5.1.6f 1 m2 Pemasangan langit - langit lambrisering kayu meranti, tebal 9 mm 156,932.40
A.4.5.1.6g 1 m2 Pemasangan langit - langit lambrisering kayu tahun ( mauni / akasia ), tebal 9 mm 156,932.40
A.4.5.1.7 1 m2 Pemasangan langit - langit gypsum board ukuran ( 120 x 240 x 9 ) 9 mm 13,982.10
A.4.5.1.8 1 m2 Pemasangan langit - langit akustik ukuran ( 60 x 240 ) Cm rangka Alluminium 98,082.75
A.4.5.1.9 1 m' Pemasangan list langit - langit kayu profil 9,862.14
A.4.5.1.10 1 m2 Pemasangan rangka besi hollow 1x40.40.2, modul 60x60 cm, plafon 66,517.29
A.4.5.1.10a 1 m' List Plafond Gypsum Kecil 4,103.43
A.4.5.1.10b 1 m' List Plafond Gypsum Besar 4,103.43

A.4.5.2 HARGA SATUAN PENUTUP ATAP

A.4.5.2.1 1 m2 Pemasangan atap genteng MKP lokal 21,027.02


A.4.5.2.1a 1 m2 Pemasangan atap genteng Mantili 21,027.02
A.4.5.2.1b 1 m2 Pemasangan atap genteng Press biasa 21,027.02
A.4.5.2.1c 1 m2 Pemasangan atap genteng Prentul eks Trenggalek / Tulungagung 21,027.02
A.4.5.2.1d 1 m2 Pemasangan atap genteng Kaca ( model karangpilang) 21,027.02
A.4.5.2.2 1 m2 Pemasangan atap genteng glazuur eks Kanmuri 21,080.31
A.4.5.2.4 1 m2 Pemasangan bubung genteng MKP lokal 53,989.26
A.4.5.2.5 1 m2 Pemasangan bubung genteng glazuur eks Kanmuri 53,989.26
A.4.5.2.6a 1 m2 Pemasangan bubung genteng bubung mantili 51,595.26
A.4.5.2.6b 1 m2 Pemasangan bubung genteng bubung Prentul eks Trenggalek / Tulungagung 53,989.26
A.4.5.2.6c 1 m2 Pemasangan bubung genteng bubung Press 53,989.26
A.4.5.2.7 1 m2 Pemasangan roof light fibreglass 90 x 180 19,268.85
A.4.5.2.8 1 m2 Pemasangan atap asbes gelombang 0,92 m x 2,50 m x 5 mm 20,299.41
A.4.5.2.9 1 m2 Pemasangan atap asbes gelombang 0,92 m x 2,25 m x 5 mm 20,299.41
A.4.5.2.10 1 m2 Pemasangan atap asbes gelombang 0,92 m x 2,00 m x 5 mm 19,574.94
A.4.5.2.11 1 m2 Pemasangan atap asbes gelombang 0,92 m x 1,80 m x 5 mm 19,574.94
A.4.5.2.12 1 m2 Pemasangan atap asbes gelombang 1,05 m x 3,00 m x 4 mm 19,574.94
A.4.5.2.13 1 m2 Pemasangan atap asbes gelombang 1,05 m x 2,70 m x 4 mm 19,574.94
A.4.5.2.14 1 m2 Pemasangan atap asbes gelombang 1,05 m x 2,50 m x 4 mm 19,574.94
A.4.5.2.15 1 m2 Pemasangan atap asbes gelombang 1,05 m x 2,25 m x 4 mm 19,574.94
A.4.5.2.16 1 m2 Pemasangan atap asbes gelombang 1,05 m x 1,50 m x 4 mm 19,574.94
A.4.5.2.17 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 3,00 m x 5 mm 19,574.94
A.4.5.2.18 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 2,50 m x 5 mm 19,574.94
A.4.5.2.19 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 2,25 m x 5 mm 19,574.94
A.4.5.2.20 1 m2 Pemasangan atap asbes gelombang besar 1,10 m x 2,00 m x 5 mm 19,574.94
A.4.5.2.21 1 m2 Pemasangan atap asbes gelombang besar 0,92 x 2,50 m x 5 mm 19,574.94
A.4.5.2.22 1 m1 Pemasangan bumbungan stel gelombang 0,92 m 21,129.90
A.4.5.2.23 1 m1 Pemasangan bumbungan stel gelombang 1,05 m 21,129.90
A.4.5.2.24 1 m1 Pemasangan bumbungan stel gelombang 1,08 m 21,129.90
A.4.5.2.25 1 m1 Pemasangan nok paten 0,92 m 21,129.90
A.4.5.2.26 1 m1 Pemasangan nok paten 1,05 m 21,129.90
A.4.5.2.28 1 m1 Pemasangan nok stel rata 0,92 m 24,930.09
A.4.5.2.29 1 m1 Pemasangan nok stel rata 1,05 m 21,129.90
A.4.5.2.30 1 m2 Pemasangan genteng beton 27,964.20
A.4.5.2.32 1 m2 Pemasangan genteng metal 26,994.63

8
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.5.2.33 1 m2 Pemasangan atap sirap kayu 41,997.03
A.4.5.2.34 1 m1 Pemasangan nok genteng beton 55,928.40
A.4.5.2.36 1 m1 Pemasangan nok genteng metal 37,826.34
A.4.5.2.37 1 m1 Pemasangan nok sirap 38,579.88
A.4.5.2.38 1 m2 Pemasangan atap seng gelombang BJLS 30 Uk 180 x 90 x 0,03 cm 16,778.52
A.4.5.2.38a 1 m2 Pemasangan atap seng gelombang BJLS 20 Uk 180 x 90 x 0,02 cm 16,778.52
A.4.5.2.38b 1 m2 Pemasangan atap seng gelombang BJLS 30 Uk 305 x 90 x 0,03 cm 16,778.52
A.4.5.2.38c 1 m2 Pemasangan atap seng gelombang BJLS 20 Uk 305 x 90 x 0,02 cm 16,778.52
A.4.5.2.39 1 m2 Pemasangan atap seng BJLS 20 20,248.11
A.4.5.2.39a 1 m2 Pemasangan atap seng BJLS 27 20,248.11
A.4.5.2.39b 1 m2 Pemasangan atap seng BJLS 30 20,248.11
A.4.5.2.40 1 m2 Pemasangan atap alumunium tebal 0,25 mm 97,409.58
A.4.5.2.40a 1 m2 Pemasangan atap alumunium tebal 0,30 mm 97,409.58
A.4.5.2.40b 1 m2 Pemasangan atap alumunium tebal 0,35 mm 97,409.58
A.4.5.2.40c 1 m2 Pemasangan atap alumunium tebal 0,40 mm 97,409.58
A.4.5.2.41 1 m2 Pemasangan nok alumunium 34,057.50
A.4.5.2.42 1 m2 Pemasangan alumunium foil / sisalation 18,209.79

A.4.6.1 PEKERJAAN KAYU

A.4.6.1.1 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu jati eks Bojonegoro 2,950,804.50
A.4.6.1.1a 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu jati lokal 2,950,804.50
A.4.6.1.1b 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu kamfer 2,950,804.50
A.4.6.1.1c 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu balau 2,950,804.50
A.4.6.1.1d 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu kempas 2,950,804.50
A.4.6.1.1e 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu kruing 2,950,804.50
A.4.6.1.1f 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu meranti 2,950,804.50
A.4.6.1.1g 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela , kayu tahun ( mahuni/akasia ) 2,950,804.50
A.4.6.1.2 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu jati eks Bojonegoro 2,529,261.00
A.4.6.1.2a 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu jati lokal 2,529,261.00
A.4.6.1.2b 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu kamfer 2,529,261.00
A.4.6.1.2c 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu balau 2,529,261.00
A.4.6.1.2d 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu kempas 2,529,261.00
A.4.6.1.2e 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu kruing 2,529,261.00
A.4.6.1.2f 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu meranti 2,529,261.00
A.4.6.1.2g 1 m3 Pembuatan dan pemasangan kusen pintu dan kusen jendela kaca, kayu tahun ( mauni / akasia ) 2,529,261.00
A.4.6.1.3 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu Jati eks Bojonegoro 147,594.09
A.4.6.1.3a 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu Jati 147,594.09
A.4.6.1.3b 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu kamfer 147,594.09
A.4.6.1.3c 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu balau 147,594.09
A.4.6.1.3d 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu kempas 147,594.09
A.4.6.1.3e 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu kruing 147,594.09
A.4.6.1.3f 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu meranti 147,594.09
A.4.6.1.3g 1 m2 Pembuatan dan pemasangan pintu klamp standart, kayu tahun ( mauni / akasia ) 147,594.09
A.4.6.1.4 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu Jati eks Bojonegoro 147,594.09
A.4.6.1.4a 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu Jati 147,594.09
A.4.6.1.4b 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu kamfer 147,594.09
A.4.6.1.4c 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu balau 147,594.09
A.4.6.1.4d 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu kempas 147,594.09
A.4.6.1.4e 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu kruing 147,594.09
A.4.6.1.4f 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu meranti 147,594.09
A.4.6.1.4g 1 m2 Pembuatan dan pemasangan pintu klamp sederhana, kayu tahun ( mauni / akasia ) 147,594.09

9
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.6.1.5 1 m2 Pembuatan dan pemasangan pintu panel, kayu Jati eks Bojonegoro 421,543.50
A.4.6.1.5a 1 m2 Pembuatan dan pemasangan pintu panel, kayu Jati lokal 421,543.50
A.4.6.1.5b 1 m2 Pembuatan dan pemasangan pintu panel, kayu kamfer 421,543.50
A.4.6.1.5c 1 m2 Pembuatan dan pemasangan pintu panel, kayu balau 421,543.50
A.4.6.1.5d 1 m2 Pembuatan dan pemasangan pintu panel, kayu kempas 421,543.50
A.4.6.1.5e 1 m2 Pembuatan dan pemasangan pintu panel, kayu kruing 421,543.50
A.4.6.1.5f 1 m2 Pembuatan dan pemasangan pintu panel, kayu meranti 421,543.50
A.4.6.1.5g 1 m2 Pembuatan dan pemasangan pintu panel, kayu tahun ( mauni / akasia ) 421,543.50
A.4.6.1.6 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu Jati eks Bojonegoro 337,234.80
A.4.6.1.6a 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu Jati lokal 337,234.80
A.4.6.1.6b 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu kamfer 337,234.80
A.4.6.1.6c 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu balau 337,234.80
A.4.6.1.6d 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu kempas 337,234.80
A.4.6.1.6e 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu kruing 337,234.80
A.4.6.1.6f 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu meranti 337,234.80
A.4.6.1.6g 1 m2 Pembuatan dan pemasangan pintu dan jendela kaca, kayu Tahun papan ( Mauni/akasia) 337,234.80
A.4.6.1.7 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu Jati papan eks. Bojonegoro 421,543.50
A.4.6.1.7a 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu jati papan lokal 421,543.50
A.4.6.1.7b 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu kanfer 421,543.50
A.4.6.1.7c 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu balau 421,543.50
A.4.6.1.7d 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu kempas 421,543.50
A.4.6.1.7e 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu kruing 421,543.50
A.4.6.1.7f 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu meranti 421,543.50
A.4.6.1.7g 1 m2 Pembuatan dan pemasangan pintu dan jendela jalusi, kayu tahun ( mauni / akasia ) 421,543.50
A.4.6.1.8 1 m2 Pembuatan daun pintu plywood rangka kayu Jati eks Bojonegoro tertutup lebar sampai 90 Cm 295,080.45
A.4.6.1.8a 1 m2 Pembuatan daun pintu plywood rangka kayu Jati lokal tertutup lebar sampai 90 Cm 295,080.45
A.4.6.1.8b 1 m2 Pembuatan daun pintu plywood rangka kayu kamfer tertutup lebar sampai 90 Cm 295,080.45
A.4.6.1.8c 1 m2 Pembuatan daun pintu plywood rangka kayu balau tertutup lebar sampai 90 Cm 295,080.45
A.4.6.1.8d 1 m2 Pembuatan daun pintu plywood rangka kayu kempas tertutup lebar sampai 90 Cm 295,080.45
A.4.6.1.8e 1 m2 Pembuatan daun pintu plywood rangka kayu kruing tertutup lebar sampai 90 Cm 295,080.45
A.4.6.1.8f 1 m2 Pembuatan daun pintu plywood rangka kayu meranti tertutup lebar sampai 90 Cm 295,080.45
A.4.6.1.8g 1 m2 Pembuatan daun pintu plywood rangka kayu tahun ( mauni / akasia ) tertutup lebar sampai 90 Cm 295,080.45
A.4.6.1.9 1 m2 Pembuatan daun pintu plywood rangka expose kayu Jati eks Bojonegoro 337,234.80
A.4.6.1.9a 1 m2 Pembuatan daun pintu plywood rangka expose kayu Jati lokal 337,234.80
A.4.6.1.9b 1 m2 Pembuatan daun pintu plywood rangka expose kayu kamfer 337,234.80
A.4.6.1.9c 1 m2 Pembuatan daun pintu plywood rangka expose kayu balau 337,234.80
A.4.6.1.9d 1 m2 Pembuatan daun pintu plywood rangka expose kayu kempas 337,234.80
A.4.6.1.9e 1 m2 Pembuatan daun pintu plywood rangka expose kayu kruing 337,234.80
A.4.6.1.9f 1 m2 Pembuatan daun pintu plywood rangka expose kayu meranti 337,234.80
A.4.6.1.9g 1 m2 Pembuatan daun pintu plywood rangka expose kayu tahun ( mauni / akasia ) 337,234.80
A.4.6.1.10 1 m2 Pemasangan jalusi kusen, kayu Jati eks Bojonegoro 313,787.85
A.4.6.1.10a 1 m2 Pemasangan jalusi kusen, kayu Jati lokal 313,787.85
A.4.6.1.10b 1 m2 Pemasangan jalusi kusen, kayu kamfer 313,787.85
A.4.6.1.10c 1 m2 Pemasangan jalusi kusen, kayu balau 313,787.85
A.4.6.1.10d 1 m2 Pemasangan jalusi kusen, kayu kempas 313,787.85
A.4.6.1.10e 1 m2 Pemasangan jalusi kusen, kayu kruing 313,787.85
A.4.6.1.10f 1 m2 Pemasangan jalusi kusen, kayu meranti 313,787.85
A.4.6.1.10g 1 m2 Pemasangan jalusi kusen, kayu tahun ( mauni / akasia ) 313,787.85
A.4.6.1.11 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Jati eks Bojonegoro 337,234.80
A.4.6.1.11a 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Jati lokal 337,234.80
A.4.6.1.11b 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Kamfer 337,234.80
A.4.6.1.11c 1 m2 Pemasangan teakwood rangkap, rangka expose kayu Balau 337,234.80

10
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.6.1.11d 1 m2 Pemasangan teakwood rangkap, rangka expose kayu kempas 337,234.80
A.4.6.1.11e 1 m2 Pemasangan teakwood rangkap, rangka expose kayu kruing 337,234.80
A.4.6.1.11f 1 m2 Pemasangan teakwood rangkap, rangka expose kayu meranti 337,234.80
A.4.6.1.11g 1 m2 Pemasangan teakwood rangkap, rangka expose kayu tahun ( mauni / akasia ) 337,234.80
A.4.6.1.12 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Jati eks Bojonegoro 358,365.84
A.4.6.1.12a 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Jati lokal 358,365.84
A.4.6.1.12b 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Kamfer 358,365.84
A.4.6.1.12c 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Balau 358,365.84
A.4.6.1.12d 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Kempas 358,365.84
A.4.6.1.12e 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Kruing 358,365.84
A.4.6.1.12f 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu Meranti 358,365.84
A.4.6.1.12g 1 m2 Pemasangan teakwood rangkap lapis formika, rangka expose kayu tahun ( mauni / akasia ) 358,365.84
A.4.6.1.13 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Jati Eks Bojonegoro bentang 6 meter 1,686,174.00
A.4.6.1.13a 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu lokal bentang 6 meter 1,686,174.00
A.4.6.1.13b 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Jati Kamfer bentang 6 meter 1,686,174.00
A.4.6.1.13c 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Balau bentang 6 meter 1,686,174.00
A.4.6.1.13d 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Kempas bentang 6 meter 1,686,174.00
A.4.6.1.13e 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Kruing bentang 6 meter 1,686,174.00
A.4.6.1.13f 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu Meranti bentang 6 meter 1,686,174.00
A.4.6.1.13g 1 m3 Pemasangan konstruksi kuda kuda konvensional kayu tahun ( mauni / akasia ) bentang 6 meter 1,686,174.00
A.4.6.1.14 1 m3 Pemasangan konstruksi kuda kuda expose kayu Jati eks Bojonegoro 2,824,341.45
A.4.6.1.14a 1 m3 Pemasangan konstruksi kuda kuda expose kayu Jati lokal 2,824,341.45
A.4.6.1.14b 1 m3 Pemasangan konstruksi kuda kuda expose kayu Kamfer 2,824,341.45
A.4.6.1.14c 1 m3 Pemasangan konstruksi kuda kuda expose kayu Balau 2,824,341.45
A.4.6.1.14d 1 m3 Pemasangan konstruksi kuda kuda expose kayu Kempas 2,824,341.45
A.4.6.1.14e 1 m3 Pemasangan konstruksi kuda kuda expose kayu Kruing 2,824,341.45
A.4.6.1.14f 1 m3 Pemasangan konstruksi kuda kuda expose kayu Meranti 2,824,341.45
A.4.6.1.14g 1 m3 Pemasangan konstruksi kuda kuda expose kayu Tahun ( mauni / akasia ) 2,824,341.45
A.4.6.1.15 1 m3 Pemasangan konstruksi gordeng, kayu Jati eks Bojonegoro 2,824,341.45
A.4.6.1.15a 1 m3 Pemasangan konstruksi gordeng, kayu Jati lokal 2,824,341.45
A.4.6.1.15b 1 m3 Pemasangan konstruksi gordeng, kayu kamfer 2,824,341.45
A.4.6.1.15c 1 m3 Pemasangan konstruksi gordeng, kayu Balau 2,824,341.45
A.4.6.1.15d 1 m3 Pemasangan konstruksi gordeng, kayu Kempas 2,824,341.45
A.4.6.1.15e 1 m3 Pemasangan konstruksi gordeng, kayu Kruing 2,824,341.45
A.4.6.1.15f 1 m3 Pemasangan konstruksi gordeng, kayu Meranti 2,824,341.45
A.4.6.1.15g 1 m3 Pemasangan konstruksi gordeng, kayu Tahun ( mauni / akasia ) 2,824,341.45
A.4.6.1.16 1 m2 Pemasangan rangka atap genteng keramik, kayu Jati eks Bojonegoro 19,616.55
A.4.6.1.16a 1 m2 Pemasangan rangka atap genteng keramik, kayu Jati lokal 19,616.55
A.4.6.1.16b 1 m2 Pemasangan rangka atap genteng keramik, kayu Kamfer 19,616.55
A.4.6.1.16c 1 m2 Pemasangan rangka atap genteng keramik, kayu Balau 19,616.55
A.4.6.1.16d 1 m2 Pemasangan rangka atap genteng keramik, kayu Kempas 19,616.55
A.4.6.1.16e 1 m2 Pemasangan rangka atap genteng keramik, kayu Kruing 19,616.55
A.4.6.1.16f 1 m2 Pemasangan rangka atap genteng keramik, kayu Meranti 19,616.55
A.4.6.1.16g 1 m2 Pemasangan rangka atap genteng keramik, kayu Tahun ( mauni / akasia ) 19,616.55
A.4.6.1.17 1 m2 Pemasangan rangka atap genteng beton, kayu Jati eks Bojonegoro 19,616.55
A.4.6.1.17a 1 m2 Pemasangan rangka atap genteng beton, kayu Jati lokal 19,616.55
A.4.6.1.17b 1 m2 Pemasangan rangka atap genteng beton, kayu Kamper 19,616.55
A.4.6.1.17c 1 m2 Pemasangan rangka atap genteng beton, kayu Balau 19,616.55
A.4.6.1.17d 1 m2 Pemasangan rangka atap genteng beton, kayu Kempas 19,616.55
A.4.6.1.17e 1 m2 Pemasangan rangka atap genteng beton, kayu Kruing 19,616.55
A.4.6.1.17f 1 m2 Pemasangan rangka atap genteng beton, kayu Meranti 19,616.55
A.4.6.1.17g 1 m2 Pemasangan rangka atap genteng beton, kayu Tahun ( mauni / akasia ) 19,616.55

11
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.6.1.18 1 m2 Pemasangan rangka atap sirap, kayu Jati eks Bojonegoro 19,616.55
A.4.6.1.18a 1 m2 Pemasangan rangka atap sirap, kayu Jati lokal 23,539.86
A.4.6.1.18b 1 m2 Pemasangan rangka atap sirap, kayu Kamfer 23,539.86
A.4.6.1.18c 1 m2 Pemasangan rangka atap sirap, kayu Balau 23,539.86
A.4.6.1.18d 1 m2 Pemasangan rangka atap sirap, kayu Kempas 23,539.86
A.4.6.1.18e 1 m2 Pemasangan rangka atap sirap, kayu Kruing 23,539.86
A.4.6.1.18f 1 m2 Pemasangan rangka atap sirap, kayu Meranti 23,539.86
A.4.6.1.18g 1 m2 Pemasangan rangka atap sirap, kayu Tahun ( mauni / akasia ) 23,539.86
A.4.6.1.19 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Jati eks Bojonegoro 53,599.95
A.4.6.1.19a 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Jati lokal 53,599.95
A.4.6.1.19b 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Kamfer 53,599.95
A.4.6.1.19c 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Balau 53,599.95
A.4.6.1.19d 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Kempas 53,599.95
A.4.6.1.19e 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Kruing 53,599.95
A.4.6.1.19f 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Meranti 53,599.95
A.4.6.1.19g 1 m2 Pemasangan rangka langit langit ( 50 x 100 ) cm kayu Tahun ( mauni / akasia ) 53,599.95
A.4.6.1.20 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Jati eks Bojonegoro 50,502.00
A.4.6.1.20a 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Jati lokal 50,502.00
A.4.6.1.20b 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Kamfer 50,502.00
A.4.6.1.20c 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Balau 50,502.00
A.4.6.1.20d 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Kempas 50,502.00
A.4.6.1.20e 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Kruing 50,502.00
A.4.6.1.20f 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Meranti 50,502.00
A.4.6.1.20g 1 m2 Pemasangan rangka langit langit ( 60 x 60 ) cm kayu Tahun 9 mauni / akasia ) 50,502.00
A.4.6.1.21 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Jati eks Bojonegoro 30,885.45
A.4.6.1.21a 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Jati lokal 30,885.45
A.4.6.1.21b 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Kamfer 30,885.45
A.4.6.1.21c 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Balau 30,885.45
A.4.6.1.21d 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Jati Kempas 30,885.45
A.4.6.1.21e 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Kruing 30,885.45
A.4.6.1.21f 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Meranti 30,885.45
A.4.6.1.21g 1 m1 Pemasangan lisplank ukuran ( 3 x 20 ) cm, kayu Tahun ( mauni / akasia ) 30,885.45
A.4.6.1.22 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Jati eks Bojonegoro 30,885.45
A.4.6.1.22a 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Jati lokal 30,885.45
A.4.6.1.22b 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Kamfer 30,885.45
A.4.6.1.22c 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Balau 30,885.45
A.4.6.1.22d 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Kempas 30,885.45
A.4.6.1.22e 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Kruing 30,885.45
A.4.6.1.22f 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Meranti 30,885.45
A.4.6.1.22g 1 m1 Pemasangan lisplank ukuran ( 3 x 30 ) cm, kayu Tahun ( mauni / akasia ) 30,885.45
A.4.6.1.23 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Jati eks Bojonegoro 63,285.39
A.4.6.1.23a 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Jati lokal 63,285.39
A.4.6.1.23b 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Kamfer 63,285.39
A.4.6.1.23c 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Balau 63,285.39
A.4.6.1.23d 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Kempas 63,285.39
A.4.6.1.23e 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Kruing 63,285.39
A.4.6.1.23f 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Meranti 63,285.39
A.4.6.1.23g 1 m2 Pemasangan rangka dinding pemisah ( 60 x 120 ) cm, kayu Tahun ( mauni / akasia ) 63,285.39
A.4.6.1.24 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Jati eks Bojonegoro 63,285.39
A.4.6.1.24a 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Jati lokal 63,285.39
A.4.6.1.24b 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Kamfer 63,285.39
A.4.6.1.24c 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Balau 63,285.39

12
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.6.1.24d 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Kempas 63,285.39
A.4.6.1.24e 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Kruing 63,285.39
A.4.6.1.24f 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Meranti 63,285.39
A.4.6.1.24g 1 m2 Pemasangan dinding pemisah teakwood rangkap,rangka kayu Tahun ( mauni / akasia ) 63,285.39
A.4.6.1.25 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Jati eks Bojonegoro 94,004.40
A.4.6.1.25a 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Jati lokal 94,004.40
A.4.6.1.25b 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Kamfer 94,004.40
A.4.6.1.25c 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Balau 94,004.40
A.4.6.1.25d 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Kempas 94,004.40
A.4.6.1.25e 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Kruing 94,004.40
A.4.6.1.25f 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Meranti 94,004.40
A.4.6.1.25g 1 m2 Pemasangan dinding pemisah plywood rangkap,rangka kayu Tahun ( mauni / akasia ) 94,004.40
A.4.6.1.26 1 m2 Pemasangan dinding lambrisering dari papan kayu Jati eks Bojoneoro 252,926.10
A.4.6.1.26a 1 m2 Pemasangan dinding lambrisering dari papan kayu Jati lokal 252,926.10
A.4.6.1.26b 1 m2 Pemasangan dinding lambrisering dari papan kayu Kamfer 252,926.10
A.4.6.1.26c 1 m2 Pemasangan dinding lambrisering dari papan kayu Balau 252,926.10
A.4.6.1.26d 1 m2 Pemasangan dinding lambrisering dari papan kayu Kempas 252,926.10
A.4.6.1.26e 1 m2 Pemasangan dinding lambrisering dari papan kayu Kruing 252,926.10
A.4.6.1.26f 1 m2 Pemasangan dinding lambrisering dari papan kayu Meranti 252,926.10
A.4.6.1.26g 1 m2 Pemasangan dinding lambrisering dari papan kayu Tahun ( mauni / akasia ) 252,926.10
A.4.6.1.27 1 m2 Pemasangan dinding lambrisering dari plywood ukuran 120 x 240 cm 10,564.95
A.4.6.1.28 1 m2 Pemasangan dinding bilik, rangka kayu Jati eks Bojonegoro 13,982.10
A.4.6.1.28a 1 m2 Pemasangan dinding bilik, rangka kayu Jati lokal 13,982.10
A.4.6.1.28b 1 m2 Pemasangan dinding bilik, rangka kayu Kamfer 13,982.10
A.4.6.1.28c 1 m2 Pemasangan dinding bilik, rangka kayu Balau 13,982.10
A.4.6.1.28d 1 m2 Pemasangan dinding bilik, rangka kayu Kempas 13,982.10
A.4.6.1.28e 1 m2 Pemasangan dinding bilik, rangka kayu Kruing 13,982.10
A.4.6.1.28f 1 m2 Pemasangan dinding bilik, rangka kayu Meranti 13,982.10
A.4.6.1.28g 1 m2 Pemasangan dinding bilik, rangka kayu Tahun ( mauni / akasia ) 13,982.10

A.4.6.2 PEKERJAAN KUNCI DAN KACA

A.4.6.2.1 1 bh Pemasangan kunci tanam antik eks Miler 72,621.99


A.4.6.2.1a 1 bh Pemasangan kunci tanam ( SES ) 72,621.99
A.4.6.2.2 1 bh Pemasangan kunci tanam biasa 57,664.05
A.4.6.2.2a 1 bh Pemasangan kunci tanam slot tanam eks Kuda 2x putaran 57,664.05
A.4.6.2.3 1 bh Pemasangan kunci Slot tanam kamar mandi eks Miler 57,058.14
A.4.6.2.3a 1 bh Pemasangan kunci Slot tanam kamar mandi 57,058.14
A.4.6.2.5 1 bh Pemasangan engsel pintu kupu - kupu 18,160.88
A.4.6.2.5a 1 bh Pemasangan engsel kuningan Arc Asli eks Elitech 4" 18,160.88
A.4.6.2.5b 1 bh Pemasangan engsel pintu ( H ) 18,160.88
A.4.6.2.5c 1 bh Pemasangan engsel pintu ( Arc ) nylon 18,160.88
A.4.6.2.5d 1 bh Pemasangan engsel pintu eks Union 4" 18,160.88
A.4.6.2.5e 1 bh Pemasangan engsel Stainlesstel Dekson 3" 18,160.88
A.4.6.2.5f 1 bh Pemasangan engsel Stainlesstel Dekson 4" 18,160.88
A.4.6.2.5g 1 bh Pemasangan engsel Stainlesstel Dekson 5" 18,160.88
A.4.6.2.5h 1 bh Pemasangan engsel Sendok 18,160.88
A.4.6.2.6 1 bh Pemasangan engsel jendela kupu kupu 12,103.67
A.4.6.2.6a 1 bh Pemasangan engsel jendela eks Union 3" 12,103.67
A.4.6.2.6b 1 bh Pemasangan engsel jendela ( H ) 12,103.67
A.4.6.2.6c 1 bh Pemasangan engsel jendela ( Arch ) 12,103.67
A.4.6.2.6d 1 bh Pemasangan grendel biasa ( besar ) 8" 12,103.67

13
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.6.2.6e 1 bh Pemasangan grendel biasa ( kecil ) 3" 12,103.67
A.4.6.2.6f 1 bh Pemasangan grendel eks AEG 12,103.67
A.4.6.2.6g 1 bh Pemasangan grendel jendela merk SES 12,103.67
A.4.6.2.6h 1 bh Pemasangan grendel pintu panjang ( sespen ) 12,103.67
A.4.6.2.6i 1 bh Pemasangan grendel pintu ganda Dekson 40 cm komplit 12,103.67
A.4.6.2.6j 1 bh Pemasangan grendel tanam kuningan besar eks Cavel 60 mm 12,103.67
A.4.6.2.6k 1 bh Pemasangan grendel tanam kuningan kecil eks beluci 4" 12,103.67
A.4.6.2.6l 1 bh Pemasangan grendel tanam merk SES 12,103.67
A.4.6.2.7 1 bh Pemasangan hak angin 30,400.67
A.4.6.2.7a 1 bh Pemasangan hak angin ( Sikutan ) biasa 30,400.67
A.4.6.2.7b 1 bh Pemasangan hak angin 4 mm lurus / plat 4 x 150 mm 30,400.67
A.4.6.2.7c 1 bh Pemasangan hak angin lurus 30,400.67
A.4.6.2.7d 1 bh Pemasangan hak angin merk SES 30,400.67
A.4.6.2.9 1 bh Pemasangan kait angin 18,936.54
A.4.6.2.10 1 bh Pemasangan door closer 60,572.19
A.4.6.2.11 1 bh Pemasangan kunci sloot 2 putaran eks CAVEL ( dengan handle ) 24,207.33
A.4.6.2.11a 1 bh Pemasangan kunci sloot 2 putaran eks kodai 24,207.33
A.4.6.2.11b 1 bh Pemasangan kunci sloot 2 putaran eks YALE ( dengan handle ) 24,207.33
A.4.6.2.11c 1 bh Pemasangan kunci sloot ( kunci pintu ) merk SES 24,207.33
A.4.6.2.11d 1 bh Pemasangan kunci sloot ( kunci pintu ) merk SES 24,207.33
A.4.6.2.11e 1 bh Pemasangan kunci sloot Rossete Dekson 24,207.33
A.4.6.2.11f 1 bh Pemasangan kunci sloot ( kunci pintu ) lokal 24,207.33
A.4.6.2.12a 1 bh Pemasangan Handle 60,572.19
A.4.6.2.12b 1 bh Pemasangan Handle pintu ganda Dekson 30 cm komplit 60,572.19
A.4.6.2.12c 1 bh Pemasangan Handle pintu ganda Dekson 40 cm komplit 60,572.19
A.4.6.2.12d 1 bh Pemasangan Handle ointu stainless steel besar 60,572.19
A.4.6.2.12e 1 bh Pemasangan Handle ointu stainless steel kecil 60,572.19
A.4.6.2.12h 1 bh Pemasangan Pegangan pintu P=20 60,572.19
A.4.6.2.13 1 bh Pemasangan Door stoper Stainlees 12,588.45
A.4.6.2.14 1 bh Pemasangan Rel pintu dorong 72,621.99
A.4.6.2.15 1 bh Pemasangan Kunci lemari 30,264.55
A.4.6.2.15a 1 bh Pemasangan Kunci laci ( 808 ) 30,264.55
A.4.6.2.15b 1 bh Pemasangan Kunci gembok besar stainless 40 mm 30,264.55
A.4.6.2.15c 1 bh Pemasangan Kunci gembok besar stainless 30 mm 30,264.55
A.4.6.2.16 1 m2 Pemasangan kaca bening tebal 3 mm 18,160.88
A.4.6.2.16a 1 m2 Pemasangan kaca buram tebal 3 mm 18,160.88
A.4.6.2.16b 1 m2 Pemasangan kaca Es tebal 3 mm 18,160.88
A.4.6.2.17 1 bh Pemasangan kaca bening tebal 5 mm 18,160.88
A.4.6.2.17a 1 bh Pemasangan kaca Ray band tebal 5 mm 18,160.88
A.4.6.2.18 1 m2 Pemasangan kaca bening tebal 7 mm 20,581.62
A.4.6.2.18a 1 m2 Pemasangan kaca Ray band tebal 7 mm 20,581.62
A.4.6.2.19 1 m2 Pemasangan kaca tebal 10 mm 30,264.55
A.4.6.2.20 1 m2 Pemasangan kaca cermin tebal 5 mm 18,936.54
A.4.6.2.21 1 m2 Pemasangan kaca cermin tebal 3 mm 21,454.23
A.4.6.2.22 1 m2 Pemasangan kaca Stained glass tebal 5 mm 18,936.54
A.4.6.2.22a 1 m2 Pemasangan kaca air tebal 5 mm 18,936.54
A.4.6.2.22b 1 m2 Pemasangan kaca bluegreen tebal 8 mm 18,936.54
A.4.6.2.22c 1 m2 Pemasangan kaca profil ( bevel / moulding ) 18,936.54
A.4.6.2.23 1 m2 Pemasangan kaca patri 23,191.02

A.4.7.1 PEKERJAAN PENGECATAN

14
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.4.7.1.1 1 m2 Pengikisan / pengerokan permukaan cat lama 12,036.69
A.4.7.1.2 1 m2 Pencucian Bidang permukaan tembok yang pernah dicat 12,036.69
A.4.7.1.3 1 m2 Pengerokan karat pada permukaan baja cara manual 12,575.34
A.4.7.1.4 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur , 1 lapis cat dasar , 2 lapis cat penutup) 7,239.57
A.4.7.1.5 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur , 1 lapis cat dasar , 3 lapis cat penutup) 15,672.15
A.4.7.1.6 1 m2 Pelaburan bidang kayu dengan teak oil 15,835.74
A.4.7.1.7 1 m2 Pelaburan bidang kayu dengan pelitur 10,555.83
A.4.7.1.8 1 m2 Pelaburan bidang kayu dengan cat residu dan ter 8,455.38
A.4.7.1.9 1 m2 Pelaburan bidang kayu dengan vernis 3,871.44
A.4.7.1.10 1 m2 Pengecatan tembok baru (1 lapis plamuur , 1 lapis dasar , 2 lapis cat penutup) 8,230.29
A.4.7.1.10a 1 m2 Pengecatan tembok Eksterior 8,230.29
A.4.7.1.10b 1 m2 Pengecatan tembok Interior 8,230.29
A.4.7.1.11 1 m2 Pengecatan tembok lama (1 lapis cat dasar ,2 lapis cat penutup) 6,739.91
A.4.7.1.13 1 m2 Pelaburan tembok dengan kapur sirih 12,083.54
A.4.7.1.14 1 m2 Pelaburan tembok lama dengan kapur sirih 3,896.52
A.4.7.1.15 1 m2 Pemasangan wallpaper 21,974.93
A.4.7.1.16 1 m2 Pengecatan permukaan baja dengan menie besi 21,974.93
A.4.7.1.17 1 m2 Pengecatan permukaan baja dengan menie besi dengan perancah 42,992.25
A.4.7.1.18 1 m2 Pengecatan permukaan baja galvanis secara manual 4 lapis 44,842.30
A.4.7.1.19 1 m2 Pengecatan permukaan baja galvanis secara manual sistem 1 lapis cat terakhir 11,691.27
A.4.7.1.20 1 m2 Pengecatan permukaan baja galvanis secara manual sistem 3 lapis 113,965.80
A.4.7.1.21 1 m2 Pengecatan permukaan baja galvanis secara semprot sistem 3 lapis cat terakhir 103,893.90
A.4.7.1.21a 1 m2 Pengecatan langit-langit (plafond) 8,230.29
A.4.7.1.21b 1 m2 Couttting ( Glasur batu alam ) 11,834.91
A.4.7.1.21c 1 m2 Pengecatan genteng ( 1 lapis cat dasar, 2 lapis cat penutup) 6,686.04
A.4.7.1.21d 1 m2 Sending impra ( melamine) 42,123.00

A.5.1.1 PEKERJAAN SANITASI DALAM GEDUNG

A.5.1.1.1 1 Bh Pemasangan closet duduk keramik 375,065.70


A.5.1.1.1a 1 Bh Pemasangan closet duduk keramik komplit eks AMSTAD 375,065.70
A.5.1.1.1b 1 Bh Pemasangan closet duduk keramik komplit eks INA 375,065.70
A.5.1.1.1c 1 Bh Pemasangan closet duduk keramik komplit eks TOTO 375,065.70
A.5.1.1.1d 1 Bh Pemasangan closet monoblock lokal 375,065.70
A.5.1.1.2 1 Bh Pemasangan closet jongkok keramik eks AMSTAD 246,405.30
A.5.1.1.2a 1 Bh Pemasangan closet jongkok keramik eks INA 246,405.30
A.5.1.1.3 1 Bh Pemasangan closet duduk jongkok teraso 234,555.00
A.5.1.1.4 1 Bh Pemasangan urinoir 184,195.50
A.5.1.1.5 1 Bh Pemasangan wastafel besar warna muda eks INA 246,747.30
A.5.1.1.5a 1 Bh Pemasangan wastafel besar warna tua eks INA 246,747.30
A.5.1.1.6 1 Bh Pemasangan bathcuip porselen 81,719.19
A.5.1.1.7 1 Bh Pemasangan bak fiberglass vol 1 m3 741,826.50
A.5.1.1.8 1 Bh Pemasangan bak mandi batu vol 0,30 m3 773,928.90
A.5.1.1.9 1 Bh Pemasangan bak mandi teraso vol 0,30 m3 741,826.50
A.5.1.1.10 1 Bh Pemasangan bak mandi fiberglass vol 1 m3 70,366.50
A.5.1.1.11 1 Bh Pemasangan bak mandi beton vol 1 m3 685,853.64
A.5.1.1.12 1 Bh Pemasangan bak cuci piring stainlessteel 34,174.35
A.5.1.1.13 1 Bh Pemasangan bak cuci piring teraso 56,957.25
A.5.1.1.14 1 Bh Pemasangan floor drain plastik 11,391.45
A.5.1.1.14a 1 Bh Pemasangan floor drain staninlees steel 11,391.45
A.5.1.1.15 1 Bh Pemasangan bak kontrol pasangan bata 30x30 tinggi 35cm 241,310.58
A.5.1.1.16 1 Bh Pemasangan bak kontrol pasangan bata 45x45 tinggi 50cm 356,353.17

15
HARGA SAT
NO URAIAN KEGIATAN UPAH
(Rp)
1 2 3
A.5.1.1.17 1 Bh Pemasangan bak kontrol pasangan bata 60x60 tinggi 65cm 356,353.17
A.5.1.1.18 1 m' Pemasangan pipa galvanis diameter 1/2" 16,190.28
A.5.1.1.19 1 m' Pemasangan kran diameter 1/2" 41,607.15
A.5.1.1.19a 1 m' Pemasangan kran diameter 3/4" 41,607.15
A.5.1.1.19b 1 m' Pemasangan kran dupon 41,607.15
A.5.1.1.19c 1 m' Pemasangan kran Toto 1/2" 41,607.15
A.5.1.1.19d 1 m' Pemasangan stop kran diameter 1" 41,607.15
A.5.1.1.19e 1 m' Pemasangan stop kran diameter 1/2" 41,607.15
A.5.1.1.19f 1 m' Pemasangan stop kran diameter 3/4" 41,607.15
A.5.1.1.19g 1 m' Pemasangan stop kran diameter 1" kuningan 41,607.15
A.5.1.1.19h 1 m' Pemasangan stop kran diameter 1/2" kuningan 41,607.15
A.5.1.1.19i 1 m' Pemasangan stop kran diameter 3/4" kuningan 41,607.15
A.5.1.1.19j 1 m' Pemasangan stop kran diameter 1" plastik 41,607.15
A.5.1.1.19k 1 m' Pemasangan stop kran diameter 1/2" 41,607.15
A.5.1.1.20 1 m' Pemasangan pipa galvanis diameter 3/4" 16,190.28
A.5.1.1.21 1 m' Pemasangan pipa galvanis diameter 1" 16,190.28
A.5.1.1.22 1 m' Pemasangan pipa galvanis diameter 1 1/2" 27,101.79
A.5.1.1.22a 1 m' Pemasangan pipa galvanis diameter 2" 27,101.79
A.5.1.1.22b 1 m' Pemasangan pipa galvanis diameter 2 1/2" 27,101.79
A.5.1.1.23 1 m' Pemasangan pipa galvanis diameter 3" 34,011.33
A.5.1.1.24 1 m' Pemasangan pipa galvanis diameter 4" 34,011.33
A.5.1.1.25 1 m' Pemasangan pipa PVC tipe AW diameter 1/2" 9,069.84
A.5.1.1.26 1 m' Pemasangan pipa PVC tipe AW diameter 3/4" 9,069.84
A.5.1.1.27 1 m' Pemasangan pipa PVC tipe AW diameter 1" 9,069.84
A.5.1.1.28 1 m' Pemasangan pipa PVC tipe AW diameter 11/2" 13,604.76
A.5.1.1.29 1 m' Pemasangan pipa PVC tipe AW diameter 2" 13,604.76
A.5.1.1.30 1 m' Pemasangan pipa PVC tipe AW diameter 21/2" 20,353.28
A.5.1.1.31 1 m' Pemasangan pipa PVC tipe AW diameter 3" 20,353.28
A.5.1.1.32 1 m' Pemasangan pipa PVC tipe AW diameter 4" 20,353.28
A.5.1.1.33 1 m' Pemasangan pipa air limbah jenis pipa tanah Ø 20 cm 10,706.88
A.5.1.1.35 1 m' Pemasangan pipa beton diameter 15-20 cm 18,737.04
A.5.1.1.36 1 m' Pemasangan pipa beton diameter 30 cm 50,857.68
A.5.1.1.36a 1 m' Pemasangan pipa beton diameter 40 cm 50,857.68
A.5.1.1.36b 1 m' Pemasangan pipa beton diameter 50 cm 50,857.68
A.5.1.1.36c 1 m' Pemasangan pipa beton diameter 60 cm 50,857.68
A.5.1.1.36d 1 m' Pemasangan pipa beton diameter 80 cm 50,857.68
A.5.1.1.36e 1 m' Pemasangan pipa beton diameter 100 cm 50,857.68

ANALISA TAMBAHAN

1 1 m2 Pemasangan lantai batu ampyang 136,212.62


2 1 m2 Pemasangan HPL 215,019.50
3 1 m2 Pengecatan Flexy 41,151.44
4 1 m2 Pemasangan Alumunium Composite Panel Ex. Alucopan 331,208.76

16
REKAPITULASI
HARGA SATUAN PEKERJAAN ( AHSP )
BIDANG PEKERJAAN UMUM

OVERHEAD DAN PROFIT 14%

HARGA SATUAN KONTRAK BAWAH


BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6

669,564.18 - 725,492.58
802,619.28 - 863,335.68
537,044.88 - 587,558.28
719,224.86 - 738,841.41
1,614,040.50 6,771.60 2,108,475.60
2,193,690.60 - 2,446,200.60
1,732,817.10 - 2,022,485.40
1,661,669.70 - 1,951,338.00
- - 13,195.50
18,875.21 - 308,543.51
255,412.44 - 289,219.14
80,814.60 - 159,443.25
- - 1,113,000.24
- - 556,500.12
4,724.46 - 13,150.20
324,028.47 - 379,407.39
- - 88,863.00
- - 41,738.25
- - 26,391.00
- - 26,391.00
- - 135,631.50
- - 83,476.50
- - 1,010,040.00

17
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
- - 676,134.00

- - 61,260.75
- - 75,128.85
- - 89,212.41
- - 81,537.36
- - 123,598.80
- - 98,555.85
- - 4,443.15
- - 26,847.00
- - 44,431.50
- - 44,431.50
237,074.40 - 261,578.70
369,409.59 - 480,787.59
52,668.00 - 65,997.45
255,816.00 - 278,031.75
112,860.00 - 135,075.75

844,557.60 - 1,045,311.60
792,847.20 - 993,601.20
756,978.24 - 957,732.24
731,770.56 - 932,524.56
697,196.64 - 897,950.64
725,020.62 - 925,774.62
834,538.71 - 1,035,292.71
788,774.55 - 989,528.55
506,214.72 - 610,606.80
2,258,394.72 - 2,628,256.89
704,654.52 - 985,465.59
1,124,704.28 - 1,275,662.51
688,222.33 - 805,363.03

18
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6

858,607.87 - 1,024,148.98
899,356.94 - 1,064,898.05
931,100.47 - 1,096,641.58
842,021.78 - 962,337.38
968,869.58 - 1,134,410.69
1,004,618.62 - 1,170,159.73
1,031,939.86 - 1,197,480.97
1,049,341.73 - 1,214,882.84
1,079,446.32 - 1,244,987.43
1,088,699.54 - 1,254,240.65
1,124,051.86 - 1,334,604.16
1,136,214.74 - 1,380,342.89
1,111,454.40 - 1,322,006.70
57,336.30 - 65,366.46
77,206.50 - 87,005.37
108,448.20 - 119,155.08
128,694.60 - 142,041.15
127,691.40 - 136,955.04
337,052.40 - 344,028.63
164,205.60 - 236,912.52
183,956.10 - 256,663.02
309,732.30 - 402,014.16
321,582.60 - 413,864.46
364,908.30 - 457,190.16
266,532.00 - 358,813.86
269,900.70 - 362,182.56
122,260.44 - 140,470.23
3,726,580.20 - 4,454,885.73
4,657,116.60 - 5,481,238.56
7,933,955.40 - 8,959,686.36
6,106,546.80 - 6,999,350.91
5,604,775.80 - 6,333,401.10
5,336,419.80 - 6,064,725.33
5,609,706.30 - 6,433,828.26
72,225.84 - 93,648.15
80,865.90 - 116,239.53
- - 312,360.00

77,508.14 - 90,764.63
96,883.13 - 113,471.27
105,090.22 - 124,921.09
145,309.64 - 170,195.27
313,567.09 - 321,918.73
32,143.44 - 36,412.17
30,063.74 - 34,332.47
- - 5,975.31
- - 10,549.56

19
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
- - 8,531.76
- - 52,250.19
- - 53,857.59
- - 48,471.09
- - 44,925.69
68,077.15 - 96,692.29
- - 64,261.23

20,189.40 - 33,395.73
20,189.40 - 31,959.33
11,343.00 16,416.00 46,416.24
1,003,621.80 - 1,209,541.71
38,030.40 3,876.00 47,499.24
177,898.37 - 305,352.08
625,518.00 - 855,099.18
509,580.00 - 595,892.82
718,314.00 - 815,143.32
431,832.00 - 627,997.50
116,359.80 - 124,789.53
727,570.80 - 744,239.48
1,004,112.00 - 1,020,920.16
124,830.00 - 193,541.79
202,685.05 - 530,227.57
97,438.31 - 117,054.86
105,087.71 - 124,704.26
89,161.91 - 108,778.46
88,534.91 - 108,151.46
487,874.40 - 526,137.93
182,072.82 - 220,336.35
61,596.48 - 107,978.52
89,262.00 - 136,789.74
99,180.00 - 165,697.29

237,142.80 - 307,372.50
223,615.56 - 293,845.26
214,003.08 - 284,232.78
209,769.12 - 279,998.82
209,883.12 - 280,112.82
228,545.78 - 298,775.48
113,500.68 - 148,615.53
106,792.92 - 141,907.77
103,115.28 - 138,230.13
100,812.48 - 135,927.33
99,845.76 - 134,960.61
97,242.00 - 132,356.85
115,775.55 - 150,890.40
103,336.67 - 138,451.52
100,546.40 - 135,661.25

20
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
1,400,633.64 - 1,445,012.13
1,088,558.64 - 1,132,937.13
1,404,204.12 - 1,448,582.61
1,092,129.12 - 1,136,507.61
1,015,765.08 - 1,070,076.96
874,690.08 - 929,001.96
1,018,149.96 - 1,072,461.84
877,074.96 - 931,386.84
641,313.84 - 676,428.69
641,313.84 - 676,428.69
643,701.00 - 678,815.85
643,701.00 - 678,815.85
701,829.60 - 736,944.45
318,789.60 - 353,904.45
710,274.72 - 750,425.52
94,371.48 - 129,217.01

29,559.74 - 69,710.54
22,336.70 - 62,487.50
19,332.58 - 59,483.38
17,182.08 - 57,332.88
16,098.62 - 56,249.42
15,173.86 - 55,324.66
14,708.74 - 54,859.54
14,243.62 - 54,394.42
17,450.55 - 59,588.37
18,049.05 - 60,186.87
17,285.02 - 59,422.84
15,851.59 - 57,989.41
29,882.59 - 83,632.45
25,877.09 - 67,724.78
22,909.44 - 76,659.30
21,565.15 - 75,315.01
20,231.81 - 73,981.67
19,993.66 - 78,881.50
16,098.62 - 36,281.18
4,710.48 - 51,676.20
87,780.00 - 148,113.36
55,290.00 - 115,623.36
8,700.48 - 43,815.33
4,960.37 - 25,142.93
2,553.60 - 12,029.28
13,730.16 - 53,880.96
5,187.00 - 31,954.20
15,013.80 - 20,688.15

67,118.64 - 103,361.52
98,692.74 - 133,490.10

21
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
229,175.75 - 262,741.91
148,400.64 - 242,085.84
92,359.86 - 186,045.06
98,692.74 - 192,377.94
231,561.49 - 325,246.69
287,826.71 - 381,511.91
309,017.51 - 402,702.71
428,489.77 - 522,174.97
213,293.56 - 306,978.76
138,151.47 - 231,836.67
130,966.08 - 224,651.28
176,757.70 - 270,442.90
103,805.85 - 197,491.05
100,298.84 - 193,984.04
185,160.94 - 278,846.14
96,500.59 - 190,185.79
98,692.74 - 192,377.94
95,891.66 - 189,576.86
112,089.22 - 205,774.42
97,068.72 - 190,753.92
115,189.02 - 136,510.44
23,919.48 - 43,322.28
160,673.88 - 254,359.08
164,903.28 - 258,588.48
257,708.40 - 351,393.60
226,652.52 - 320,337.72
266,167.20 - 359,852.40
199,705.20 - 293,390.40
199,705.20 - 293,390.40
2,820,241.44 - 2,913,926.64
294,806.28 - 388,491.48
162,969.84 - 256,655.04
161,519.76 - 255,204.96
119,588.28 - 213,273.48
35,910.00 - 69,312.00
50,691.24 - 171,143.64
87,123.36 - 207,575.76
142,046.28 - 262,498.68
142,046.28 - 262,498.68
88,281.60 - 208,734.00
105,078.36 - 225,530.76
87,677.40 - 208,129.80
92,511.00 - 212,963.40
92,511.00 - 212,963.40
176,253.12 - 296,705.52
88,281.60 - 208,734.00
87,677.40 - 208,129.80
169,244.40 - 289,696.80
224,709.96 - 345,162.36
351,471.12 - 471,923.52
358,721.52 - 479,173.92
346,033.32 - 466,485.72

22
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
284,284.08 - 404,736.48
264,224.64 - 384,677.04
183,503.52 - 303,955.92
203,442.12 - 323,894.52
197,762.64 - 318,215.04
197,762.64 - 318,215.04
2,818,298.88 - 2,938,751.28
292,863.72 - 413,316.12
161,027.28 - 281,479.68
139,759.44 - 260,211.84
180,482.52 - 300,934.92
159,939.72 - 280,392.12
571,883.28 - 692,335.68
139,396.92 - 259,849.32
246,219.48 - 366,671.88
246,219.48 - 366,671.88
246,219.48 - 366,671.88
357,677.28 - 531,664.08
361,906.68 - 535,893.48
454,711.80 - 628,698.60
188,670.00 - 282,355.20
167,352.00 - 261,037.20
168,480.60 - 262,165.80
22,771.50 - 67,890.99
77,155.20 - 99,258.66
61,049.74 - 83,122.99
111,229.80 - 132,251.40
94,677.00 - 115,698.60
127,782.60 - 148,804.20
107,091.60 - 128,113.20
148,473.60 - 169,495.20
101,574.00 - 122,595.60
120,885.60 - 141,907.20
100,194.60 - 121,216.20
120,885.60 - 141,907.20
100,194.60 - 121,216.20
102,953.40 - 123,975.00
86,400.60 - 107,422.20
86,400.60 - 107,422.20
79,503.60 - 100,525.20
100,194.60 - 121,216.20
82,262.40 - 103,284.00
107,091.60 - 128,113.20

18,242.28 - 28,904.13
13,477.08 - 24,138.93
573,374.40 - 596,914.26
314,298.00 - 337,837.86
91,838.40 - 291,574.95
33,847.74 - 233,584.29

23
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
630,445.08 - 787,377.48
385,915.08 - 542,847.48
197,815.08 - 354,747.48
202,517.58 - 359,449.98
146,087.58 - 303,019.98
136,682.58 - 293,614.98
103,765.08 - 260,697.48
89,657.58 - 246,589.98
35,155.32 - 49,137.42
467,360.10 - 565,442.85
3,901.08 - 13,763.22
99,180.00 - 165,697.29
24,384.60 - 28,488.03
31,207.50 - 35,310.93

74,100.00 - 95,127.02
91,200.00 - 112,227.02
65,550.00 - 86,577.02
142,500.00 - 163,527.02
324,900.00 - 345,927.02
285,000.00 - 306,080.31
55,458.72 - 109,447.98
137,538.72 - 191,527.98
51,582.72 - 103,177.98
45,198.72 - 99,187.98
44,286.72 - 98,275.98
166,451.40 - 185,720.25
65,999.16 - 86,298.57
69,453.36 - 89,752.77
76,088.16 - 95,663.10
61,040.16 - 80,615.10
25,261.26 - 44,836.20
36,409.32 - 55,984.26
34,172.64 - 53,747.58
48,769.20 - 68,344.14
46,128.96 - 65,703.90
46,351.26 - 65,926.20
50,198.76 - 69,773.70
55,331.04 - 74,905.98
55,633.14 - 75,208.08
75,216.06 - 94,791.00
99,043.20 - 120,173.10
99,145.80 - 120,275.70
145,492.50 - 166,622.40
48,153.60 - 69,283.50
57,045.60 - 78,175.50
51,129.00 - 76,059.09
91,006.20 - 112,136.10
62,720.52 - 90,684.72
79,508.16 - 106,502.79

24
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
254,493.60 - 296,490.63
50,362.92 - 106,291.32
47,196.00 - 85,022.34
21,181.20 - 59,761.08
59,660.76 - 76,439.28
44,738.16 - 61,516.68
56,822.16 - 73,600.68
40,998.96 - 57,777.48
26,972.40 - 47,220.51
14,557.80 - 34,805.91
15,686.40 - 35,934.51
61,400.40 - 158,809.98
71,814.30 - 169,223.88
82,228.20 - 179,637.78
91,804.20 - 189,213.78
23,757.60 - 57,815.10
13,167.00 - 31,376.79

38,662,131.00 - 41,612,935.50
26,247,531.00 - 29,198,335.50
13,143,231.00 - 16,094,035.50
13,488,081.00 - 16,438,885.50
9,349,881.00 - 12,300,685.50
8,660,181.00 - 11,610,985.50
6,935,931.00 - 9,886,735.50
6,246,231.00 - 9,197,035.50
42,173,331.00 - 44,702,592.00
28,630,131.00 - 31,159,392.00
14,334,531.00 - 16,863,792.00
14,710,731.00 - 17,239,992.00
10,196,331.00 - 12,725,592.00
9,443,931.00 - 11,973,192.00
7,562,931.00 - 10,092,192.00
6,810,531.00 - 9,339,792.00
1,681,283.40 - 1,828,877.49
1,029,203.40 - 1,176,797.49
527,603.40 - 675,197.49
540,143.40 - 687,737.49
389,663.40 - 537,257.49
364,583.40 - 512,177.49
276,803.40 - 424,397.49
239,183.40 - 386,777.49
1,681,283.40 - 1,828,877.49
1,029,203.40 - 1,176,797.49
527,603.40 - 675,197.49
540,143.40 - 687,737.49
389,663.40 - 537,257.49
364,583.40 - 512,177.49
276,803.40 - 424,397.49
239,183.40 - 386,777.49

25
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
1,681,152.30 - 2,102,695.80
1,029,072.30 - 1,450,615.80
527,472.30 - 949,015.80
540,012.30 - 961,555.80
389,532.30 - 811,075.80
364,452.30 - 785,995.80
276,672.30 - 698,215.80
239,052.30 - 660,595.80
1,012,969.80 - 1,350,204.60
621,721.80 - 958,956.60
320,761.80 - 657,996.60
328,285.80 - 665,520.60
237,997.80 - 575,232.60
222,949.80 - 560,184.60
170,281.80 - 507,516.60
147,709.80 - 484,944.60
2,696,499.00 - 3,118,042.50
1,653,171.00 - 2,074,714.50
850,611.00 - 1,272,154.50
870,675.00 - 1,292,218.50
629,907.00 - 1,051,450.50
589,779.00 - 1,011,322.50
449,331.00 - 870,874.50
389,139.00 - 810,682.50
1,129,610.04 - 1,424,690.49
722,060.04 - 1,017,140.49
408,560.04 - 703,640.49
416,397.54 - 711,477.99
322,347.54 - 617,427.99
306,672.54 - 601,752.99
251,810.04 - 546,890.49
228,297.54 - 523,377.99
2,431,889.04 - 2,769,123.84
1,518,977.04 - 1,856,211.84
816,737.04 - 1,153,971.84
834,293.04 - 1,171,527.84
623,621.04 - 960,855.84
588,509.04 - 925,743.84
465,617.04 - 802,851.84
412,949.04 - 750,183.84
2,523,310.20 - 2,837,098.05
1,545,190.20 - 1,858,978.05
792,790.20 - 1,106,578.05
811,600.20 - 1,125,388.05
585,880.20 - 899,668.05
548,260.20 - 862,048.05
416,590.20 - 730,378.05
360,160.20 - 673,948.05
1,147,074.84 - 1,484,309.64
739,524.84 - 1,076,759.64
426,024.84 - 763,259.64
433,862.34 - 771,097.14

26
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
339,812.34 - 677,047.14
324,137.34 - 661,372.14
269,274.84 - 606,509.64
245,762.34 - 582,997.14
1,311,747.84 - 1,670,113.68
904,197.84 - 1,262,563.68
590,697.84 - 949,063.68
598,535.34 - 956,901.18
504,485.34 - 862,851.18
488,810.34 - 847,176.18
433,947.84 - 792,313.68
410,435.34 - 768,801.18
39,046,390.80 - 40,732,564.80
26,631,790.80 - 28,317,964.80
14,906,890.80 - 16,593,064.80
13,872,340.80 - 15,558,514.80
9,734,140.80 - 11,420,314.80
9,044,440.80 - 10,730,614.80
7,320,190.80 - 9,006,364.80
6,630,490.80 - 8,316,664.80
42,557,590.80 - 45,381,932.25
29,014,390.80 - 31,838,732.25
14,718,790.80 - 17,543,132.25
15,094,990.80 - 17,919,332.25
10,580,590.80 - 13,404,932.25
9,828,190.80 - 12,652,532.25
7,947,190.80 - 10,771,532.25
7,194,790.80 - 10,019,132.25
38,998,374.00 - 41,822,715.45
26,583,774.00 - 29,408,115.45
13,479,474.00 - 16,303,815.45
13,824,324.00 - 16,648,665.45
9,686,124.00 - 12,510,465.45
8,996,424.00 - 11,820,765.45
7,272,174.00 - 10,096,515.45
6,582,474.00 - 9,406,815.45
622,588.20 - 642,204.75
423,954.60 - 443,571.15
214,285.80 - 233,902.35
219,803.40 - 239,419.95
153,592.20 - 173,208.75
142,557.00 - 162,173.55
114,969.00 - 134,585.55
103,933.80 - 123,550.35
696,323.40 - 715,939.95
473,989.20 - 493,605.75
239,303.10 - 258,919.65
245,479.05 - 265,095.60
171,367.65 - 190,984.20
159,015.75 - 178,632.30
128,136.00 - 147,752.55
128,136.00 - 147,752.55

27
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
492,620.68 - 516,160.54
334,616.68 - 358,156.54
167,834.68 - 191,374.54
172,223.68 - 195,763.54
119,555.68 - 143,095.54
110,777.68 - 134,317.54
88,832.68 - 112,372.54
80,054.68 - 103,594.54
544,418.40 - 598,018.35
370,614.00 - 424,213.95
187,153.80 - 240,753.75
191,981.70 - 245,581.65
134,046.90 - 187,646.85
124,391.10 - 177,991.05
100,251.60 - 153,851.55
90,595.80 - 144,195.75
576,942.60 - 627,444.60
392,980.80 - 443,482.80
198,798.90 - 249,300.90
203,908.95 - 254,410.95
142,588.35 - 193,090.35
132,368.25 - 182,870.25
106,818.00 - 157,320.00
96,597.90 - 147,099.90
455,544.00 - 486,429.45
279,482.40 - 310,367.85
144,050.40 - 174,935.85
147,436.20 - 178,321.65
106,806.60 - 137,692.05
100,035.00 - 130,920.45
76,334.40 - 107,219.85
66,177.00 - 97,062.45
463,022.40 - 493,907.85
283,700.40 - 314,585.85
145,760.40 - 176,645.85
149,208.90 - 180,094.35
107,826.90 - 138,712.35
100,929.90 - 131,815.35
76,790.40 - 107,675.85
66,444.90 - 97,330.35
1,179,022.20 - 1,242,307.59
722,566.20 - 785,851.59
371,446.20 - 434,731.59
380,224.20 - 443,509.59
274,888.20 - 338,173.59
257,332.20 - 320,617.59
195,886.20 - 259,171.59
169,552.20 - 232,837.59
1,076,839.44 - 1,140,124.83
760,831.44 - 824,116.83
427,267.44 - 490,552.83
436,045.44 - 499,330.83

28
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
330,709.44 - 393,994.83
313,153.44 - 376,438.83
269,263.44 - 332,548.83
251,707.44 - 314,992.83
1,091,839.56 - 1,185,843.96
775,831.56 - 869,835.96
442,267.56 - 536,271.96
451,045.56 - 545,049.96
345,709.56 - 439,713.96
328,153.56 - 422,157.96
284,263.56 - 378,267.96
266,707.56 - 360,711.96
296,012.40 - 548,938.50
181,898.40 - 434,824.50
94,118.40 - 347,044.50
96,312.90 - 349,239.00
69,978.90 - 322,905.00
65,589.90 - 318,516.00
50,228.40 - 303,154.50
43,644.90 - 296,571.00
46,067.40 - 56,632.35
648,425.62 - 662,407.72
456,563.62 - 470,545.72
254,042.62 - 268,024.72
259,372.12 - 273,354.22
195,418.12 - 209,400.22
184,759.12 - 198,741.22
158,111.62 - 172,093.72
147,452.62 - 161,434.72

269,952.00 - 342,573.99
247,494.00 - 320,115.99
80,370.00 - 138,034.05
80,370.00 - 138,034.05
82,992.00 - 140,050.14
158,004.00 - 215,062.14
46,740.00 - 64,900.88
90,174.00 - 108,334.88
16,416.00 - 34,576.88
11,172.00 - 29,332.88
54,036.00 - 72,196.88
60,534.00 - 78,694.88
142,158.00 - 160,318.88
162,678.00 - 180,838.88
13,794.00 - 31,954.88
23,028.00 - 35,131.67
40,926.00 - 53,029.67
19,038.00 - 31,141.67
19,836.00 - 31,939.67
16,416.00 - 28,519.67

29
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
7,866.00 - 19,969.67
36,822.00 - 48,925.67
27,018.00 - 39,121.67
59,280.00 - 71,383.67
210,672.00 - 222,775.67
305,520.00 - 317,623.67
177,840.00 - 189,943.67
46,740.00 - 58,843.67
19,836.00 - 50,236.67
24,282.00 - 54,682.67
21,090.00 - 51,490.67
41,496.00 - 71,896.67
38,304.00 - 68,704.67
19,836.00 - 38,772.54
246,924.00 - 307,496.19
239,058.00 - 263,265.33
122,550.00 - 146,757.33
140,904.00 - 165,111.33
322,620.00 - 346,827.33
322,620.00 - 346,827.33
358,758.00 - 382,965.33
109,326.00 - 133,533.33
96,216.00 - 156,788.19
130,416.00 - 190,988.19
308,142.00 - 368,714.19
581,970.00 - 642,542.19
229,140.00 - 289,712.19
79,686.00 - 140,258.19
57,342.00 - 69,930.45
308,712.00 - 381,333.99
16,416.00 - 46,680.55
17,214.00 - 47,478.55
37,506.00 - 67,770.55
40,128.00 - 70,392.55
79,959.60 - 98,120.48
142,283.40 - 160,444.28
145,920.00 - 164,080.88
134,383.20 - 152,544.08
143,035.80 - 161,196.68
190,494.00 - 211,075.62
222,345.60 - 242,927.22
291,190.20 - 321,454.75
181,077.60 - 200,014.14
158,004.00 - 179,458.23
1,571,512.80 - 1,590,449.34
118,753.80 - 137,690.34
943,008.00 - 961,944.54
9,405.00 - 28,341.54
3,143,356.20 - 3,166,547.22

30
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
991.80 - 13,028.49
661.20 - 12,697.89
661.20 - 13,236.54
37,306.50 - 44,546.07
43,883.16 - 59,555.31
3,324.24 - 19,159.98
40,947.43 - 51,503.26
2,314.20 - 10,769.58
9,165.60 - 13,037.04
11,751.12 - 19,981.41
51,559.92 - 59,790.21
24,309.36 - 32,539.65
8,310.60 - 15,050.51
5,010.30 - 17,093.84
5,717.10 - 9,613.62
13,429.20 - 35,404.13
4,114.26 - 26,089.19
15,598.62 - 58,590.87
11,050.02 - 55,892.32
20,705.82 - 32,397.09
24,775.62 - 138,741.42
20,691.00 - 124,584.90
9,972.72 - 18,203.01
32,171.94 - 44,006.85
17,784.00 - 24,470.04
71,392.50 399.00 113,914.50

727,215.12 - 1,102,280.82
2,521,326.60 - 2,896,392.30
1,663,725.12 - 2,038,790.82
3,230,294.88 - 3,605,360.58
1,177,344.12 - 1,552,409.82
310,878.00 - 557,283.30
202,350.00 - 448,755.30
180,393.60 - 414,948.60
1,714,069.80 - 1,898,265.30
418,129.20 - 664,876.50
462,069.36 - 708,816.66
2,723,961.60 - 2,805,680.79
384,189.12 - 1,126,015.62
691,608.82 - 1,465,537.72
140,831.04 - 882,657.54
384,189.12 - 454,555.62
3,931,936.49 - 4,617,790.13
374,718.00 - 408,892.35
366,966.00 - 423,923.25
12,768.00 - 24,159.45
54,036.00 - 65,427.45
193,480.80 - 434,791.38
298,885.20 - 655,238.37

31
HARGA SATUAN KONTRAK BAWAH
BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp)
4 5 6
468,974.34 - 825,327.51
40,464.30 - 56,654.58
31,643.84 - 73,250.99
37,571.84 - 79,178.99
182,351.84 - 223,958.99
349,703.84 - 391,310.99
27,083.84 - 68,690.99
35,633.84 - 77,240.99
23,093.84 - 64,700.99
92,291.84 - 133,898.99
87,617.84 - 129,224.99
67,895.84 - 109,502.99
23,777.84 - 65,384.99
29,705.84 - 71,312.99
51,949.80 - 68,140.08
79,515.00 - 95,705.28
120,509.40 - 147,611.19
164,507.70 - 191,609.49
209,919.60 - 237,021.39
271,234.50 - 305,245.83
392,450.70 - 426,462.03
5,124.30 - 14,194.14
15,372.90 - 24,442.74
19,437.00 - 28,506.84
30,745.80 - 44,350.56
35,693.40 - 49,298.16
51,066.30 - 71,419.58
61,314.90 - 81,668.18
91,884.00 - 112,237.28
178,845.71 - 189,552.59
129,151.97 - 147,889.01
200,242.94 - 251,100.62
236,358.14 - 287,215.82
308,839.34 - 359,697.02
323,260.34 - 374,118.02
381,195.14 - 432,052.82
598,513.34 - 649,371.02

126,973.20 - 263,185.82
215,986.91 - 431,006.41
91,792.80 4,389.00 137,333.24
597,046.50 - 928,255.26

32
REKAPITULASI
ANALISA HARGA SATUAN PEKERJAAN ( AHSP )
KONTRAK BAWAH DAN ATAS
BIDANG PEKERJAAN UMUM
TAHUN ANGGARAN 2018
I
AAN ( AHSP )
TAS
UM
18

You might also like