Annex I to Arrangement on the allocation of funds for planning ammunition storage facilities
I APPROVE
. . . . . . . . . . . . . . 20 No '
I . Project title: typical project for the construction of a special purpose structure.
2.1. S t ru c t u r e
under reconstruction - none;
during the preparation of project proposals for the construction of the structure.
2.6. Stages of project preparation - project proposals, technical project and project implementation
supervision.
3 . 1 . 1 . Plot boundary determination document - Property registered in the Real Estate Register on 04-
02-1992;
3 . 1 . 3 . Certificate of a land plot registered in the Real Estate Register and the right to it - unique No.
3 . 3 . 1 . Certificate of a land plot registered in the Real Estate Register and the right to it - unique No.
3.4.1.Certificate of a land plot registered in the Real Estate Register and the right to i t - unique No.
3 . 5 . 1 . Certificate of a land plot registered in the Real Estate Register and the right to it - unique No.
3 . 6 . 1 . Certificate of a land plot registered in the Real Estate Register and the right to it - unique
No.8638-0004-0008;
3.7. Lithuanian Armed Forces Grand Duke Vytenis General Support Logistics Battalion
(Kazlu Ruda):
3.7.1.Certificate of a land plot registered in the Real Estate Register and the right to it - unique No.
5144-0001-0024;
4. The basis of the software task: funding specified in the KAS 2021-2030 planning guide and
agreement with the Federal Ministry of Defense of the Federal Republic of Germany on the allocation
8.2. Lithuanian Grand Duke Kestutis Motorized Infantry Battalion (Taurage) - I warehouse;
8.5. Duke Vaidotas Mechanized Infrantry Battalion (Pabrade Central Landfill) - I warehouse;
8.6. Lithuanian Armed Forces Grand Duke Vytenis General Support Logistics Battalion (Kazlu
Ruda) - I warehouse;
9.1. Military ammunition and explosive materials storage room (hereinafter - storage room), about
2 2 2
440 m 8 . 1 and 8.7 in clause mentioned units and an area of about 440 m (400 m for main storage
2
room and 40 m for ammunition for another compatibility class) 8.2 - 8.6 in clause mentioned units;
2
9.2. Technical room, about I O m , where it is necessary to install: microclimate and other equipment
9.4. Closed and heated roof, where it is necessary to store electric loader.
IO. I . The structure stores military ammunition and explosives of various types and calibers according
I 0.2. Maximum amount of net explosives quantity (NEQ) stored in the structure (hazard class 1 . 1 ) -
10.3. Military ammunition and explosives are stored in the storage room using NATO standard
pallets (axb, I OOOx 1200 mm), which can be stacked on top of each other up to 3.9 m. height. The
highest pallets are raised to a height of 0.5 m from the top of the pallets below them during transfer,
1 1 . Installation requirements:
1 1 . 1 . Requirements for the structure:
1 1 . 1 . l . To provide an above-ground structure covered with a reinforced soil layer (Annex No. I), in
1 1 . 1 . 3 . To provide an extension of the structure (for the installation of the technical room (PU clause
1 1 . 1 . 4 . If necessary to provide means of containment of the blast wave for buildings around
warehouses;
1 1 . 2 . 1 . To provide for the storage room to withstand an instantaneous e x p l o s i o n impact of at least 7.0
Bar inside the structure (follow the documentation provided in clauses 25.3, 25.9, 2 5 . 1 O);
1 1 . 2 . 2 . To provide the height of the storage room (from floor level to the vault) comprehensive
assessment of clause I 0.3 the intended storage height, engineering system i n s t a l l a t i o n solutions in the
1 1 . 2 . 3 . To provide solutions that meet the requirements of physical protection (burglary resistance)
(follow the requirements of clause 25.2): external walls of the storage room, overlaps - at least 150
mm of reinforced concrete or materials with similar physical properties ensuring burglary resistance.
To provide safety g r i l l e s on the inner s i d e of ventilation hatches and other openings ( i f they are larger
than l 80x 1 8 0 mm) and a steel safety net on the outer side;
1 1 . 2 . 4 . To provide that an electric forklift ( l 900x I 200mm) with a removable rechargeable battery
adapted for use in explosive atmospheres and h a v i n g a l i f t i n g capacity of up to 2 t and a lifting height
of 3 111 will be used for loading/unloading of military ammunition and explosives stored in the storage
l 0268 840-seat ed-po wered-ex p I osi on-proof- fork I i ft -600111111-reach-d i st a nee- for-ammunition-
depots. ht m 1 . Requirements for typical electric forklift also are provided in clause 2 5 . 1 1 ;
1 1 . 2 . 5 . The floor level of a l l storage rooms must be the same a and not to create an obstacle to other
1 1 . 2 . 6 . To provide a gate (with an opening of at least 4x4 m) in the storage room, which opens to the
outside of the room and meets the requirements for security class I (in accordance with sub-clause
25.12). Gate must comply requirements provided in AASTP-1 and protected against burglary. The
most suitable type of gate and more precise requirements for them are coordinated with the customer
during design;
11.2.7.The storage room must have a constant rnicroclimat e (relative humidity to 60 per cent,
1 1 . 2 . 8 . To provide measures to protect the storage room from the formation of water condensate.
Ammunition storage room must be as dry as possible. If necessary, air dehumidifiers must be
installed;
11.2.9. To provide an antistatic floor in the storage room, resistant to m echanical and dynamic effects,
2
which must withstand a load of at least 50 kN/m ;
1 1 . 2 . 1 0. To provide coatings in the storage room, depending on the purpose of the room. Coatings
11.2.12.To provide electrical switches outside the storage room, voltage - 220 V;
11.2.1 3.To provide lighting solutions that would provide at least - 75 Ix l i g h t i n g at the floor surface
level;
11.2.14.To prov
idea fire alarm. The signal output location shall be adjusted d u r i n g design ;
11.2.15.Provide alert on electricity, HY A C , electricity generator, etc. system fault warning signal.
1 1 . 2 . 1 6 . The gate locks shall be subject to the technical requirements of MIL-DTL-43607H and MIL
DTL-436071. The requirements u nder the above code are available at h tt p ://every s p e c.co m /.
support equipment and control, internal and external lighting control and other engineering systems
1 1 . 3 . 3 . To provide the microclimate regime of the technical room and its maintenance measures,
taking into account the requirements for the equipment to be installed in the room;
1 1 . 3 . 4 . To provide a fire alarm. The signal output location shall be adjusted during design;
1 1 . 4 . 1 . To provide a static loading/unloading site with a hard artificial surface (asphalt, etc.) suitable
for four-axle vehicles of class N3 (2600xl2000x4500 mm) intended for the carriage of goods. The
technically permissible maximum laden mass of the vehicle is at least 48 t. The designer must assess
the maximum permissible vehicle loads provided by legal acts and during the design proposal an
1 1 . 4 . 2 . Provide natural pavement access roads to structures adapted to the vehicles referred to in
clause 1 1 . 4 . l. The type of pavement shall be coordinated with the builder (customer) during the
project preparation.
1 2 . Installation of security systems - electronic security systems for the warehouse and other
structures installation will be coordinated during design. The initial requirements for protection
systems is provided in Annex No. 9. The customer will specify the security system solutions after the
16.2. R equired - III (the category may change after assessing the n eed provided for in clause 1 8 .2) ;
17. Sp ecific r equirements for the installation of engineering systems of the structure:
17 . 1 . To provide, taking into account the purpose of the structure, all engineering systems necessary
for the functioning of the structure, economically j ustified and safe to operate in an explosive
environment ;
1 7 . 2 . To provide temperature (thermal) and relative hu mi dity sensors that respond to changes in the
temperature and relative humidity in the storage room ( specified in clause 11.2.7.). S ignal
17.3. To provide monitoring and fault warning systems for electrical, HV AC and power generator
systems. D uring the design, the locations of monitoring and fault signals will be indicated.
18. Sp ecific r equirements for engineering structures ensuring the func tioning of the structure:
1 8 . 1 . To evaluate the existing engineering networks in the territory, their capacities, provide for the
18.2. To provide an electricity generator of the required power to ensure an uninterrupted supply of
1 8 . 3 . To provide protection of the structure and equipment from lightning and static electricity. All
metal a nd other electrically conductive parts of technological equipment must be earthed, regardless
1 8 . 4 . To provide lighting for the structure accesses and entrances to the structure during the dark
18.5. To provide for the transmission of fire warning signals to the structures agreed with the
comm unication channels 2xd 1 1 0 with intermediate passage wells every 50 m and at corners, internal
communication between buildings ( 2xdl 10) which would be u sed for laying signal cables. The pipes
mu st be integrated into the technical premises w here the control units of all signaling I control devices
will be installed. If necessary , network laying works outside t he site may be carried out in a closed
manner without the wells and pipes specified in sub-clauses 9.2 and 9.3 and up to the structures I
1 8 . 7 . To provide for the discharge of surface (rain) wastewater from the structure and the area around
the structure. Also provide fire safety measures (including preventive measures) for extinguishing
1 8 . 8 . To provide for the restoration of all damaged, destroyed pavements during the construction,
including all works necessary for the proper use of the infrastructure (greenery, roads, engineering
networks/systems, etc.);
18.9. To provide for the fencing of the area around the warehouse in accordance with the
requirements of clauses 25.2 and 25.5 and Annex No. 9. The need for fencing of each territory and
20. Need to perform engineering geological and geotechnical surveys - to provide for mandatory
21.1.1.Description of solutions for the planning of the structure (premises) from the functional
21.1.2.Descriptions and schematic diagrams of future foundations, floors, overlays, coatings, roof,
retaining walls, blast wave containment measures around the structure and other supporting
structures;
2 1 . 1 . 3 . The maximum amount of net explosives quantity (NEQ) allowed to be stored in the structure
(hazard class 1.1) must be indicated, drawings and calculations of the hazardous areas of the
warehouse must be attached and the rotation angles of the warehouses with respect to the surroundin g
objects were selected accordingly. Only after performing the above-mentioned actions and
coordinating them with the customer, the designer submits the final layout plan of buildings
(warehouses) for the customer's approval. Based on the above information, the designer must select
the storage locations and rotation angles so that the maximum safe amount of NEQ allowed to be
stored in the warehouses can be stored. If it is not possible to change the location of the structure due
to non-compliance with safety requirements, the designer must evaluate and propose solutions for the
21.1.4.Specifications of construction materials/works and technology to be used for the floors, walls,
21.1.5.Information on the heating, ventilation, air conditioning and other systems provided in the
structure;
21.1.6.Information on the planned solutions for the disposal of surface (rain) wastewater (from the
2 1 . 1 . 8 . Information on the planned solutions of engineering systems that ensure the functioning of the
structure;
2 1 . 2 . To prepare design proposals for each structure in the territories specified in the Annex, the
composition of which:
2 1 . 2 . l . Description of the designed structure and its adjacencies and conditions: place of construction
of the structure, relief, type of construction, purpose of the structure, category of the structure, other
necessary data;
21.2.2.Brief description of the construction site: buildings, engineering networks and equipment on
the site, greenery, geological, hydrogeological conditions, hygienic and ecological situation,
environmental construction;
21.2.3.Description of the engineering networks and communications on the construction site and
2 1 . 2 . 5 . The minimum safety distance (based on calculations) from the designed warehouse to the
engineering networks;
21.2.7.Descriptions of the site arrangement, communication and other structures and schematic
21.2.9.Project proposals must be prepared specifically for each object. Also project proposals must
2 2 . 1 . Designing begins only after coordinating all issues with the builder (customer) and specifying
the software task, compliance with the valid spatial planning documents;
22.3. To coordinate the project with other state supervision institutions, as required by laws, other
legal acts or the builder (customer) may instruct the designer to do so;
22.4. To receive the builder's (customer's) approval of the essential solutions of the project and the
approval of the project - in accordance with clauses 52-55 of STR 1.04.04: 2 0 1 7 "Structure design,
project expertise".
22.5. The designer must submit the acts of coordination of the solutions of the project components,
signed by the project manager and the managers of the project parts, and assume responsibility for
the content of these acts and the conformity of the solutions to the actual construction conditions;
22.6. The designer must submit the project manager's approval for the appointment (hiring) of the
22.7. Any amendment, supplement or correction of design solutions must be agreed with the builder
(customer) and formalized in accordance with the procedure established by legal acts;
22.8. Correction or replacement of bad design solutions; elimination of errors in design solutions or
replacement with other design solutions during the entire term of the contract must be performed by
the designer free of charge, within the term agreed with the builder (customer). Amendments,
supplements and corrections to the project are made by preparing a new edition design solution
document, and a new edition is assigned to this document. If the project documents are amended,
supplemented and corrected several times, a new edition of the documents is issued each time. The
designer, having prepared the project, its amendments, supplements and corrections, and having
signed it, confirms that the project complies with the provisions of laws, other legal acts, project
preparation documents, normative construction technical documents, normative structure safety and
purpose documents, and is responsible for the quality of the whole project, the consequences of
22.9. If bad project solutions (not in accordance with the requirements of the applicable legal acts,
not based on calculations, inconsistent with each other and resulting in the need to amend/correct the
project) and/or errors are revealed during the preparation or contracting of the work project, the
designer must correct the project without additional remuneration and coordinate it with the builder
(customer), other institutions, by issuing a project document of a new edition and, if necessary, obtain
a new construction permit and pay the builder (customer) costs of re-examination of the
2 3 . 1 . The main normative documents and other conditions under which the work will be performed
23.2. The technical specifications of the project components must be written specifically for this
23.3. The designer must ensure and, at the request of the builder (customer) manager, submit
documents ensuring that construction products, materials, equipment, products, etc. complying with
the technical specifications of the project components can be supplied by at least three manufacturers.
This information must be provided in the technical specifications of the project components at the
23.4. All materials, construction products, equipment and items specified in the project must be duly
23.5. Workload sheets must be prepared in accordance with the requirements of the project task. To
group works in project drawings, workload sheets according to project components and individual
work groups (the division of work groups must be coordinated between project parts).
23.6. When forming the minimum requirements for construction works technologies and quality, use
references to the descriptions of relevant construction works technologies and quality in the current
editions of www.statybostaisyklos.lt.
23.7. The project is completed and formalized in accordance with the procedure established by LST
1516: 2015.
23.7.1.Projects must be prepared specifically for each object. Also projects must be prepared for each
object separately.
23.8.
24.1. The designer undertakes to organize and ensure the proper performance of the supervision of
the construction project execution provided for in the contract and valid legal acts throughout the
construction period of the structure, from the beginning of the construction of the structure to the
completion of the construction of the structure in accordance with the procedure established by legal
acts. All costs related to the project implementation supervision activities are the responsibility of the
24.2. The supervision of the construction project implementation shall be carried out in accordance
with Chapter VI "Description of the procedure for supervision of the execution of the structure
24.3. It is obligatory to supervise the implementation of the solutions of all components of the
structure project, which is carried out by the designer who prepared the structure project.
24.4. Before the start of construction of the structure, the designer shall submit and agree the
a) Schedule of the structure project execution supervision works, the course of the execution
b) Composition of the structure project execution supervision team (names, surnames, positions,
issuance, validity dates and numbers of documents granting the right to hold the respective
supervision manager and the managers of all parts of the structure project execution supervision
managers;
c) Time and procedure for visiting the construction site. The designer must visit the structure
being constructed (construction site) during the whole period of project supervision at such a
frequency that would ensure proper execution if project supervision, however, in all cases, he
must devote at least 8 hours per week (for each manager and manager of the execution of a part
of the structure project) per week (unless the parties agree otherwise) and, if reasonably
instructed by the builder (customer), more frequently. The results of site visits and project
24.5. The duties and rights of the manager of the structure project execution supervision and the
manager of the structure project part execution supervision appointed (hired) by the designer are
defined in the fourth section of Chapter VI of STR l . 0 6. 01 :20 1 6. The manager of the structure project
execution supervision and the manager of the structure project part execution supervision shall be
responsible for the performance of duties and the exercise or non-exercise of rights in accordance
24.7. The designer must organize and perform, free of charge, the correction of the observed errors
24.8. During the supervision of the structure project execution, the changes of the structure project
solutions shall be performed in accordance with the procedure established in Chapter VI "Structure
24.9. Changes in the project solutions made during the supervision of the structure project must be
registered in the Construction Works Log. Upon the instruction of the builder (customer), the designer
24. 10. The manager of the structure project execution supervision and the manager of the structure
project part execution supervision, supervising the execution of the structure project (part of the
project) must ensure that in all cases the changes made to the solutions of the structure project (part
of the project) comply with the essential requirements of the structures specified in Regulation (EU)
No. 305/2011, the requirements of the normative construction technical and normative structure
safety and purpose documents. In all cases, such changes must be agreed with the builder (customer)
in writing.
2 4 . 1 1 . The designer must ensure the obligation of the managers of the structure project execution
supervision (according to their competence) to sign the inspection of hidden construction works,
recognition as suitable for use and other construction execution documents, if they comply with the
solutions of the supervised part of the structure project, the requirements of normative constrnction
contractors (subcontractors), coordinate their submitted work project and I or its components,
if they are prepared in accordance with legal requirements and comply with the project
solutions;
b) Provide recommendations and take all necessary actions to ensure the quality of the structure
c) Take all necessary steps to correct errors in the construction and finishing work of the
structure;
( subcontractors) does not follow the designer's recommendations and/or instructions (when the
e) A t the reasoned request of the b uilder (customer), the designer must participate in all
production, coordination, w ork, etc. meetings or consultations, which deal with issues related
f) Carry out all other actions provided for in the applicable legal acts regulating the supervision
of the execution of the structure project, as well as necessary for its proper assurance;
g) Pa rticipate in the structure completion procedures, in the work of the commission for
recognition of the structure as suitable for use, together with the contractor to prepare all the
necessary documentation, which shall be provided for the commission work and the structure
2 4 . 1 3 . The designer undertakes to provide the builder (customer) with project execution supervision
reports:
a) Interim reports shall be drawn up at least every 3 months. They briefly describe the process
of supe rv ision of the structure project execution, recommendations and conclusions on the
compliance of the work with the project solutions, provide comments recorded in the
construction log and/or official notices, complete and provide a table of changes to the solutions
c) The final report shall be submitted before the start of the structure completion procedures of
the information system of the Republic of Lithuania "Infostatyba". This report briefly describes
the process of supervision of the structure project execution, provides recommendations for the
operation of the structure, completes and presents a final table of changes to the design solutions
of the structure project (all components). Together with the construction contractor, the designer
forms and prepares for the uploading to the information system of the Republic of Lithuania
"lnfostatyba" the final editions of the project solution documents of the structure project,
design, project expertise" and LST 1516:2015 "Structure project. General formalization
requirements".
24.14. The end of the supervision of the execution of the structure project is considered to be the day
25. Legislation and other documents establishing specific requirements for the installation of a
structure KAS:
2 5 . 1 . "Regulations on the Storage, Transport and Destruction of Explosive Materials and Explosive
Measures", approved by Order No. 188 of the Minister of National Defense dated 5 March 1993;
25.2. "Requirements for Physical Protection of Warehouses Holding Weapons, Their Parts,
Ammunition and Explosives and Weapons Repair Premises", approved by Order No. V-254 of the
25.3. Guide to NATO Security Principles for the Storage of Military Ammunition and Explosives
AASTP-1, approved by the Director General of Capabilities and Armaments of the Ministry of
25.4. U nited Nations International Ammunition Technical Guidelines, Part 5, Explosives F acilities
25.5. General Requirements for the Physical Security of C lassified Information and M ethodological
R ecommendations for the Assessment of Premises for Recognition as Appropriate for Storage or
H andling of lassified
C Information, approved by Protocol No. of the C oordinating C ommission for
the Protection of S ecrets of the Republic of Lithuania dated 2 F ebruary 2007 (Official Gazette, 2007,
No. 29- 10 8 5) ;
25.7. U nified facilities criteria (UFC) interior and exterior lighting systems and controls"
,. UFC 3-
53 0 -01 ;
2 5 .8. Un fi i ed facilities criteria (UFC) ,, security fences and gates" UFC 4-022-03;
25.9. U nified facilities criteria (UFC) "Structures to Resist the Effects of Accidental E xplosions" US
UFC -3-340-02;
25.10. DDESB Technical P aper 1 5 , Approved Protective C onstruction, Revision 3. U S DDESB. May
2010 ;
R egulation on the Approval of the Regulation on the Organization of the Protection of Military
O bjects" and on 1 3 August 2 0 1 8 by Resolution No. 820" On the Implementation of the La w on S tate
ATTACHED:
2. Annex No. 2. B utigeidis Dragoon B attalion Territory Scheme (Klaipeda, K airi a i) , I page;
3. Annex No. 3. Lithuanian Grand Duke Kestutis Motorized Infantry Battalion Territory
6. Annex No. 6. Lithuanian Army Depot Service Armament Depot Territory Scheme
(Linkaiciai), I page;
8. Annex No. 8. Lithuanian Armed Forces Grand Duke Vytenis General Support Logistics
9. Annex No. 9. Requirements for the installation of a fence, gate and "sterile" area.