MEJORAMIENTO Y MANTENIMIENTO DE LA VIA FONSECA- ALMAPOQUE EN EL MUNCIPIO DE FONSECA, LA GUAJIRA

INTERVENTOR: CONSORCIO CGB GUAJIRA


TRAMO: ALMAPOQUE PERIODO: DEL 19 DICIEMBREE HASTA 18 DE ENERO DEL 2018

ASFALTO
ABSCISADO
Longitud PRIMERA SEGUNDA LADO LADO Espesor (e)
ITEM: FECHA Ancho Volumen m3
DESDE HASTA (L) mts. CAPA CAPA IZQUIERDO DERECHO mts.

ASFALTO 1/3/2018 K7+000 K7+555 555 3.50 X X 0.05 97.13


ASFALTO 1/4/2018 K6+400 K7+000 600 3.50 X X 0.05 105.00
ASFALTO 1/5/2018 K5+900 K6+400 500 3.50 X X X 0.05 87.50
ASFALTO 1/6/2018 K5+500 K5+900 400 3.50 X X X 0.05 70.00
ASFALTO 1/8/2018 K4+900 K5+500 600 3.50 X X X 0.05 105.00
ASFALTO 1/9/2018 K4+300 K4+900 600 3.50 X X 0.05 105.00
ASFALTO 1/10/2018 K3+760 K4+300 540 3.50 X X 0.05 94.50
ASFALTO 1/11/2018 K6+955 K7+555 600 3.50 X X 0.05 105.00
ASFALTO 1/12/2018 K6+355 K6+955 600 3.50 X X 0.05 105.00
ASFALTO 1/13/2018 K5+955 K6+355 400 3.50 X X 0.05 70.00
ASFALTO 1/15/2018 K5+400 K5+955 555 3.50 X X 0.05 97.13
ASFALTO 1/16/2018 K4+860 K5+400 540 3.50 X X 0.05 94.50
ASFALTO 1/17/2018 K4+360 K4+860 500 3.50 X X 0.05 87.50
ASFALTO 1/18/2018 K3+760 K4+360 600 3.50 X X 0.05 105.00
ASFALTO K1+400 K1+540 140 3.50 X 0.05 24.50
ASFALTO K1+010 K1+180 170 3.50 X 0.05 29.75
ASFALTO K1+180 K1+300 120 3.50 X 0.05 21.00
ASFALTO K1+300 K1+430 130 3.50 X 0.05 22.75
ASFALTO K1+430 K1+540 110 3.50 X 0.05 19.25
ASFALTO K1+540 K1+700 160 3.50 X 0.05 28.00
ASFALTO K0+000 K0+280 280 3.00 0.05 42.00
ASFALTO K0+280 K0+440 160 3.00 0.05 24.00
TOTAL ASFALTO 1,539.50