INVESTMENT OPPORTUNITY

IN PALM OIL PLANTATIONS IN


SOUTH KALIMANTAN
OVERVIEW OF COMPANY
COMPANY BACKGROUND

PT Borneo Indo Tani established in 2008.


The business activities of PT. Borneo Indo Tani focus on harvesting fresh fruit bunches
(“FFB”) from palm oil trees, PT. Borneo Indo Tani manages 19,101,14 hectares of Izin
Lokasi, planted of palm oil plantation.
The scope of the company consists of plantation development, trade, and the field of post-
plantation processing, located in Desa Cinta Puri, Martapura, South Kalimantan.
The company plans to construct Palm Oil Mill/ Pabrik Kelapa Sawit (PKS) in capacity of 60
tons/hour, the PKS construction is estimated to be finished in 2018.
The company manages Izin Lokasi of total area of 19.083 ha with in-planted area of 5.923
ha (core and plasma). The total number of workers is +/- 426, consists of both permanent
and out-sourced workers.
Besides developing plantation of palm oil in the core area, this company also partnering in
5 village unions (KUD), including KUD Mas Intan Jaya, KUD Berkat Subur, KUD Bauntung
Betuah, KUD Bina Benua Bersama, and KUD Cinta Puri Darusalam.
MANAGEMENT SYSTEM

The company is partnering with 5 different village unions


(KUD) in order to develop plasma plantation of palm trees
and to promote the villages where the plantations are
located. KUD MAS INTAN KUD BERKAT
Those village unions (KUD) are Entity Under Common JAYA SUBUR

Control with the company


35% of shared-profit to all farmers.

KUD BINA BENUA KUD BAUNTUNG


BERSAMA BATUAH

KUD CINTAPURI
DARUSALAM
AREA OF OPERATION

South Kalimantan
The Plantation has
IZIN LOKASI certificate for 19.101,14 hectares
IZIN USAHA PERKEBUNAN 19.080,14 hectares
HGU 7.743,23 Hectares.
GENERAL LOCATION
PT Borneo Indo Tani plantation located in South Kalimantan, in
Cinta puri Kabupaten Banjar, only 2 hours from Banjarmasin
airport.
COVER OF HGU
MAP OF IZIN LOKASI
MAP OF HGU
IZIN LOKASI & HGU
Izin lokasi
No Date Area (Ha)
32/IL-BP2T/08/2012 02/08/2012 9.586,52 Izin Lokasi 1

52/IL-BP2T/12/2012 10/12/2012 6.294,44 Izin Lokasi 2

63/IL-BKPM2T/11/2014 20/11/2014 1.735,23 Izin Lokasi 3

31/IL-BKPM2T/06/2015 11/06/2015 1.466,95 Izin Lokasi 4

Total Izin Lokasi PT. BIT 19.083,14

HGU
Description No Date Area (Ha)
HGU 1 Certificate No : 011-017 July 2014 3.408,00

HGU 2 963/P-63/XI/2015 12/11/2015 4.334,88

Total HGU 7.742,88


SERTIFIKAT HAK MILIK

Sertifikat Hak Milik

Sertifikat Hak Guna Bangunan

PT. BIT has Sertifikat Hak Guna Bangunan No.0001 NIB


17.02.22.05.3.00001 with area 670,200 M2. This permit use for palm
oil mill.
Performance
Planted palm : 5923Ha
Plasma area : 2423Ha
Mature Hectares (TM) : 1150Ha
Immature Hectares (TBM) : 4850Ha

New plantings are going forward at approximately 2100ha per year.


Control Tower 6 years 5 years
AREAL STATEMENT
PT. BIT base on year of planting
2500

2000

1500
Nucleus + Plasma
1000 (Ha)

500

0
2010 2011 2012 2013 2014 2015 Year of Nucleus Plasma Total
planting (Ha) (Ha)

2010 178 131 309


2011 386 - 386
2012 452 386 838
2013 1164 796 1960
2014 1320 910 2231
Nursery plantation 2015 - 200 200
Total 3500 2423 5923
AREAL STATEMENT
The difference between nucleus and plasma
1400
1200
1000
800 Nucleus (Ha)
600
Plasma (Ha)
400
200
0
2010 2011 2012 2013 2014 2015

Year of Nucleus (Ha) Year of Plasma (Ha)


planting planting
2010 178 2010 131
2011 386 2012 386
2012 452 2013 796
2013 1164 2014 910
2014 1320 2015 200
Total 3500 Total 2423
CONDITION OF PLANTATION

Canal Border road

Hauling road Main road


MAP OF NUCLEUS AND
PLASMA
PRODUCTION
Nucleus
Name Year of Actual to date
planting
2015 Jan-April 2016
TM(Ha) Tonnage Tonnage/ Size of Tonnage Tonnage/
of Ha TM(Ha) of Ha
production production

Estate 2010 178.00 841.94 4.73 178.00 920.66 5.17


Cintapuri
Darusalam 1
2011 386.00 1.501.54 3.89 386.00 1.607.27 4.16

2012 452.00 1.491.60 3.30 452.00 1.446.40 3.20

Total 1.016.00 3.835.08 3.97 1.016.00 3.974.33 4.18

Estate - - - - - - -
Cintapuri
- - - - - - -
Darusalam 2
- - - - - - -
- - - - - - -
Total - - - - - -
PRODUCTION
Plasma
Name Year of Actual to date
planting
2015 Jan-April 2016

Size of Tonnage of Tonnage/ Size of Tonnage of Tonnage/Ha


TM(Ha) production Ha TM(Ha) production

Estate 2010 131 614.75 4.69 131.00 530.84 4.05


Cintapuri
Darusalam 1 2012 386.00 1.443.64 3.74 386.00 1.486.97 3.85

Total 517.00 2.058.39 3.98 517.00 2.017.81 3.95

Estate - - - - - - -
Cintapuri
Darusalam 2 Total - - - - - -
AREA CONDITION
The geographical location of this plantation is well situated, near with jetty and this keeps transport costs low.
Ground level of plantation area is flat, Average total rainfall per year is 2,500 mm well distributed throughout the
year with a short two month dry season.
Terracing has been implemented as a standard policy, leguminous cover crops have been planted and the land is
well drained with no significant drainage problems.
The first company in South Kalimantan to gather plasma plantation with nucleus plantation in one concession.
There is a jetty. There are main roads, collection roads, having bridges where required.
The plantation is divided into blocks for efficient management.
INFRASTRUCTURE AND SUPPORTING FACILITIES

Infrastructure in relation to housing is adequate. There are staff houses,


guesthouse and workers housing. Additionally there is an office,
warehouse, canteen and a mosque.
INFRASTRUCTURE AND SUPPORTING FACILITIES

Canteen Nursery plantation

Mosque Housing and office


INFRASTRUCTURE AND SUPPORTING FACILITIES

Mess for employees

Warehouse
HEAVY EQUIPMENT
Excavator standard 5 unit
Truck 6 unit
Motorcycle 20 unit
Excavator long arm 2 unit
Double cabin car 4 unit
Tractor 1 unit
Pick Up car 5 unit
DRONE RESULTS
Land condition after land clearing
Nursery plantation
PRODUCTION COST
Nucleus
Actual to Date
Name Cost 2015 2016
Rupiah Rp/Kg Rp/Ha Rupiah Rp/kg Rp/Ha
Crops 528.370 .905 138 673.184.256 169
Estate Hauling 134.227.800 35 139.101.401 35
Cintapuri
Fertilization 5.332.447.552 5.248.472 2.079.654.545 2.046.904
Darusalam 1
Maintenance 9.072.880 8.930 3.538.423 3.483

Others 651.310.864 641.054 254.011.237 250.011


Overhead 665.543.000 655.062 314.948.986 309.989
Total 7.320.973.002 173 3.464.438.849 204
Crops - - - -
Hauling - - - -
Estate
Crops and others - - - -
Cintapuri
Darusalam 2 Fertilization - - - -
Maintenance - - - -
Others - - - -
Overhead - - - -
Total - - - -
PRODUCTION COST
Plasma
Actual to Date
Name Cost 2015 2016
Rupiah Rp/Kg Rp/Ha Rupiah Rp/kg Rp/Ha
Crops 283.591.085 138 341.783.472 169
Estate Hauling 72.043.724 35 70.623.398 35
Cintapuri
Fertilization 2.713.460.024 5.248.472 1.058.249.409 2.046.904
Darusalam 1
Maintenance 4.616.810 8.930 1.800.556 3.483
Others 331.424.918 641.054 129.255.718 250.011
Overhead 340.513.656 658.634 160.171.255 309.809
Total 3.745.650.216.37 173 1.761.883.809 204

Crops - - - -
Estate Hauling - - - -
Cintapuri
Crops and - - - -
Darusalam 2
others
Fertilization - - - -
Maintenance - - - -
Others - - - -
Overhead - - - -
Total - - - -