Professional Documents
Culture Documents
SUMMARY PT. BIT PDF - Compressed
SUMMARY PT. BIT PDF - Compressed
KUD CINTAPURI
DARUSALAM
AREA OF OPERATION
South Kalimantan
The Plantation has
IZIN LOKASI certificate for 19.101,14 hectares
IZIN USAHA PERKEBUNAN 19.080,14 hectares
HGU 7.743,23 Hectares.
GENERAL LOCATION
PT Borneo Indo Tani plantation located in South Kalimantan, in
Cinta puri Kabupaten Banjar, only 2 hours from Banjarmasin
airport.
COVER OF HGU
MAP OF IZIN LOKASI
MAP OF HGU
IZIN LOKASI & HGU
Izin lokasi
No Date Area (Ha)
32/IL-BP2T/08/2012 02/08/2012 9.586,52 Izin Lokasi 1
HGU
Description No Date Area (Ha)
HGU 1 Certificate No : 011-017 July 2014 3.408,00
2000
1500
Nucleus + Plasma
1000 (Ha)
500
0
2010 2011 2012 2013 2014 2015 Year of Nucleus Plasma Total
planting (Ha) (Ha)
Estate - - - - - - -
Cintapuri
- - - - - - -
Darusalam 2
- - - - - - -
- - - - - - -
Total - - - - - -
PRODUCTION
Plasma
Name Year of Actual to date
planting
2015 Jan-April 2016
Estate - - - - - - -
Cintapuri
Darusalam 2 Total - - - - - -
AREA CONDITION
The geographical location of this plantation is well situated, near with jetty and this keeps transport costs low.
Ground level of plantation area is flat, Average total rainfall per year is 2,500 mm well distributed throughout the
year with a short two month dry season.
Terracing has been implemented as a standard policy, leguminous cover crops have been planted and the land is
well drained with no significant drainage problems.
The first company in South Kalimantan to gather plasma plantation with nucleus plantation in one concession.
There is a jetty. There are main roads, collection roads, having bridges where required.
The plantation is divided into blocks for efficient management.
INFRASTRUCTURE AND SUPPORTING FACILITIES
Warehouse
HEAVY EQUIPMENT
Excavator standard 5 unit
Truck 6 unit
Motorcycle 20 unit
Excavator long arm 2 unit
Double cabin car 4 unit
Tractor 1 unit
Pick Up car 5 unit
DRONE RESULTS
Land condition after land clearing
Nursery plantation
PRODUCTION COST
Nucleus
Actual to Date
Name Cost 2015 2016
Rupiah Rp/Kg Rp/Ha Rupiah Rp/kg Rp/Ha
Crops 528.370 .905 138 673.184.256 169
Estate Hauling 134.227.800 35 139.101.401 35
Cintapuri
Fertilization 5.332.447.552 5.248.472 2.079.654.545 2.046.904
Darusalam 1
Maintenance 9.072.880 8.930 3.538.423 3.483
Crops - - - -
Estate Hauling - - - -
Cintapuri
Crops and - - - -
Darusalam 2
others
Fertilization - - - -
Maintenance - - - -
Others - - - -
Overhead - - - -
Total - - - -