BELT CONVEYOR (BC-02)

Fungsi : Mengangkut kristal aluminium sulfat dari Rotary Dryer ke dalam bin produk
sebanyak 12626.2094 kg/jam
Kode : BC-02
Jenis : Idler pulley 20o
Perhitungan:
Kapasitas = 12626.2094 kg/jam
Kapasitas belt yang ditetapkan = 12626.2094 kg/jam
Spesifikasi belt conveyor
Lebar = 28 in
Slope = 20o
Kecepatan belt=200 fpm
Tinggi belt conveyor = 3 m = 9.842 ft

H L

X = H / tan 20o
Tan 20o = 0,3639
X = 8,2440 m
L = (X2 + H2)0,5
= 8,7728 m
Maka panjang belt conveyor = 8,7728 m
Menghitung Power (G.G. Brown hal 57)
 Untuk belt kosong
Hp1 = (F*(L+Lo) * (0,03 Ws)) /990
 Untuk belt isi (tidak termasuk belt)
Hp2 = (F*(L+Lo) * T) /990
 Untuk belt dengan sudut kemiringan
Hp3 = (T* ΔZ)/990
C1
Dimana:
F = factor friksi untuk plan bearing = 0,1
L = panjang conveyor outer pulley = 28,7821 ft
Lo = untuk plain bearing = 100
S = kecepatan belt = 200 fpm
T = kapasitas belt = 27.6076 ton/jam
ΔZ = kenaikan elevasi material = 8,7728 m
W = massa yang bergerak (lb)/jarak normal pulley (ft)
Waktu tempuh antar pulley
T =L/S
= 0,1439 menit
Tabel 16 Brown
Berat belt conveyor = 2 lb/(in lebar belt, ft panjang belt)
Berat idler = 1 lb/(in lebar belt, ft panjang belt)
W = (2+1 lb / (in) (ft) x 14
= 42 lb/ft
Besarnya power
Hp1 = 1,4558 Hp
Hp2 = 0,1595 Hp
Hp3 = 0,1223 Hp
Total power = 1.7376 Hp
Efisiensi motor = 50%
Power motor = 3.4752
Dipakai motor standar = 3 Hp

C2
2. BIN ALUMINIUM SULFAT (B-03)

Fungsi : untuk menyimpan produk aluminium sulfat untuk 7 hari produksi.


Jenis : tangki silinder tegak dengan bagian bawah berbentuk cone 60o
Tekanan (P) : 1 atm
Suhu (T) : 30oC

Neraca Massa

Komponen Masuk Keluar ρ (kg/l) V (l/jam)


(kg/jam) (kg/jam)
Al2(SO4)3 12626.2094 12626.2094 2,670 4728.9174

ρ slurry = 2,67 kg/L


Volume bahan = 4728.9174 L/jam
= 4728.9174 L/jam x 24 jam/hari x 7 hari
= 794458.1186 L/7 hari
Over design = 20%
volume perancangan = 953349.7423 + (20/100 x 953349.7423)
= 476674,8718 L/7 hari
= 953.3497 m3/7 hari
Menentukan diameter (D) dan tinggi (H) bin
Asumsi = H = 1.5 D
Volume head = πD3/24 tan 30o
Volume silinder = ¼ πD2 H
= ¼ πD2 (3/2 D)
=3/8 πD3
Volume bin = volume silinder + volume head
= 3/8 πD3 + πD3/24 tan 30o
953.3497 = 1.1775 D3 + 0.2266 D3
953.3497 = 1.4041 D3
D3 = 678.9757

C3
D = 8.7892 m = 28.8357 ft = 274.6299213 in
H = 13.1839 m = 43.2536 ft = 411.9488189 in
Menentukan tebal shell
P operasi = 14,7 Psi
P design = 1,2 x P operasi = 17,64 Psi
Bahan = carbon steel
Tebal shell = [(P x ri) / (fE – 0,6 Pi)] +C
Keterangan:
P = tekanan design = 17,64 psi
E = efisiensi welded joint = 0,8 (table 13.2 Brownell)
f = tegangan maksimum yang diijinkan = 12650 Psi
ri = jari-jari bin = 137,3150 in
C = 0,125
Jadi:
Tebal shell = [(17.64 x 137,3150)/(12650 x 0.8 – 0.6x17,64)] + 0.125
= 0.3646 in
Dipilih tebal shell standar = 0.3750 in
Menentukan tebal head
Tebal head = {[ PD ] / [ 2 cos Ɵ (f E – 0,8 P )]} + C
Keterangan :
P : tekanan reactor = 14,7 Psi
E : efisiensi welded joint = 0,8 (table 13.2 Brownell)
f : tegangan maksimum yang diijinkan = 12650 Psi
D : diameter bin = 274,6299 in
Jadi:
Tebal head = {[14,7 x 274,6299] / [ 2 cos Ɵ (12650 x 0,8 – 0,8 x 14,7 )]} + 0,125
= 0.3556 in
Dipilih tebal head standar = 0,3750 in

Menentukan tinggi bin


Tinggi bin = tinggi silinder + tinggi bottom
Tinggi bottom (hb) = b + sf + th
Dimana b = (1/2 D) / tan Ɵ
C4
b = (1/2 x 274,6299) / tan Ɵ
b = 237,8365 in
= 6,041 m
Dari Brownell table 5.6 hal 88, untuk tebal head 0,3750 sf= 1,5 – 3 diambil 1,5
Jadi tinggi bottom = 6,041 + 1,5 + 0,009525
tinggi bottom = 7.550525 m
Jadi :
Tinggi bin = 13,1839 + 7,5505
= 20.7344 m