Professional Documents
Culture Documents
These hotels are generally more stylish and comfortable than one and two-star hotels, and
they offer a wider range of services and amenities: a fitness center, a pool, business services,
an on-site restaurant, room service, conference rooms, and valet services
These hotels don't offer extra amenities or special services. In other words, you're
not going to get a nightly turndown service with a Godiva chocolate on your pillow
here. However, you should have access to nearby public transportation and
reasonably priced meals and entertainment.
The hotel rooms are larger with higher-quality, contemporary furnishings and often
include fancy extras like flat-screen TVs with extended cable. Three-star hotels are
located near a major expressway and local attractions, and they are often geared
toward business travelers.
Roughly estimated the implementation period will take about 15 months from the first actual
negotiations with investors to the start of commercial production. As an industrial site in Broadhurst will
be levelled and fully serviced by electricity, water and infrastructure any difficulties which might cause
delays are not expected.
The implementation time schedule is shown in the following bar diagram. As this feasibility study has
ben excuted on the basis of tenders from different equipment suppliers any major deviation from the
selected technology is not taken into consideration. Practically taken same technology for nail
production has been suggested by all nail machine suppliers. Even the performance characteristics of
machines differ very little from each other as can be seen from Tables 2-4 in Chapter 6. The same applies
to the machines for chain link fence net (Table 4 in Chapter 6).Thus the final selection can be made
without long delay and inquiries can be sent to equipment manufacturers in a very short time. Final
discussions could take place within 2 1/2 months' time and the necessary equipment could be ordered.
The same timing appears to be relevant for civil engineering works as there are no special problems
about technology. The final discussions with building contractors and acceptance of bids can take place
at the same time as the machinery is ordered. Final drawings can be delivered about a month later. Of
the estimated implementation period the first phase of 3-4 months has been devoted to finance and
sales negotiations (especially with wholesalers) in onier to meet a ready market at tre start of the
production.
It is assumed that the promoters will not have any technical experience about this kind of manufacture.
The employment of a managerial technical expert is essential in order to select suitable equipment for
the plant and also to cooperate with the architect and authorities about the factory building and the
plant. For the employment of the managerial technical expert totally 15.000 birr has been allowed
(schedule 9), including a stay of about 2 1/2 months on the spot at the start of the implementation and
an additional 1 1/2 months' supervision period at the start of production. The provision also includes
two trips between home country and Botswana. This allowance may increase by unexpected delays in
implementation.
For training of manpower an expatriate technician has to be engaged for a period of at least three
months. For this training period a11d for one trip between home country and Botswana totally 9.000
Pula '..as been allowed. The local architect's fees are es~1mated to 3.000 Pula. The costs for supervision
of t~e construction work are supposed to be included in the costs of the building.
The manager and the secretary should be employed about three months before the start-up. The local
technician has to participate in the implementation at the end of the construction period and at the
erection. Erection and test-run will be supervised by the staff of the machine suppliers. The costs are
included in the machine erection costs in schedule 6-2. Training period is dependent on the skill of the
employed staff. Training period may be far longer than estimated and thus increase training costs.
The suggested implementation progratm:lE. is shown in the attached bar chart and is tabulated below:
Months Action
Attract (investors) promoters.\ Negotiate
sources of finance.
Negc:tiah· government concessions.
Contact distribution channels.
Register compar.y.
Employ managerial technical consultant
giving 2id at final dibcussions with officials and
whnlesalers, ~reparing machinery specifications,
sp~cifi~ations for archit~ct~
specifications for raw-material, giving aid in
acquisition of plot. Final discussion about
technical equipment.
Receive raw-material
Employ manpower.
Prepare for start-up.
A. Personnel
Designation No Salary/month Total Salary/
month
General manger 1 5,000 5,000.00
p.32
ANNEXED 4
The capacity suggested in this report, at 75% capacity is milling 27 tons of wheat per day The
plant will operate 2 shifts of 8 hours a day and for 25 days in a month. Over all total milling
capacity is about 675 .00 tons of wheat per month.
Particular Qty per tone Cost per tones T/ Cost per Month
7,863,750.
Wheat 675.00 11,650.00 00
pp bags 506.25 120.00 60,750.
00
6,581.
sewing thread 506.25 13.00 00
Transportation Lump sum 30,000.00
7,961,081.00
Total
Particular COST
Oil & Lubricants 167.00
Repair & maintains 20,500.00
Lab. & Cleaning 417.00
21,084.00
Particular COST
Insurance 1,250.00
Promotion 1,667.00
p.33 2,917.00
F. Others Expenses