Professional Documents
Culture Documents
Dokumen - Tips - Unique Design Concrete Preheater Tower Ppccoza Coal Mill Building Clinker
Dokumen - Tips - Unique Design Concrete Preheater Tower Ppccoza Coal Mill Building Clinker
268oC
3 Air 2.5m diameter
3
Pre-Heater
H2
4
Pre-Heater
H3
5
Pre-Heater
H4
6
Pre-Heater
H5
7
Pre-Heater
H6
8
Pre-Heater
H7
9
Pre-Heater
H8
10
Pre-Heater
H9
11
Pre-Heater
H9
12
1200 Metres of Piling Installed
March 2007 13
Constructed Using 80 ton Slide Platform
14
15
Around the Clock Construction
16
17
18
19
Preheater Topped-Out After 58 Days
May 2007 20
Preheater Structure Dominates the Skyline
21
Mechanical Installation Began Immediately
June 2007 22
Structural Steel Floor H3
26
Kiln 2 Cooler ESP
Kiln 2 LT Substation
New Clinker
Return System
Burners Platform
Clinker Cooler
Kiln Pier 1
August 200727
Riding Ring Hoisted into Position
28
August 2007 29
30
31
32
33
34
35
Raw Mill Building: Sept 2007 36
‘Kopanelang’ Contractors Village
Feb 2006 37
Contractors Camp Catering Facilities
38
28 New Staff Houses Built
Existing Village
New Houses
Nov 2006 39
2 Lost Time Injuries Recorded to Date
Morethan
More than22million
millionman
man
hoursworked
hours workedtotodate
date 40
Focus on Local Community Involvement
Excellentlabour
Excellent labourrelations
relationsbetween
betweencontractors
contractors&&local
localcommunity
communityemployees
employees
41
Batsweledi in the Community
Opening of Holfontein
Pension Payout &
Recruitment Centre
(June 2006)
Jupiter Clinker Milling Facility Upgraded
43
Upgrade Programme at Jupiter
44
Clinker Storage Facility Enclosed
45
Dust Collectors Upgraded
Forongoing
For ongoingproject
projectupdate
updaterefer
referPPC
PPCwebsite:
website:www.ppccement.co.za
www.ppccement.co.za
48
Thank You