You are on page 1of 1

DAFTAR KUANTITAS DAN HARGA

PEKERJAAN : “PEKERJAAN PEMBUATAN TALUD/DINDING PENAHAN"


LOKASI : MANADO
TA. : 2021

HARGA SATUAN HARGA SATUAN


NO URAIAN PEKERJAAN VOLUME SATUAN
(Rp) (Rp)

I. PEKERJAAN PERSIAPAN 11,750,000.00


1 Mobilisasi 1.00 Ls 4,000,000.00 4,000,000.00
2 Biaya Sewa Alat 3.00 Hari 2,250,000.00 6,750,000.00
3 Biaya Pembongkaran 1.00 Ls 1,000,000.00 1,000,000.00

II. PEKERJAAN GALIAN DAN PASANGAN 26,270,301.57


1 Galian Tanah 12.000 m3 115,225.00 1,382,700.00
2 Timbunan kembali 126.870 m3 38,005.00 4,821,694.35
3 Pek. Pengangkutan Tanah jarak 50 meter 126.870 m3 65,708.50 8,336,437.40
4 Pemasangan 1 m2 paving block 42.290 m2 277,358.00 11,729,469.82

III. PEKERJAAN BETON 86,557,604.93


1 Pas. Batu Kosong 3.600 m3 584,792.00 2,105,251.20
2 Pasangan Batu kali 28.800 m3 1,093,624.00 31,496,371.20
3 Pondasi Telapak 3.600 m3 6,800,980.00 24,483,528.00
4 Kolom Beton 30 x 30 cm 0.97 m3 8,057,781.00 7,832,163.13
5 Sloof 25 x 30 cm 0.90 m3 6,988,986.00 6,290,087.40
6 Pek. Plesteran Siar 24.00 m2 86,823.00 2,083,752.00
7 Pek. Pasangan Dinding 20.40 m2 163,644.00 3,338,337.60
8 Pek. Kolom Praktis 6.80 m 136,514.00 928,295.20
9 Pek. Plesteran 40.80 m2 88,622.00 3,615,777.60
10 Pek. Acian 40.80 m2 54,611.00 2,228,128.80
11 Pek. Pengecetan 40.80 m2 52,841.00 2,155,912.80

IV. PEKERJAAN SEPTIC TANK 5,111,969.39


1 Galian tanah 4.14 m³ 115,225.00 477,031.50
2 Pas. Batu Kosong 0.20 m³ 584,792.00 116,958.40
3 Urugan Pasir 0.12 m³ 370,936.00 42,657.64
4 Lantai kerja 0.23 m³ 1,125,555.00 258,877.65
5 Pek. Pasangan Dinding 9.80 m² 163,644.00 1,603,711.20
6 Plasteran Dinding Sp 1 : 3 9.80 m² 88,622.00 868,495.60
7 Plat beton penutup 0.23 m³ 6,800,980.00 1,564,225.40
8 Pipa PVC AW 4" 1.20 m' 150,010.00 180,012.00

JUMLAH 129,689,875.89
142,658,863
Tomohon , 7 Januari 2021

PT. KARMEL JAYA