Professional Documents
Culture Documents
www.siemens.com/energy/controls
Reprint
POWER Magazine
Vol. 156/ No. 5 / May 2012
Author
Dr. Robert Peltier, PE, POWER Magazine Editor-in-Chief
www.siemens.com/energy/controls
L
akeland Electric, the public power 1. Three technologies. The 982-MW 2. New lease on life. With low gas
arm of the City of Lakeland, Fla., C.D. McIntosh, Jr. Power Plant consists of prices, the combined cycle unit has assumed
since 1904, serves 100,000 custom- coal-fired Unit 3 (right), the gas- and oil-fired baseload responsibilities from the coal-fired
ers in a 255-square-mile area surrounding Units 1 and 2, a 365-MW combined cycle units. To the right of the concrete stack is the
the central Florida city, located between plant (left), and (not visible) 20 2.5-MW EMD heat recovery steam generator (HRSG) with
diesel engines used for emergency peaking. selective catalytic reduction and ammonia
Orlando and Tampa. Low-cost electric- Courtesy: Lakeland Electric injection. At a right angle to the HRSG and
ity is the name of the game for Lakeland. W501G combustion turbine is the bypass
The utility features the lowest rates for stack. The 125-MW steam turbine is located
small and big businesses in Florida and in the building in the background. Courtesy:
has the third-lowest residential rates in Lakeland Electric
the state.
Lakeland relies on two power genera-
tion complexes for most of its electricity:
the 130-MW Larsen Power Plant and the
982-MW C.D. McIntosh, Jr. Power Plant
(MPP). Both plant sites are located on
Lake Parker in Polk County.
Lakeland is a member of the Florida 365-MW coal-fired conventional steam
Municipal Power Pool (MPP), along plant that burns blends of Central Ap-
with Orlando Utilities Commission and palachian and Illinois Basin coals; it has heat recovery boiler to cool the ceramic
the Florida Municipal Power Agency’s also burned small amounts of refuse-de- barrier coated transitions at the exit of
All-Requirements Project. The MPP is rived fuel mixed with coal in past years. each combustor. A temporary package
not a capacity pool but an energy pool The unit, 40% owned by the Orlando boiler supplied steam for the turbine’s
that centrally commits and dispatches all Utilities Commission, was one of the steam needs during initial simple cycle
the pool members’ generating resources first scrubbed, zero-discharge coal units operation (Figure 2).
in the most economical manner to meet in the nation when it entered service on The conversion from simple cycle
the pool’s total load requirements. How- September 1, 1982. Gas- and oil-fired to combined cycle began in Septem-
ever, each member of the MPP remains Units 1 (90 MW) and 2 (110 MW) were ber 2001 with the addition of the waste
responsible for planning and serving the commissioned in February 1971 and heat boiler and a 120-MW steam tur-
electricity needs of its service territory June 1976, respectively (Figure 1). bine. Construction was completed in the
and for maintaining system reserves suf- Advanced combined cycle technology spring of 2002 with the fully operational
ficient to meet the Florida Reliability Co- is also used at the MPP. In 1999, con- combined cycle plant declared commer-
ordinating Council reserve requirements. struction of the simple cycle combustion cial in May 2002. To meet emerging air
turbine (CT) portion of Unit 5 began, and emissions rules, during 2009, Lakeland
Technology Trifecta the unit was released for commercial op- Electric installed an ammonia injection
MPP features three different power gen- eration in May 2001. You may recall that system and selective catalytic reduction
eration technologies. Unit 3 is a nominal the 501G uses 1,050F steam from the on Unit 3. The rating of the completed
|
May 2012 POWER
quently expanded when the steam bot- the already scheduled October/Novem-
3. Operator interface upgraded. The
DCS upgrade used the graphic designs from toming plant was added in 2002. ber 2010 Unit 5 outage.
the earlier system to accelerate operators’ By the time Unit 5 was built, the The DCS replacement strategy took
familiarity with the new system. Suggestions WDPF system, first released in the mid- two paths: upgrade the software and
from the staff, based on almost a decade of 1980s and updated to WDPF-II in the minimize the hardware changes required.
operation, were also used in the upgraded
mid 1990s, was a mature product that The software upgrades began by ensur-
DCS design. Source: Lakeland Electric
was rapidly approaching obsolescence. ing that the entire list of Siemens turbine
Replacing cards that were no longer technical advisories and function logic
manufactured was problematic, and the software upgrades were installed with
cost of parts when available was quickly the new DCS. For example, the new DCS
rising. Just as significant, some of the includes 2-out-of-3 logic improvements
processors were operating at maximum for the CT speed signals that were not
capacity. By 2010, WDPF was in need of available with the old DCS.
immediate replacement. The operating The Siemens engineers began the soft-
reliability of the entire plant now hinged ware upgrade by using the latest refer-
on the performance of a 25-year-old con- ence functional software release for the
trol system. W501G and the steam turbine governor
control. Next, a one-to-one logic conver-
combined cycle plant is 346 MW sum- Project Gets Commission sion was completed based on the actual
mer and 365 MW winter. Approval balance-of-plant equipment and steam
The third power generation technol- Approval was received from the City turbine auxiliary systems managed by
ogy used at MPP is the diesel-fueled Commission in early 2010 to replace the the old WDPF software. To ease the
peaker engine. Lakeland Electric uses obsolete Unit 5 control system with a hardware transition in the field, the con-
20 remotely operated EMD 20-cylinder modern DCS. Siemens, the CT original trols engineers reused the existing tag-
reciprocating engines driving 2.5-MW equipment manufacturer, was the natural ging system for all hardwired input and
generators during system emergencies. choice, given its intimate knowledge of output (I/O) signals and those signals
MPP Unit 5 features the first Siemens the W501G and its integrated plant op- transferred to the existing PI plant histo-
Power Generation W501G combustion erating requirements and strategies. The rian.
turbine (CT) installed in the U.S. Today, Siemens SPPA-T3000 is also the only Unlike the software upgrades that are
the fleet totals 24 units. When purchased, control system that has been retrofitted invisible to the operator, the monitor
the W501G was configured with a West- to an existing W501G. With City Com- screen graphics used by the technicians
inghouse Distributed Processor Fam- mission approval in hand, plans were to operate the plant are personalized to
ily (WDPF) distributed control system quickly made for Siemens engineers and meet the plant’s unique needs. Siemens
(DCS). The WDPF system was subse- technicians to install the new DCS during duplicated the dozens of existing graphi-
cal screens of the human-machine in-
4. DCS overview. The DCS upgrade can be visualized as consisting of three layers. The terface so well that it took a sharp eye
field terminal cabinets retained their original WDPF card-edge connectors and field device wir- to recognize the differences. Many ad-
ing. A central application/automation server was added that communicates with the HMI user ditional graphic monitoring and alarm
interfaces in the control room via redundant Ethernet cables. Thin client workstations connect screens on 24-inch monitors were added
to the server using a web interface. Courtesy: Siemens Power Generation
once the operators became familiar with
the significantly increased capabilities of
the T3000 DCS (Figure 3).
Field hardware upgrades began with
Siemens technicians removing all the
old cards and then stripping the remain-
ing equipment from the cabinets, with
the exception of the original card-edge
connectors and card-edge connector wir-
ing. The hardware upgrades were config-
ured such that the new processors, I/O,
and other PROFIBUS modules could
be used in conjunction with the original
card-edge connectors to minimize wiring
changes from the field instrumentation to
the cabinets. The new I/O modules were
tied to the original field wiring by plug-
ging the existing card-edge connectors
onto a Siemens-designed interface card.
INSTRUMENTATION & CONTROL
|
May 2012 POWER
INSTRUMENTATION & CONTROL
plant control and monitoring, although generator, rather than cycling offline
5. Quick cabinet retrofit. The existing access can be determined by role. SP- every three days or so, as in past years.
field termination cabinets were stripped and PA-T3000 applications are hosted by a A new low-load turndown capability
restocked with new control hardware, signifi-
fault-tolerant application server with a was also added during the DCS retrofit.
cantly reducing the time required for the retro-
fit. Electrical & Controls Engineer Scott Fowler dual-redundant architecture that elimi- The combined cycle plant, originally
noted that a new optical cable was run across nates single points of failure and safe- able to operate within emissions limits
the plant to link all the remote cabinets togeth- guards data integrity (Figure 4). down to 50% of CT baseload, now has
er with the control room. Source: POWER With the field wiring updated and the capability to operate down to 30%.
new DCS cards and components in Unit 3 (the coal-fired unit) is able to
place, Siemens personnel efficiently cycle down at night to about 50% load.
made the hardware conversions and Together, the wide operating range of
performed I/O andloop checks on the both units provides Lakeland Electric
combustion and steam turbine trip and considerable operating flexibility when
protection systems. The subsequent meeting its MPP commitments.
plant startup of the completed DCS was During the summer of 2011, Unit
completed without incident (Figure 5). 5 operated continuously for 122 days
However, the team had to overcome a until it was knocked off-line by a light-
number of challenges to complete the ning strike that damaged the voltage
project on time (see sidebar). regulator, air emission monitor, and
Also completed during the “double other equipment. After a one-week
major” outage of the combustion and outage for repairs, the combined cycle
steam turbines was a major inspection plant resumed baseload operation. As
of the W501G gas generator (at 47,468 of mid-April, the 2012 YTD equivalent
hours) so the heavy mechanical portion availability factor was 82.7%, which in-
of the outage was the outage critical cludes a combustor inspection outage,
path. However, as the mechanical work and the equivalent forced outage rate
reached about the 80% completion was only 1.43%.
point, the critical path predictably shift- The plant heat rate is much improved
A subcontractor simultaneously ran ed to the controls upgrade work, forcing with the installation of a new CT turbine
the new cabling between cabinets and the controls team to work around the rotor and DCS in 2011. During and prior
the control room and all the (thin client) clock for several days to maintain the to 2010, the plant heat rate was approxi-
HMI control stations. A web browser aggressive outage schedule. mately 7,000 Btu/kWh. The plant heat
installed on each thin client provides rate today is about 6,740 Btu/kWh. The
the user interface hosted by the DCS Highly Anticipated Results 2011 gross average heat rate was 6,606
Application Server. Each management, One year after the DCS upgrades were Btu/kWh. ■
maintenance, operation, or engineer- completed, Unit 5 is now operating —Dr. Robert Peltier, PE is POWER’s
ing station has a view of all aspects of baseload as the utility’s lowest cost editor-in-chief.
Posted with permission from May 2012. POWER, Access Intelligence. Copyright 2012. All rights reserved.
For more information on the use of this content, contact Wright’s Media at 877-652-5295 91354
All rights reserved.
Trademarks mentioned in this
document are the property of Siemens
AG, its affiliates, or their respective
owners.
www.siemens.com/energy/controls