30-Jan-20

1. ADOBE BLOCK WORK


2 7.30 m Length
Adobe block work for second
0.40 m Width classroom (door area is
2.30 m Depth deducted)
2.84 m2 Opening Opening
10.60 m3 Volume m³
2 7.30 m Length
Adobe block work above the
0.40 m Width window and blow the roof work
2.30 m Depth
13.43 m3 Volume m³
2 3.65 m Length
GABLE WALL which is above
0.40 m Width the top tie beam
1.50 m Depth
4.38 m3 Volume m³
4 7.80 m Length
On left and right side of above
0.20 m Width the top tie beam
0.65 m Depth
4.06 m3 Volume m³
CARRIED TO BILL OF QUANTITY  32.47 m3 Volume m³
2. HCB BLOCK WORK (for Toilet Building)
8 2.10 m Length
10cm thick HCB block work for
2.24 m Height
2
Toilet Internal partition
37.63 m3 Volume m
2 2.30 m Height HCB block work for Toilet
0.82 m Length Building @ Disable toilet from
2
3.77 m3 Volume m verandah side
CARRIED TO BILL OF QUANTITY 
2
41.40 m3 Volume m
2 4.00 m Length
20 cm thick HCB block work for
2.20 m Height Toilet front and rear wall
2
17.60 m3 Volume m
1 2.70 m Height
20 HCB block work for Toilet
5.54 m Length Bilding @ Longer Axis
2
14.96 m3 Volume m
CARRIED TO BILL OF QUANTITY  32.56 m3 Volume m
2

3. PLASTERING WORK (for Toilet Building)

16 2.10 m Length
10cm thick HCB block work for
2.24 m Height toilet Internal partition
2
75.26 m3 Volume m
4 2.30 m Height
0.80 m Length
2
7.36 m3 Volume m
CARRIED TO BILL OF QUANTITY 
2
82.62 m3 Volume m
2 5.14 m Length 20 cm thick HCB block work for
2.70 m Height Toilet Internal partition @
27.76 m3 Volume m
2 Longer Axis
4 2.55 m Height
20 HCB block work for Toilet
4.37 m Length
2 building
44.57 m3 Volume m
2
CARRIED TO BILL OF QUANTITY  72.33 m3 Volume m
6 2.24 m Height
HCB block work for Toilet
0.16 m Length
2
building
2.15 m3 Volume m
6 3.10 m Height
0.29 m Length for columen
2
5.39 m3 Volume m
6 0.48 m Height
0.58 m Length for columen above the wall
2
1.67 m3 Volume m
2 0.82 m Height
for beam @ Longer Axis
5.54 m Length
2 building
9.09 m3 Volume m
3 0.82 m Height
4.37 m Length for beam @ Short Axis building
2
10.75 m3 Volume m
CARRIED TO BILL OF QUANTITY 
2
29.05 m2 Area m
2
184.00 m2 Area m
4. EDGE PLASTERING WORK (for Toilet Building)
16 2.24 m Length 10cm thick HCB Wall for toilet
partition
35.84 m Length ml
14 3.10 m Length
for the column

Report for chamo school class room and toilet JAN 30.xlsx
for the column

43.40 m Length ml
8 0.48 m Length
For the column above the wall

3.84 m Length ml
4 5.54 m Length
Long TT beam

22.16 m Length ml
8 4.37 m Length
Short TT beam

34.96 m Length ml
4 3.60 m Length wall @ inside front and rear
opening
14.40 m Length ml
CARRIED TO BILL OF QUANTITY  150.76 m Length ml
4 3.60 m Length Copping @ front and rear
opening
14.40 m Length ml
5. Door Production (for Toilet Building)
10

CARRIED TO BILL OF QUANTITY  10. pcs


6. Roof Cover Work (for Toilet Building)
2 3.90 m Length
7.90 m Width
2
CARRIED TO BILL OF QUANTITY  61.62 m3 Volume m
7. Truss (for Toilet Building)
5 7.900 m Length

CARRIED TO BILL OF QUANTITY  39.500 m Length Pcs


8. Rafter (for Toilet Building)
10 7.800 m Length

CARRIED TO BILL OF QUANTITY  78.000 m Length Pcs

9. Purlin (for Toilet Building)


10
7.900 m Length
CARRIED TO BILL OF QUANTITY  79. pcs Pcs
10. Ridge Cover (for Toilet Building)
1 7.90 m Length

CARRIED TO BILL OF QUANTITY  7.900 m Length ml

CLASS ROOM BLOCK


11. Plastering for (class rooms)
4 7.75 m Length
TT beam above the window as we know the
beam is 50x20cm so the area that cover by
1:3 ratio is (0.65+0.2+0.2+(0.1+0.1) is the
top beam section
1.25 m Width
38.75 m2 Area m³ TT beam
24 2.80 m Length as we know the column is 70x25cm
1.85 m Width so the area that cover by 1:3 ratio is
(0.7+0.25+0.7+0.25)
124.32 m2 Area m³
163.07 m2 Area m² TOTAL AREA OF PLASTERING

12. EDGE PLASTERING WORK (class rooms)


24 11.20 m Length 2.8 is the length of column it copping is
268.80 m Length ml done on its side =2.8*4=11.20

8 7.75 m Length 7.75 is the length of the beam its copping


62.00 m Length ml is done with its 4 side =7.75*4=31
7.75-(0.25*6) is the length of the
8 6.25 m Length beam its copping is done with its 4
50.00 m Length ml side =7.75*4=33

380.80 m2 Area ml TOTAL Length OF PLASTERING

DESCRIPTION QUNTITY UNIT RATE AMOUNT Deducted material cost in ETB


1. ADOBE BLOCK WORK

Report for chamo school class room and toilet JAN 30.xlsx
400mm*200mm*150mm thick adobe
3
1 bloock beded and jointed with mud 32.47 m3 Volume m 1,227.19 39,840.72 No material cost to Deduct
morter english bond pattern

2. HCB BLOCK WORK (for Toilet Building)


2.1 20cm thick class H.C.B wall bedded and
jointed with cement 2
41.40 m2 Area m 220.00 9,108.88
mortar 1:3. with English bond pattern ETB 502.70
2.2 10cm thick class H.C.B wall bedded and
2
jointed with cement 32.56 m2 Area m 205.00 6,674.39
mortar 1:3. with English bond pattern ETB 417.30

3. PLASTERING WORK (for Toilet Building)


3.1 Plaster with cement mortar 1:3 184.00 m2 Area m
2
95.00 17,480.44

4. EDGE PLASTERING WORK (for Toilet Building)


4 Plaster with cement mortar 1:3 150.76 m Length ml 35.00 5,276.60 No material cost to Deduct

5. Door Production (for Toilet Building)


LTZ metal sheet door making and
5 No material cost to Deduct
installation for toilet building 10. pcs PCS 2850.00 28,500.00
6. Roof Cover Work (for Toilet Building)
2
6 28G CIS roof Cover 61.62 m2 Area m 59.50 3,666.39 Only labor cost of roof cover

7. Truss (for Toilet Building)


7 Eucalyptus 39.500 m Length ml 546.00 21,567.00 No material cost to Deduct

8. Rafter (for Toilet Building)


8 Eucalyptus Rafter 78.000 m Length ml 58.00 4,524.00 No material cost to Deduct

9. Purlin (for Toilet Building)


9 Zigeba batten pulin 79. pcs ml 150.00 11,850.00 No material cost to Deduct

10. Ridge Cover (for Toilet Building)


10 28G Sheet Roof for 7.900 m Length ml 120.00 948.00 No material cost to Deduct

11. Plastering for (class rooms)


2
11 28G Sheet Roof for 163.07 m2 Area m 95.00 15,491.65

12. EDGE PLASTERING WORK (class rooms)


12 28G Sheet Roof for 380.800 m Length ml 30.00 11,424.00 No material cost to Deduct

13. Window Sill Precast molding and placement


Window Sill Precast molding and
13
placement 40. pcs PCS 750.00 30,000.00

14. Toilet sink and installation


13 Toilet sink and installation 10. pcs PCS 830.00 8,300.00

15. Door for Classroom


13 Door for Classroom Frame 4. pcs PCS 1200.00 4,800.00

Total Amount ETB 219,452.07 ETB 920.00


Total Deducted Amount ETB 218,532.07

250pcs 35 gauge of roof cover of Omotic changed to 47,500 birr and we bought 38pcs CIS with 15,960 ETB. The
remaining 31,540 ETB plus 80,000. ETB advance payment will be deduct from this payment.
ETB 106,992.07
VAT 15% ETB 16,048.81
GRAND TOTAL AMOUNT (ETB) ETB 123,040.88

Report for chamo school class room and toilet JAN 30.xlsx