fin Innovasi
IMN Mitra
/Nusantara
| (QHSE Form Title» Doc ID FIMN-COM-004 Eft Date: 24 June 2019
Audit Plan Revision _:0 Page: Page | of 2
Planned Audit Date 189 19 February, 2020
an 1. Verify the compliances of QHSE-MS refer to audit criteria
Objective of Audit 2. Verify the consistency of QHSE-MS implementation
3. Identification possibility of QHSE-MS improvement
4. Verify manufacturer compliances to the requirement of API Spec 6A
5. Verification of previously intemal and external audit finding (ifany )
; ‘The audit to be conduct to area of PT. Innovasi Mitra Nusantara and coverage for
Scope of Audit 1. All Audit Criteria Clauses
2. All QHSE-MS process ( ISO 9001;14001: 45000 ) that applicable to PT. IMN
3. All manufacturing process that comply with API Spec 6A
won T, 180 9001:2015
Aude Citerss 2. 180 14001 :2015
3. ISO 45001 : 2018
4. APL Spec 6A Latest edition
- T, Documents! record verification
Method of Audit a
3._ Observation of process
‘Auditor Team 1. Ardest 2, Avie 3. Hidayah 7Dedik
4. Ariel 5. Ali 6, Devi
‘Audit Area ‘Audit Area ‘Auditee
Engineering Arief! Dedik
‘CNC Manufacturing) Production | Arief/Dedik/ Rifaldi/ Dono
Warehouse Arief/Dedik/ Rifaldi/ Dono
‘Maintenance ‘ArieffDedik/ Rifaldi/ Dono
Planning ‘Arief/ Devi
Purchasing Ardest/ Ali
[QC & NDT ‘Ardest/ Avrie! Syaiful
Marketing Ardest/ Reni
Document Control ‘Ardest/ Reni
GA- Training ‘Atdest/ Hidayah
HSE Dwi / Avric / Dono
‘Management ‘Axdest/ Reni
Planned Opening Meeting | Date : 18" February, 2020
Time : 08.30AM_
‘Venue : IMN Meeting Room
Planned Closing Mecting | Date: 198 February, 2020
Time: 04,00 PM
‘Venue : IMN Meeting RoomInnovasi
i Me
‘QHSE Form Title Doc 1D FIMN-COM-004 Eff Date = 24 June 2019
Audit Plan Revision 0 Page Page 2 of 2
‘Times of Audit
1 Day Schedule, (08.30-09.00 ‘Opening Meeting
18° February, 2020 All Auditor = Introduction scope of audit
= Introduction plan of audit
MR, Dept Head, all = Introduction ‘methods of audit
| personnel
1* Day Schedule, (09.00 - 10.00 Plant Tour (all Innovasi Mitra Nusantara area)
18 February, 2020 All Auditor Point check
- Manufacture Flow Storage Material
MR, Dept Head, all = Identification =Policy
personnel Traceability ~ Segregation Material
= __58 & HSE (concern)_- Working Knowledge
1 Day Schedule, 10.00 12.00
18% February, 2020 > Documentation, interview and observation of
Ardest Avrie Engineering
MR, Dept Head, related Ali Hidayah > Documentation, interview and observation of
sonnel Planning
1" Day Schedule, 13.00- 15.00
18% February, 2020 > Documentation, interview and observation of
Ali Avric Warehouse
MR, Dept Head, related Ardest /Hidayah > Documentation, interview and observation of
personnel Maintenance
1" Day Schedule, 15,00- 17.00
18 February, 2020
Avtic / Ali > Documentation, interview and observation of
MR, Dept Head, related (ENC Manufacture
personnel Ardest > Documentation, interview and observation of
HSE
27 Day Schedule, 08.00- 10.00
19 February, 2020 > Documentation, interview and observation of
Arief / Devi Purchasing
MR, Dept Head, related Dedik > Documentation, interview and observation of
personnel Marketing _
2" Day Schedule, 10.00- 12.00
19® February, 2020 > Documentation, interview and observation of
Arie / Devi Qc-NDT
MR, Dept Head, related Dedike > Documentation, interview and observation of
personnel GA. Training
"Day Schedule, 13:00- 15.00
19 February, 2020 > Documentation, interview and observation of
Arief / Devi Document Control
MR, Dept Head, related Dedik > Documentation, interview and observation of
personnel Management (Internal audit, Obj. Target,
Management review, ete related to management)
2 Day Schedule, 15.00- 16.00
19 February, 2020
All Auditor > Compile report
2 Day Schedule, 16.00- 17.00
19 February, 2020
All Auditor > Closing Meeting, Finding Review & Timing
MR, Dept Head, all closing finding
nel