PART I –GENERAL INSTRUCTIONS TO BIDDERS
INSTRUCTIONS TO BIDDER
1. PROJECT DESCRIPTION
Right after the War, CNPCI’s Iraqi Project Team headed by Mr. Chen Lei(acting
president of the Company) entered Iraq three times to restore and develop long-
standing friendly relations with Ministry of Oil, Iraq, under the guidance of Mr. Sun
Bigan, Chief of the working group from Foreign Ministry of PRC, during which
CNPCI actively extended its wishes to conduct five rounds of training plans for
senior staff in technical and administrative sectors from the Ministry from 2004-2005,
which was highly appreciated by Ministry of Oil. As an active feedback, the first ten
Senior Iraqi technical experts arrived in Beijing in Apr 2004, and Training Plans were
implemented successfully, which will be destined to bear fruitful results for bi-lateral
relationship.
In addition, Al-Waha Petroleum Co. and CNPCI have kept permanent contacts with
Iraqi Governing Council in spite of daily contacts with Ministry of Oil, Iraq to cement
the inherent relationship and reactivate DPC of Ahdeb Oilfield as well as cooperation
on other petroleum projects. The Company will endeavor to undertake all its
obligations stipulated by the DPC and start its full operation ASAP subject to the
approval by the Ministry of Oil on the reactivation of the contract as well as the
security situation improved in the country. The Company also would like to reiterate
restart of negotiations for other development projects with Ministry of Oil as it did
before the war.
Al-Waha Petroleum Co. Ltd. as a Petroleum Company, being strong backuped by
CNPCI/CNPC, would like to express its sincere hopes here to further strengthen and
expand cooperation with Ministry of Oil of Iraq by following its own core philosophy:
“Credibility, Innovation, and Performance”.
(b) These instructions are to inform Bidder of the proper practices, which
must be adopted to satisfy the requirements of Company for the
submission of Bid and the award of Contract. Deviations from these
instructions may result in Bidder’s Bid being disqualified.
(i) Cover Letter (Including: Invitation to Bid Letter & Acknowledgement Form )
3. ITB ACKNOWLEDGEMENT
Bidder shall check the contents of the ITB Documents to ensure that there
are no omissions or discrepancies. Bidder shall immediately notify Company
in writing of any omissions or discrepancies found in the ITB Documents or
any doubt as to the precise meaning of any item, word or figure or any other
question whatsoever.
4. GENERAL
5. PREPARATION OF BID
(d) Bidder is to ensure that all prices and other details in the Bid are
correct at the time of submission. Company will not entertain any
changes or revisions due to typographical or arithmetical errors after
the Bid closing date.
(e) All costs in the preparation and submission of the Bid including any
clarifications, discussions and/or meetings shall be at Bidder’s cost,
irrespective of whether a Contract is entered into or not.
(b) Bidder is required to submit the Bid in USD. The price shall prevail
throughout the life of the Contract and shall not be subject to revision
by reason of currency fluctuations.
5.5. Licensing
Bidder shall obtain and submit copies of all necessary consents, permits,
licences, approvals, authorisations, executions and/or waivers.
6. BID PRICE
The contract shall be on the basis of lump-sum price. Price shall under
includes all costs on product to be delivered to AHDEB OIL FIELD
SITE/WAREHOUSE
6.1 The Bid price shall be stated in the Form of BID and analysed in the
relevant Price Schedules. The Contract price must be firm.
6.2 The Bidder shall enter in the place provided in the appropriate Price
Schedule the amount, if any, to be added to his price for providing the
required performance Security. The cost, if any, of providing the required
Performance Security will be taken into account when evaluating
Tenders.
Each Bid shall be submitted in a sealed and stamped package and shall
include:
In the event of any discrepancy between the original set and copies, the
original set shall govern.
Address: Ahdeb Oil Field Camp, Al Ahrar City, Wasit Province, Iraq
Provision of Maintenance Tools & WPS spare parts
ITB NO.:005/PC/21(2nd)
Bidder :xxxxxxxxxx
Company:
Address:
Contact Information:
(Stamp)
(a) Bidder is strongly advised to deliver the Bid by hand to ensure timely
receipt by Company. If Bidder elects to mail the Bid, Bidder is
advised to use fast and reliable delivery service e.g. courier.
(a) Bidder must ensure that the Bid is delivered to the above address no
later than 12:00 AM on April 6, 2022.
8 EVALUATION OF BID
The Bid will be evaluated against, but not limited to the following criteria and
Bidder must ensure that its Bid includes the following information in the
relevant Bid forms:
(a) Scope of supply and technical document fully comply with ITB
requirement
In the event that Bidder is successful in securing this tender, Bidder Prices
and rates quoted shall prevail throughout the duration of the CONTRACT to
be signed between AL-WAHA & Contractor shall not be subject to revision
by reason of cost escalation nor currency fluctuation.
8.3 Clarifications
9. CONSIDERATION OF BID
Company reserves the right to request any further information it may deem
necessary to evaluate the Bid, which may include but not be limited to a
breakdown of, or supplement to, any lump sum prices, rates or percentages
proposed.
(a) Company may reject any or all Bids received, or may accept any Bid
that, in Company’s sole judgment, is the most advantageous to
Company. Company reserves the right to accept or reject, all, or
parts of, Bidder’s Bid at Company’s discretion, and will be under no
obligation to explain the reasons thereof.
(b) The successful Bidder will be required to enter into a formal contract
with Company which will be on the same terms and subject to the
same conditions as are contained in the ITB Documents, subject to
any clarifications issued during or prior to the evaluation of the Bid.
(c) Company shall not be deemed to have accepted any offer unless
and until a Contract is duly signed or Company sends a letter of
intent to award to the successful Bidder, signed by duly authorised
representative of Company.
12. REQUEST FOR FURTHER INFORMATION BY BIDDER
Any such request must be made not later than seven (7) calendar
days prior to the Bid closing date.
13 MODIFICATION BY COMPANY
(a) Company reserves the right to modify the ITB Documents following
issue of the same to the Bidder. Any modification to the ITB
Documents made by Company shall be advised to Bidder not later
than seven (7) calendar days prior to the Bid closing date. Any
modification shall be issued as invitation to bid supplements (notice-
to-Bidders and/or addendum) and shall be deemed to constitute part
of the ITB Documents.
(b) Company reserves the right to issue clarifications modifying the ITB
Documents during the evaluation period if it so requires.
14 CONFIDENTIALITY OF BID
(b) the prices in the Bid have been arrived at independently, without
consultation, communication, agreement or understanding for the
purpose of restricting competition, as to any matter relating to such
prices, with any other bidders or with any competitors;
(c) unless otherwise required by law, the prices which have been quoted
in the Bid have not knowingly been disclosed by Bidder, directly or
indirectly, to any other bidders or competitors, nor will they be so
disclosed;
(d) no attempt has been made or will be made by Bidder to induce any
other person or company to submit or not to submit a Bid for the
purpose of restricting competition; and
(e) Bidder has adhered to the highest standards of business ethics and,
in particular, has established precautions to prevent any of its
officers, employees, or agents from making, receiving or offering
substantial gifts, entertainment, payment, loans, or other
considerations which may influence individuals in respect of this
invitation to Bid.
15 VALIDITY OF BID
The Bid shall be firm and irrevocable and shall be valid for a period
of _365_ calendar days from the Bid closing date and shall not be
retracted or withdrawn during the period. Company shall have the
right to accept any Bid at any time before the expiration date.
16 LOCAL REGISTRATION
CONTRACTOR shall abide by the Iraq’s law and register company or office
in Iraq, CONTRACTOR should be fully responsible for all liability, in case of
failure to registration. CONTRACTOR shall protect and indemnify
COMPANY and hold COMPANY safe and harmless from any and all claims
or liability.
BIDDER shall submit a Technical Proposal which clearly describes all non-
commercial matters that form part of Bidder’s proposal. The Technical Proposal
shall be prepared with the following Table of Contents and as per the details
mentioned in the preceding sections below:
(a) Introduction and Purpose
(b) Acknowledgment of Receipt of ITB, Addenda and Clarifications
(c) BIDDER Profile and Organization, company size and certificate
(d) Bidder requirements:
(e) The Bidder’s and manufacturer’s Scale and last 3-year revenue
(f) Bidder’s or Manufacturer’s Certificate
(g) The manufacturer’s QHSE Certification
(h) Scope of supply and technical description
(i) Related successful experience and historical performance
(j) Quality Guarantee
(k) Delivery Plan
(l) Qualification Documents including but not limited the independent third
party inspection report.
(m) Financial Capabilities
(n) Documents Establishing Bidders Eligibility and Qualifications
(o) Packaging Solution and maintenance
(p) Other matters at Bidder’s discretion
Background of company
Main activity/business
Equity/shareholders/Directors
Affiliates/principal/subsidiaries company
Qualification Documents
Documentation for processing quality control
Documentation for Production development
5. Bidder REQUIREMENTS:
6. AUTHORIZATION LETTER
If Bidder participates in this project as an agent, a valid authorization letter
authenticated by the Manufacturer must be provide, otherwise, Bidder will
be disqualified directly.
7. EXPERIENCE
Experience and capability must be sufficient in order that the objectives of
the CONTRACT are achieved. BIDDER shall emphasize on projects where
BIDDER as a prime contractor, or as a significant joint-venture partner, has
successfully executed projects of similar nature. .
6. FINANCIAL CAPABILITIES
BIDDER and / or each member of its joint-venture /consortium shall submit
the following:
(a) Audited financial statements for the last three (3) years;
(b) Credit references from banks and / or other credit references
8. QUALIFICATION DOCUMENTS
A diagram of the goods with specifications and data sheet including full
information
Standards to follow
Quality assurance, Inspection and Test Plan, (ITP) etc. for this project
Life span guarantee
Other information if Bidder thinks necessary.
Contractor shall guarantee the quality of all the supplied products within the
service life based on API standard and practices. If there is any quality problem
which is verified by third-party inspection or occupation standard, WAPEC keeps
the right to investigate and affix contractor’s responsibility, and contractor shall
bear his legal responsibility and compensation accordingly even if the contract is
terminated or the quality guarantee is expired.
The delivery terms are binding and essential and consequently, no delay is
allowed without the written approval of WAPEC. Any request concerning delay will
be void unless accepted by WAPEC through a Change Order to the CONTRACT.
Price shall be under delivery to Kut Camp warehouse, Ahdeb Oil Field
Camp, Al Ahrar City, Wasit Province, Iraq
2. SCHEDULE OF PAYMENTS
All payments will be paid within Forty-five (45) working days received by WAPEC
Finance Department via telegraphic transfer (T/T), upon receipt of two (2) original
invoices by Finance Department:
First payment: Eighty percent (80%) of goods value for each shipment shall be
paid within 45 days received by Finance Department on the condition that all
goods invoiced arrived at WAPEC warehouse, and upon receipt of the following
documents:
1. Commercial Invoice covering the amount of the eight percent
(80%) in two (2) original.
2. Acceptance issued by User Department of WAPEC
3. The Quality Guarantee of ten percent (10%) of Contract Value
would be provided to WAPEC, with validity twelve (12) months date of
certificate acceptance of the goods.
Second payment: Twenty percent (20%) of Contract Value Shall be paid six
month later when all goods arrived at WAPEC warehouse. Contractor shall be
responsible to pay any and all taxes and duties levied by Iraqi government
according to the IRAQI taxation law.
4. Others refer to the Section II GERERAL CLAUSES