You are on page 1of 61

Contractor’s (CMJV) Response Sheet

Ref # SMEC/5060126/CSC1/2018-863 (DM) Dated 04 December, 2018


SL# Comments Reply
1.1 General:
 PDA Test is a Dynamic Load Test, not a Static Load Test, please make
correction accordingly.  Revised as per comments in
1
 You are to describe this Pile Driving Analyser (PDA) system clearly in item No.1.2.
this section. In addition, you are also to describe its detailed purpose in
conjunction with the Static Load Test as stated.
2. Relevant Specification and Standards
 You are to provide and submit the Relevant Specification and Standards
of PDA Test such as ASTM D 4945 - 08 officially to the Engineer for
review and approval, and attach them to this Method Statement as an
Appendix.
 ASTM 01143-81 is a Standard Test Method for Piles Under Static
2 Noted and revised as per comment.
Axial Compressive Load, not a Dynamic Load Test.
 ASTM D1143M-07 is a Standard Test Methods for Deep Foundations
Under Static Axial Compressive Load, not a Dynamic Load Test.
 JGJ 106-2014 is a Chinese Technical Code for Testing of Building
Foundation Piles. It is not relevant to Pile Driving Analyzer®
(PDA-8G) of Pile Dynamics, Inc. (PDI).
4.2. PDA Procedure
 PDA Test Procedure shall refer to and follow the procedure of Pile
Driving Analyzer® (PDA-8G) of Pile Dynamics, Inc. (PDI) including
the use of Field-to-office data transmission with Sitelink, Up to 16
channels of data acquisition available with eight wifi boxes and any
 Noted and revised as per
combination of strains and accelerometers, Traditional PDI wireless
comment in item No.4.1.
sensors, WiFi or traditional cabled options available, CAPWA 肘 ,
3  Noted and revised as per
GRLWEAP and iCAP® software for data analysis.
comment in Appendix-2 Risk
 No details of the Hammer found. You are to describe the detail
Assessment, item 10.
specification of Hammer used and also its potential height including its
supporting structure or steel frame in order to maintain its direction in
line with the pile axis position while being released hammering onto
the pile top. A strict safety precaution and hazard analysis shall also
be described for this kind of hammer dropping activities.
7. Occupational and Safety Control Plan
No specific Occupational and Safety Control Plan specifying the PDA Test
 Noted and revised as per
works, particularly all the hazardous work activities related to use and
4 comment.
dropping of the heavy weight hammer onto the pile top. Also you are to
describe how the strict safety policy around works perimeter will be
implemented durfng the works. This shall refer to the Sub-Clause A 9.2.1.
SL# Comments Reply
Appendix-1 Inspection and Test Plan (ITP)
No fully detailed and Specific Inspection and Test Plan (ITP) for PDA
5 Test according to ASTM D 4945 Noted and revised as per comment.
- 08 found in the document as per Sub-Clause A 5.1. Please submit it
officially and attach it onto this Method Statement.
Appendix-2 Risk Assessment
No proper, specific and visible Risk Assessment found in the document
Noted and revised as per comment in
reflecting the specific Risk Assessment for PDA Test works, particularly all
6 Appendix-2 Risk Assessment, item
the hazardous work activities related to use and dropping of the heavy
10.
weight hammer onto the pile top. Please improve this Risk Assessment and
revise it more detailed accordingly.
Pile Driving Analyzer® (PDA-8G) of Pile Dynamics, Inc. (PDI)
PDA test is performed by PDA machine manufactured and supplied by Pile
7 Dynamics Inc (PDI). Your machine as given in Section 4.4 is not the same to Noted and revised as per comment.
perform the PDA test. We however note that your personnel have
certification to perform PDA test.
ASTM D 4945 - 08 Standard Test Method for High-Strain Dynamic
Testing of Deep Foundations
The PDA Test must conform to ASTM 04945 standard. Your referenced
8 Noted and revised as per comment.
ASTM standard in Section 2 is not accepted for this test. We are not aware
of JIG standard (Chinese standard) and not accepted as PDA test. Your
indicated JIG may not be applicable in large diameter piles.
Force to attain Ultimate Bearing Capacity
Pile shall be fully mobilised with enough force to attain ultimate bearing
9 Noted and revised as per comment.
capacity. Permanent settlement is required and minimum impact force shall
be more than the ultimate design bearing capacity of the pile.
28 Days Old Concrete Pile
7 days old concrete pile shall not be tested as we need full strength (28 days)
10 Noted and revised as per comment.
to mobilise the pile to achieve ultimate axial bearing capacity of pile. Refer
Section 4.2.
PDA Strain Transducers
Due to larger diameter pile 4 strain transducer and 4 accelerometers will be
11 required. PDA uses strain transducer. In your document somewhere Noted and revised as per comment.
proposed strain transducer, somewhere force transducer. We understand
there are some limitations of force transducer.
Placement of the Strain Transducers
12 The transducers shall be placed 1.5D below pile head. You have shown 1D. Noted and revised as per comment.
Will you excavate to place the transducer or use a steel head?

CAPWAP Software for PDA Data Analysis


CAPWAP analysis software of PDA data is essential for a Dynamic Load
13 Noted and revised as per comment.
Test. It provides the soil resistance distribution along the foundation and
simulates a static load test. You have not indicated CAPWAP analysis.
Method Statement on Embankment Construction in Waterlogged and Marshy Area

Revision Control Table


Rev.
Description Date Prepared By Checked By Approved By
No.

2nd December Md. Rayhanur


A First Issue Matt Rahman Chen Yongyi
2018 Chowdhury
Contractor’s (CMJV) Response
22nd Md. Rayhanur
(Revised) Ref#
B December Matt Rahman Chen Yongyi
SMEC/5060126/CSC1/2018- Chowdhury
2018
863(DM)

DCRP/CMJV/MS-015, Rev. B
METHOD STATEMENT FOR PDA TEST

Table of Content
Table of Content.................................................................................................................. 1

1. Introduction..................................................................................................................... 2

1.1 General.................................................................................................................. 2

1.2 Purpose.................................................................................................................. 2

1.3 Scope..................................................................................................................... 2

2. Relevant Specification and Standards............................................................................. 4

3. Work Flow Chart............................................................................................................. 5

3.1 Work Sequence...................................................................................................... 5

3.2 Work Sequence...................................................................................................... 5

4. PDA Test..........................................................................................................................6

4.1 PDA Method..........................................................................................................6

4.2 PDA Procedure...................................................................................................... 8

4.3 Pile Head Preparation............................................................................................ 9

4.4 Apparatus.............................................................................................................10

4.5 Data Processing................................................................................................... 11

4.6 Interpretation and Evaluation.............................................................................. 12

4.7 Report.................................................................................................................. 12

5. QA/QC (Inspection and Testing Plan)...........................................................................13

6. Certificate...................................................................................................................... 13

7. Occupational and Safety Control Plan.......................................................................... 13

7.1 Health, Safety and Environment Management Plan....................................13

7.2 Safety Officer.............................................................................................. 15

7.3 Personal Protective Equipment....................................................................16

8. Environmental Control.................................................................................................. 16

9. Risk Assessment............................................................................................................ 16

DCRP-CMJV-MS-015, REV.B Page 1 of 47


METHOD STATEMENT FOR PDA TEST

1. Introduction
1.1 General
Pile Driving Analyzer (PDA) will be carried out in accordance with the Specification
D 5.4: Integrity Testing of Piles and other relevant clauses in the specification as per
ASTM D 4945-2012. This Method Statement is based on the above specifications and
ASTM Standard. In case of any discrepancies or deviation observed in the Method
Statement, the specification and ASTM Standard will prevail and method statement
shall be amended unless agreed by the Engineer on the specific issues. This method
statement describes the procedure of Pile Driving Analyzer (PDA) for Cast-in-Place
pilot piles to be constructed at Bridges.
The objective of this method statement is to describe the methodology of PDA Test
for cast-in- place concrete piling works by using Rotary machine. The size of the pile
to be covered by this method statement is diameter 1200mm.
1.2 Purpose
The purpose of PDA test is to determine whether the vertical compressive bearing
capacity of single pile meets the design requirements and test the integrity of the pile.
1.3 Scope
At least 25% of the total number of cast in place pilot piles shall be tested by PDA
tests. PDA test piles shall be selected and approved by the engineer. This MS scope of
work covers the pilot piles only which will be tested under Dynamic load of total 9
piles and under PDA of total 3 piles where the location will be finalized by discussion
with the Engineer. Pilot pile list is shown blow:
Pilot Pile Chainage and Related Parameters

Bridge Chainage Name of Overall No. of pilot


SL Vent Span(m) Remark
No. (Km) River/Crossing Length( m) pile

1 96 60+175 Kathakh ali Khal 2 30 62 1 9 nos Pilot Pile will be

DCRP-CMJV-MS-015, REV.B Page 2 of 47


METHOD STATEMENT FOR PDA TEST

Bridge Chainage Name of Overall No. of pilot


SL Vent Span(m) Remark
No. (Km) River/Crossing Length( m) pile

2 98 61+535 Bogacha ri Khal 2 25 52 1 tested for Dynamic

3 100 62+650 Canal 2 25 52 1 Load Test and 3 nos

4 109 66+132 Khal 1 40 41 1 Pilot Pile will be tested

for PDA Test


5 124 73+706 EidGha River 4 25 104 2

6 130 76+740 Khal 1 40 41 1

7 147 84+886 Sonajori Khal 2 25 52 1

8 155 90+014 Bakh Khali River 4 40 164 2

9 161 92+969 Canal 2 30 62 1

10 162 93+595 Umkhali Khal 2 30 62 1

Total 12

DCRP-CMJV-MS-015, REV.B Page 3 of 47


METHOD STATEMENT FOR PDA TEST

2. Relevant Specification and Standards


 Specification Subsection D5.
 ASTM D 4945-2012: Pile Driving Analyzer (PDA)

DCRP-CMJV-MS-015, REV.B Page 4 of 47


METHOD STATEMENT FOR PDA TEST

3. Work Flow Chart


3.1 Work Sequence

3.2 Work Sequence

DCRP-CMJV-MS-015, REV.B Page 5 of 47


METHOD STATEMENT FOR PDA TEST

4. PDA Test
4.1 PDA Method

High strain testing shall be in accordance with ASTM D4945-2012.


The transducers were calibrated to installation and fixed on the external pile with
expansion bolts to insure an accuracy of 3% throughout the applicable measurement
range.
The strain transducers shall include compensation for temperature effects and shall
have linear output over the fill operating range(typically between -2000 and
+2000microstain),their natural frequency shall be in excess of 2000Hz. Sketch of
sensors installation. Sketch of sensors installation is shown in figure 1.
The acceleration velocity date used in this project shall be obtained by using the
dynamic measurement apparatus to integrate the acceleration signals from
accelerometers.T he accelerometers shall be mounted to the pile with small rigid
metal blocks, accelerometers shall be linear to at least 1000g and 1000Hz,the resonant
frequency shall be above 3000Hz.
The hammering guide frame is used to ensure the alignment of the hammer and the
longitudinal axis of the pile to prevent the pile from bending during the test, and the
hammer force is perpendicular to the surface of the pile head. The high strain hammer
(length - 99.5cm;width -99.5cm;hight - 116cm) used in this experiment is 9 t. The test
starts with small drop height to verify pile hammer alignment and capacity transfer.
Then the falling height is increased to ensure that sufficient impact energy is applied
to the pile to fully mobilize the soil resistance around the pile.
High strain dynamic testing instrument shall be adopt PAX-8 channel pile driving
analuzer that product by PDI company. Pax has four strain channels and four
acceleration channel, in real time or after the trial data files can be processed and got
the soil resistance, the pile top and pile end pressure stress, along the pile body tensile

DCRP-CMJV-MS-015, REV.B Page 6 of 47


METHOD STATEMENT FOR PDA TEST

stress, conversion of energy and the pile body integrity. Data processing is CAPWAP
method. According to the measured force and velocity recorded by the sensor, the
distribution of soil resistance, the dynamic response and the static load test are
determined by the signal fitting analysis. The test report include single pile limit
bearing force measured value , simulation of the pile body profile and the Q-S curve,
measurement and waveform fitting curve, lateral soil resistance of pile and pile end
soil resistance distribution, axial force distribution diagram and detailed calculation
results table etc.
The two acceleration sensors and two ramus variable type force sensor are
respectively and symmetrically arranged at a distance from the pile top 1.5 times of
the pile diameter of pile side surface of high strain dynamic testing, the hammer of not
less than the characteristic value of single pile bearing capacity 1% ~ 2% times is
increased to a certain height from the top of pile and free falling to hammer pile. The
acceleration and the force signal of instantaneous impact was enlarged , signal
preprocessed and A/D conversed by pile dynamic testing system and into a digital
signal to the computer, signals is processed by computer software (fault diagnosis,
bilateral, average acceleration integral and CASE method etc.) and stored in the disk,
at the same time the computer displays the measured waveform .

DCRP-CMJV-MS-015, REV.B Page 7 of 47


METHOD STATEMENT FOR PDA TEST

Figure.1 Sketch of sensors installation

4.2 PDA Procedure

Dynamic pile testing (High Strain dynamic Testing) is conducted by attaching strain
transducers and accelerometers to the sides of the pile approximately 1 to 1.5 times
pile dia, below the pile top. A pair of transducers is fixed onto opposite sides of the
pile so as to detect bending in the pile if any during testing.
The transducers are then connected through the main cable to a pile diving Analyzer,
which is a State of Art Computer System with ability to collect, record and process
strain and acceleration values.
The signals are triggered by the impacting of a ram falling from a pre-determined
height. The ram weight and fall height is determined in advance.
Upon impact, the strain transducers measure strains whereas, acceleration are
measured by accelerometers connected on either sides of the piles.
The capacity mobilized under the blow is then obtained from the force and velocity

DCRP-CMJV-MS-015, REV.B Page 8 of 47


METHOD STATEMENT FOR PDA TEST

induced. The PDA has an in-built program which calculate and generates over 30 pile
variable based on pile top force, displacement and velocity. Immediate field results in
the from of the capacity of the pile top settlement etc. Integrity and stresses developed
in the pile etc, are obtained.
4.3 Pile Head Preparation

a. PDA test shall not be performed until the concrete has cured for a minimum 28
days unless otherwise approved by the Engineer.

b. The surface of the concrete level. On pile side and pile diameter direction, set up
across the two areas, used to install the sensor, the area size of about 20 cm x 20 cm,
polishing concrete and the area.
c. The soil near the pile head paving and compaction, guarantee the stability of guide
frame can be installed.
d. Ensure the hammer center and the pile axis on a straight line, if necessary, placed
around the pile of concrete block, ensure the smooth progress of test.
e. Equipment installation pictures see figure 2.

Fig 2. PDA Equipment Installation

DCRP-CMJV-MS-015, REV.B Page 9 of 47


METHOD STATEMENT FOR PDA TEST

4.4 Apparatus

For applying force- Any conventional pile driving hammer or similar device is used

for applying the impact force provided it is capable of generating a net measurable
pile penetration, or an estimated mobilized static resistance. The device is positioned
so that the impact is applied axially to the head of the pile and concentric with the pile
axis.
Obtaining Dynamic Measurements—The transducers, which are capable of

measuring strain and acceleration versus time independently at a specific location


along the pile axis during the impact event. A minimum of two of each of these
devices, one of each on opposing sides of the pile, shall be securely attached so that
they do not slip. Generally, bolt-on is practiced, glued-on and weld-on transducers are
also practiced. Traditional wire connected strain gauges and accelerometers are used
for measuring force and displacement. Piezoelectric (PE) or piezoresistive (PR) type
accelerometers will be used in this test.
Record and display- The signals from the transducers during the impact event is
transmitted to Pile Driving Analyzer, PDA. Pile Driving Analyzer model PAX-8 of
Pile Dynamics Inc, USA will be used for the purposes. PDA is a state of the art
instrument for receiving, recording, displaying, conditioning of data. Signals from the
transducers displayed on LCD graphics screen of PDA, on which the force and
velocity versus time can be observed for each hammer blow.
The apparatus provide signal conditioning, amplification and calibration for the force
measurement system comprising strain transducers and compute the forces. The
apparatus also compute velocity and then displacement by double integration of the
acceleration over time.
Striking hammer & guide- Any conventional pile driving hammer or similar device
may be used for applying the impact force onto the pile head. The impact should be

DCRP-CMJV-MS-015, REV.B Page 10 of 47


METHOD STATEMENT FOR PDA TEST

capable to generating a net measurable pile penetration. Mass of the hammer should
be around 1 to 2%. A trip gear is used to ensure free fall of the hammer and a guide
also used to avoid eccentric strike and protect hammer from toppling.
Lifting device-Crane is preferable, if not available any other lifting device i.e.
tripod-winch, gantry, derrick etc may also be used. Lifting device should be capable to
lift, hold and drop the hammer very comfortably.
4.5 Data Processing

Under each hammer blow, the Pile Driving is triggered and data acquisition beings at
this time. The PDA automatically processes each blow recorded during monitoring
and can display computed values. The capacity of the pile is immediately indicated at
the end of the field testing. This is than verified with the CAse Pile Wave Equation
Analysis Program (CAPWAP) for a typical blow.
The (CAPWAP) program is an analytical method that combines measured field data
with pile wave equation type procedures, to predict the pile’s static bearing capacity
and soil resistance distribution. Measured force and velocity data is directly input
from the PDA. Based on the measured velocity data, the program computes force
required to induce the imposed velocity. Both measured and computed force are
plotted as a function of time and the iterative analysis is continued till there is good
agreement between both the curves. If the agreement is not satisfactory, the soil
resistance’s at the pile point and along the pile are adjusted until a good match is
obtained. This gives better estimates of the actual pile capacity measured during field
testing, and also the friction and end bearing components.
The PDA and subsequent CAPWAP analysis indicate the amount of static capacity
that is actually mobilized during any blow delivered to the pile during testing. In order
to fully mobilize pile static capacity, a pile set in excess of 3mm per blow is required.
Should the pile set be less than 3mm, than not all the static pile resistance will be

DCRP-CMJV-MS-015, REV.B Page 11 of 47


METHOD STATEMENT FOR PDA TEST

mobilized during any one blow and the subsequent CAPWAP and PDA analysis will
under-predict the true ultimate static capacity of the pile. In other word, the ultimate
capacity of the pile will be still higher than that indicated after field testing /
CAPWAP analysis. This provided some in-built conservatism to the capacities
indicated by the PDA and CAPWAP system in the event of small set being recorded.
4.6 Interpretation and Evaluation

a. The interpretation and evaluation shall be done by an experience professional.

b. The calculation principle of this method and the specific method are: the pile soil
model and the parameters of each unit Dan Yuanjie area, elastic modulus of materials,
the distribution of soil resistance, the ratio of the pile end resistance, the soil damping,
the maximum elastic displacement and the ultimate resistance) are assumed
firstly ,test the velocity wave signal (or force wave signal) as the boundary condition
is imported and wave equation is solved with characteristic line method and pile top
force (or the speed) is inversely calculated. If calculation force (or velocity) curve and
measured force (or velocity) waveform (and hammering number)does not meet, the
adjustment of the pile-soil model and the unit parameters and the iterative calculation
will be continued,until the confidence of fit of the results of the force (or velocity)
curve and measured force wave (or wave velocity) curve cannot be improved further
so far eventually results including the single pile ultimate bearing capacity, simulation
pile profile, simulate the Q-S curve and soil resistance along the pile distribution
diagram and detailed calculation results table are given.
4.7 Report

The high strain testing report will include the project profiles, pile foundation
construction units, pile foundation construction machinery, test pile construction, and
test pile test information and the testing incorporate result of CAPWAP analysis and
the any foundation which design engineer required.

DCRP-CMJV-MS-015, REV.B Page 12 of 47


METHOD STATEMENT FOR PDA TEST

5. QA/QC (Inspection and Testing Plan)


Inspection and Testing Plan is attached in appendix-1.

6. Certificate
All test and calibration certificate of related equipment and devices will be attached in
appendix-3.

7. Occupational and Safety Control Plan


7.1 Health, Safety and Environment Management Plan
The HSE Plan which will address the following issues:
1. Health and safety risks on the Site including but not necessarily limited to the
following:
(1)Safety of Contractor’s personnel working by the side of the operational railway
tracks;
(2)Obstruction of the kinematic envelope, in particular caused by obstacles falling
on the running track such as construction equipment, tools, machinery, sleepers,
ballast, earth, construction materials and track fittings used in the construction
activities;
(3)Excavation may threaten the stability and integrity of the existing embankment,
bridges and culverts which may lead to total or partial collapse of existing
embankments, tracks, bridges and culverts.
2. How the Contractor will implement and comply specifically with all duties
responsibilities and obligations stipulated in the relevant sub-clauses of Clause 6 of
the Conditions of Contract and any other relevant clauses in the Conditions of
Contract in addition to any duties, obligations and responsibilities contained within
the Specifications and the EMP.
3. The HSE Plan shall specify the Contractor’s organisational structure through
which all health, safety and environmental issues will be mitigated and managed.

DCRP-CMJV-MS-015, REV.B Page 13 of 47


METHOD STATEMENT FOR PDA TEST

4. Appropriate controls and measures to eliminate and or reduce as appropriate,


safety risks in accordance with internationally accepted good practice.
5. The requirements for monitoring, recording, communication and reporting.
6. Specific induction and training needs for:
(1) Contractor’s personnel and teams’ personnel working on the Site;
(2) Supervising Engineer’s personnel working on the Site;
(3) Employer’s personnel visiting the site;
(4) Any other person who are authorised to be on the Site, by the Engineer and or the
Employer.
7. The Contractor shall take all reasonable steps including training and drills to
ensure the safety of all persons on the Site, whether in his employ or not and shall at
all times promote the merits of safety awareness throughout the construction period.
8. Specific arrangements for health related activities such as but not necessarily
limited to:
(1) Routine matters within the Contractor’s facilities relating to preventative
measures to mitigate against naturally occurring outbreaks of disease;
(2) Routine matters within the Contractor’s facilities including mitigation measures
to prevent the spread of naturally occurring outbreaks of disease;
(3) Minor health related issues arising from accidents or incidents at work or within
the Contractor’s facilities;
(4) Major trauma issues arising from accidents or incident at work or within the
Contractor’s facilities;
(5) Provision of assistance to members of the public in the case of an accident or
incident involving operating railways;
(6) Ongoing education relating to sexually transmitted diseases especially
HIV/AIDS.
For each location where construction activities are to be undertaken adjacent to an

DCRP-CMJV-MS-015, REV.B Page 14 of 47


METHOD STATEMENT FOR PDA TEST

operating railway track, the Contractor must engage a safety supervisor who is
conversant with the safe operation procedures as practiced by BR and who has the
physical and linguistic ability to communicate with relevant BR offices and officers to
discover the latest situation of trains running in the section and to report any incidents
which may affect the safety of the traveling public or the Contractor’s personnel.
In addition, the location specific safety supervisor must have the physical and
linguistic capabilities to communicate with the Contractor’s construction supervisory
staff and senior management. Specifically, the Contractor’s construction supervisors
and the site specific safety supervisors shall be provided with suitable equipment to
provide an audible and visual warning to workers and equipment operators in the
vicinity of the track, about an approaching train and its direction.
Notwithstanding any statements contained in the HSE Plan or any subsequent
approval by the Engineer of the HSE Plan, the Contractor will be liable for any
damage to persons or property, which may occur as a result of the Contractor’s
construction activities or from any safety related incidents which are wholly or
partially attributable to the Contractor’s construction activities or failure to take
proper precautions. The Contractor will clearly identify the safety measures and
precautions to be undertaken in each of the above cases.
7.2 Safety Officer
The Contractor shall appoint both a Safety Manager and an Accident Prevention
Officer at the Site, jointly responsible for maintaining health and safety and protection
against accidents. They shall both have at least 10 years’ experience in management
of construction safety issues in general and at least 5 years in construction within
operational railway environments and shall have the authority to issue instructions
and take protective measures to prevent incidents or accidents. Throughout the
execution of the Works, the Contractor shall provide whatever is required by this
person to exercise this responsibility and authority. If the Engineer so directs, the

DCRP-CMJV-MS-015, REV.B Page 15 of 47


METHOD STATEMENT FOR PDA TEST

Contractor shall immediately replace the Safety Officer or any other safety supervisor
without hesitation or appeal.
7.3 Personal Protective Equipment
The Contractor shall provide all his personnel and that of the Engineer and Employer,
with sufficient quantities of personal protective equipment (PPE) appropriate to the
work being carried out and ensure its’ proper use. For clarification, PPE includes but
is not limited to safety helmets, high visibility reflective jackets, hearing protectors,
safety goggles, gloves, safety shoes, waterproof clothing, full body safety harnesses,
shock absorbing lanyards, self-retracting lifelines, welding gloves and aprons and the
like. The Contractor shall take disciplinary action against any personnel who do not
properly utilise or who misuse or abuse the supplied PPE.
Where work is in, over or near water, regardless of depth, life vests shall be issued to
all workers, and life belts, lifelines and rescue boats shall be provided. All safety and
rescue equipment shall be fully maintained in accordance with the manufacturers’
instructions and made available at site at all times.

8. Environmental Control
With regard to the environmental aspects and impacts of this Dynamic load test, all
works shall be carried out following the established Health, Safety and Environment
Management Plan Ref.CCECC-MAX-DCRP-BR-18-H&K-0521 (Revision B).

9. Risk Assessment
Risk assessment for this works described in this method statement is attached in the
appendix-2 by identifying anticipated hazards and impact associated with safety and
environmental issues in order to take precautions and preventive measure.

DCRP-CMJV-MS-015, REV.B Page 16 of 47


METHOD STATEMENT FOR PDA TEST

Appendix-1

Inspection and Testing Plan

DCRP-CMJV-MS-015, REV.B Page 17 of 47


METHOD STATEMENT FOR PDA TEST

ITP-2: BRIDGES & CULVERTS


Single Line Dual Gauge Railway Track from Chakaria to Cox’s Bazar
ICB No: BR/PD/DCP/ADB/ICB/2016/WD1:LOT2

DCRP-CMJV-MS-015, REV.B Page 18 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 19 of 47


METHOD STATEMENT FOR PDA TEST

Appendix-2
Risk Assessment

DCRP-CMJV-MS-015, REV.B Page 20 of 47


METHOD STATEMENT FOR PDA TEST

No. Description of Job Hazard Hazard Events Precaution/Preventive Measure Remark

a. Make sure all lifting devices in good condition.

b. Provide signalman.

c. Barricade the lifting area to avoid other people to enter.

1 Lifting operation Falling object Injury of people d. Ensure objects to lift are free from loose materials.

e. Tagline will be used to prevent suspended from swaying.

f. Signalmen to ensure no personnel under suspended load.

g. Reflective vest

a. Only one person should be appointed for signaling work.


Movement of heavy machinery
b. All signals should be known to all staff and workers.
2 around the site & lifting Miscommunication of signal Injury of people/worker
c. Signalman should stay where operator can see his signal.
operations
d. Machine operator should not operate when he get doubtful signals.

The damage to neighborhood Make sure all machinery free of oil leak. Repairing/maintenance of machinery should be done
3 Machinery Oil spill to earth
inhabitants with proper way to avoid oil spill to earth/drain.

The damage to neighborhood When transporting and placing construction materials near residential areas, dust should be
4 Scattering of dust
inhabitants controlled very carefully.

The damage to neighborhood When heavy equipment are being operated near residential areas, work time should be carefully
5 Noise
inhabitants determined and protection fence is to be installed when necessary.

Heavy equipment access on Physical damage to existing road and Access entrance should be always cleaned. Damage should be repaired when found. Existing
6
existing road scattering of dirt on it. road shall be restored back to the original position.

Engineer to check & ensure access is safe for use. Installation area will be cordoned off with
Fall from height hazard worker Injury / death Workman, surrounding
7 warning signage. Restrainer will be attached on the steel plate for worker to secured
exposed to fall from height workers
their safety harness

DCRP-CMJV-MS-015, REV.B Page 21 of 47


METHOD STATEMENT FOR PDA TEST

No. Description of Job Hazard Hazard Events Precaution/Preventive Measure Remark

Wear life jacket with reflective vest Buddy system Barricade the area with warning signage to
8 Working near Water Injury/ death of people/worker
avoid r people to enter.

Everybody gather nearest assembly point & Contact with Site

Safety Personnel In-charge. Site Safety Personnel In-charge will take over & control the
9 Emergency Procedure Injury of people/worker
scenario/situation in case of any emergency Fire Alarm / siren, Fire Extinguisher First-Aider

First-Aid Box Briefing on Emergency Procedure Safety Induction Training TBM Meeting

The site engineer and Safety Personnel In-charge carefully check the hammer used in the Weight of Hammer

10 Hammer Striking Injury/ death of people/worker experiment and the supporting structure; In the process of experiment, it is ensured that the is 9t and potential

hammer strike direction is consistent with the pile axis. height is 5.1m.

General Note:

1) Personal Protective Equipment (PPE) to be worn:

i) Mandatory: Safety Shoes/Boots, Hard Helmet, High Visibility/Reflective Vest.

ii) As necessary: Full body harness, Safety goggles, Safety Gloves, Ear plug or Ear muff, Face Shield, Dust /Face Musk etc.

2) First-Aider Name: i) Mr. Fezar, Contact Number: 01636809758

ii) Mr. Alauddin, Contact Number: 01816104799

3) Hospital Name: i) Eidgah Medical Center and Hospital, Contact number: 01618-142366, 03432-58346

ii) Napitkhali Community Clinic, Contact Number: 01814-817847, 01813-14256

4) Emergency Contact Number: Fezar: 01636809758 (CCECC), Kamrul: 01753108639 (JV), Mizan: 01716300045 (JV)

DCRP-CMJV-MS-015, REV.B Page 22 of 47


METHOD STATEMENT FOR PDA TEST

Appendix-3
Certificate of Related Equipment and Devices

DCRP-CMJV-MS-015, REV.B Page 23 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 24 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 25 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 26 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 27 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 28 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 29 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 30 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 31 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 32 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 33 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 34 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 35 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 36 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 37 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 38 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 39 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 40 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 41 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 42 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 43 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 44 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 45 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 46 of 47


METHOD STATEMENT FOR PDA TEST

DCRP-CMJV-MS-015, REV.B Page 47 of 47


Designation: D4945 − 12

Standard Test Method for


High-Strain Dynamic Testing of Deep Foundations1
This standard is issued under the fixed designation D4945; the number immediately following the designation indicates the year of
original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. A
superscript epsilon (´) indicates an editorial change since the last revision or reapproval.

1. Scope 1.5 The values stated in SI units are to be regarded as


standard. No other units of measurement are included in this
1.1 This dynamic test method covers the procedure for
standard.
applying an axial impact force with a pile driving hammer or
a large drop weight that will cause a relatively high strain at the 1.6 All observed and calculated values shall conform to the
top of an individual vertical or inclined deep foundation unit, guidelines for significant digits and rounding established in
and for measuring the subsequent force and velocity response Practice D6026.
of that deep foundation unit. High-strain dynamic testing 1.7 The method used to specify how data are collected,
applies to any deep foundation unit, also referred to herein as calculated, or recorded in this standard is not directly related to
a “pile,” which functions in a manner similar to a driven pile or the accuracy to which the data can be applied in design or other
a cast-in-place pile regardless of the method of installation, and uses, or both. How one applies the results obtained using this
which conforms with the requirements of this test method. standard is beyond its scope.
1.2 This standard provides minimum requirements for dy- 1.8 This standard does not purport to address all of the
namic testing of deep foundations. Plans, specifications, or safety concerns, if any, associated with its use. It is the
provisions (or combinations thereof) prepared by a qualified responsibility of the user of this standard to establish appro-
engineer may provide additional requirements and procedures priate safety and health practices and determine the applica-
as needed to satisfy the objectives of a particular test program. bility of regulatory limitations prior to use. For a specific
The engineer in responsible charge of the foundation design, precautionary statement, see Note 4.
referred to herein as the “Engineer”, shall approve any
deviations, deletions, or additions to the requirements of this 2. Referenced Documents
standard. 2.1 ASTM Standards:2
C469 Test Method for Static Modulus of Elasticity and
1.3 The proper conduct and evaluation of high-strain dy-
Poisson’s Ratio of Concrete in Compression
namic tests requires special knowledge and experience. A
D198 Test Methods of Static Tests of Lumber in Structural
qualified engineer should directly supervise the acquisition of
Sizes
field data and the interpretation of the test results so as to
D653 Terminology Relating to Soil, Rock, and Contained
predict the actual performance and adequacy of deep founda-
Fluids
tions used in the constructed foundation. A qualified engineer
D1143/D1143M Test Methods for Deep Foundations Under
shall approve the apparatus used for applying the impact force,
Static Axial Compressive Load
driving appurtenances, test rigging, hoist equipment, support
D3689 Test Methods for Deep Foundations Under Static
frames, templates, and test procedures.
Axial Tensile Load
1.4 The text of this standard references notes and footnotes D3740 Practice for Minimum Requirements for Agencies
which provide explanatory material. These notes and footnotes Engaged in Testing and/or Inspection of Soil and Rock as
(excluding those in tables and figures) shall not be considered Used in Engineering Design and Construction
as requirements of the standard. The word “shall” indicates a D6026 Practice for Using Significant Digits in Geotechnical
mandatory provision, and the word “should” indicates a Data
recommended or advisory provision. Imperative sentences
indicate mandatory provisions. 3. Terminology
3.1 Definitions—For common definitions of terms used in
this standard, see Terminology D653.
1
This test method is under the jurisdiction of ASTM Committee D18 on Soil and
2
Rock and is the direct responsibility of Subcommittee D18.11 on Deep Foundations. For referenced ASTM standards, visit the ASTM website, www.astm.org, or
Current edition approved May 1, 2012. Published June 2012. Originally contact ASTM Customer Service at service@astm.org. For Annual Book of ASTM
approved in 1989. Last previous edition approved in 2008 as D4945 – 08. DOI: Standards volume information, refer to the standard’s Document Summary page on
10.1520/D4945-12. the ASTM website.

Copyright © ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States
--`,`,,,``,``,`,``,,,,````,,,`,,-`-`,,`,,`,`,,`---

No reproduction or networking permitted without license from IHS Not for Resale, 01/10/2016 04:50:31 MST
D4945 − 12
3.2 Definitions of Terms Specific to This Standard: 3.2.7 hammer cushion, n—the material inserted between the
3.2.1 cast in-place pile, n—a deep foundation unit made of hammer striker plate and the helmet on top of the deep
cement grout or concrete and constructed in its final location, foundation.
for example, drilled shafts, bored piles, caissons, auger cast 3.2.8 impact event, n—the period of time during which the
piles, pressure-injected footings, etc. deep foundation is moving due to the impact force application.
3.2.2 deep foundation, n—a relatively slender structural See Fig. 1.
element that transmits some or all of the load it supports to the 3.2.9 impact force, n—in the case of strain transducers, the
soil or rock well below the ground surface, that is, a driven impact force is obtained by multiplying the measured strain (ε)
pile, a cast-in-place pile, or an alternate structural element with the cross-sectional area (A) and the dynamic modulus of
having a similar function. elasticity (E).
3.2.3 deep foundation cushion, n—the material inserted 3.2.10 mandrel, n—a stiff structural member placed inside a
between the helmet on top of the deep foundation and the deep thin shell to allow impact installation of the thin section shell.
foundation (usually plywood).
3.2.11 moment of impact, n—the first time after the start of
3.2.4 deep foundation impedance, n—a measure of the deep the impact event when the acceleration is zero. See Fig. 1.
foundation’s resistance to motion when subjected to an impact
3.2.12 particle velocity, n—the instantaneous velocity of a
event. Deep foundation impedance can be calculated by
particle in the deep foundation as a strain wave passes by.
multiplying the cross-sectional area by the dynamic modulus of
elasticity and dividing the product by the wave speed. 3.2.13 restrike, n or v—the redriving of a previously driven
Alternatively, the impedance can be calculated by multiplying pile, typically after a waiting period of 15 min to 30 days or
the mass density by the wave speed and cross-sectional area. more, to assess changes in ultimate axial compressive static
capacity during the time elapsed after the initial installation.
Z 5 ~ EA/c ! 5 ρcA (1)
3.2.14 wave speed, n—the speed with which a strain wave
where: propagates through a deep foundation. It is a property of the
Z = impedance, deep foundation composition and for one-dimensional wave
E = dynamic modulus of elasticity, propagation is equal to the square root of the quotient of the
A = cross-sectional area, Modulus of Elasticity divided by mass density: c = (E/ρ) 1/2.
c = wave speed, and
ρ = mass density. 4. Significance and Use
3.2.5 driven pile, n—a deep foundation unit made of pre- 4.1 Based on the measurements from strain or force, and
formed material with a predetermined shape and size and acceleration, velocity, or displacement transducers, this test
typically installed by impact hammering, vibrating, or pushing. method obtains the force and velocity induced in a pile during
3.2.6 follower, n—a structural section placed between the an axial impact event (see Figs. 1 and 2). The Engineer may
impact device and the deep foundation during installation or analyze the acquired data using engineering principles and
testing. judgment to evaluate the integrity of the pile, the performance

FIG. 1 Typical Force and Velocity Traces Generated by the Apparatus for Obtaining Dynamic Measurements
--`,`,,,``,``,`,``,,,,````,,,`,,-`-`,,`,,`,`,,`---

No reproduction or networking permitted without license from IHS Not for Resale, 01/10/2016 04:50:31 MST
D4945 − 12
event to fully mobilize the capacity. However, high displacement driven
piles may require greater movement to avoid under predicting the static
capacity, and cast-in-place piles often require a larger cumulative perma-
nent net penetration for a series of test blows to fully mobilize the
capacity. Static capacity may also decrease or increase over time after the
pile installation, and both static and dynamic tests represent the capacity
at the time of the respective test. Correlations between measured ultimate
axial static compression capacity and dynamic test estimates generally
improve when using dynamic restrike tests that account for soil strength
changes with time (see 6.8).
NOTE 2—Although interpretation of the dynamic test analysis may
provide an estimate of the pile’s tension (uplift) capacity, users of this
standard are cautioned to interpret conservatively the side resistance
estimated from analysis of a single dynamic measurement location, and to
avoid tension capacity estimates altogether for piles with less than 10 m
embedded length. (Additional transducers embedded near the pile toe may
also help improve tension capacity estimates.) If the Engineer does not
have adequate previous experience for the specific site and pile type with
the analysis of dynamic test data for tension capacity, then a static load test
carried out according to Test Method D3689 should be used to verify
tension capacity estimates. Test Method D3689 provides a direct and more
reliable measurement of static tension capacity.
NOTE 3—The quality of the result produced by this test method is

--`,`,,,``,``,`,``,,,,````,,,`,,-`-`,,`,,`,`,,`---
dependent on the competence of the personnel performing it, and the
suitability of the equipment and facilities used. Agencies that meet the
criteria of Practice D3740 are generally considered capable of competent
and objective testing/sampling/inspection/etc. Users of this test method
are cautioned that compliance with Practice D3740 does not in itself
assure reliable results. Reliable results depend on many factors; Practice
D3740 provides a means of evaluating some of those factors.

5. Apparatus
FIG. 2 Typical Arrangement for High-Strain Dynamic Testing of a 5.1 Impact Device—A high-strain dynamic test measures
Deep Foundation the pile response to an impact force applied at the pile head and
in concentric alignment with its long axis (see Figs. 2 and 3).
of the impact system, and the maximum compressive and The device used to apply the impact force should provide
tensile stresses occurring in the pile. sufficient energy to cause pile penetration during the impact
event adequate to mobilize the desired capacity, generally
4.2 If sufficient axial movement occurs during the impact producing a maximum impact force of the same order of
event, and after assessing the resulting dynamic soil response magnitude, or greater than, the ultimate pile capacity (static
along the side and bottom of the pile, the Engineer may analyze plus dynamic). The Engineer may approve a conventional pile
the results of a high-strain dynamic test to estimate the ultimate driving hammer, drop weight, or similar impact device based
axial static compression capacity (see Note 1). Factors that on predictive dynamic analysis, experience, or both. The
may affect the axial static capacity estimated from dynamic impact shall not result in dynamic stresses that will damage the
tests include, but are not limited to the: (1) pile installation pile, typically less than the yield strength of the pile material
equipment and procedures, (2) elapsed time since initial after reduction for potential bending and non-uniform stresses
installation, (3) pile material properties and dimensions, (4) (commonly 90 % of yield for steel and 85 % for concrete). The
type, density, strength, stratification, and saturation of the soil, Engineer may require cushions, variable control of the impact
or rock, or both adjacent to and beneath the pile, (5) quality or energy (drop height, stroke, fuel settings, hydraulic pressure,
type of dynamic test data, (6) foundation settlement, (7) etc.), or both to prevent excessive stress in the pile during all
analysis method, and (8) engineering judgment and experience. phases of pile testing.
If the Engineer does not have adequate previous experience
with these factors, and with the analysis of dynamic test data, 5.2 Dynamic Measurements—The dynamic measurement
then a static load test carried out according to Test Method apparatus shall include transducers mounted externally on the
D1143/D1143M should be used to verify estimates of static pile surface, or embedded within a concrete pile, that are
capacity and its distribution along the pile length. Test Method capable of independently measuring strain and acceleration
D1143/D1143M provides a direct and more reliable measure- versus time during the impact event at a minimum of one
ment of static capacity. specific location along the pile length as described in 5.2.7.
NOTE 1—The analysis of a dynamic test will under predict the ultimate 5.2.1 External Transducers—For externally mounted
axial static compression capacity if the pile movement during the impact transducers, remove any unsound or deleterious material from
event is too small. The Engineer should determine how the size and shape the pile surface and firmly attach a minimum of two of each of
of the pile, and the properties of the soil or rock beneath and adjacent to
the pile, affect the amount of movement required to fully mobilize the type of transducer at a measurement location that will not
static capacity. A permanent net penetration of as little as 2 mm per impact penetrate the ground using bolts, screws, glue, solder, welds, or
may indicate that sufficient movement has occurred during the impact similar attachment.

No reproduction or networking permitted without license from IHS Not for Resale, 01/10/2016 04:50:31 MST
D4945 − 12
strain transducers, and place all transducers so that they have
immediate contact with the pile material.
5.2.4 Strain Transducers—The strain transducers shall in-
clude compensation for temperature effects, and shall have
linear output over the full operating range (typically between
–2000 and +2000 microstrain plus an additional allowance for
possible strain induced by mounting on a rough surface).
Attachment points shall be spaced (dimensions S and H in
Figs. 4-7) no less than 50 mm and no more than 100 mm apart.
When attached to the pile, their natural frequency shall be in
excess of 2000 Hz.
5.2.4.1 As an alternate to strain transducers, axial force
measurements can be made by force transducers placed be-
tween the pile head and the impact device, or affixed in the pile
cross-section, although such transducers may alter the dynamic
characteristics of the driving system, the dynamic pile
response, or both. Force transducers shall have impedance
between 50 and 200 % of the pile impedance. The output signal
shall be linearly proportional to the axial force, even under
eccentric load application. The connection between the force
transducers and the deep foundation shall have the smallest
possible mass and least possible cushion necessary to prevent
damage.
5.2.5 Acceleration, Velocity, or Displacement
Transducers—Velocity data shall be obtained by using the
dynamic measurement apparatus to integrate the acceleration

NOTE 1—Strain transducer and accelerometer may be combined into


one unit on each side of the deep foundation.
FIG. 3 Schematic Diagram of Apparatus for Dynamic Monitoring
of Deep Foundations

5.2.2 Embedded Transducers—Position the embedded


transducers at each measurement location prior to placing the
pile concrete, firmly supported by the pile reinforcement or
formwork to maintain the transducer location and orientation
during the concrete placement. When located near the pile
head, one of each type of embedded transducer located at the
centroid of the pile cross-section should provide adequate
measurement accuracy, which may be checked by proportion-

--`,`,,,``,``,`,``,,,,````,,,`,,-`-`,,`,,`,`,,`---
ality (see 6.9). Embedded transducers installed along the pile
length and near the pile toe help define the distribution of the
dynamic load within the pile, but usually require data quality
checks other than proportionality, such as redundant transduc-
ers (see 6.9). Embedded transducers shall provide firm anchor-
age to the pile concrete to obtain accurate measurements; the
anchorage and sensors should not significantly change the pile
impedance.
5.2.3 Transducer Accuracy—The transducers shall be cali-
brated prior to installation or mounting to an accuracy of 3 %
throughout the applicable measurement range. If damaged or
functioning improperly, the transducers shall be replaced,
repaired and recalibrated, or rejected. The design of
transducers, whether mounted or embedded as single units or
as a combined unit, shall maintain the accuracy of, and prevent
NOTE 1—Shown as separate transducers or alternative combined
interference between, the individual measurements. In general, transducers.
avoid mounting or embedding acceleration, velocity, or dis- FIG. 4 Typical Arrangement for Attaching Transducers to
placement transducers so that they bear directly on the force or Pipe Piles

No reproduction or networking permitted without license from IHS Not for Resale, 01/10/2016 04:50:31 MST
D4945 − 12

NOTE 1—Shown as separate transducers. NOTE 1—Shown as combined transducers.


FIG. 5 Typical Arrangement for Attaching Transducers to Con- FIG. 6 Typical Arrangement for Attaching Transducers to
crete Piles Wood Piles

signals from accelerometers. The accelerometers shall be cancel axial bending stresses. Arrange accelerometers so that
directly attached to the pile surface, mounted to the pile with when averaged their measurements cancel movements due to
small rigid (solid, nearly cubic shape) metal blocks, or embed- bending. Unless located at the pile centroid, place similar types
ded in the pile. Do not use overhanging brackets or plastic of transducer so that they are symmetrically opposed and
mounting blocks that can deform during impact. Accelerom- equidistant from the pile centroid in a plane perpendicular to
eters shall be linear to at least 1000 g and 1000 Hz for concrete the pile axis. Verify the final position, firm connection, and
piles. For steel piles, it is advisable to use accelerometers that alignment of all transducers, both external and embedded.
are linear to at least 2000 g and 2000 Hz. For piezoelectric Section 6.9 describes an important proportionality check re-
accelerometers using an AC coupled signal path, the resonant quired for both external and embedded transducers that helps
frequency shall be above 30 000 Hz when rigidly mounted, or verify measurement accuracy.
above 10 000 Hz if the mounting is damped, and the time
constant shall be at least 1.0 s to preserve the low frequency 5.3 Signal Transmission—The signals from the transducers
signal content. If piezoresistive accelerometers are used, then shall be transmitted to the apparatus for recording, processing,
they should have a resonant frequency of at least 2500 Hz and and displaying the data (see 5.4) by means of a cable or
a damped mounting. Alternatively, velocity or displacement wireless equivalent. An intermediate apparatus may be used for
transducers may be used to obtain velocity data, provided they initial signal processing prior to transmission of the signal data
are equivalent in performance to the specified accelerometers. to the apparatus for recording, processing, and displaying the
5.2.6 Combined Transducers—Force and velocity instru- data if the processing functions it provides meet the require-
mentation may use individual transducers connected separately ments of 5.4. Cables shall be shielded to limit electronic and
to the pile, or transducers connected together and attached to other transmission interference. If wireless transmission is
the pile as a combined unit. used, the signals arriving at the apparatus shall accurately
5.2.7 Placement of Transducers—To avoid irregular stress represent the continuity and magnitude of the transducer
concentrations at the ends of the pile, locate transducers a measurements over the frequency range of the dynamic mea-
distance of at least 1.5 times the pile width from the top (or surement apparatus.
bottom) of pile as illustrated in Figs. 4-7. (These figures are 5.4 Recording, Processing, and Displaying Data:
typical, but not exclusionary.) Align transducers with their 5.4.1 General—The signals from the transducers (see 5.2)
sensitive direction parallel to the long axis of the pile. Arrange shall be transmitted during the impact event to an apparatus for
strain transducers so that when averaged their measurements recording, processing, and displaying the data. The apparatus
--`,`,,,``,``,`,``,,,,````,,,`,,-`-`,,`,,`,`,,`---

No reproduction or networking permitted without license from IHS Not for Resale, 01/10/2016 04:50:31 MST
D4945 − 12
000 Hz for timber or steel piles. Both analog and digital
processing shall include signal conditioning that retains the
frequency content appropriate to the sampling rate of the
interpreted velocity signal. The minimum total time sampled
for each impact event shall be the greater of 100 milliseconds
or 3L/c (where L is the pile length and c is the pile material
wave speed) with most of this time following the moment of
impact as shown in Fig. 1.
5.4.3 Processing Data—As a minimum, the apparatus for
processing signals from the transducers shall provide the
following functions:
5.4.3.1 Force Measurements—The apparatus shall provide
signal conditioning for the force measurement system. If strain
transducers are used (see 5.2.4), the apparatus shall compute
the net axial force on the cross-section of the pile. The force
output shall be balanced to a reference level (for example,
zero) prior to the impact event.
5.4.3.2 Velocity Data—If accelerometers are used (see
5.2.5), the apparatus shall integrate the acceleration over time
to obtain velocity. If displacement transducers are used, the
apparatus shall differentiate the displacement over time to
obtain velocity. If required, the apparatus shall zero the
velocity between impact events and shall adjust the velocity
record to account for transducer zero drift during the impact
event.
5.4.3.3 Signal Conditioning—The signal conditioning for
force and velocity shall have equal frequency response curves
to avoid relative phase shifts and relative amplitude differences
and retain all frequency components in the data below at least
2000 Hz.
NOTE 1—Shown as separate transducers.
FIG. 7 Typical Arrangement for Attaching Transducers to H-Piles
5.4.4 Display of Data—For each impact event, the raw or
processed signals from the transducers specified in 5.2 shall be
displayed during data acquisition or replay as a function of
shall include a visual graphics display of the force and velocity time, such as on a digital graphics display.
versus time, non-volatile memory for retaining data for future 5.4.5 Field Supervision—A qualified engineer shall directly
analysis, and a computational means to provide results consis- supervise all field testing and assess data quality and reliability
tent with Engineer’s field testing objectives, for example, for later detailed evaluation (see 6.9). Alternatively, field
maximum stresses, maximum displacement, energy transferred personnel may transmit the data concurrently as acquired to a
to the pile, etc. The apparatus for recording, processing, and qualified engineer supervising the testing from a remote
displaying data shall include compensation for temperature location.
effects and provide a self-calibration check of the apparatus for
recording, processing and displaying. No error shall exceed
6. Procedure
2 % of the maximum signal expected. Fig. 3 shows a typical
schematic arrangement for this apparatus. 6.1 General—Allow sufficient time for driven and cast-in-
5.4.2 Recording Data—The raw data from the transducers place deep foundations constructed of concrete to gain ad-
shall be recorded on site, electronically in digital form, with a equate structural strength prior to testing. Record applicable
minimum of 12 bit ADC resolution and including at most only project information (Section 7). Attach the transducers (Section
the minimal processing required to obtain the force and 5) to the deep foundation, perform any calibration checks
velocity. Transducer data recorded after minimal processing recommended by the equipment manufacturer, and take the
--`,`,,,``,``,`,``,,,,````,,,`,,-`-`,,`,,`,`,,`---

shall also record the information required to recover the raw dynamic measurements for the impacts during the interval to
data signals for later reprocessing as needed, for example, be monitored together with routine observations of number of
calibrations, wave speed, mass density, pile area, etc. When blows per unit penetration (“blow count”) or set per blow.
determining velocity by analog integration of acceleration, or Determine the pile response to the high-strain dynamic test
analog differentiation of displacement, use a minimum sample from a minimum of ten impact records during initial driving
frequency for each data channel of 5000 Hz for concrete piles and, when used for soil resistance computations, normally from
and 10 000 Hz for timber or steel piles. When determining one or two representative blows at the beginning of a restrike.
velocity by digital integration of acceleration, or digital differ- NOTE 4—Warning—Never approach a deep foundation being tested
entiation of displacement, use a minimum sample frequency while the hammer or large drop weight is operating as materials or
for each data channel of 10 000 Hz for concrete piles and 40 appurtenances may break free and jeopardize the safety of persons in the

No reproduction or networking permitted without license from IHS Not for Resale, 01/10/2016 04:50:31 MST
D4945 − 12
vicinity. Preferably the contractor crew will attach the transducers to the piles and wood piles may be determined from measurements made during
pile. a compression test performed in accordance with Test Methods C469 or
D198 respectively. The Engineer should then estimate the dynamic
6.2 Determination of Wave Speed for Deep Foundations— modulus (typically assumed 10 % greater) from this measurement.
The wave speed of concrete or wood piles should preferably be
determined from an early impact event if a tensile reflection 6.5 Preparation—Mark the pile clearly at appropriate unit
from the pile toe is clearly identified. Divide two times the intervals to prepare for recording blow counts. Attach the
length of pile below transducers by the observed time between transducers as described in Section 5. Determine the pile wave
start of the impact (for example, initial sharp rise of the signal) speed (see 6.2) and density (see 6.3). For concrete piles or
and the start of the tensile reflection (for example, later relative concrete filled pipe piles, place a pile cushion made of plywood
velocity increase) to obtain the wave speed. For piles with or other material with similar stiffness on top of the pile. For
instrumentation at both the head and near the toe, the wave concrete filled pipe piles, the concrete must completely fill the
speed can be calculated from dividing the distance between pile top so that the impact is transferred through the pile
these locations by the time between impact arrivals at these cushion to the concrete. Position the impact device on the pile
locations. Alternatively, place the pile on supports or level head to apply the impact force concentric with the long axis of
ground free and clear from neighboring piles and obstructions. the pile. Prepare the apparatus for recording, processing, and
Then attach an accelerometer to the pile and strike the end of displaying data to receive the dynamic measurements and
the pile with a sledge hammer of suitable weight. Take care not balance the strain (or force) and acceleration signals to their
to damage or dent the pile. Record (see 5.4.2) and display (see respective reference levels (for example, zero).
5.4.4) the accelerometer signal. Measure the total time between 6.6 Recording Hammer Information—Record the mass of
acceleration peaks for at least three cycles of reflection or 6L/c the hammer ram or drop weight. For drop hammers and single
(where L is the pile length and c is the pile material wave acting diesel and air/steam/hydraulic hammers, record the drop
speed). Divide the product of the number of cycles and twice height of the ram or the ram travel length. For double acting
the total pile length by this total time to determine the wave diesel hammers, measure the bounce pressure, and for double
speed. The wave speed of structural steel piles can be assumed acting steam or compressed air hammers, measure the steam or
as 5123 m/s. Assumed wave speed values, and those deter- air pressure in the pressure line to the hammer. For hydraulic
mined during a low strain event, should be verified directly or hammers or any of the previously listed hammer types, record
indirectly if possible. The overall wave speed observed during the kinetic energy from the hammer readout when available.
a high-strain event as described above may differ (typically Record the number of impact blows per minute delivered by
slower) from the local wave speed used to compute impedance the hammer.
because of variability in pile properties, degradation of pile
material during repeated hammer blows, or splices in the pile 6.7 Taking Measurements—Take, record, and display force
length. and velocity measurements for each impact event. Compare the
force and the product of velocity and impedance at the moment
6.3 Determination of Mass Density of Deep Foundations— of impact (see 6.9). Obtain the net permanent displacement per
The density of each wood pile shall be determined from the impact from the pile driving blow count record, or from marks
total weight of the pile, or a sample of the pile, the correspond- placed on the pile prior to and after the test using the same
ing volume, and the gravitational constant. The density of reference, directly from the displacement transducers (if used),
concrete or grout can be measured in a similar manner. or by integration of the velocity versus time record (typically
Alternately, the density of concrete piles is often assumed to be less reliable). Obtain the maximum energy transferred to the
2450 kg/m3 and the density of grout used for auger-cast or location of the transducers from the integral over time of force
similar types of piles is often assumed to be 2150 kg/m3. The multiplied by velocity.
mass density of structural steel piles can be assumed as 7850
kg/m3. The mass density of composite deep foundations, such 6.8 Time of Testing—Dynamic tests performed during the
as concrete filled steel pipes, can be computed from a weighted initial installation of a driven pile typically monitor the
average of the areas of the materials at each differing cross- performance of the impact device, the driving stresses in the
section. Assumed and computed values of mass density should pile, the pile integrity, and relative changes in capacity. If the
be verified directly if possible, or indirectly through their effect test results are used for static capacity computations, then
on impedance and proportionality (see 6.9). dynamic measurements should (also) be performed during
restrikes of the deep foundation, after waiting a period of time
6.4 Determination of Dynamic Modulus of Elasticity of
following the initial installation sufficient to allow pore water
Deep Foundations—The dynamic modulus of elasticity (E) for
pressure and soil strength changes to occur. (See Note 1.)
concrete, wood, steel, or composite piles can be computed as
the product of the square of the wave speed (determined as 6.9 Data Quality Checks—Confirm the accuracy of dynamic
indicated in 6.2) times the mass density (E = ρc 2). The measurements obtained near the pile head by periodically
dynamic modulus of elasticity may be assumed as 207 × 106 checking that the average of the measured force signals and the
kPa for structural steel. Assumed and computed values of the product of the impedance and the average of the measured
dynamic modulus of elasticity should be verified directly if velocity signals agree proportionally at the moment of impact.
possible, or indirectly through their effect on impedance and Do not expect proportionality when reflections occur from pile
proportionality (see 6.9). impedance changes nearby and below the transducers or from
NOTE 5—Alternatively, the static modulus of elasticity for concrete soil resistance, such as for transducers near the pile bottom or,
--`,`,,,``,``,`,``,,,,````,,,`,,-`-`,,`,,`,`,,`---

No reproduction or networking permitted without license from IHS Not for Resale, 01/10/2016 04:50:31 MST
D4945 − 12
depending on the rise time to the initial force peak, transducers smooth, flat, clean surface on which to mount the transducers
located between the pile head and the bottom. Reject non parallel to the pile axis. Because cast-in-place piles may have
proportional data. Two velocity signals should generally agree non uniform material properties and a variable, irregular
well at a particular measurement location, even though the two cross-section, when using externally mounted transducers con-
force signals may indicate significant bending. Two embedded sider placing four strain transducers equally spaced around the
strain measurements made in close proximity to the pile axis at perimeter and as described in 5.2.7. The average force deter-
the same location, or at adjacent locations on the pile axis, can mined from each diametrically opposed pair of transducers can
provide a consistency check of each other. For piles with a high then be compared together, and with the average velocity as in
percentage of end bearing, analysis of measurements made 6.9, to assess the data quality of all force measurements.

--`,`,,,``,``,`,``,,,,````,,,`,,-`-`,,`,,`,`,,`---
near the pile head may provide confirmation of measurements NOTE 7—The strength and dynamic modulus of elasticity for cast-in-
near the pile bottom. For an impact device delivering relatively place deep foundations depends on the quality and the age of concrete, and
similar impacts, the force and velocity versus time over a series can vary considerably over the cross-section and along the length of the
deep foundation. The dynamic modulus of elasticity as calculated from the
of consecutive impact events should be relatively consistent. wave speed (see 3.2) will therefore be an average value which may differ
Consistent and proportional signals of (average) force versus from the modulus at the transducer location. If the cast-in-place deep
(average) velocity times pile impedance are the result of the foundation is encased in a steel shell, then use a composite mass density
transducer systems performing properly and the apparatus for and composite dynamic modulus of elasticity.
recording, processing, and displaying data being properly
calibrated. If the signals are not consistent, or are not in 7. Report
proportionality agreement, investigate the cause and correct as 7.1 The report of the load test shall include any information
necessary. If the cause is loose or misaligned instrumentation, required by the Engineer plus the following information when
then correct the problem prior to continuing the test. If the applicable and as available.
cause is determined to be a transducer malfunction, it must be
repaired or recalibrated, or both, before further use. If the cause 7.2 General:
cannot be determined and rectified, then the test is to be 7.2.1 Project identification and location, and
rejected. Perform self-calibration checks of the apparatus used 7.2.2 Log(s) of nearby or typical test boring(s).
for recording, processing, and displaying data periodically
7.3 Deep Foundation Installation Equipment:
during testing as recommended by the manufacturer, and
recalibrate before further use if found to be out of manufac- 7.3.1 For driven piles: description of driving methods and
turer’s tolerance. installation equipment used for driving piles, testing piles, or
NOTE 6—It is generally recommended that all components of the both as appropriate, for example, make, model, and type of
apparatus for obtaining dynamic measurements and the apparatus for hammer, size (ram weight and stroke), manufacturer’s energy
recording, processing and displaying data be calibrated at least once every rating, capabilities, operating performance levels or pressures,
two years to the standards of the manufacturer. fuel settings, hammer cushion and pile cushion descriptions
6.10 Followers and Mandrels—If a follower is used for with cushion exchange details, and description of lead type and
installing and testing cast-in-place concrete deep foundations, any special installation equipment such as a follower, mandrel,
this follower should have an impedance between 80 and 150 % punch, pre-drill or jet.
of that of the deep foundation. However, additional caution and 7.3.2 For cast-in-place concrete piles: description of con-
analysis may be required if the impedance is not within 10 % struction methods, drilling or augering equipment, and con-
of that of the deep foundation. For mandrel-driven piles, the crete or grout placement, for example, type of drill rig, type
mandrel may be instrumented in a similar way to a driven pile and dimensions of drill tool(s), auger(s), and cleanout tool(s),
provided that the mandrel is constructed of a single member tremie, concrete or grout pump, and casings.
with no joints.
7.4 Test Pile(s):
6.11 Testing Cast-in-Place Deep Foundations—For testing
7.4.1 Identification (name and designation) of test pile(s),
cast-in-place piles it is often advantageous to build up the top
of the pile to encase protruding reinforcement, to strengthen it 7.4.2 Required ultimate axial static compressive capacity,
for the impact using a steel shell, or to eliminate excessive 7.4.3 Type and dimensions of deep foundation(s) including
excavation (sensors must be mounted at least 1.5 diameters nominal or actual cross-sectional area, or both, length, wall
below the impact location). The pile top should be flat and thickness of pipe or casing, and diameter (as a function length
square to the longitudinal pile axis, and should be protected for tapered or composite deep foundations),
with plywood cushions, or other cushion material of uniform 7.4.4 For driven or cast-in-place concrete piles: date(s) test
thickness. A thick steel plate may also be placed on top of the pile constructed or cast, design and measured concrete cylinder
plywood to distribute the impact. Preferably apply a series of strengths and date of test(s), density, effective prestress, and
single impact blows using a drop mass having a weight of at description of internal and external reinforcement (type, grade,
least 1 to 2 % of the desired ultimate test capacity, beginning size, length, number and arrangement of prestress wire, longi-
with a low drop height to check transducer function and pile tudinal bars, lateral ties, and spiral stiffeners; casing or shell
stresses and then progressing to greater drop heights to size and length),
mobilize additional pile capacity. For externally mounted 7.4.5 For steel piles: steel designation, grade, minimum
transducers, carefully select transducer locations having sound yield strength, and type of pile (for example, seamless or spiral
concrete, and grind or sand the pile as necessary to obtain a weld pipe, H section designation),

No reproduction or networking permitted without license from IHS Not for Resale, 01/10/2016 04:50:31 MST
D4945 − 12
7.4.6 For timber piles: length, straightness, preservative appropriate the overall magnitude of the dynamic and static
treatment, tip and butt dimensions (and area as a function of axial compressive capacity mobilized at the time of testing, the
length), and measured density for each pile, distribution of the dynamic and static axial compressive
7.4.7 Description and location of splices, special pile tip capacity along the pile length, and the engineering properties
protection, and any special coatings applied if applicable, of the pile and the soil or rock adjacent to the pile as used in
7.4.8 Inclination angle from vertical, design and installed, the interpretation,
and 7.6.8 Comments on the performance of the impact device as
7.4.9 Observations of deep foundations including spalled measured by the energy transferred into the deep foundation
areas, cracks, head surface of deep foundations. with comparison to manufacturer’s rating or ram weight and
7.5 Deep Foundation Installation : drop height,
7.5.1 For cast-in-place piles, include the volume of concrete 7.6.9 Comments on the driving stresses within the deep
or grout placed in deep foundation (volume versus depth, if foundation, and whether measured or estimated through
available), and a description of installation procedures used, analysis,
such as casing installation or extraction, 7.6.10 Comments on the integrity of the deep foundation,
7.5.2 For driven piles, include date of installation, driving and
records with blow count, and hammer stroke or operating level 7.6.11 Numerical summary of measured and interpreted
for final unit penetration, results, with statistical analysis as appropriate, reporting time
7.5.3 Elevations of the pile top, pile bottom, and ground in milliseconds at the rate digitized, and other quantities with
surface referenced to a datum, and three significant digits, but not to exceed the precision of the
7.5.4 Cause and duration of installation interruptions and measurement.
notation of any unusual occurrences.
7.6 Dynamic Testing: 8. Precision and Bias
7.6.1 Description of the dynamic test apparatus, including 8.1 Precision—Test data on precision is not presented due to
make, model, analog or digital velocity integration, sampling the nature of this test method. It is either not feasible or too
rate, transducers, measurement location(s), etc., costly at this time to have ten or more agencies participate in
7.6.2 Date of test(s), sequence of testing (for example, “end an in situ testing program at a given site. The inherent
of driving” or “beginning of restrike”), and elapsed time since variability of the soil, or rock, or both surrounding the pile, the
end of initial driving for restrikes, pile driving apparatus, and the pile itself adversely affect the
7.6.3 Density, wave speed, and dynamic modulus of elas- determination of precision.
ticity of the test deep foundation, reporting each quantity with 8.1.1 The Subcommittee D18.11 is seeking any data from
three significant digits, but not to exceed the precision of the the users of this test method that might be used to make a
measurement, limited statement on precision.
7.6.4 Penetration resistance (blows per unit penetration, or
set per blow) and embedment depth, 8.2 Bias—There is no accepted reference value for this test
7.6.5 Graphical presentation of velocity and force measure- method, therefore bias cannot be determined.
ments in the time domain for representative blows,
7.6.6 Analysis method(s) used to interpret or evaluate test 9. Keywords
measurements, 9.1 augered piles; deep foundations; drilled shafts; driven
7.6.7 Interpretation of the test measurements, including piles; driving stresses; dynamic testing; pile bearing capacity;
measurements down the pile if applicable, to estimate as pile driving hammer performance; pile integrity

ASTM International takes no position respecting the validity of any patent rights asserted in connection with any item mentioned
in this standard. Users of this standard are expressly advised that determination of the validity of any such patent rights, and the risk
of infringement of such rights, are entirely their own responsibility.

This standard is subject to revision at any time by the responsible technical committee and must be reviewed every five years and
if not revised, either reapproved or withdrawn. Your comments are invited either for revision of this standard or for additional standards
and should be addressed to ASTM International Headquarters. Your comments will receive careful consideration at a meeting of the
responsible technical committee, which you may attend. If you feel that your comments have not received a fair hearing you should
make your views known to the ASTM Committee on Standards, at the address shown below.

This standard is copyrighted by ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959,
United States. Individual reprints (single or multiple copies) of this standard may be obtained by contacting ASTM at the above
address or at 610-832-9585 (phone), 610-832-9555 (fax), or service@astm.org (e-mail); or through the ASTM website
(www.astm.org). Permission rights to photocopy the standard may also be secured from the Copyright Clearance Center, 222
Rosewood Drive, Danvers, MA 01923, Tel: (978) 646-2600; http://www.copyright.com/

--`,`,,,``,``,`,``,,,,````,,,`,,-`-`,,`,,`,`,,`---

No reproduction or networking permitted without license from IHS Not for Resale, 01/10/2016 04:50:31 MST

You might also like