Module 6 - EVM1 - W22 - PMPG5013 - NB
Module 6 - EVM1 - W22 - PMPG5013 - NB
Management
Module 6 – Winter 2022
Public
Project Progress and Performance Measurement
Public
Module 6: Agenda
• Review Quiz 4
• Cost Monitoring & Control: Earned Value
Management
• In-class Exercises
• Quiz #5
3
Project Cost Management Processes
Plan Cost Management
• Establishes the policies, procedures, and documentation for
planning, managing, expending, and controlling project costs
COST MANAGMENT
Estimate Costs
• Developing an approximation of the monitory resources
needed to complete project activities
Determine Budget
• Aggregating the estimated costs of individual work packages
to establish an authorized cost baseline
Control Costs
• Monitoring the status of the project to update the
project costs and managing changes to the cost
4
baseline
EVM
• WHAT IS EVM?
5
CONTROL COSTS – Tools & Techniques
• DATA ANALYSIS
100000
80000
Projected
60000
Actual
40000
20000
0
Jan-03 Feb-03 Mar-03 Apr-03 May-03 Jun-03 Jul-03 Aug-03 Sep-03 Oct-03 Nov-03 Dec-03
7
Glossary of Terms
EV Earned value for a task is simply the percent complete times its original budget. Stated differently,
EV is the percent of the original budget that has been earned by actual work completed.
PV The planned time-phased baseline of the value of the work scheduled. An approved cost estimate
of the resources scheduled in a time-phased cumulative baseline [BCWS—budgeted cost of the
work scheduled].
AC Actual cost of the work completed. The sum of the costs incurred in accomplishing work.
[ACWP—actual cost of the work performed].
CV Cost variance is the difference between the earned value and the actual costs for the work
completed to date where CV = EV – AC.
SV Schedule variance is the difference between the earned value and the baseline line to date where
SV = EV – PV.
BAC Budgeted cost at completion. Total budgeted cost of the baseline or project cost accounts.
VAC Cost variance at completion. VAC indicates expected actual over- or under-run cost at completion.
8
Development of Project Baselines
• Purposes of a Baseline (PV)
– An anchor point for measuring performance
• A planned cost and expected schedule against
which actual cost and schedule are measured.
• A basis for cash flows and awarding progress payments.
• A summation of time-phased budgets (cost accounts as
summed work packages) along a project timeline.
• What Costs Are Included in Baselines?
– Labor, equipment, materials, project direct overhead
costs (DOC)
9
Planned Value (PV) /
Budgeted Cost of Work Scheduled (BCWS)
10
Planned Value (PV) /
Budgeted Cost of Work Scheduled (BCWS)
120000
100000
80000
60000 BCWS
40000
20000
0
May-…
Aug-03
Sep-03
Dec-03
Nov-03
Oct-03
Apr-03
Feb-03
Mar-03
Jul-03
Jan-03
Jun-03
11
Earned Value (EV) /
Budgeted Cost of Work Performed (BCWP)
12
Earned Value (EV) /
Budgeted Cost of Work Performed (BCWP)
120000
100000
80000
55000 BCWP
60000
49000 BCWS
40000
20000
Nov-03
Jan-03
Jun-03
Jul-03
Feb-03
Mar-03
Apr-03
May-03
Aug-03
Sep-03
Dec-03
Oct-03
13
Actual Cost (AC) /
Actual Cost of Work Performed (ACWP)
14
Actual Cost (AC) /
Actual Cost of Work Performed (ACWP)
120000
100000
80000
56000 BCWP
60000
ACWP
49000
40000
20000
Nov-03
Jan-03
Jun-03
Jul-03
Feb-03
Mar-03
Apr-03
May-03
Aug-03
Sep-03
Dec-03
Oct-03
15
Methods of Variance Analysis
16
Methods of Variance Analysis (cont.)
18
Earned-Value Exercise
19
Indexes to Monitor Progress
Performance Indexes
20
Interpretation of Indexes
21
EVM & Basic Project Management Questions
22
Common Terms and Interpretations
23
Formulas
Name Formula
Cost Variance (CV) EV – AC
Schedule Variance (SV) EV – PV
Cost Performance Index (CPI) EV / AC
Schedule Performance Index (SPI) EV / PV
Estimate at Completion (EAC) BAC / CPI
Estimate to Complete (ETC) EAC – AC
Variance at Completion (VAC) BAC - EAC
24
References
25
EVM 1 In-class Exercises
26
Public
Next Week: Agenda
• Review Quiz #5
• Individual Assignment Overview
• Mid-term Exam –When/Where/Structure etc
• Mid-term Exam review/exercises
27
QUIZ #5
WHEN YOU ARE DONE your Quiz, COST CLASS IS FINISHED! See
you next week!
28
PMPG 5013
THANK YOU.