ESTIMATION OF TOTAL CAPITAL INVESTMENT (TCI)

Sr. Particular % of Cost in Rs.


No. equipment
cost
Direct plant Cost
1. Purchase equipment cost - 12,77,68,000/-

2. Installation cost 35% 4,47,18,800/-


3. Instrumentation and control 15% 1,91,65,200/-
4. Piping cost 30% 3,83,30,400/-
5. Electrical cost 20% 2,55,53,600/-

6. Building 25% 3,19,42,000/-


7. Services Facilities 10% 5,11,07,200/-
8. Land improvement 2% 1,02,21,440/-
9. Land 2% 1,02,21,440/-
Indirect Plant cost
11. Construction and legal expenses 12% 4,29,30,048/-
12. Engineering and supervision 15% 5,36,62,560/-
13. Contingencies 10% 3,57,75,421/-
14. Legal expenses 2% 71,55,231/-
Total 49,72,73,056/-