You are on page 1of 1

TRANSMISION ZONA III BARINAS

S/E CIUDAD BOLIVIA


ACTUALIZADO POR :
SOCOPO BARINAS IV ING. ESTRADA RAFAEL

T.P N° II DE 115 KV
(S,T) (S,T)
T.P N° I DE 115 KV 21/05/2012
H201 H101

H203 H103

115 Kv BP

H214
DISTANCIA ENTRE PLANTA
Y S/E: 250 metros
H110

PLANTA CIUDAD BOLIVIA TRAFO No. 1


115/13.8 Kv
32 GENERADORES
DE 450 KVA C/U 20 MVA
D190

D193 D183
9.72 MW
S.A. C.A 13.8 Kv
BARRA “A” 13.8 KV D180 110 V
13.8 KV
18 GENERADORES 110-220 V D184
DE 500 KVA C/U D290 D190
B.P DE 13.8 KV

6.08 MW D293 D494


D404 D304 D204 D104 D134
20 GENERADORES
BARRA “B” 13.8 KV
DE 450 KVA C/U D405 D305 D130
D390 D205 D105

D403 D303
D393 D203 D103 D136
6.85 MW
13.8 Kv
220-110 V D406 D306 D206 D106
BARRA “C” 13.8 KV
B.T 13.8 KV

B.P DE 13.8 KV D401 D301 D201 D101


FUNDACEA CIUDAD CIUDAD
CURBATI
BOLIVIA II BOLIVIA I

You might also like