Revision: A O_103_ATSS_001_Method Statement Date: 03/08/2019

Method Statement
Department : Utility - building Submitted by : Date :
Process : Approved By :
Permit
Method / Steps / Tasks Risk Area Duration No. of Person PPE Required
Needed
Cleaning listplank / façade

full body harnest,Helmet,


1 Install / fabrikasi Scaffolding 5 days 8 Pekerja safety shoes, Safety gloves, work at hight
safety glasses

full body harnest,Helmet,


Cleaning listplank / façade (menggunakan detergen (Sunlight) dan air 1:20. Manlifting
2 60 days 8 Pekerja + 2 org Operator safety shoes, Safety gloves, work at hight
menggunakan boomlift dan scaffolding) safety glasses & Masker