This document contains a project progress report with the following information:
1) It reports on the progress of various construction tasks over the past week and in total to date, showing the planned progress, actual progress, and deviation.
2) The overall project progress to date is reported as 38.85%, which is ahead of the planned progress of 30.05% by 8.80%.
3) In conclusion, the project is progressing faster than planned according to the report.
Original Description:
pembangunan unit rumah dan renovasi
Original Title
Contoh _LAPORAN PROGRESS_MINGGU III_21-26 MARET 2022
This document contains a project progress report with the following information:
1) It reports on the progress of various construction tasks over the past week and in total to date, showing the planned progress, actual progress, and deviation.
2) The overall project progress to date is reported as 38.85%, which is ahead of the planned progress of 30.05% by 8.80%.
3) In conclusion, the project is progressing faster than planned according to the report.
This document contains a project progress report with the following information:
1) It reports on the progress of various construction tasks over the past week and in total to date, showing the planned progress, actual progress, and deviation.
2) The overall project progress to date is reported as 38.85%, which is ahead of the planned progress of 30.05% by 8.80%.
3) In conclusion, the project is progressing faster than planned according to the report.