Dayalbagh Educational Institute

Question Paper-ARM 603 (2020-2021) CT-I

B.Arch-3rd Yr.

Estimation Costing and Specifications


Time:-100 Minutes

Total marks: 40

Attempt Any Five questions Question No. -1 is compulsory

Each question carries equal marks

1. Find out the any six Quantities in given figure assume dimension yourself where
missing?
2. What is Estimate?
3. Describe the importance of estimate?
4. What is the difference between MKS and SI system of units?
5. Write down the unit of Brick work, plaster, Earth work in excavation, Skirting, RCC,
White washing , Wooden work, Flooring, laying of bitumen, False ceiling.
6. Analyze the rate of Earth work in excavation in per Cubic meter assume suitable data?
7. Calculate the quantity of cement concrete used in lintel, for door of width 1.20 m. also
calculate the quantity of Steel?