Rate Comparision sheet for Mitali Vs Ronak Construction

Rates given to Rate prop. by Old Rates -


Sr. No. Description Unit Mitali Ronak Ronak
Construction Construction Construction
Excavation work 0.0 to 1.5 mtr-By hydraulic machine, including site
1 clearance & other relevant works Cmt 80 80

2 Excavation work 1.5 to 3.0 mtr-By hydraulic machine Cmt 90 90 75


3 Excavation work 3.0 to 4.5 mtr-By hydraulic machine Cmt 100 100
4 Excavation work 4.5 to 6.0 mtr-By hydraulic machine Cmt 110 110
Excavation by manual means for all depths including site clearance &
5 other relevant works Cmt 350 350 350

6 Excavated material Carting 3 km lead from the site Cmt 120 120 NA
7 Soil Re-filling work as per specification Cmt 45 40 40
Providing and laying P.C.C. Work 1:3:6 M-10 complete as per
8 specification. Cmt 2950 2900 2950

R.C.C. Work with providing & laying M-20 concrete, cutting, bending &
9 fixing of reinforcement with binding wire, shuttering and compaction etc. Cmt 6225 6000 NA
complete as per satisfaction of site-in-charge.
10 Brick masonry 0.0 to 1.5 mtr Depth, complete as per specification Cmt 3400 3350
2600
11 Brick masonry 1.5 to 3.0 mtr Depth, , complete as per specification Cmt. 3400 3350

Plaster work 15mm thick including labour & material, complete as per
12 specification. Smt. 160 150 90

Providing & fixing FRC SHEET COVER with frame SIZE (0.9x0.9x0.15mm
13 0.6 Dia) Nos. 6500 6500 NA

14 300 mm pipe Lowering, Laying and Jointing complete Labour charge R.mtr 150 140 113

15 450 mm pipe Lowering, Laying and Jointing complete Labour charge R.mtr 215 210 196

16 600 mm pipe Lowering, Laying and Jointing complete Labour charge R.mtr 300 300 NA

17 900 mm pipe Lowering, Laying and Jointing complete Labour charge R.mtr 350 340 102.35

18 1000mm pipe Lowering, Laying and Jointing complete Labour charge R.mtr 450 430 NA

19 1200 mm pipe Lowering, Laying and Jointing complete Labour charge R.mtr 650 640 418.3

20 1400 mm pipe Lowering, Laying and Jointing complete Labour charge R.mtr 725 700 NA

21 1600 mm pipe Lowering, Laying and Jointing complete Labour charge R.mtr 825 800 NA

22 1800 mm pipe Lowering, Laying and Jointing complete Labour charge R.mtr 925 900 679.426

23 FRC Cover with frame fixing labour charge (Frame By RBL) Nos. 1200 1100 730

24 CATCHPIT lowering and rising without FRC cover (By RBL) Nos. 1200 1100 700

25 Manhole lowering and rising without FRC cover Nos. 1550 1500 NA
26 Foot step fixing with material and labour work Nos. 215 200 47.6
27 300 to 1200 mm pipe dummy and joint connection Nos. 3500 3500 1500

28 300 mm DI pipe Lowering, Laying and Jointing complete Labour charge R.mtr NA 110 110

29 250 mm DI pipe Lowering, Laying and Jointing complete Labour charge R.mtr NA 90 90

30 150 mm DI pipe Lowering, Laying and Jointing complete Labour charge R.mtr NA 65 65

31 Making Connection DI pipe 150/250 mm dia. Nos. NA 1100 1500


32 Breakdown repair DI pipe Nos. NA 1100 1100
Gate Valve fixing 250 MM dia. Nos. NA 1700 1680
Gate Valve fixing 150 MM dia. Nos. NA 900 895
33
Gate Valve fixing 300 MM dia. Nos. NA NA 2115
Gate Valve fixing 450 MM dia. Nos. NA NA 4675
34 Bend, Tee, Reducer etc. (DI special) kg NA 12 12