Professional Documents
Culture Documents
Method Statement - Testing & Commissioning
Method Statement - Testing & Commissioning
(989689-M)
CIDB REGISTERED PLUMBING CONTRACTOR
No.G-1-7, Pusat Komersial Jalan Kuching, Jalan Kepayang, Off Jalan
Kuching, 51200 Kuala Lumpur.
Tel: 03-6242 9689 Fax: 03-6241 9589 Email: yllplumbing@gmail.com
PROJECT TITLE :
……………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………
……………………………………………………………………………………………………………………………
B - Approved With Comments. Contractor id allowed to proceed with the works. Resubmission is required.
C - Rejected. The contractor is not allowed to proceed with the works. Resubmission is required.
Commented By :
(M&E Engineer) Signature : …………………………… Date : …………………………….
CADANGAN PEMBANGUNAN 1 BLOK PEJABAT 47 TINGKAT YANG MENGANDUNGI:
I. 43 TINGKAT PEJABAT PERDAGANGAN
II. 4 TINGKAT TEMPAT LETAK KERETA BESERTA 3 TINGKAT LETAK KERETA BAWAH TANAH
DI ATAS PT 169(PLOT 5 (C7.9)) “TUN RAZAK EXCHANGE”, SEKSYEN 67, JALAN TUN RAZAK, BANDAR KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR UNTUK TETUAN AFFIN BANK BERHAD.
PACKAGE 4 - MAIN BUILDING WORKS
TABLE OF CONTENTS
1.0 Objective…………………………………………………………………….......................................... 3
2.0 Scope…………………………………………………………………………………………………… 3
3.0 Definition……………………………………………………………………………………………..... 3
4.0 Responsibilities……………………………………………………………………………………….... 3
5.0 T&C For Pumpset Functional Test…………………………………………………………………….. 3
6.0 T&C For Soil Pipe Flow Test…..…………………………………………………………………….... 5
7.0 T&C For RWDP Flow Test…...……………………………………………………………………….. 6
8.0 T&C For Water Tank Chlorine Sanitization Test……………………………………………………… 8
9.0 T&C For WC Flushing Test…………………………………………………………………………… 9
2
CADANGAN PEMBANGUNAN 1 BLOK PEJABAT 47 TINGKAT YANG MENGANDUNGI:
I. 43 TINGKAT PEJABAT PERDAGANGAN
II. 4 TINGKAT TEMPAT LETAK KERETA BESERTA 3 TINGKAT LETAK KERETA BAWAH TANAH
DI ATAS PT 169(PLOT 5 (C7.9)) “TUN RAZAK EXCHANGE”, SEKSYEN 67, JALAN TUN RAZAK, BANDAR KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR UNTUK TETUAN AFFIN BANK BERHAD.
PACKAGE 4 - MAIN BUILDING WORKS
1.0 Objective
- The purpose of this method statement is to describe the outline of Testing & Commissioning for overall
plumbing services.
2.0 Scope
3.0 Definition
- This method statement describes the Testing & Commissioning procedure for the completed CWSP & RWDP
at the AFFIN BANK BERHAD Tower from basement 3 to roof
4.0 Responsibilities
- Site Supervisor
- Project Coordinator
- Project / Site Manager
5.1 References
3
CADANGAN PEMBANGUNAN 1 BLOK PEJABAT 47 TINGKAT YANG MENGANDUNGI:
I. 43 TINGKAT PEJABAT PERDAGANGAN
II. 4 TINGKAT TEMPAT LETAK KERETA BESERTA 3 TINGKAT LETAK KERETA BAWAH TANAH
DI ATAS PT 169(PLOT 5 (C7.9)) “TUN RAZAK EXCHANGE”, SEKSYEN 67, JALAN TUN RAZAK, BANDAR KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR UNTUK TETUAN AFFIN BANK BERHAD.
PACKAGE 4 - MAIN BUILDING WORKS
- Pressure Gauges
- Clamp Ammeter
- Portable Hand tools
- Tachometer
- Note the details of each motor such as make, model number, frame size, KW rating and
RPM
- Check that the Chiller water & Condenser pump piping network is complete with proper
valves, pressure switches and instruments in place as per final approved shop drawing.
- Ensure the pump shafts are rotated by hand freely.
- Ensure that electrical power connections and earthing is proper.
- Ensure that the field wiring is pre-tested for continuity and insulation resistance.
- Ensure that all the relevant valves are in open position. Pump discharge valve should be in
closed position. Direction of rotation and RPM shall be checked during commissioning.
- Check the pumps are properly bolted
- Check for proper installation of pressure
gauges. Check identification and labeling
for equipment.
4
CADANGAN PEMBANGUNAN 1 BLOK PEJABAT 47 TINGKAT YANG MENGANDUNGI:
I. 43 TINGKAT PEJABAT PERDAGANGAN
II. 4 TINGKAT TEMPAT LETAK KERETA BESERTA 3 TINGKAT LETAK KERETA BAWAH TANAH
DI ATAS PT 169(PLOT 5 (C7.9)) “TUN RAZAK EXCHANGE”, SEKSYEN 67, JALAN TUN RAZAK, BANDAR KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR UNTUK TETUAN AFFIN BANK BERHAD.
PACKAGE 4 - MAIN BUILDING WORKS
6.1 Reference
- Buckets
- Adequate Water Supply
- Check and ensure that piping to be tested has sufficient hangers and brackets.
5
CADANGAN PEMBANGUNAN 1 BLOK PEJABAT 47 TINGKAT YANG MENGANDUNGI:
I. 43 TINGKAT PEJABAT PERDAGANGAN
II. 4 TINGKAT TEMPAT LETAK KERETA BESERTA 3 TINGKAT LETAK KERETA BAWAH TANAH
DI ATAS PT 169(PLOT 5 (C7.9)) “TUN RAZAK EXCHANGE”, SEKSYEN 67, JALAN TUN RAZAK, BANDAR KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR UNTUK TETUAN AFFIN BANK BERHAD.
PACKAGE 4 - MAIN BUILDING WORKS
7.1 Reference
- Buckets
- Adequate Water Supply
6
CADANGAN PEMBANGUNAN 1 BLOK PEJABAT 47 TINGKAT YANG MENGANDUNGI:
I. 43 TINGKAT PEJABAT PERDAGANGAN
II. 4 TINGKAT TEMPAT LETAK KERETA BESERTA 3 TINGKAT LETAK KERETA BAWAH TANAH
DI ATAS PT 169(PLOT 5 (C7.9)) “TUN RAZAK EXCHANGE”, SEKSYEN 67, JALAN TUN RAZAK, BANDAR KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR UNTUK TETUAN AFFIN BANK BERHAD.
PACKAGE 4 - MAIN BUILDING WORKS
a) Roof to Level 27
- Check and ensure that piping to be tested has sufficient hangers and brackets.
- Ensure the water discharge from the collection area reached rainwater harvesting tank at level 27.
b) Level 27 to P1
- Before the water discharge enters to the RWHT, ensure the water discharge is flow through the first flush
filter in order to remove any dirt or leaves so that only clean water enters the tank.
- From the RWHT, ensure the overflow discharge reach rainwater harvesting tank at P1
7
CADANGAN PEMBANGUNAN 1 BLOK PEJABAT 47 TINGKAT YANG MENGANDUNGI:
I. 43 TINGKAT PEJABAT PERDAGANGAN
II. 4 TINGKAT TEMPAT LETAK KERETA BESERTA 3 TINGKAT LETAK KERETA BAWAH TANAH
DI ATAS PT 169(PLOT 5 (C7.9)) “TUN RAZAK EXCHANGE”, SEKSYEN 67, JALAN TUN RAZAK, BANDAR KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR UNTUK TETUAN AFFIN BANK BERHAD.
PACKAGE 4 - MAIN BUILDING WORKS
8.1 Reference
- N/A
- Chlorine
- Adequate Water Supply
- Ensure all the valves for the water tank is tightly closed after water is fully filled
- Once the water tank is full, pour in the chlorine inside the water tank and leave for 24 hours to let the chlorine
absorb all the dirt inside the water tank.
- After 24 hours, open back the drain valve to release all the dirt water which absorbed by chlorine.
8
CADANGAN PEMBANGUNAN 1 BLOK PEJABAT 47 TINGKAT YANG MENGANDUNGI:
I. 43 TINGKAT PEJABAT PERDAGANGAN
II. 4 TINGKAT TEMPAT LETAK KERETA BESERTA 3 TINGKAT LETAK KERETA BAWAH TANAH
DI ATAS PT 169(PLOT 5 (C7.9)) “TUN RAZAK EXCHANGE”, SEKSYEN 67, JALAN TUN RAZAK, BANDAR KUALA
LUMPUR, WILAYAH PERSEKUTUAN KUALA LUMPUR UNTUK TETUAN AFFIN BANK BERHAD.
PACKAGE 4 - MAIN BUILDING WORKS
- Ensure the water is full inside the cistern before start the flushing test.
- Press the Flush button and monitor the WC outlet for the flush water discharge.
- If the water flows freely and did not backflows, then the test is considered successful.