ID WBS Task Task Name Duration Start Finish Cost Jul '20 Aug '20 Sep '20 Oct

Cost Jul '20 Aug '20 Sep '20 Oct '20 Nov '20 Dec '20
Mode W-2 W1 W3 W5 W7 W9 W11 W13 W15 W17 W19 W21 W23
0 0 Three Story RCC Building 104 days 7/30/20 12/10/20 80,776,232 K 0%
1 1 Preliminary Work 2 days 7/30/20 8/4/20 650,000 K 0%
2 1.1 Site Clearing Work 1 day 7/30/20 7/30/20 50,000 K
3 1.2 Surveying, Setting Out &  1 day 8/4/20 8/4/20 600,000 K
Levelling Work
4 2 Sub Structure Work 30 days 8/5/20 9/8/20 15,955,329 K 0%
5 2.1 Earthwork Excavation For 4 days 8/5/20 8/8/20 1,360,080 K 0%
Foundation
8 2.2 Hardcore Work with Sand 1 day 8/10/20 8/10/20 1,364,685 K
Filling for Foundation
9 2.3 Lean Concrete Work For 4 days 8/11/20 8/14/20 1,491,775 K 0%
Foundation
16 2.4 M.S Rod Cut, Bend & Fixing Work 8 days 8/14/20 8/22/20 3,754,365 K 0%
for Foundation
21 2.5 Form Work for Foundation (3  9 days 8/24/20 9/2/20 2,085,396 K 0%
times used)
26 2.6 (1:2:4) RC Concrete Work for  5 days 9/3/20 9/8/20 3,730,515 K 0%
Foundation (Up to Plinth)
31 2.7 Brick walling with (1:4) Cement  6 days 8/15/20 8/21/20 2,168,514 K 0%
Mortar (Up to Plinth)
34 3 Super Structure Work 39 days 9/9/20 10/23/20 44,991,878 K 0%
35 3.1 Compacted Sand Filling Work  3 days 9/9/20 9/11/20 434,700 K
Under Ground Floor Slab
36 3.2 4.5" thk; (1:3:6) Concrete  1 day 9/12/20 9/12/20 963,900 K
Flooring Work
37 3.3 1.5" thk; (1:2:4) Concrete  1 day 9/14/20 9/14/20 519,750 K
Flooring Work
38 3.4 3/4" thk Plastering with (1:3)  2 days 9/15/20 9/16/20 142,875 K
Cement Mortar (Up to Plinth)
39 3.5 M.S Rod Cut, Bend & Fixing Work 13 days 9/9/20 9/23/20 3,907,713 K 0%
Ground Floor to First Floor
45 3.6 Form Work for Ground Floor to  11 days 9/12/20 9/24/20 7,100,642 K 0%
First Floor(3 times used)
51 3.7 (1:2:4) RC Concrete Work for  5 days 9/25/20 9/30/20 3,396,193 K 0%
Ground Floor to First Floor
57 3.8 M.S Rod Cut, Bend & Fixing Work 11 days 9/11/20 9/23/20 3,455,436 K 0%
for First Floor to Second Floor
63 3.9 Form Work for First Floor to  9 days 9/25/20 10/5/20 6,276,006 K 0%
Second Floor (3 times used)
69 3.10 (1:2:4) RC Concrete Work for  5 days 10/6/20 10/10/20 2,964,686 K 0%
First Floor to Second Floor
75 3.11 M.S Rod Cut, Bend & Fixing Work 11 days 9/23/20 10/5/20 4,113,887 K 0%
for Second Floor to Top Floor 
81 3.12 Form Work for Second Floor to 11 days 10/6/20 10/17/20 7,911,922 K 0%
Top Floor and Roof(3 times
87 3.13 (1:2:4) RC Concrete Work for  5 days 10/19/20 10/23/20 3,804,168 K 0%
Second Floor to Top Floor and 
93 4 Architectural Work 48 days 10/7/20 12/10/20 19,179,025 K 0%
94 4.1 4 1/2"thk; Brick Walling With 28 days 10/7/20 11/12/20 6,271,736 K 0%
(1:3) Cement Motar
98 4.2 M.S Rod Cut, Bend & Fixing 7 days 10/10/20 10/17/20 1,059,351 K 0%
Work for Stiffner & Lintel
102 4.3 Form Work for Stiffner and 7 days 10/13/20 10/20/20 4,935,600 K 0%
Lintel(3 times used)
106 4.4 (1:2:4) RC Concrete Work for  3 days 10/14/20 10/16/20 2,467,800 K 0%
Stiffner and Lintel
110 4.5 3/4" thk Plastering with (1:3)  20 days 11/13/20 12/10/20 4,444,538 K 0%
Cement Mortar