ID Task Task Name Duration Start Finish PredecessorsResource % Complete October 2021 November 2021 December 2021 January

% Complete October 2021 November 2021 December 2021 January 202


Mode Names 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 1
1 Open a coffee shop 66 days 10/1/21 12/31/21 51%
2 Startup 10 days 10/1/21 10/14/21 100%
3 Determine the budget 4 days 10/1/21 10/6/21 NghiaHTY 100% NghiaHTY
4 Define project scope 4 days 10/7/21 10/12/21 3 NghiaHTY 100% NghiaHTY
5 Cost estimate. 2 days 10/13/21 10/14/21 4 NghiaHTY 100% NghiaHTY
6
7 Estimated completion time 4 days 10/1/21 10/6/21 ThaoTN 100% ThaoTN
8 Resource management and 4 days 10/7/21 10/12/21 7 ThaoTN 100% ThaoTN
control plan
9 Marketing plan 2 days 10/13/21 10/14/21 8 ThaoTN 100% ThaoTN
10
11 Ideas for the shop 4 days 10/1/21 10/6/21 TramTTM 100% TramTTM
12 Drinking water survey 2 days 10/7/21 10/8/21 11 TramTTM 100% TramTTM
13 Evaluate and list countries 4 days 10/11/21 10/14/21 12SF TramTTM 100% TramTTM
14
15 Survey the location of 4 days 10/1/21 10/6/21 SuongNTK 100% SuongNTK
opening the shop
16 Evaluation of choosing a place 4 days 10/7/21 10/12/21 15 SuongNTK 100% SuongNTK

17 Deal price and sign contract 2 days 10/13/21 10/14/21 16 SuongNTK 100% SuongNTK
18
19 Make an application for 3 days 10/1/21 10/5/21 AnhDTK 100% AnhDTK
license registration
20 Apply for license registration 3 days 10/6/21 10/8/21 19 AnhDTK 100% AnhDTK

21 Material supplier survey 3 days 10/11/21 10/13/21 20 AnhDTK 100% AnhDTK


22 Evaluation Choose a raw 1 day 10/14/21 10/14/21 21 AnhDTK 100% AnhDTK
material supplier
23
24 Deal price and sign contract of 5 days 10/1/21 10/7/21 LocDB 100% LocDB
raw material supplier
25 Drawing Interior Layout 5 days 10/8/21 10/14/21 24 LocDB 100% LocDB
Diagram
26
27 Drawing Electrical Layout 5 days 10/1/21 10/7/21 MyHTD 100% MyHTD
Diagram
28 Draw a Water Pipe Diagram 5 days 10/8/21 10/14/21 27FF MyHTD 100% MyHTD
29 Buy furniture 7 days 10/15/21 10/25/21 100%
37 Buy machines, tools for 7 days 10/26/21 11/3/21 100%
preparing drinks, serving tools
45 Construction 20 days 11/4/21 12/1/21 48%
46 Service bar 7 days 11/4/21 11/12/21 NghiaHTY 45% NghiaHTY
47 Cashier counter 7 days 11/15/21 11/23/21 46 NghiaHTY 55% NghiaHTY

Task Project Summary Manual Task Start-only Deadline

Project: NghiaHTY_180303_Ope Split Inactive Task Duration-only Finish-only Progress


Date: 11/11/21 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone