Faculty of Engineering Semester SPRING 2021

Course Code: MEN4233 Course Title: POWER PLANTS


Maximum Marks: 20 Duration: 90 mins

Note:
 10 minutes time is allowed for scanning and uploading the result on MS Teams
after the exam ends.
 In case you can’t upload the result on MS Teams; whatsapp (03006646606) the
result.
 Your result should only be a single pdf file. Name the pdf file with the following
format: F17-XXXX MA YourName .
 Write your name, roll number on top of your answer paper.
 You have to remain signed in on TEAMS during the entire period of your exam.
You will be marked absent if you leave TEAMS.

QUESTION # 1: [CLO1 – C2] (5 Marks)

i) Flue gas treatment is a process designed to reduce the amount of pollutants emitted from the burning
of fossil fuels at an industrial facility, a power plant, or another source. Summarize!

QUESTION # 2: [CLO3 – C4] (7+4+4 Marks)

i) In a gas turbine cycle, reheating, intercooling and regeneration are usually applied in order to improve the
overall performance of the cycle. What are these processes and where are they applied. How do they impact
the performance of gas turbine cycle. Illustrate!
ii) What criterion should a gas turbine combustor fulfill to achieve the best design option. Illustrate!
iii) What are steam generators? Illustrate their working with complete diagram. Also explain their types.