Professional Documents
Culture Documents
1 UPAH KERJA
1 Tukang 125,000.00 HOK
2 Pekerja 80,000.00 HOK
3 Pekerja (Lansir Material) 80,000.00 HOK
2 BAHAN / MATERIAL
1 Tanah Timbun 134,500.00 M3
2 Pasir Urug 115,000.00 M3
3 Pasir Pasang 127,000.00 M3
4 Sirtu 127,625.00 M3
5 Batu Pecah 2-3cm 341,750.00 M3
5 Kerikil Cor 334,250.00 M3
6 Batu Kali (Batu Mangga) 126,250.00 M3
7 Batu Kali 126,250.00 M3
8 Kayu Papan Bekisting 3,500,000.00 M3
9 Bambu (dia. 8-10 cm) 8,400.00 M
10 Baut + Muur 10 mm (5 cm) 2,500.00 Bh
11 Plat Bunga 3mm 1,080,000.00 Lbr
12 Papan Kayu (300x20x4)cm 3,640,000.00 M3
14 Besi Beton Ø 12mm 22,000.00 Kg
15 Besi Beton Ø 8mm 22,000.00 Kg
Kawat Beton 23,000.00 Kg
16 Besi Siku 50.50.5 208,000.00 Btg
17 Semen @ 50 kg/zak 76,000.00 Zak
18 Semen Warna 4,200.00 Kg
19 Kayu Kelas III 2,600,000.00 M3
20 Kayu Kelas II 3,640,000.00 M3
21 Kayu Balok 5/7 cm 3,640,000.00 M3
22 Papan Kayu (300x20x4)cm 3,640,000.00 M3
23 Kayu Papan 3,640,000.00 M3
24 Kayu Cerucuk Ø8-10cm 24,500.00 M
25 Kayu Dolken Ø8-10cm 50,400.00 Btg
26 Balok Kayu Kelas III 2,600,000.00 M3
27 Balok Kayu 3,500,000.00 M3
BAHAN / MATERIAL
Kaema Telaumbanua X5
No. Uraian Harga (Rp) Satuan Ket.
BAHAN / MATERIAL
68 Bola Lampu TL 23 W 45,400.00 Bh
69 Saklat Tunggal 10,700.00 Bh
70 Saklar Ganda 17,300.00 Bh
71 Stop Kontak 64,100.00 Bh
72 Closet Jongkok 312,000.00 Bh
73 Kran Air 1/2" 29,900.00 Bh
74 Bak Air Fiber 650,000.00 Bh
75 Pipa Dia 1/2" 18,100.00 M
76 Pipa Dia 3" 51,300.00 M
77 Pipa Dia 4" 77,100.00 M
78 Lubang Angin Beton 8,500.00 Bh
3 ALAT
1 Kereta Sorong 663,000.00 Unit
2 Gergaji Kayu 35,000.00 Bh
3 Palu 163,600.00 Bh
4 Ember Kecil 8,000.00 Bh
5 Skop 52,000.00 Bh
Kakak Tua 25,000.00 Bh
6 Benang 3,000.00 Bh
7 Cangkul 132,600.00 Bh
8 Sewa Bor Listrik 251,200.00 Hr
10 Sewa Mesin Las 1,500,000.00 Hr
11 Sendok Semen 25,000.00 Bh
Kaema Telaumbanua X5
Progaram : Program Pembangunan dan Pemberdayaan Masyarakat Desa
Kabupaten : X1
Kecamatan : X2
Desa : X3
Kades : X4
Nip. :
FK :
FT :
TPK : X5
Tanggal : 2018
Volume Lokasi
Kegiatan 1 : Pemb. Parit Beton Lap. Sepak Bol436,5 Meter Dusun II
Kegiatan 2 : Pemb. Plat Duiker 1 Unit Dusun II
Kegiatan 3 : Pemb. Pagar Lapangan Bola #NAME? Dusun III
Kegiatan 4 : Pemb. Parit Beton (Ruas II) 135 Meter Dusun II
Kegiatan 5 :
akat Desa
125
200
Dusun III 90
70
70
DAFTAR HARGA SATUAN UPAH, BAHAN DAN ALAT
Bidang : Pelaksanaan Pembangunan Desa
Desa : X3
Tahun Anggaran : 2018
III. PERALATAN
1 Kereta Sorong 663,000.00 Unit
2 Skop 52,000.00 Bh
3 Raskam 23,000.00 Bh
4 Sendok Semen 24,000.00 Bh
5 Benang 2,900.00 Bh
6 Kakak Tua 25,100.00 Bh
7 Ember Kecil 8,000.00 Bh
8 Cangkul 132,600.00 Bh
9 Sewa Chainsaw 250,000.00 Hr
X3, 2018
Disetujui/ Mengesahkan Tim Penyusun RKPDes/
Kepala Desa X3 Kader Teknis
X4 X5
PERHITUNGAN BIAYA LANGSIR BAHAN
PEMBANGUNAN PARIT BETON
Jarak Tempuh Rata rata : = 555 = 100.00 M
Upah 1 HOK Pekerja = 80,000 /Hari
PERHITUNGAN BIAYA PIKUL MATERIAL SEMEN (/ZAK)
Asumsi : - Beban Angkut Kerja = 1.00 zak/trip ………….. A
- Waktu Kerja Efektif = 7.00 jam per hari ………….. B
- Jarak Tempuh = 100.00 m' ………….. C
- Kecepatan Berjalan = 40.00 m'/menit ………….. D
(BxD)x60
- Jumlah trip (pulang pergi) per hari =
2L
= 84.00 ………….. E
(BxD)x60
- Jumlah trip (pulang pergi) per hari =
2L
= 84 ………….. F
FxA
- Kapasitas Kerja per hari =
E
= 3.00 ………….. G
(BxD)x60
- Jumlah trip (pulang pergi) per hari =
2L
= 84 ………….. F
FxA
- Kapasitas Kerja per hari =
E
= 3.11 ………….. G
Dibuat Oleh :
Ketua Tim Pelaksanaa Kegiatan /
Kader Teknik
Rudianto Simatupang
Program Pembangunan dan Pemberdayaan Masyarakat Desa
Sketsa Perhitungan
I. Pekerjaan Pembersihan Lahan
P = 60.0 m L = 1.00 m
V = 60 m2
Dibuat Oleh :
Kader Teknik
X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
Sketsa Perhitungan
Bidang B
P = 60.00
La = 0.20
Lb = 0.25
T = 1.2
V = 0,2 + 0.25 x 1.20 x 60.00 x 2
2
V = 32.4 m3
Total volume = VA + VB
= 39.6 m3
Analisa SNI:2016. A.3.2.1.2. Pemasangan 1 m3 pondasi batu kali campuran 1SP : 4PP
Upah
- Pekerja = 1.50 x 39.60 = 59.4 HOK » 59 HOK
- Tukang = 0.75 x 39.60 = 29.7 HOK » 30 HOK
Bahan
- Batu Kali = 1.20 x 39.60 = 47.5 m3 » 48 m3
- Semen Portland @50kg = 3.26 x 39.60 = 129.1 Zak » 129 Zak
- Pasir Pasang = 0.52 x 39.60 = 20.592 m3 » 21 m3
X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
Sketsa Perhitungan
Analisa SNI:2016. A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa, slump (120 ± 20) mm
Upah
- Pekerja = 1.650 x 0.90 = 1.485 HOK » 2 HOK
- Tukang = 0.275 x 0.90 = 0.2475 HOK » 1 HOK
Bahan
- Kerikil Cor = 0.762 x 0.90 = 0.686 m3 » 1 m3
- Semen Portland @50kg = 6.52 x 0.90 = 5.868 Zak » 6 Zak
- Pasir Pasang = 0.543 x 0.90 = 0.4886 m 3
» 1 m3
Dibuat Oleh :
Kader Teknik
X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
Sketsa Perhitungan
PEKERJAAN PLAT DUIKER (5 x 0,8 x 0,8) 1 UNIT
0.20 1.20 0.20
.
Pas Batu
. I. Pekerjaan Galian
Cor Beton 0.30
K-200 P = 5.00 m
.
0.20 L = 2.00 m
.
T = 1.20 m
Plesteran V = 5 x 2 x 1.2
0.80
Pas Batu Cor Beton V = 12.00 m 3
Kali K-175
.
0.15
. Analisa SNI:2016. A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
0.30
Lantai Kerja .
0.05 Upah
(t =5cm)
0.80 0.60
- Pekerja = 0.75 x 12.00 = 9 HOK » 9 HOK
0.60
.
Bidang B
P = 5.00 m
La = 0.40 m
Lb = 0.60 m
T = 1.00 m
V = 0,4 + 0.60 x 1.0 x 5.00 x 2
2
V = 5.0 m3
Dibuat Oleh :
Kader Teknik
X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
Sketsa Perhitungan
Loning Kiri Kanan
0.40 0.40
P = 1.60 m
.
.
L = 0.20 m
T = 0.30 m
B B
1.00
V = 1.60 x 0.20 x 0.3 x 2
V = 0.192 m 3
0.60 0.60
Analisa SNI:2016. A.3.2.1.2. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP
Upah
- Pekerja = 1.50 x 7.89 = 11.838 HOK » 12 HOK
- Tukang = 0.75 x 7.89 = 5.919 HOK » 6 HOK
Bahan
- Batu Kali = 1.20 x 7.89 = 9.4704 m3 » 10 m3
- Semen Portland @50kg = 3.26 x 7.89 = 25.728 Zak » 26 Zak
- Pasir Pasang = 0.52 x 7.89 = 4.1038 m3 » 4 m3
Dibuat Oleh :
Kader Teknik
X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
Sketsa Perhitungan
Analisa SNI:2016. A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa, slump (120 ± 20) mm
Upah
- Pekerja = 1.650 x 0.60 = 0.99 HOK » 1 HOK
- Tukang = 0.275 x 0.60 = 0.165 HOK » 1 HOK
Bahan
- Kerikil Cor = 0.762 x 0.60 = 0.4573 m3 » 1 m3
- Semen @50kg/Zak = 6.52 x 0.60 = 3.912 Zak » 4 Zak
- Pasir Pasang = 0.543 x 0.60 = 0.3257 m 3
» 0.5 m3
1.14 P = 2.66 m
Besi Beton Ø12
Arah Melintang = 34.00 x 2.66 = 90.44 m
Besi Tul Ø12-150
= 80.22 Kg
0.05
1.14 = 7.54 Btg
0.05
4.94
Dibuat Oleh :
Kader Teknik
X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
Sketsa Perhitungan
C. Arah Melintang
J = 9.00 bh
P = 10.26 m
Besi Beton Ø12
= 9.00 x 10.26 = 92.34 m
= 81.91 Kg
= 7.70 Btg
Analisa SNI:2016. A.4.1.1.17 Pembesian 1 kg dengan besi polos atau besi ulir
Upah
- Pekerja = 0.007 x 165.67 = 1.1597 HOK » 1 HOK
- Tukang = 0.007 x 165.67 = 1.1597 HOK » 1 HOK
Bahan
- Besi Beton = 1.050 x 165.67 = 173.96 Kg » 174 Kg
- Kawat Beton = 0.015 x 165.67 = 2.4851 Kg » 2 Kg
Analisa SNI:2016. A.4.1.1.6 Membuat 1 m3 beton mutu f’c = 16,9 Mpa (K-200)
Upah
- Pekerja = 1.650 x 1.20 = 1.98 HOK » 2 HOK
- Tukang = 0.275 x 1.20 = 0.33 HOK » 1 HOK
Bahan
- Batu Pecah 2-3 cm = 0.764 x 1.20 = 0.9164 m3 » 1 m3
- Semen @50kg/Zak = 7.04 x 1.20 = 8.448 Zak » 8 Zak
- Pasir Pasang = 0.522 x 1.20 = 0.6266 m3 » 1 m3
Dibuat Oleh :
Kader Teknik
X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
Sketsa Perhitungan
Dibuat Oleh :
Kader Teknik
X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
RENCANA ANGGARAN BIAYA (RAB)
Desa : X3 No. RAB :1
Kecamatan : X2 Bidang : Pelaksanaan Pembangunan Desa
Kabupaten : X1 Kegiatan : Pemb. Parit Beton Lap. Sepak Bola
Provinsi : Sumatera Utara Item : Pembersihan Lahan
Sub Total 1) - -
2. ALAT KERJA
2.1 Cat Pilox 1.0 - 1.0 Bh II.a 34,953 - 34,953
Sub Total 1) - -
2. ALAT KERJA
2.1 Cangkul 4.0 - 4.0 Bh II.a 224,600 - 898,400
X4 X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
RENCANA ANGGARAN BIAYA (RAB)
Desa : X3 No. RAB :3
Kecamatan : X2 Bidang : Pelaksanaan Pembangunan Desa
Kabupaten : X1 Kegiatan : Pemb. Parit Beton Lap. Sepak Bola
Provinsi : Sumatera Utara Item : Pekerjaan Lantai Kerja
X4 X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
RENCANA ANGGARAN BIAYA (RAB)
Desa : X3 No. RAB :4
Kecamatan : X2 Bidang : Pelaksanaan Pembangunan Desa
Kabupaten : X1 Kegiatan : Pemb. Parit Beton Lap. Sepak Bola
Provinsi : Sumatera Utara Item : Pekerjaan Pas. Batu Kali (1:4)
Sub Total 2) - -
3. UPAH -
3.1 Pekerja ### 59.0 - 59.0 HOK III.a 89,400 - 5,274,600
3.2 Tukang 30.0 - 30.0 HOK III.a 125,400 - 3,762,000
X4 X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
RENCANA ANGGARAN BIAYA (RAB)
Desa : X3 No. RAB :5
Kecamatan : X2 Bidang : Pelaksanaan Pembangunan Desa
Kabupaten : X1 Kegiatan : Pemb. Parit Beton Lap. Sepak Bola
Provinsi : Sumatera Utara Item : Plesteran (1:4)
Sub Total 2) - -
3. UPAH -
3.1 Pekerja ### 12.0 - 12.0 HOK III.a 89,400 - 1,072,800
3.2 Tukang 6.0 - 6.0 HOK III.a 125,400 - 752,400
X4 X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
RENCANA ANGGARAN BIAYA (RAB)
Desa : X3 No. RAB :6
Kecamatan : X2 Bidang : Pelaksanaan Pembangunan Desa
Kabupaten : X1 Kegiatan : Pemb. Parit Beton Lap. Sepak Bola
Provinsi : Sumatera Utara Item : Pengecoran (K-175)
X4 X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
Desa : X3
Kecamatan : X2
Kabupaten : X1
Provinsi : Sumatera Utara
Bidang : Pelaksanaan Pembangunan Desa
Kegiatan : Pemb. Parit Beton Lap. Sepak Bola Dusun II X3
Volume : 436,5 Meter
Volume Jumlah
Kategori Harga Satuan
Uraian Sat.
Biaya (Rp)
Dana Desa
Dana Desa (Rp.)
c=a-b d e f h=cxf
1. BAHAN
1.1 Pasir Urug 3.0 M3 I.a 97,900 293,700
1.2 Batu Kali 48.0 M3 I.a 157,500 7,560,000
1.3 Semen @ 50 kg/zak 140.0 Zak I.a 82,400 11,536,000
1.4 Pasir Pasang 23.0 M3 I.a 168,000 3,864,000
1.5 Kerikil Cor 1.0 M3 I.a 503,700 503,700
X4 X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
RENCANA ANGGARAN BIAYA (RAB)
Desa : X3 No. RAB :7
Kecamatan : X2 Bidang : Pelaksanaan Pembangunan Desa
Kabupaten : X1 Kegiatan : Pemb. Parit Beton Lap. Sepak Bola
Provinsi : Sumatera Utara Item : Pekerjaan Plat Duiker (1 Unit)
X4 X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
Desa : X3
Kecamatan : X2
Kabupaten : X1
Provinsi : Sumatera Utara
Bidang : Pelaksanaan Pembangunan Desa
Kegiatan : Pemb. Parit Beton Lap. Sepak Bola Dusun II
Volume : 436,5 Meter
Volume Jumlah
Kategori Harga Satuan
Uraian Sat.
Biaya (Rp)
Dana Desa
Dana Desa (Rp.)
c=a-b d e f h=cxf
1. BAHAN
1.1 Pasir Urug 4.0 M3 I.a 115,000 460,000
1.2 Batu Kali 58.0 M3 I.a 126,250 7,322,500
1.3 Semen @ 50 kg/zak 180.0 Zak I.b 76,000 13,680,000
1.4 Pasir Pasang 29.0 M3 I.a 127,000 3,683,000
1.5 Kerikil Cor 2.0 M3 I.a 334,250 668,500
1.6 Besi Beton Ø 12mm 174.0 Kg I.b 22,000 3,828,000
1.7 Kawat Beton 2.0 Kg I.b 23,000 46,000
1.8 Kayu Dolken Ø8-10cm 24.0 Btg I.a 50,400 1,209,600
1.9 Paku 5-12 cm 2.0 Kg I.b 12,400 24,800
1.10 Kayu Papan Bekisting 0.2 M3 I.a 3,500,000 700,000
1.11 Balok Kayu 0.1 M3 I.a 3,500,000 350,000
1.12 Batu Pecah 2-3cm 1.0 M3 I.a 341,750 341,750
X4 X5
Program Pembangunan dan Pemberdayaan Masyarakat Desa
REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
Desa : X3
Kecamatan : X2
Kabupaten : X1
Provinsi : Sumatera Utara
Bidang : Pelaksanaan Pembangunan Desa
Kegiatan : Pemb. Parit Beton Lap. Sepak Bola Dusun II
Volume : 436,5 Meter
Terbilang : Dua Ratus Tiga Puluh Sembilan Empat Ratus Enam Puluh Enam Ribu Enam Ratus Rupiah
X3, 2018
Menyetujui, Tim Penyusun RKPDes
Kepala Desa X3 Kader Teknis
X4 X5
DAFTAR HARGA PAJAK BAHAN GALIAN MINERAL BUKAN LOGAM DAN BATUAN (GOLONGAN "C") DALAM
WILAYAH KABUPATEN TAPANULI TENGAN
SURAT KEPUTUSAN BUPATI TAPANULI TENGAH NO : 635.1 / TAMBEN / 2010
X5