CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECTO: CREACION DEL CENTRO AGROECOLOGICO MUNICIPAL EN EL SECTOR GOLLOGIRCA, DISTRITO DE MIRGAS - ANTONIO
RAIMONDI - ANCASH

M1 M2 M3
Idem Descripción Und. Cantidad
34.86% 37.79% 27.34%
1 ACCESORIOS DIVERSOS u 0.6270 0.22 0.24 0.17
2 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 572.2743 199.49 216.26 156.46
3 ACORDAMIENTO PARA LIMITACION u 3.0000 1.05 1.13 0.82
4 ADAPTADOR PVC SAP 1 " u 4.0000 1.39 1.51 1.09
5 ADAPTADOR PVC SAP 1 1/2" u 2.0000 0.70 0.76 0.55
6 ADAPTADOR PVC SAP 2" u 2.0000 0.70 0.76 0.55
7 ADITIVO IMPERMEABILIZANTE gal 0.1652 0.06 0.06 0.05
8 ADOBE 0.38 X 0.38 X 0.08 m u 5,808.3636 2024.80 2194.98 1588.01
9 AGUA m3 35.7683 12.47 13.52 9.78
10 ALAMBRE NEGRO RECOCIDO # 16 kg 40.6220 14.16 15.35 11.11
11 ALAMBRE NEGRO RECOCIDO # 8 kg 55.3820 19.31 20.93 15.14
12 ARENA FINA m3 2.3875 0.83 0.90 0.65
13 ARENA GRUESA m3 6.8542 2.39 2.59 1.87
14 ASFALTO RC-250 gal 0.3990 0.14 0.15 0.11
15 ASIENTO DE PLASTICO PARA INODORO u 1.0000 0.35 0.38 0.27
16 BARANDA DE MADERA. u 3.0000 1.05 1.13 0.82
17 BARRENO 5' X 1/8" u 1.2111 0.42 0.46 0.33
18 BARRO PREPARADO m3 112.0795 39.07 42.35 30.64
19 BIODIGESTOR DE 600 LTS u 1.0000 0.35 0.38 0.27
20 BOMBA MANUAL PARA PRUEBA DE TUBERIA hm 20.2665 7.06 7.66 5.54
21 BORRADOR ROTRING u 25.0000 8.72 9.45 6.84
22 BOTAS DE PUNTA DE ACERO par 10.0000 3.49 3.78 2.73
23 CALAMINA GALVANIZADA ZINC 28 CANALES 1.83 X 0.830 m X 0.27 mm pl 100.0960 34.89 37.83 27.37
24 CANASTILLA DE PVC 11/2" u 1.0000 0.35 0.38 0.27
25 CAPACITACION.. glb 1.0000 0.35 0.38 0.27
26 CARRIZO DE 1",L=2.30m m 465.9000 162.41 176.06 127.38
27 CARTELES DE OBRA 3.60x2.40m glb 1.0000 0.35 0.38 0.27
28 CARTULINA u 10.0000 3.49 3.78 2.73
29 CASCO DE SEGURIDAD u 10.0000 3.49 3.78 2.73
30 CEMENTO PORTLAND TIPO I (42.5 kg) bls 307.8530 107.32 116.34 84.17
31 CHALECOS REFLECTORES pza 10.0000 3.49 3.78 2.73
32 CLAVOS kg 33.1965 11.57 12.54 9.08
33 CLAVOS PARA CALAMINA kg 11.7760 4.11 4.45 3.22
34 CLAVOS PARA MADERA CON CABEZA DE 2 1/2" kg 1.9920 0.69 0.75 0.54
35 CLAVOS PARA MADERA CON CABEZA DE 3" kg 35.5325 12.39 13.43 9.71
36 CLAVOS PARA MADERA CON CABEZA DE 4" kg 5.0670 1.77 1.91 1.39
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECTO: CREACION DEL CENTRO AGROECOLOGICO MUNICIPAL EN EL SECTOR GOLLOGIRCA, DISTRITO DE MIRGAS - ANTONIO
RAIMONDI - ANCASH

M1 M2 M3
Idem Descripción Und. Cantidad
34.86% 37.79% 27.34%
37 CLAVOS PARA MADERA CON CABEZA DE 5" kg 61.5000 21.44 23.24 16.81
38 CODO DE FºGº 1/2 "*90º u 2.0000 0.70 0.76 0.55
39 CODO DE FºGº 2"*90º u 2.0000 0.70 0.76 0.55
40 CODO PVC SAL 2" X 90° u 6.0000 2.09 2.27 1.64
41 CODO PVC SAL 4" X 90° pza 1.0000 0.35 0.38 0.27
42 CODO PVC SAP 1 1/2"*90º u 2.0000 0.70 0.76 0.55
43 CODO PVC SAP 1"*90º u 14.0000 4.88 5.29 3.83
44 CODO PVC SAP 1/2"*90º u 7.0000 2.44 2.65 1.91
45 CODO PVC SAP 11/2"x22.5º u 5.0000 1.74 1.89 1.37
46 CODO PVC SAP 11/2"x45º u 6.0000 2.09 2.27 1.64
47 CODO PVC SAP 2"x22.5º u 34.0000 11.85 12.85 9.30
48 CODO PVC SAP 2"x45º u 19.0000 6.62 7.18 5.19
49 CODO PVC SAP 2"x90º u 9.0000 3.14 3.40 2.46
50 COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP hm 74.5059 25.97 28.16 20.37
51 COMPUTADORA PORTATIL hm 8.0000 2.79 3.02 2.19
52 CONO DE REBOSE PVC SAP DE 2" A 4" u 3.0000 1.05 1.13 0.82
53 DINAMITA AL 65% kg 97.7800 34.09 36.95 26.73
54 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD glb 1.0000 0.35 0.38 0.27
55 ESTACA DE MADERA EUCALIPTO u 125.8890 43.88 47.57 34.42
56 ESTACION TOTAL hm 33.6124 11.72 12.70 9.19
57 FLETE TERRESTRE ALTERNATIVA 01 glb 1.0000 0.35 0.38 0.27
58 FULMINANTE COMUN # 8 pza 488.9000 170.43 184.76 133.67
59 GRAVA PARA FILTRO DE 1" - 2" m3 2.0370 0.71 0.77 0.56
60 GRUPO ELECTROGENO PORTATIL hm 1.3180 0.46 0.50 0.36
61 GUANTES DE CUERO par 10.0000 3.49 3.78 2.73
62 GUIA m 488.9000 170.43 184.76 133.67
63 HIPOCLORITO DE CALCIO AL 70% kg 1.4580 0.51 0.55 0.40
64 HORMIGON m3 43.8541 15.29 16.57 11.99
65 IMPRIMANTE PARA MUROS gal 28.0917 9.79 10.62 7.68
66 INODORO TANQUE BAJO NORMAL BLANCO INCLUYE ACCESORIOS u 1.0000 0.35 0.38 0.27
67 LADRILLO KING KONG 18 HUECOS 9 X 12 X 24 cm u 871.7400 303.89 329.43 238.33
68 LAPIZ NEGRO u 25.0000 8.72 9.45 6.84
69 LAVATORIO 16"X12" DE 1 LLAVE B INCLUYE ACCESORIOS u 1.0000 0.35 0.38 0.27
70 LENTES DE PROTECCION pza 10.0000 3.49 3.78 2.73
71 LIJA u 9.9260 3.46 3.75 2.71
72 LIJA DE FIERRO # 80 hja 12.2045 4.25 4.61 3.34
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECTO: CREACION DEL CENTRO AGROECOLOGICO MUNICIPAL EN EL SECTOR GOLLOGIRCA, DISTRITO DE MIRGAS - ANTONIO
RAIMONDI - ANCASH

M1 M2 M3
Idem Descripción Und. Cantidad
34.86% 37.79% 27.34%
73 MADERA EUCALIPTO ROLLIZO 6" m 8.0000 2.79 3.02 2.19
74 MADERA EUCALIPTO ROLLIZO4" m 12.5460 4.37 4.74 3.43
75 MADERA TORNILLO p2 1,544.3377 538.36 583.61 422.22
76 MADERA TORNILLO PARA REGLAS p2 2.9700 1.04 1.12 0.81
77 MARCO FIERRO FUNDIDO PARA D=0.60 m u 1.0000 0.35 0.38 0.27
78 MASILLA kg 0.1000 0.03 0.04 0.03
79 MEZCLADORA DE CONCRETO DE 9 -11p3 hm 28.5657 9.96 10.79 7.81
80 MITIGACION AMBIENTAL glb 1.0000 0.35 0.38 0.27
81 MOTOPIONJAR hm 57.3774 20.00 21.68 15.69
82 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIENTA glb 1.0000 0.35 0.38 0.27
83 NITRATO kg 48.8900 17.04 18.48 13.37
84 OCRE ROJO kg 4.4550 1.55 1.68 1.22
85 OFICIAL hh 1,129.3847 393.70 426.79 308.77
86 OPERADOR DE EQUIPO LIVIANO hh 61.7735 21.53 23.34 16.89
87 OPERADOR DE EQUIPO PESADO hh 85.1180 29.67 32.17 23.27
88 OPERARIO hh 1,535.1820 535.16 580.15 419.72
89 OPERARIO TOPOGRAFO hh 33.6124 11.72 12.70 9.19
90 PAPEL BOND mil 5.0000 1.74 1.89 1.37
91 PAPELOGRAFOS u 10.0000 3.49 3.78 2.73
92 PEGAMENTO PARA PVC gal 6.7438 2.35 2.55 1.84
93 PEON hh 6,402.5182 2231.92 2419.51 1750.45
94 PERNO DE ANCLAJE PARA INODORO pza 2.0000 0.70 0.76 0.55
95 PERNO HEXAGONAL DE 3/4" X 3 1/2" pza 9.0000 3.14 3.40 2.46
96 PETROLEO gal 2.9454 1.03 1.11 0.81
97 PIEDRA GRANDE DE 8" m3 77.5155 27.02 29.29 21.19
98 PIEDRA MEDIANA m3 11.0250 3.84 4.17 3.01
99 PIEDRA MEDIANA DE 6" m3 2.8854 1.01 1.09 0.79
100 PIEDRA ZARANDEADA DE 1/2" A 3/4" m3 10.3329 3.60 3.90 2.83
101 PINTURA ANTICORROSIVA gal 0.0580 0.02 0.02 0.02
102 PINTURA ESMALTE gal 3.5490 1.24 1.34 0.97
103 PINTURA ESMALTE SINTETICO gal 0.4400 0.15 0.17 0.12
104 PINTURA LATEX gal 16.8159 5.86 6.35 4.60
105 PISON MANUAL PARA COMPACTACION hm 12.0025 4.18 4.54 3.28
106 PLUMON pza 12.0000 4.18 4.53 3.28
107 PROTECTOR DE OIDOS pza 10.0000 3.49 3.78 2.73
108 PROYECTOR MULTIMEDIA hm 8.0000 2.79 3.02 2.19
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECTO: CREACION DEL CENTRO AGROECOLOGICO MUNICIPAL EN EL SECTOR GOLLOGIRCA, DISTRITO DE MIRGAS - ANTONIO
RAIMONDI - ANCASH

M1 M2 M3
Idem Descripción Und. Cantidad
34.86% 37.79% 27.34%
109 PUERTA CONTRAPLACADA DE MADERA TORNILLO TIPO P-2 (0.90x2.10) u 3.0000 1.05 1.13 0.82
110 PUERTA METALICA CON PLANCHA u 1.0000 0.35 0.38 0.27
111 REGILLA DE 2" pza 1.0000 0.35 0.38 0.27
112 RESPIRADOR CONTRA POLVO u 10.0000 3.49 3.78 2.73
113 RETROEXCAVADORA CARGADORA SOBRE LLANTAS 90 HP 1 yd3 hm 85.1180 29.67 32.17 23.27
114 SERVICIO DE TERMOFUSION Union 1.3180 0.46 0.50 0.36
115 SOLDADURA CELLOCORD kg 0.0500 0.02 0.02 0.01
116 TABLERO DE MADERA u 25.0000 8.72 9.45 6.84
117 TAPA CON MARCO FIERRO FUNDIDO DE DESAGUE 12" X 24" pza 5.0000 1.74 1.89 1.37
118 TAPA DE CONCRETO ARMADO PARA BUZON D=0.60M u 1.0000 0.35 0.38 0.27
119 TAPA METALICA SANITARIA 0.60*0.60M*1/8" u 3.0000 1.05 1.13 0.82
120 TAPA METALICA SANITARIA 0.80*0.80M*1/8" u 1.0000 0.35 0.38 0.27
121 TAPON PVC AGUA S.P. 1" u 5.5050 1.92 2.08 1.51
122 TAPON PVC AGUA S.P. 1/2" u 0.0453 0.02 0.02 0.01
123 TAPON PVC AGUA S.P. 11/2" u 0.0400 0.01 0.02 0.01
124 TAPON PVC AGUA S.P. 2" u 6.2500 2.18 2.36 1.71
125 TAPON PVC AGUA S.P. 4" u 2.0000 0.70 0.76 0.55
126 TEE PVC SAP 1 1/2" u 2.0000 0.70 0.76 0.55
127 TEE PVC SAP 1" u 2.0000 0.70 0.76 0.55
128 TEE PVC SAP 1/2" u 4.0000 1.39 1.51 1.09
129 TEE PVC SAP 2" u 7.0000 2.44 2.65 1.91
130 THINNER gal 0.6923 0.24 0.26 0.19
131 TIERRA DE CHACRA O VEGETAL m3 43.0000 14.99 16.25 11.76
132 TIJERAL DE MADERA T-1 u 3.0000 1.05 1.13 0.82
133 TIJERAL DE MADERA T-3 u 3.0000 1.05 1.13 0.82
134 TRAMPA BOTELLA MOPLEN GRIS 1 1/4" PARA LAVATORIO u 1.0000 0.35 0.38 0.27
135 TRIPLAY DE 8 mm m2 8.6400 3.01 3.27 2.36
136 TUBERIA HDPE PE 80 SDR 21 PN 6 110mm m 67.2180 23.43 25.40 18.38
137 TUBERIA PVC SAL 2" m 14.9675 5.22 5.66 4.09
138 TUBERIA PVC SAL 4" m 95.6750 33.35 36.16 26.16
139 TUBERIA PVC SAP C-10 DE 1"x5M m 947.0500 330.14 357.89 258.92
140 TUBERIA PVC SAP C-10 DE 1/2"X5M m 12.5025 4.36 4.72 3.42
141 TUBERIA PVC SAP C-10 DE 11/2"x5M m 8.4000 2.93 3.17 2.30
142 TUBERIA PVC SAP C-10 DE 4"x5M m 1.0000 0.35 0.38 0.27
143 TUBERIA PVC SAP C-7.5 DE 2"x5M m 52.5000 18.30 19.84 14.35
144 TUBO DE ABASTO 1/2" X 5/8" PVC. u 2.0000 0.70 0.76 0.55
CRONOGRAMA DE ADQUISICION DE MATERIALES

PROYECTO: CREACION DEL CENTRO AGROECOLOGICO MUNICIPAL EN EL SECTOR GOLLOGIRCA, DISTRITO DE MIRGAS - ANTONIO
RAIMONDI - ANCASH

M1 M2 M3
Idem Descripción Und. Cantidad
34.86% 37.79% 27.34%
145 TUBO DE FIERRO GALVANIZADO DE 2" m 0.5000 0.17 0.19 0.14
146 TURBA m3 43.0000 14.99 16.25 11.76
147 UNION DOBLE CAMPANA S/P DE PVC DE 2" u 4.0000 1.39 1.51 1.09
148 UNION UNIVERSAL DE PVC SAP DE 1 1/2" u 2.0000 0.70 0.76 0.55
149 UNION UNIVERSAL DE PVC SAP DE 1" u 4.0000 1.39 1.51 1.09
150 UNION UNIVERSAL DE PVC SAP DE 2" u 2.0000 0.70 0.76 0.55
151 VALVULA COMPUERTA BRONCE 1 1/2" u 1.0000 0.35 0.38 0.27
152 VALVULA COMPUERTA BRONCE 1" u 2.0000 0.70 0.76 0.55
153 VALVULA COMPUERTA BRONCE 2" u 1.0000 0.35 0.38 0.27
154 VENTANA DE MADERA+FIERRO TIPO V-2 (0.40x0.40) u 1.0000 0.35 0.38 0.27
155 VENTANA DE MADERA+FIERRO TIPO V-3 (1.00x0.80) u 5.0000 1.74 1.89 1.37
156 VIBRADOR DE CONCRETO 4 HP 1.50" hm 7.4761 2.61 2.83 2.04
157 VIDRIO SEMIDOBLE p2 49.7070 17.33 18.78 13.59
158 VOLQUETE DE 15 M3 hm 21.6563 7.55 8.18 5.92
159 WINCHA DE 30 m u 1.2590 0.44 0.48 0.34
160 YEE PVC SAL 2" u 4.0000 1.39 1.51 1.09
161 YEE PVC SAL 4" u 1.0000 0.35 0.38 0.27
162 YESO DE 28 Kg bls 87.8753 30.63 33.21 24.03
163 YESO EN BOLSAS DE 20 kg bls 8.2087 2.86 3.10 2.24