It’s to be recalled that we were instructed to evaluate the financial proposal document
submitted by 2 (two) technically responsive consulting firms named as Tollen consulting
Architect and Engineers and Amerti Construction for the above mentioned project.
Accordingly, we went through each submitted document and came up with our evaluation
report attached with this letter. This is to let you have 3 pages of our final evaluation result
and recommendation for your approval.
With Regards
Committed to Breakthrough!
Baankii Hojii Gamtaa Oromiyaa
የኦሮሚያ ኀብረት ሥራ ባንክ
1. Evaluation Process
The evaluation is made by checking each item for multiplication and summation error as
well. Accordingly, we went through two bidder submitted documents and have completed
the arithmetic checking. The errors found and the corrections made for each error are
shown in the following tables.
Committed to Breakthrough!
Baankii Hojii Gamtaa Oromiyaa
የኦሮሚያ ኀብረት ሥራ ባንክ
Committed to Breakthrough!
Baankii Hojii Gamtaa Oromiyaa
የኦሮሚያ ኀብረት ሥራ ባንክ
Detail description of the material and methods of work to be done in terms of type, brand
and quality of material not clearly specified.
Unit of measurement not defined.
Unit price or Unit rate not properly defined.
Summary of total amount not clearly specified.
Grand summary of the work not specified.
On financial proposal there are also missed items (works).
In general, the submitted financial proposal by Amerti construction firms lacks the above points and
hence it is difficult to undergo the financial proposal evaluation.
NB:-Since these financial proposals will be incorporated as part of contract document, we should be
alert for
Variation work
Missed work
Incomplete specification.
Quality of work and
Financial failure.
Committed to Breakthrough!
Baankii Hojii Gamtaa Oromiyaa
የኦሮሚያ ኀብረት ሥራ ባንክ
We recall receiving a recent financial proposal dated 04/05/2021 from two consulting firm Tollen
and Amerti for the interior design that we intend to renovate Finfinne branch. In this proposal these
two firms have offered a total sum of Birr 7,824,898.94 and 9,999,364.425 respectively including
VAT before arithmetic checking for the interior design and construction.
In response to your instruction to evaluate the potential difference between the two quotations, and
to come up with our proposal, we have thoroughly assessed the two proposals, and learned that the
main difference between the two proposals arose from differences in design concept.
Following our evaluation on the financial proposals offered by the two firms, we have come to the
following conclusions:
Therefore, this is to let you have 5 pages of our final evaluation result and recommendation for
your approval
Regards,
Committed to Breakthrough!
Baankii Hojii Gamtaa Oromiyaa
የኦሮሚያ ኀብረት ሥራ ባንክ
1. Evaluation Process
The evaluation is made by checking each item for multiplication and summation error as
well. Accordingly, we went through two bidder submitted documents and have completed
the arithmetic checking. The errors found and the corrections made for each error are
shown in the following tables.
Committed to Breakthrough!
Baankii Hojii Gamtaa Oromiyaa
የኦሮሚያ ኀብረት ሥራ ባንክ
Price
Ite Before Price After
m Curre Arithmetic Arithmetic
No Item of Work ncy Check Check Errors Remarks
B Construction Work
Demolishing and repair
1 works BIRR 58,449.98 58,449.98 0.00
2
Office ceiling works BIRR 827,332.74 827,332.74 0.00
Committed to Breakthrough!
Baankii Hojii Gamtaa Oromiyaa
የኦሮሚያ ኀብረት ሥራ ባንክ
1,304,264.9
15% VAT BIRR 3 1,304,264.93 0.00
9,999,364.4
Grand Total BIRR 3 9,999,364.43 0.00
BUDJET FOR THE
PROJECT BIRR
Committed to Breakthrough!
Baankii Hojii Gamtaa Oromiyaa
የኦሮሚያ ኀብረት ሥራ ባንክ
Committed to Breakthrough!
Baankii Hojii Gamtaa Oromiyaa
የኦሮሚያ ኀብረት ሥራ ባንክ
Thus as we compared the financial proposal of the two firms, we found TOLLEN
CONSULTING ARCHITECTS & ENGINEERS offered the list price.
Note:-The price offered by the two firms after cost of furniture deduction will be as follow