METRADO
PART. ESPECIFICACION METRADO TOTAL
UNID. BLOQ.VIVIENDA BLOQ.ADMIN. BLOQ.EDUC.
02.03.02 COLUMNAS
02.03.02.01 CONCRETO F'C=210 KG/CM2 EN COLUMNAS M3 6.19 8.53 12.90 27.62
02.03.02.03 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 87.01 117.71 176.03 380.75
02.03.02.04 ACERO PARA COLUMNAS GRADO 60 KG 941.57 1,184.45 1,780.38 3,906.40
02.03.03 VIGAS
02.03.03.01 CONCRETO F'C=210 KG/CM2 EN VIGAS M3 5.37 8.62 10.31 24.30
02.03.03.03 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS M2 58.40 92.54 111.01 261.95
02.03.03.04 ACERO PARA VIGAS GRADO 60 KG 509.29 870.05 1,013.08 2,392.42
02.03.04 COLUMNETAS
02.03.04.01 CONCRETO F'C=175 KG/CM2 M3 - 3.83 3.68 7.51
02.03.04.02 ENCOFR.Y DESENCOFR.NORMAL M2 - 51.57 48.96 100.53
02.03.04.03 ACERO FY=4200 KG/CM2 KG - 472.06 467.70 939.76
02.03.05 VIGUETAS
02.03.05.01 CONCRETO F'C=175 KG/CM2 M3 - 1.05 1.47 2.52
02.03.05.02 ENCOFR.Y DESENCOFR.NORMAL M2 - 14.09 19.57 33.66
02.03.05.03 ACERO FY=4200 KG/CM2 KG - 129.85 166.34 296.19
02.03.01 ZAPATAS
02.03.02 COLUMNAS
ANCHO(M)/
DESCRIPCION N° VECES LARGO(M) ALTO(M) PARCIAL(M3)
AREA (M2)
02.03.03 VIGAS
02.03.01 ZAPATAS
02.03.02 COLUMNAS
ANCHO(M)/
DESCRIPCION N° VECES LARGO(M) ALTO(M) PARCIAL(M3)
AREA (M2)
BLOQUE ADMINISTRATIVO-COMEDOR
C-1 16.00 0.35 0.25 4.05 5.67
C-3 (PORTICO EJE A/EJES 1) 1.00 0.35 0.25 4.95 0.43
C-3 (PORTICO EJE A/EJES 2) 1.00 0.35 0.25 7.43 0.65
C-3 (PORTICO EJE A/EJES 3) 1.00 0.35 0.25 4.65 0.41
C-3 (PORTICO EJE D/EJES 1) 1.00 0.35 0.25 4.95 0.43
C-3 (PORTICO EJE D/EJES 2) 1.00 0.35 0.25 7.43 0.65
C-4 (PORTICO EJE D/EJES 3) 1.00 0.25 0.25 4.65 0.29
TOTAL(M3): 8.53
BLOQUE ADMINISTRATIVO-COMEDOR
C-1 16.00 1.20 4.05 77.76
C-3 (PORTICO EJE A/EJES 1) 1.00 1.20 4.95 5.94
C-3 (PORTICO EJE A/EJES 2) 1.00 1.20 7.43 8.92
C-3 (PORTICO EJE A/EJES 3) 1.00 1.20 4.65 5.58
C-3 (PORTICO EJE D/EJES 1) 1.00 1.20 4.95 5.94
C-3 (PORTICO EJE D/EJES 2) 1.00 1.20 7.43 8.92
C-4 (PORTICO EJE D/EJES 3) 1.00 1.00 4.65 4.65
TOTAL(M2): 117.71
02.03.03 VIGAS
02.03.04 COLUMNETAS
02.03.05 VIGUETAS
M.EDUCACIONAL Página 23
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
M.EDUCACIONAL Página 24
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
M.EDUCACIONAL Página 25
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
M.EDUCACIONAL Página 26
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
02.03.01 ZAPATAS
M.EDUCACIONAL Página 27
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
M.EDUCACIONAL Página 28
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
M.EDUCACIONAL Página 29
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
02.03.02 COLUMNAS
ANCHO(M)/
DESCRIPCION N° VECES LARGO(M) ALTO(M) PARCIAL(M3)
AREA (M2)
BLOQUE EDUCACIONAL
NAVE BIBLOTECA
C-1 8.00 0.35 0.25 4.05 2.84
C-3 (PORTICO EJE 1/EJES A) 1.00 0.35 0.25 4.95 0.43
C-3 (PORTICO EJE 1/EJES B) 1.00 0.35 0.25 7.43 0.65
C-3 (PORTICO EJE 1/EJES C) 1.00 0.35 0.25 4.65 0.41
C-3 (EJE 5-EJES A) 1.00 0.35 0.25 4.05 0.35
C-3 (EJE 3-EJES C) 1.00 0.35 0.25 4.05 0.35
NAVE AULAS
C-1 18.00 0.35 0.25 4.05 6.38
C-3 (PORTICO EJE A/EJES 1) 1.00 0.35 0.25 4.95 0.43
C-3 (PORTICO EJE A/EJES 2) 1.00 0.35 0.25 7.43 0.65
C-3 (PORTICO EJE A/EJES 3) 1.00 0.35 0.25 4.65 0.41
TOTAL(M3): 12.90
M.EDUCACIONAL Página 30
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
BLOQUE EDUCACIONAL
NAVE AULAS
C-1 8.00 1.20 4.05 38.88
C-3 (PORTICO EJE 1/EJES A) 1.00 1.20 4.95 5.94
C-3 (PORTICO EJE 1/EJES B) 1.00 1.20 7.43 8.92
C-3 (PORTICO EJE 1/EJES C) 1.00 1.20 4.65 5.58
C-3 (EJE 5-EJES A) 1.00 1.20 4.05 4.86
C-3 (EJE 3-EJES C) 1.00 1.20 4.05 4.86
EJE 5 ENTRE EJES D-F
C-1 18.00 1.20 4.05 87.48
C-3 (PORTICO EJE A/EJES 1) 1.00 1.20 4.95 5.94
C-3 (PORTICO EJE A/EJES 2) 1.00 1.20 7.43 8.92
C-3 (PORTICO EJE A/EJES 3) 1.00 1.00 4.65 4.65
TOTAL(M2): 176.03
02.03.03 VIGAS
M.EDUCACIONAL Página 31
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
EJE C' ENTRE EJES 3-4 1.00 3.05 0.25 0.35 0.27
EJE C' ENTRE EJES 4-5 1.00 3.00 0.25 0.35 0.26
EJE F ENTRE EJES 3-4 1.00 3.05 0.25 0.35 0.27
EJE F ENTRE EJES 4-5 1.00 3.00 0.25 0.35 0.26
EJE H ENTRE EJES 3-4 1.00 3.05 0.25 0.35 0.27
EJE H ENTRE EJES 4-5 1.00 3.00 0.25 0.35 0.26
EJE J ENTRE EJES 3-4 1.00 3.05 0.25 0.35 0.27
EJE J ENTRE EJES 4-5 1.00 3.00 0.25 0.35 0.26
EJE L ENTRE EJES 3-4 1.00 3.05 0.25 0.35 0.27
EJE L ENTRE EJES 4-5 1.00 3.00 0.25 0.35 0.26
EJE 3 ENTRE EJES C'-D 1.00 3.60 0.25 0.35 0.32
EJE 5 ENTRE EJES C'-D 1.00 3.60 0.25 0.35 0.32
EJE 3 ENTRE EJES F-G 1.00 3.60 0.25 0.35 0.32
EJE 5 ENTRE EJES F-G 1.00 3.60 0.25 0.35 0.32
EJE 3 ENTRE EJES H-I 1.00 3.60 0.25 0.35 0.32
EJE 5 ENTRE EJES H-I 1.00 3.60 0.25 0.35 0.32
EJE 3 ENTRE EJES J-L 1.00 2.75 0.25 0.35 0.24
EJE 5 ENTRE EJES J-L 1.00 2.75 0.25 0.35 0.24
PORTICO EJE L/ EJE 3-5
1 5.15 0.25 0.35 0.45
1 5.95 0.25 0.35 0.52
TOTAL(M3): 10.31
M.EDUCACIONAL Página 32
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
M.EDUCACIONAL Página 33
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
02.03.04 COLUMNETAS
M.EDUCACIONAL Página 34
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
02.03.05 VIGUETAS
M.EDUCACIONAL Página 35
SUSTENTO DE METRADOS
(BLOQUE EDUCACIONAL)
M.EDUCACIONAL Página 36