Appendix 2

Safe Sequence of Work


ACTIONS DETAIL
Brief Description Of the Work & Location Installation of uPVC Pipes

Sequence of Work and how Operations are Work Sequence:


controlled Site Preparation
Necessary Permits
Investigation of utilities
Excavation
Laying Pipes
Concreting
Backfilling & Compaction
Control of operation :
Barricade the work site to restrict
unauthorized entry
Fill up STARRT Card
Check for utilities & obtain necessary permit
Inspect & maintain daily checklist for
equipment
Control Mobile Equipment Personnel
Interface (MEPI)
Ensure all personnel in proper PPEs at site.
Ensure Third party certificate-TUV for all
operators of equipment.
Ensure consistent supervision at site.
Maintain housekeeping
Fire Extinguisher for LPG work

Onsite Supervision Arrangements Supervision by Site Engineer, Site Supervisor


or Foreman
Individual Responsible for Controls & Site Engineer
Monitoring
Plant & Equipment to be used Electrical tool box, Excavator ,Blow torch
with LPG
Operator Training Requirements Check Excavator Operator training &
authorization

Risk Assessment applicable Prepared & Attached

Safety Control measures for third parties Site Area to be barricaded & appropriate
Signs to be provided, Restrict entry to site &
keep signage for the same.
Environmental Controls Take appropriate control measures ,sprinkle
water to control dust
First Aid & PPE Requirements First Aider & First Aid Box at site and All must
wear Hard Hat, Safety Shoes, Reflective Vest,
Safety Goggles & Hand Gloves
Emergency Procedures Site Specific Emergency Arrangement

Contractor: Rezayat Company Limited ContractNo : 097-C76R

Prepared by:Md Shadan Position:Safety Manager Date:10.02.2019

Approved by:Engr Mustafa Ali Position:Project Manager Date:10.02.2019

Person Carrying out work:Foreman Signature: Date:10.02.2019