Professional Documents
Culture Documents
TSE-G-GN-00-ILF-G-EN-BOD-00001-R01 Basis of Design
TSE-G-GN-00-ILF-G-EN-BOD-00001-R01 Basis of Design
REVISIONS
TABLE OF CONTENTS
1 INTRODUCTION................................................................................................ 14
1.1 Background ........................................................................................................ 14
1.2 Objectives .......................................................................................................... 16
1.3 Scope ................................................................................................................. 16
1.4 Stakeholders ...................................................................................................... 17
1.5 References......................................................................................................... 18
2 GENERAL ......................................................................................................... 19
2.1 Project Description ............................................................................................. 19
2.2 Applicable Codes and Standards ....................................................................... 20
2.3 Definitions .......................................................................................................... 22
2.3.1 General Terms ................................................................................................... 22
2.3.2 Pressure in Systems .......................................................................................... 23
2.3.3 Pressure Definition for the Elements of the System ............................................ 23
2.3.4 Diameters........................................................................................................... 23
2.3.5 Measuring Units ................................................................................................. 24
2.3.6 Meteorological and Seismic Design Data ........................................................... 25
2.4 Design Period..................................................................................................... 26
2.5 Responsibilities .................................................................................................. 26
2.6 Procurement ...................................................................................................... 27
2.7 Permits ............................................................................................................... 28
2.8 Operational Concept .......................................................................................... 29
2.8.1 Operational Modes ............................................................................................. 29
2.8.2 Redundancies for Emergency Scenarios............................................................ 29
2.8.3 Equipment Redundancies .................................................................................. 30
2.9 Tagging .............................................................................................................. 31
2.9.1 Tagging Logic..................................................................................................... 31
2.9.2 System Code...................................................................................................... 32
2.9.3 Location Code .................................................................................................... 32
2.9.4 Equipment and Subsequent Equipment - Code 3 and 4 ..................................... 33
2.9.5 SCADA Alarm and Events – Code 5 .................................................................. 35
TABLES
Table 1: Project Documents .................................................................................................18
Table 2: Measuring Units......................................................................................................24
Table 3: Design Data ............................................................................................................25
Table 4: Rain Intensity ..........................................................................................................26
Table 5: Design and Construction Periods............................................................................26
Table 6: Entities Involved in this Project ...............................................................................26
Table 7: Operations Periods and Design Flows ....................................................................29
Table 8: Letter Codes for Instrumentation.............................................................................34
Table 9: Serviceability Limit State for Shallow Foundations ..................................................37
Table 10: Residual Pressure ................................................................................................45
Table 11: Pipe Velocities ......................................................................................................45
Table 12: Pipe Roughness, Friction Factors and Losses ......................................................46
Table 13: Typical k Values ...................................................................................................48
Table 14: Recommended Material Selection for RCRC TSE Distribution Network ................51
Table 15: Non-Immersed, Aggressive Conditions .................................................................54
Table 16: Immersed (Non-Potable) Conditions .....................................................................54
Table 17: Non-Immersed Non-Aggressive Conditions ..........................................................55
Table 18: Immersed in Potable water ...................................................................................55
Table 19: Storage Criteria ....................................................................................................62
Table 20: Dead Loads ..........................................................................................................64
Table 21: Superimposed Dead Loads ..................................................................................65
FIGURES
Figure 1: Overview of Proposed TSE Main Lines for Each Lot .............................................15
Figure 2: Locations of Existing WWTP .................................................................................15
Figure 3: SCS Overview .....................................................................................................119
APPENDICES
Appendix 1: TSE System Schematic ..................................................................................141
ABBREVIATIONS
1 INTRODUCTION
1.1 Background
The Treated Sewage Effluent (TSE (240,000 m3/day)) represents approximately
16% of the overall generated effluent in Riyadh City. Most of the TSE is produced
from Manfouha Wastewater Treatment Plant (WWTP). The other two plants in
operation (Heet and Al-Hair) contribute to some extent to the TSE supply.
The Green Riyadh Program now has a significant impact on the increase of TSE
in Riyadh City. TSE will be the main source for the irrigation of the numerous
planned greening projects. A volume of 1 million m3/day of TSE is reserved, serving
the Green Riyadh Strategy needs in the year 2030.
Until the year 2030, the implementation of the Green Riyadh Strategy (GRS)
Program.
At the same time, the Green Strategy represents a major investment program
comprising the implementation of various greening opportunities. The final target
is to increase today’s green area coverage of 91 km2 to 541 km2 in the year 2030.
The project has been divided into three (3) Lots. For each lot, one Design
Consultant will be assigned to complete the tasks for the detailed design of a
hydraulically independent TSE distribution network, followed by construction later.
Each lot include Main Pipelines, pumping stations, connections to Strategic TSE
Reservoirs, connections to Secondary Mains, Strategic TSE Reservoirs,
Neighbourhood Tanks, TSE treatment facilities if required, filling stations, and any
other facility that can be required for the operation of the systems. The Main
Pipelines for each lot are shown in Figure 1.
The TSE supply for the greening projects is generated at the location of the existing
three WWTPs in Riyadh (see Figure 2), from where it has to be conveyed to the
irrigation project sites via the conveyance and storage network.
1.2 Objectives
The purpose of this document is to define the Client’s requirements related to the
Basis of Design (BOD) of the three (3) Design Consultants (DC) appointed to carry
out detailed engineering.
The document, therefore, provides the technical approach toward similar topics for
each lot that must be harmonized and the requirements that must be formulated in
a similar manner for each lot. Topics that are addressed are (but are not limited to)
design philosophy and design criteria (expected lifetime, redundancy, safety
margin, material selection, etc.), TSE supply, demand, and quality, and cost
estimates.
Considering the involvement of multiple entities with specific design, the respective
tasks that require utmost attention by Client/ Project Management Consultant
(PMC and must be taken into account to guarantee consistency in design and
implementation are summarized below: below:
▪ Establishment of the uniform basis of design;
▪ Establishment of uniform project specifications;
▪ Identify which installations require design consistency or standardization;
▪ Identify to which level consistency or standardizations are required;
▪ Establish clear interfaces and assure proper management of those;
▪ Provide overall requirements to ensure consistency in engineering
deliverables. Such requirements include:
» Electronic document format and computer-aided design software;
» Communication protocols;
» Uniform document/drawing templates;
» Use similar standard typical drawings;
» Uniform tag numbering system.
1.3 Scope
The scope of this report is to facilitate a common project understanding between
RCRC and the three Design Consultants that carry out the detailed engineering of
Lot 1, Lot 2 and Lot 3.
This is achieved by first establishing a common operating philosophy of the overall
system with the intention to harmonise the design and construction/ operation of
all three lots. Subsequently, the key design parameters for the systems to be
designed are defined, broken down into the main design disciplines.
It is considered that this document is the basis for all designs to be completed as
part of this project. During the progression of the designs, it may become
necessary to adapt or expand this document, which will be done in coordination
with the DCs.
1.4 Stakeholders
As with all projects being completed in an established urban area, the coordination
with and approval by all relevant stakeholders is critical during design to avoid
delays during construction.
The internal stakeholders are:
King Salman Park (KSP) Developer of irrigation project and the single
largest consumer of TSE in the network
1.5 References
In this document, references have been made to the following documents:
Table 1: Project Documents
Reference No. Reference Title
TSE-G-GN-00-ILF-G-PM-STD-00001 Project Description
TSE-G-GN-00-ILF-G-GN-LST-00001 List of Applicable Codes and Standards
TSE-G-GN-00-ILF-G-IC-BOD-00002 SCADA Concept Report
TSE-G-GN-00-ILF-G-EN-PLN-00002 TSE Main Distribution System Option 5
TSE-G-GN-00-ILF-G-PP-TNT-00003 Technical Note - Pipeline Material
2 GENERAL
2.1 Project Description
The project has been divided into three lots, the first covering the north and east
side of the City, the second covering the west side of the city and the third one the
south part of the city. The main components for each lot, as was described in the
Request for Proposal, are described below.
Lot 1-East: Consultant 1 (TSE Distribution Network East):
▪ Primary Main from the Strategic Reservoir at the Cement Factory
(WT_RCRC_09) to the storage tank at King Salman Park (WT_RCRC_15);
▪ Review of the detail design of the constructed and unconstructed sections of
the NWC TSE transmission system consisting of:
» Pumping stations PS_NWC_S1 and PS_NWC_S2 located at Manfouha
WWTP;
» NWC S1 and NWC S2 pipelines from Manfouha to Princess Noura
University (PNU), including constructed and planned connections at these
pipelines.
▪ Short connection of the NWC S1 / NWC S2 pipelines to the new water tank
WT_RCRC_17 at the planned Airport Park;
▪ Short connection from NWC S1 and NWS2 pipelines to the Strategic Reservoir
at the Cement Factory (WT_RCRC_09);
▪ New Primary Main from Manfouha WWTP to the Strategic Reservoir at the
Cement Factory (WT_RCRC_09), if required (not included in the TSE
Distribution Network);
▪ Secondary Main 1 pipelines of pressure zone 7 connected to one or two of
these primary mains NWC S1 and NWC S2;
▪ Secondary Main 1 pipelines of pressure zone 2 connected to the primary main
or reservoirs located in Zone 2;
▪ Connections of the Secondary Mains 1 to the Primary Mains or water
tanks/reservoirs;
▪ Strategic Reservoir at the Cement Factory (WT_RCRC_09);
▪ Storage Tank WT_RCRC_17 at the Airport Park;
▪ The pumping station at the Strategic Reservoir at the Cement Factory
(PS_RCRC_09);
▪ Neighbourhood tanks in Zone 2 and 7;
▪ Decentralised further TSE treatment systems located in Zone 2 and Zone 7;
▪ Any other facilities which are required for the operation of the system.
Lot 2-West: Consultant 2 (TSE Distribution Network West):
▪ Primary main from new pumping station (PS_RCRC_14) at Manfouha
Wastewater Treatment Plant (WWTP) to the storage tank (WT_RCRC_15) in
the King Salman Park (KSP);
▪ Secondary Mains 1 of Zone 4;
▪ Secondary Mains 1 of Zone 3;
▪ Connections of the Secondary Mains 1 to the Primary Mains or water
tanks/reservoirs;
2.3 Definitions
2.3.1 General Terms
▪ Primary Mains (PM) starting from the TSE source at the WWTP and ending
in the Strategic Tank; starting from the TSE source at the WWTP and ending
in the Strategic Tank;
▪ Secondary Mains (SM)can be of several types:
» Start at the Pressure Reducing Valves or Isolation Valves situated on the
Primary Mains, or start at a large strategic or operational water tank;
» End at neighbourhood tanks, at in-line handover, points to large
consumers (flow meter and isolation valve required), or at irrigation tanks.
▪ Neighbourhood Tanks (NHT) will be used to store 24 hours supply for local
irrigation projects;
▪ Strategic Tanks (ST) Typically sized for 48 hours TSE supply of a designated
supply area; TSE supply of a designated supply area;
▪ Connection Points (CP)Means the point where the TSE network system
connects to the WWTPs, water wells or other facilities that will supply the TSE
network system;
▪ Booster Pumping Station: Booster Pumping is situated on the Primary
Pumping Mains or large Secondary Mains;
▪ Primary Pumping Station: Primary Pumping Stations are situated at the
WWTP, Strategic Reservoir or Zone Reservoir.
▪ Secondary Pumping Station: Secondary Pumping Station is situated at the
Zone and Neighbourhood Tanks.
▪ Tertiary Mains: Tertiary Mains start at the Irrigation Tanks and supply
individual projects.
▪ Tertiary Pumping Station: Tertiary Pumping Station is situated downstream
of the Irrigation Tanks.
▪ TSE Distribution Network: The overall distribution network is planned to be
developed based on TSE Reuse Masterplan.
▪ TSE RCRC Distribution Network: The new TSE distribution network is
planned by RCRC.
▪ Wastewater Treatment Plant: Wastewater Treatment Plants are the source
of TSE for use within the TSE distribution System.
▪ Zone Reservoirs: Reservoirs provide 48 hours of storage at high points witch
each zone.
Parameter Units
Volumetric flow l/min
m3/s or m3/h for a larger quantity
Voltage volt (V)
Weight kilogram (kg),
metric ton (t)
2.3.6 Meteorological and Seismic Design Data
Table 3: Design Data
2.5 Responsibilities
To better understand the contractual relationships and the roles and
responsibilities, Table 6 summarises the main contractual party.
Table 6: Entities Involved in this Project
Entity Specific Role and Responsibility
Royal Commission for Riyadh City
RCRC Client, owner and beneficiary of the work performed
under this contract.
Green Riyadh Programme
GR The authority that oversees the implementation of the
work, irrigation projects as well as TSE supply projects
Project Management Office
Engineering consultants contracted by RCRC to advise
PMO
GR and oversee the design and construction of the
irrigation works
PMC Project Management Consultant
2.6 Procurement
The procurement of goods and services designed by the three design consultants
will be an important input to the design works as it has significant impacts on the
design development and the documents produced as part of the design.
The procurement will be associated with the equipment list and the material take-
off list, as well as the Bill Of Quantities (BOQ) that designers should prepare based
on other documentation and design drawings that they have to elaborate on. The
general list of documents and design drawings can be found for each discipline in
this document.
It is the responsibility of the design consultants to prepare a procurement plan for
the work included in their scope of work. Furthermore, tender documents are to be
prepared, including:
▪ Design drawings;
▪ Technical specifications;
▪ GIS information;
▪ BOQ.
Tender documents consist of multiple volumes, typically subdivided as follows:
▪ Volume I – General and Special Conditions of Contract
▪ Introduction
» Background
» Program Objectives
» Project Objectives
▪ SoW
2.7 Permits
Designers shall be in charge of processing the necessary permits for the activities
and works to be carried out. Designers should prepare the permit applications,
consign the permit documentation, prepare the supporting documents, and follow
up on the permits until approval.
The designers must prepare a plan for obtaining the permits, which must include
estimated planning for the process, the definition of the possible entities before
which the permits must be processed, costs associated with the permits, personnel
in charge of the process of processing the permits. Likewise, the monthly reports
must contain a section on the status of each of the permits.
As permitting has the potential to delay the tendering of the works, special attention
must be placed on the permitting process, in particular timely submission of permit
applications and frequent follow-ups.
The following list describes the Operational Modes 2 to 9 within the primary mains:
▪ Operation Mode 2 – Failure Primary Main (02-PM01) from 01-WT13 to 02-
WT12
▪ Operation Mode 3 – Failure Primary Main (01-PM03) from 01-WT13 to 01-
WT09
▪ Operation Mode 4 – Failure Primary Main (01-PM04) from 01-WT09 to 02-
WT15
▪ Operation Mode 5 – Failure Primary Main (02-PM03) from 02-WT10 to 02-
WT15
▪ Operation Mode 6 – Failure Primary Main (02-PM02) from 02-WT12 to 02-
WT10
▪ Operation Mode 7 – Failure Primary Main (01-PM02) from 01-PS02 to 01-
WT03
▪ Operation Mode 8 – Failure Primary Main (01-PM05) from 01-WT03 to 01-
WT17
▪ Operation Mode 9 – Failure Primary Main (01-PM06) from 01-WT17 to 02-
WT15
▪ Operation Mode 10 – Failure Primary Main (03-PM01) from 03-WT01 to 01-
WT13
▪ Operation Mode 11 – Failure Primary Main (03-PM02) from 03-WT02 to 01-
WT09
2.8.3 Equipment Redundancies
2.8.3.1 General
In general, the undisturbed operation of the TSE network shall be possible also
with a single equipment failure. Consequently, the equipment design must include
the necessary spare capacities and stand-by units. This requirement must be
considered for all disciplines.
2.8.3.6 Instrumentation
For the following process instrumentation equipment, a configuration N+1 will be
foreseen:
▪ Level Transmitter in case only one tank/ vessel at a certain location shall be
foreseen. If more than one tank (section) is foreseen at a certain location, no
redundancy shall be considered as the redundancy is given with the number
of tanks;
▪ Pressure Transmitters, as far as relevant, for pressure control of the stations
(For any other pressure transmitter, no redundancy shall be foreseen);
▪ If required, for all safety-relevant instruments such as station inlet/ outlet
pressure alarms, a two-out-of-three (2oo3) configuration shall be foreseen.
2.9 Tagging
2.9.1 Tagging Logic
All equipment shall be identified by a unique ID/ Tag that allows for straightforward
reference to such equipment not just during design but also during construction
and operation. The overall tagging logic applies a location-based approach starting
at a high level of abstraction in the first few elements and becoming progressively
more detailed:
XX-XXXXX-XXXXXX-XXXXXX-XXX
1 2 3 4 5
1 System Code Two number characters, the first digit will be
used for identifying the tender package once
established, the second digit is used for
identifying design packages;
2 Location Code Up to five characters;
3 Equipment/ Unit Code Three characters for the abbreviation, three
optional characters for the Number;
2.9.4.1 General
The following equipment codes are pre-defined and should be used as required.
Changes should be requested before use.
▪ AC Air Compressor
▪ BPT Break Pressure Tank
▪ BRT Bus Rapid Transit
▪ CAB Cabinet
▪ CB Circuit Breaker
▪ CP Cathodic Protection
▪ CR Crane
▪ CYB Cyber Security
▪ DCS Distributed Control System
▪ DT Density transmitter
▪ EH Electrical Heater
▪ ENG Administration
▪ ESD Emergency Shutdown
▪ FGS Fire & Gas Detection System
▪ FI Filter
▪ GE Generator
▪ GW Groundwater
▪ HVAC Heating, Ventilating, and Air Conditioning
▪ ISV Isolation Valve
Mounting posts should be of circular hollow steel section structural steel following
ASTM A123 requirements. Posts should be jointed with bolts at the base
150 millimetres above the finished level socket type. The post heads inserted in
concrete foundations should be sealed all around to prevent the ingress of water.
All foundation works should have minimum reinforcement and be protected by two
coats of coal tar.
All steelwork should be hot-dip galvanized to the requirements of ASTM A123 or
approved equivalent. The finishing colour coats should be according to the local
traffic authority requirements.
The supply networks must be installed at a sufficient distance from the buildings to
reduce, as far as possible, the damage that could occur as a result of their
breakage.
In general, and whatever the depth at which it is measured, the minimum distances
to external wall of buildings, foundations or other similar underground facilities, will
be as follows:
▪ For pipes with DN <300 mm: Minimum distance = 0.80 m
▪ For pipes with DN ≥ 300 mm: Minimum distance = 0.35 m + 1.5 x DN
When it is not possible to choose the layout of the routing, because they run on
consolidated urban roads, with buildings and infrastructure of other pre-existing
services, the indicated separations will be adopted whenever possible, and when
not, they will be reduced leaving the maximum separation that is feasible and
adopting sufficient protections that guarantee the non-involvement between
elements and networks, which must be justified prior to its final design and
execution.
If, for justified reasons, the recommended distances cannot be maintained, prior to
its execution, the compliance with the precautionary measures that are needed
and proposed, properly calculated and justified, must be requested. In any case,
appropriate measures must be taken to avoid any direct contact with or adverse
impacts on existing or known proposed or already permitted structures.
Pipelines must not be laid closer than 60 m from the centre line of the track when
parallel to the Metro. In addition, underground stations should be avoided due to
the number of services already existing in the area and limited depth of 2 m
available above the station to the ground level.
▪ PFA ≥ DP;
▪ MAWP≥ MDP;
▪ PEA ≥ TP.
If required, gate valves of larger diameters and higher nominal pressures than
those indicated may be used, being able to reach nominal pressures of 40 bar
(PN 40).
The residual pressure requirements are shown in Table 10.
Table 10: Residual Pressure
15 m minimum at end of TSE Principal Pipelines
Valves installed on all connections directly off the
Residual Pressure
transmission pipelines (Pumping Station to Reservoir)
(above GL)
Maximum setting 90 m downstream pressure
Maximum static pressure of 90 m in distribution network
Source: TSE Reuse Masterplan, RCRC 2020
5.3.5 Velocities
The determination of the flow velocity of the TSE is essential in the design of the
supply network, since for a given flow rate the choice of the pipe diameter depends
on it. For functional reasons, the TSE flow velocity must be limited between a
maximum and a minimum value.
If the velocity is excessively high, high pressure drops occur and overpressure
derived from possible water hammer can be significant and cause pipe bursts. On
the other hand, relatively high velocities avoid the formation of deposits of
suspended solids which can lead to blockages and can cause carbonate
incrustations on the walls, thus reducing the useful cross-section of the pipe.
On the contrary, when the speed is excessively low, in addition to the underuse of
the pipe that this supposes and to the sensible reduction of the residual chlorine in
the water, facilitates the formation of deposits of suspended matter that can cause
obstructions and carbonate incrustations on the walls, thereby reducing the useful
section of passage.
It is recommended that pipes shall be designed to have a velocity not exceed the
limits shown in Table 11.
Table 11: Pipe Velocities
Velocity Pipe Type
(m/s)
0.6 TSE Transmission pipelines
Minimum
0.2 TSE Principal pipelines
1.0 Branch line connections
1.5 Principal pipelines
Maximum
2.0 Transmission pipelines
5.0 Scour flow in Pipelines
Source: TSE Reuse Masterplan. RCRC. 2020.
These are maximum values in order to limit head loss gradient and transient
pressures, and to increase lining durability. However, technically and economically
optimized systems can be designed with lower velocities.
Pipe diameter
Friction Head Loss Gradient Gradient
(mm)
600 – 1,500 Not to exceed 10 m/km
> 1,500 Not to exceed 5 m/km
Where:
▪ hf = Friction head loss (m);
▪ f = Darcy-Weisbach friction factor;
▪ L = Length of pipe (m);
▪ D = Pipe diameter (m);
▪ V = Flow velocity (m/s);
▪ g = Acceleration due to gravity (m/s2).
Darcy-Weisbach Friction Factor can be calculated using the empirical Colebrook-
White equation. This equation applies in turbulent flow conditions, i.e. Re > 4,000,
which is the case in water and wastewater applications.
Where:
▪ f = Darcy-Weisbach Friction Factor;
▪ ɛ = Pipe roughness (m);
▪ D = Pipe diameter (m);
▪ Re = Reynolds Number.
Reynolds number is calculated as:
Where:
▪ Re = Reynolds Number;
▪ V = Flow velocity (m/s);
▪ D = Pipe diameter (m);
▪ 𝜐 = Kinematic viscosity of the fluid (m2/s) which will change with temperature,
e.g. water at 25°C has a kinematic viscosity of 8.9e-7 m2/s.
Where:
▪ hL = Minor head loss (m);
▪ k = Minor loss coefficient for each type of element and material;
▪ V = Flow velocity (m/s);
▪ g = Gravity acceleration (m/s2).
In the following table the typical k values are shown. These values must be verified
against specific manufactures’ recommendations.
Table 13: Typical k Values
Description k
Entrance Bellmouth 0.005
Rounded 0.25
Sharp-Edged 0.5
Projecting 0.8
Exists 1.0
90°Bend 0.25
45°Bend 0.18
Tee, line flow 0.30
Tee, branch flow 0.75
Cross, line flow 0.50
Cross, branch flow 0.75
Wye, 45° 0.50
Ball 0.04
Check Valves Ball 0.9 - 1.7
Rubber Flapper (v < ft/s) 2.0
Rubber Flapper (v > ft/s) 1.1
Swing 0.6 - 2.2
Gate Double Disc 0.1 - 0.2
Resilient Disc 0.3
Knife Gate Metal Seat 0.2
Resilient Seat 0.3
Eccentric Plug Rectangular (80%) opening 1.0
Full bore opening 0.5
5.5 Pipelines
▪ All exploratory hole work, associated sampling, in situ testing and logging shall
be carried out in accordance with techniques outlined in:
» “Code of Practice for Ground Investigations” BS 5930:2015+A1, 2020;
» “Geotechnical Investigation and Testing - Identification, Description and
Classification of Rock - Part 1: Identification and Description” BS EN ISO
14689-1, 2018;
» “Geotechnical Investigation and Testing - Identification and Classification
of Soil - Part 1: Identification And Description” BS EN ISO 14688-1, 2018;
» “Methods of Test for Soils for Civil Engineering Purposes - Part 1: General
Requirements and Sample Preparation” BS 1377-1, 2016;
» “Geotechnical Investigation and Testing - Field Testing - Part 3: Standard
Penetration Test” BS EN ISO 22476-3: 2005.
▪ “Closed-Face Tunnelling Machines and Ground Stability: A Guideline for Best
Practice”, British Tunnelling Society and Institution of Civil Engineers (Thomas
Telford Publishing), 2005;
A desktop study should be carried out, assessing the available literature, maps,
aerial photographs, utility plans and existing site investigations. The desk study is
essential to help understand the broader geological and geotechnical issues, and
should be used to determine the scope of any intrusive investigations.
The design must include:
▪ Hydraulic requirements (of pipeline);
▪ Structural integrity;
▪ Drive lengths and alignment;
▪ Manhole requirements;
▪ Depth;
▪ Gradient (of pipeline);
▪ Ground conditions;
▪ Details of existing services and underground structures (clearances);
▪ Location of manholes and working areas;
▪ Lengths required (of the pipeline and the microtunneling);
▪ Diameters of pipeline;
▪ Diameter of casing if required;
▪ Structural and construction additional requirements (supporting walls, access
chambers, etc.);
▪ Economic.
5.5.6 Other Considerations
All pipeline arrangements should consider the shortest and most economical route.
The piping arrangements should consider the removal facilities in the vicinity of the
equipment for inspection, service and / or maintenance activities.
The facilities for the location of the lifting equipment, for valves, pipes
arrangements, etc., in the construction and / or maintenance phase, should be
considered.
5.5.7 Chambers and Manholes
The chambers and manholes will allow access to buried pipes (in particular
places), valves or other equipment / elements that require inspection during the
system operation.
Chambers and Manholes shall be specifically designed with an emphasis on safety
during installation, operation and maintenance.
The designer shall provide the proposed construction method with the design
documentation.
A secure safety grille shall be provided beneath the manhole cover for deep
chambers and manholes.
Manholes shall be designed to be constructed as segmental, panel or one-unit
structures, made of precast or cast in-situ reinforced concrete. The general shape
of manholes may be circular, rectangular, or any other shape that satisfies all
design requirements of this section. Manholes shall be designed so that structural
integrity between its components is maintained during installation and normal
service life. The effect of pipe entries on the structural integrity of the manhole
risers shall be considered during design.
All chambers and manholes shall be designed to support all existing and any
predicted future dead loads, included vehicular traffic loads.
Manholes and chambers shall also be designed to support lateral earth pressure,
hydrostatic pressure and any expected high eccentric lateral pressure due to live
load or surcharge load.
The minimum internal diameter of manholes shall be 1,050 mm.
Manholes must include a ladder in their design.
Removable concrete slabs and chambers shall be constructed of precast concrete
sections or of reinforced concrete cast in-situ in accordance with the approved
drawings. The nominal class of concrete shall be C5 (350/50) for chambers.
5.5.8 Pipelines Surge Control
A mechanical surge control system should be considered for main pipelines with
lengths greater than 500 m. The pipeline surge analysis should be done by a
specialist.
5.6.1 General
Pumping Stations considered in this chapter are in the primary network.
5.6.2 Utilities
All pumping stations shall have:
▪ Power supply via public mains;
▪ Diesel backup power supply (EDG, containerized solution);
▪ Potable water supply via public network;
▪ Sewage connection to public network;
▪ UPS for Control and emergency lighting.
5.6.3 Facility Requirements
Access should be provided from the closest public road to the pumping station.
Where access from a public road is not available then a suitable access easement
shall be created. The design of the access road shall reflect the typical size and
operating requirements of maintenance vehicles. See also Section 11.
All pumping stations require security features as follows:
▪ Must be surrounded by a perimeter protection fence or wall;
▪ Shall be equipped with security measures:
» Access control system;
» Perimeter alarm system;
» CCTV;
» Guard house (24/7).
▪ Must be well illuminated to allow routine inspection. LED lights shall be used.
Illumination shall be dimmed down during night;
▪ Must have structures to support cranes, whether temporary or permanent. The
capacity of the cranes depends on the dimensions of the pumps and other
equipment to be installed;
▪ Must have buildings for operation, maintenance and security, more details see
Section 6 and 7;
▪ Pumping stations should be designed in such a way as to allow easy
inspection and maintenance, leaving room for possible future expansions.
Each of the pumps must be fully equipped to function as an independent unit and
must be provided with all the auxiliary equipment, instruments and accessories
required to guarantee its operation under the specified conditions.
5.8 Drainage
The necessary facilities for the drainage of tank areas, pumping stations areas,
valve areas and other facilities should be designed. Consideration should also be
given to the draining of the tanks themselves and the pipelines.
In particular the destination for drained TSE must be determined as part of the
design process and consultations with/ permitting from affected stakeholder must
be progressed and secured.
The total minimum superimposed loads (including partitions, finishes and service
ceilings) shall be as follows:
▪ 5.5 kN/m2 when solid block partition is used;
▪ 4.5 kN/m2 when lightweight block partition is used;
▪ 4.0 kN/m2 when dry-wall partition is used.
6.2.3 Live Loads
The Live Loads are established based upon the architectural definitions of area
occupancy use appropriate to the building structure. These live loads are
determined in accordance with the provisions of ASCE 7. Live load reduction shall
be applied in accordance with ASCE 7 (from floor live loads and for roof live loads)
as applicable.
6.2.9.1 Surcharge
For all underground structures where no future development is planned, except
where a road exists, vertical surcharge loading of 20 KN/m2 will be applied over
the structure.
design of all structural elements. The Load Combinations producing the most
adverse load effects will be used in the design.
6.3.2 Serviceability Limit State (SLS) Design
The design load combinations under the SLS condition shall be accordance with
the last edition of the ASCE 7. These Load Combinations shall be used in the
analysis and design of foundation capacities and reactions. The Load
Combinations producing the most adverse load effects will be used in the design.
6.4 Materials
Structural Steel
Load Combination Limit
Component Description
L/500
Differential Live
(10 mm limit)
Dead + Live L/240
Vertical Deflection of Roofs
Live L/360
Supporting Brittle Elements
Wind* L/360
Dead + Live L/180
Vertical Deflection of Roofs Not
Live L/240
Supporting Brittle Elements
Wind* L/240
Dead + Live L/120
Live L/180
Vertical Deflection of Roofs Not
Wind L/180
Supporting Any Elements
Wind (overall
H/500
building)
Wind (inter-storey) H/400
Wind (Glazing
H/300
Lateral Deflection of Structures Mullions)
Seismic (inter- As per UBC
storey) requirements
Cranes** Live L/1000
All the buildings should have access control, and should be fenced with perimeter
illumination and CCTV surveillance (individually or for a group of buildings,
depending on the location).
7.1.1 Engineering Deliverables
The following engineering deliverables shall be prepared by the design
consultants:
▪ Equipment/systems specifications;
▪ Architectural materials specifications;
▪ Building architectural drawings;
▪ Building finishing drawings;
▪ Building plumbing (water and sewage plumbing if required) and drainage;
▪ Building electrical systems and illumination drawings;
▪ Building communications systems – structured network drawings;
▪ Building firefighting systems and fire detection drawings;
▪ Landscape drawings;
▪ Construction specifications;
▪ Material take-off;
▪ Bill of quantities.
▪ Offices;
▪ Prayer room;
▪ Social / meeting room;
▪ Toilets / washrooms (male/female);
▪ Locker Rooms;
▪ First aid room;
▪ Document room;
▪ Corridor;
▪ Storeroom;
▪ Room for cleaning equipment.
The station control room, electrical equipment room and the control equipment
room shall be equipped with a double floor. The clearance of the double floor shall
be 0.80 m.
Access to equipment rooms shall allow easy and safe transportation and
installation of the equipment cabinets. Clearance of building access doors to the
equipment rooms shall be 2.30 m.
Equipment rooms shall have 100% spare space to accommodate future phases.
7.2.2 Floors
▪ Electrical rooms: double floor with synthetic floor covering (antistatic);
▪ Battery room: ceramic tiles, acid resistant and antistatic;
▪ Offices, social-meeting room: synthetic floor covering;
▪ Wet rooms, HVAC-room, electrical Workshop, gas extinguishing room,
corridor: ceramic tiles.
7.2.3 Battery Room
The battery room shall be equipped with an eye-wash sink. The Battery Room shall
be equipped with a supply air opening and an exhaust air fan. The required air
exchange and the resultant wall openings shall be designed in accordance to
BS EN IEC 62485-2.
▪ Space for laboratory desk (with enough space for the different laboratory
equipment required for the water analysis based on the requirement control
parameters);
▪ Space for computer desk;
▪ Space for waste/used chemicals disposal;
▪ Space for Laboratory sinks;
▪ Space for glassware washing;
▪ Electricity room;
▪ Communications with operation building;
▪ Conference area;
▪ General deposit area;
▪ Dressing rooms and lockers area (for female and male);
▪ Security doors.
For all the above building and if there are very near it should considered a First Aid
Room, a Dining Room and a Prayers Area.
The First Aid Room should have attached a bathroom sited so as to be easily
accessible from all buildings. The door for the first aid room should be large enough
to allow the passage of a stretcher. The floor and wall should be covered with
smooth washable material easy to clean and adequate lighting and ventilation must
be provided.
The Dining Room shall be adequately ventilated and provided with sufficient tables
and chairs to accommodate at least 30% of the workers at a time. The floor area
of the meal room excluding the area occupied by equipment, fittings and furniture
other than tables and chairs or benches shall not be less than 1 m2. per person.
The dining room should be provided with windows facing an outdoor area, which
allows the enjoyment of the diners. It is necessary that the dining room has a door
to the outside, to allow the diners to go outside.
The Prayers Area should enough for all the staff that work in the facility.
Al building should have a parking area enough for the staff. Also parking space for
visitors should be considered.
7.4.5 Emergency Generator Container
The emergency generator container should withstand outdoor conditions, and shall
include the fuel tank. The fuel tank must consider the necessary elements so that
in case of fuel spillage it spreads
7.4.6 Electrical Substation Building
Electrical substations will require a building to install the switchgear and electrical
control panels. The Substation Building superstructure should be constructed from
fire-resistant, low-maintenance building materials.
The substation should have a perimeter security fence.
kW and 1.15 for motors above 250 kW and using the next larger standard
motor size;
▪ Non-slam type nozzle check shall be provided in the pump discharge piping to
prevent backflow and damage of pumps;
▪ Isolation valves shall be provided at pump suction and discharge piping along
with dismantling joints for easy service removal. Isolation valve at pump
suction side can be butterfly type. Ball valve shall be used at pump discharge
side.
8.2.2 Pump Selection
All centrifugal pumps shall be of the ANSI / HI type, according to the service
provided, being able to have a horizontal or vertical axis according to the
application or specific pumping service.
The typical selection criteria for centrifugal pumps, which are considered the most
appropriate for this type of services with water, are their design data (flow rate or
capacity (Q), discharge head (H), speed of rotation (n) and Net Positive Suction
Head (NPSH)), the properties of the fluid pumped, the application, the place of
installation and the applicable regulations, specifications, laws and codes.
The pumps shall be selected in such a way that all required operation scenarios
can be covered with efficiency as near as possible to BEP of the pump. For
application with many desired operation points, variable speed drive shall be
considered for energy saving. Decision if VSD drive is used shall be addressed in
pump selection study.
Main design features for classification of centrifugal pumps are:
▪ Number of stages (single stage / multistage);
▪ Position of the shaft (horizontal / vertical);
▪ Pump casing (radial, e. g. volute casing / axial, e. g. tubular casing);
▪ Number of impeller entries (single entry / double entry);
▪ Type of motor (dry motor / dry rotor motor, e. g. submerged motor / wet rotor
motor, e. g. canned motor, submersible motor).
Other pump classification features include:
▪ Mode of installation;
▪ Nominal diameter (for the pump size, as a function of the flow rate);
▪ Rated pressure (for wall thickness of casings and flanges);
▪ Temperature (for example for the selection of cooling equipment for shaft
seals);
▪ Fluid pumped (abrasive, aggressive, toxic fluids);
▪ Type of impeller (radial flow / axial flow depending on the specific speed);
▪ Self-priming ability;
▪ Casing partition, the position of the pump nozzles, an outer casing, etc.
Sump pumps shall be proposed for pumping drainage water that is collected in the
concrete sumps within the pump chambers.
8.2.3 Pumping Unit Set-Up
There are three ways of setting, considering the type of pump and the inlet
chamber:
▪ Pumps of vertical shaft sunk in the water of the pump well;
▪ Pumps with vertical or horizontal shafts set in a dry chamber located beside
the pump well;
▪ Pump of generally horizontal shaft located above the water level.
Within the arrangement mentioned in (a) three further cases are possible:
▪ Pump is under water and the driving motor is above the water level
In this case the electric motor is directly joined to the vertical shaft of the pump and
is located in a water-free, dry place. The advantage of this solution is the relatively
small space-requirement (there is no suction pipe and foot valve) and the easy
start and operation (priming is not needed because air cannot penetrate into the
suction pipe). Its shortcomings are, especially in case of a large level difference
between the motor and the pump, the difficulties in fitting the bearings in the vertical
shaft, loss in efficiency (due to the several guide bearings), increased corrosion,
and difficulty of checking, maintenance and repair (the pump should be drained
first). In cases of small delivery sometimes flexible shaft-driven pumps can be
used.
▪ Driving motor and main pump are above the water and the first stage under
the water level
By applying a first stage submerged part, the pump gets inflow water. No priming
is necessary before starting. The level of water delivery is controlled by the upper
part, thus the pump in fact, has a double stage made up of a low-pressure
(.submerged stage) and a higher-pressure stage. This solution partly eliminates
the above-mentioned shortcomings, by having several advantages (power take-off
shaft with lower capacity, main part of the pump is easy to maintain). This solution
is applied mostly to pumps of high pressure.
▪ Pump and driving motor under the water level
To these belong the submerged and deep-well pumps. The submerged pump is
set in a driven well.
8.2.4 Design and Performance Requirements
The suction conditions for all pumps shall be carefully determined for the rated
conditions as well as for any other operational cases the pumps will ever be
subjected to according to the operating philosophy.
NPSH Available shall be provided with sufficient safety margin over NPSH
Required taking into account the properties of the pumped water and the selected
pump type as well. Pump manufacturers’ requirements in this respect shall be fully
observed.
By the selection of the pumps, the designer shall take all required measures to
allow operation with minimum water level in the upstream tanks. Special care shall
be taken in NPSH calculation and configuration of the suction piping in order to
avoid any disturbance (e.g. vibration, cavitation) during operation with the minimum
water level in the tanks.
Not mandatory are also the number of stages, the impeller arrangement, the pump
speed or whether a single or double suction design will be used.
The pump station shall be equipped with all means required to ensure that the
pumps are only operating between their minimum and maximum allowable
continuous operating capacity.
Design of the adjacent pipe work and of the pumps shall be such that the allowable
forces and moments on the pump nozzles are not exceeded under any
circumstances. It may be required that the loads will be higher than given in or
extrapolated from pump standards and therefore the loads shall be coordinated
with/confirmed by the pump manufacturer.
Pump casing internal design pressure shall be 10 % higher than the maximum
pressure occurring during operation, which is the maximum suction pressure plus
the shut off head of the pump, or the maximum pressure during surges and other
transient conditions, whatever is higher.
Maximum tank levels and shut off heads of pumps shall be considered when
determining the maximum pressure. The hydrostatic test pressure shall be 150 %
of the above defined internal design pressure.
The pump flange rating shall be according with the next higher pressure rating.
8.2.5 Fire Fighting Pumps
The firefighting pumps shall be designed as per national standards or relevant
British standards. Firefighting pumps shall be designed to satisfy the requirement
of the fire hydrants within pumping station and other relevant areas/buildings.
Storage reservoir shall be used for the fire pump station. A rising main length and
levels shall be calculated according to the location of fire hydrant within pumping
station and other relevant areas/ buildings.
Pumps shall be motor operated with 4 poles, 380 V / 13.8 kV and having a
maximum pump rotation of 1,800 rpm.
Further details on firefighting see Section 11.
Higher velocities are acceptable at special piping sections only, such as control
valves, flow meters, etc. but shall not exceed 6 m/s.
The designer shall carefully check the suction requirements of the pumps with
respect to NPSH (Net Positive Suction Head) and flow pattern and if necessary
lower velocities shall be selected.
For the pressure design of the piping system designer shall calculate the highest
possible pressures occurring in the individual piping sections, taking into account
all steady and unsteady state conditions.
The required minimum wall thickness for the station piping shall be calculated using
the equation stated system design code.
▪ The minimum thickness shall be sufficiently defined considering internal
design pressure and external load.
The internal design pressure of equipment as well as for flanges shall be selected
in accordance with the next higher rating over the highest pressure occurring
during operation.
8.3.2 Materials for Station Piping
Carbon steel pipe with suitable coating and lining shall be used for station piping.
8.3.3 Internal Lining of Station Piping
To avoid internal and external corrosion, the piping and piping components shall
be protected.
The internal lining of station piping shall be done with high quality epoxy (e.g. fusion
bonded epoxy) or polyurethane.
Application shall be follow manufacturer’s recommendation.
8.3.4 External Coating of Station Piping
Above ground station piping shall be coated with high solid epoxy plus
polyurethane as top coat or polyurethane.
Buried station piping shall be coated with 3 layer HDPE or polyurethane.
8.3.5 Piping Layout
The piping layout in stations with existing equipment and piping shall be done in
such a way as to avoid interference with the existing piping systems, structural
steel and concrete, electrical cable trenches, conduits etc. Interconnections with
existing piping or equipment must be defined in separate interface reports, which
are part of the final design.
8.3.6 Piping Flexibility
The piping shall be designed to have sufficient flexibility to prevent expansion or
contraction causing excessive stresses in the piping material, excessive bending
moments at joints, or excessive forces or moments at points of connection to
equipment or at anchorage or guide points.
This shall be achieved by using piping arrangement such as L-shaped, U-shaped
or Z-Shaped configurations in the normal routing of any piping system.
The above ground piping shall be laid on pipe supports. Supports shall be designed
to support the pipe without causing excessive local stress in the pipe and keep the
desired freedom of movement.
Contractor shall carry out a pipe stress analysis as part of the final design proving
that stresses for piping and equipment, including tanks and nozzles, are kept within
the allowable limits.
8.3.7 Dismantling Pieces and Flange Adaptors
Dismantling pieces or flange adaptors shall be used at valves, flow meters and
other equipment installed in straight pipe runs for easy dismantling if required
during final design and depending on the piping configuration.
Flange adaptors shall only be used where no axial forces have to be transmitted.
8.3.8 Pump Suction Piping
For the pump suction piping in addition to the stress calculation, the designer, in
close co-operation with the pump manufacturer, shall carefully check the piping
arrangement and the suction pipe lengths with respect to velocity distribution at the
pump inlet which shall meet the requirements of the pumps for proper operation.
The design shown in the drawings is deemed to satisfy these requirements for the
pump types under consideration. However, all the necessary measures for
straightening the flow (e.g. elbows with straightening vanes, flow straighteners in
straight pipes, special fittings) shall be foreseen.
8.3.9 Filling and Drainage
For filling and drainage of station piping it is necessary to provide suitable filling
bypass valves, drain valves and vent valves.
The drain valves shall be at low points and the vent valves at high points.
Filling bypass valves shall be designed to handle the possible differential pressure.
8.3.10 Strainers
The Strainers shall comply with the following specifications:
▪ Shall be H or Y type and comply with international standards with rapid purge
arrangement;
▪ Standard flanged connection;
▪ Body and cover in ductile iron GGG40 or cast steel with epoxy coating;
▪ Effective filtration is required;
▪ Compact design;
▪ Easy and Fast to Maintain;
▪ Top cover removal, only;
▪ Flat stainless steel strainer mesh perpendicular to flow optimizes pressure
drop;
▪ Possibility to be equipped with an autonomous programmable flushing valve,
allowing fast;
8.4 Valves
8.6 HVAC
Minimum requirements for design of Heating, Ventilation and Air-Conditioning
(HVAC) systems are shown in this section.
8.6.1 Design Criteria for Indoor Located Air-Conditioning Units
The design criteria for indoor located air-conditioning units are shown in the
following table.
Table 37: HVAC Indoor Design Condition
Room
Units
Summer DB Winter DB Air Noise
Capacity
Area / Space Temperature Temperature Humidity Level
Split
(°C) (°C) [% RH] from dB
(%)
(A)
Offices, social rooms
control, computer,
23 ± 2 21 ± 2 50 - 60 45 2 x 100%
telecom rooms,
SCMS electronic and
Room
Units
Summer DB Winter DB Air Noise
Capacity
Area / Space Temperature Temperature Humidity Level
Split
(°C) (°C) [% RH] from dB
(%)
(A)
relay rooms and
similar rooms
Switchgear rooms for
132 kV, 220 kV or
400 kV SWGs.
Battery &
charger/LVDC 27 ± 2 21 ± 2 50 - 60 45 3 x 50%
rooms, LVAC
distribution, and A/C
plant room and
similar rooms
Stores, janitor rooms,
staircases, corridors,
indoor aux.
transformer,
capacitors, reactor, 23± 2 21 ± 2 50 - 60 45 3 x 50%
compensator and
inverter rooms,
trenches/shafts and
similar rooms
3 x 50
Power transformer
< 65 < 45 50 - 60 45 Ventilatio
room
n only)
Other process areas
such as in N+1
wastewater facilities Outside air Outside air where N
like blower rooms, temperature + temperature + Not is the
80
pumping stations, 60°C 60°C controlled number of
rooms with various (Maximum) (Maximum) units
installed process required.
equipment
Note: If rooms of different standby percent requirements are grouped under one system
due to practical reasons the higher percentage standby (i.e. 100%) shall be considered.
Note: If RH% controlled rooms and RH% uncontrolled rooms are grouped under one
system due to practical reasons both these types of rooms have to be considered in the
calculation of heater capacity required to control RH% because it is the common return air
duct which is the point of sensing.
Note: The indoor conditions of the kitchen and toilet rooms will not be controlled.
a) Summer
I. Dry bulb temperature 48ºC
II. Wet bulb temperature 28ºC
b) Winter
I. Dry bulb temperature -2.5ºC
c) Daily Range 14ºC
d) Design temperature for condenser 60ºC
2. Maximum wind speed: 160 km/h;
3. Occurrence of sand storms: frequently.
It is important to take in consideration that the HVAC equipment must be selected
to operate in maximum 60°C (DB) 28°C (WB) in summer and able to sustain -5°C
(DB) in winter
8.6.3 Air Temperature and Humidity
The external design condition shall be based on respective specific project
requirements and environmental conditions and site location. Outdoor design
conditions shall be obtained from the closest weather station to the facility location
and ASHRAE database.
The outdoor air is often very humid and laden with fine sand dust from the desert
and salt particles from the seaside.
Thereby the outdoor air is extremely corrosive to all metal parts of the entire
structure and installations.
Therefore, only the highest available material standard shall be applied with special
coating and painting of all exposed surfaces to prevent the equipment from all
corrosion effects.
In case additional auxiliary building for a guard house, a fire pump room, insulator
washing pump room, potable-water pump room are considered inside a facility,
separate decorative wall mounted type mini split units with concealed thermostat
wiring and refrigerant piping shall be provided to maintain the indoor design
temperature of 23±2°C for guard house and 30±2°C for other/facility rooms. The
capacities of this equipment shall be de-rated for the specified local outdoor air-
conditions. In case of non-availability of the certified de-rated capacity from the
Manufacturer of the equipment, the nominal capacity shall be reduced in the design
calculation by 30%. Condensed water connections with drain-traps to the main
drain pipes shall be provided.
Any area/room not covered by the a.m. a/c-units shall be air-conditioned according
to similar rooms.
HVAC equipment such as air cooled chiller, air cooled condenser, packaged air
conditioning unit, DX split unit etc., shall be selected to deliver required cooling
capacity at maximum outdoor ambient temperature.
Outdoor HVAC equipment such as air cooled chiller, outdoor condensing unit,
packaged air conditioning unit, DX type split unit, etc., shall be able to operate at
extreme outdoor ambient temperature without out tripping.
8.6.4 General Requirements
The detail designer shall consider the below general requirements for HVAC
system.
▪ Space for HVAC equipment such as AHU room, Chiller yard, HVAC equipment
yard, etc., shall be sized as per guidelines, recommendation provided by
HVAC equipment Manufacturer;
▪ Clearance shall be provided around HVAC equipment as per Manufacturer
recommendation for replacement of component and to carry out maintenance
activities;
▪ HVAC equipment such as air handling unit, chiller, packaged air-conditioner,
air cooled condensing unit for DX type AHU which are installed at ground floor
level shall have sand trap barrier around equipment area to prevent
accumulation of sand near HVAC equipment;
▪ If HVAC equipment such as air handling unit or chiller or packaged air-
conditioner or air cooled condensing unit for DX type AHU proposed to install
at roof floor of the building, then the designer shall provide stair case access
to reach equipment at roof for maintenance and component replacement
purpose;
▪ If packaged AC or AHU or air cooled condensing for DX type AHU, proposed
to install at roof floor of the building and there is no stair case access to reach
roof floor, then lifting arrangement (davit type) shall be provided at roof for
component replacement such as compressor, motor, fan, coil, filter, etc.,
during maintenance;
▪ One (1) potable water supply connection shall be provided near to AHU,
chiller, packaged air conditioner, within a ten (10) meters distance for cleaning
purpose. Floor surface shall have proper slope to drain all service water during
cleaning. Electrical power supply socket shall be provided in HVAC equipment
area for electrical power supply connection to cleaning pump during
maintenance;
▪ All condensate drainage line shall be insulated to avoid formation of
condensate. Condensate pipe material shall be metallic type, cleaning access
point shall be provided for condensate drainage line;
▪ Suitable walkways, step cross over above HVAC ducts, chilled water pipes
etc., shall be provided;
▪ If the room has equipment or panel which has voltage level in excess of 1,000
Volts inside the room then, HVAC equipment shall not be located in that room,
only a non-maintainable duct shall run inside the room;
▪ Individual power supply shall be provided to each HVAC equipment, so that in
case of trip due to HVAC fault, it shall not trip upstream breaker or trip power
supply to other equipment/system;
▪ Emergency push button with guard, electrical isolator shall be provided near
to HVAC equipment (AHU, chiller, chilled water pump, packaged air
conditioner, fans, etc.);
▪ Breaker with over load protector shall be provided for each motor of AHU,
chilled water pump etc.;
▪ Separate breaker shall be provided for electrical heater, humidifier;
▪ HVAC fresh air intake shall have detector as per requirement for HSE. Gas
detector shall be installed at HVAC fresh air intakes. Type of detector and
number of detectors at each fresh air intake shall follow HSE requirement. Gas
tight damper shall be installed at fresh air duct at downstream of gas detector,
to close the fresh air passage tightly, upon detection of gas.
8.6.5 Air System
The detail designer shall select the type of equipment to be considered such as
Packaged type air-conditioner or DX type AHU or chilled water type AHU or
Terminal air-conditioning unit (such as room split air-conditioner or Fan Coil unit
etc., located in space itself).
For small building such as Gate House, (or space where small air-conditioner units
are allowed to keep inside of space such as Power skid), Terminal air-conditioning
unit are preferred. Packaged units are preferred for small capacity or where
moderate size HVAC system capacity is arrived, so that packaged air-conditioner
can be used without excessive multiplicity of units (not less than 50% capacity of
each package unit).
Air Handling units are preferred for larger system.
8.6.6 Air Velocity in HVAC Ducting System
The duct work shall be designed on equal friction method. The velocity of air in the
duct and its friction rate which shall be used during the detailed design are
summarized below.
Table 38: Velocity of Air and Friction Rate in the Duct
Maximum Friction
Maximum Velocity
HVAC Duct System Rate
(m/s)
(Pa/m)
Supply Air
Main duct small system (less than 6 0.8
3,000 LPS)
Main duct large system (above 3,000 LPS) 8 0.8
Duct branch with more than one diffuser or 4 0.8
register directly connected
Flexible ducts to outlets. (maximum length 2 0.8
3 m)
Duct branch to single diffuser or register 3 -
Return Air
Main duct small system (less than 6 0.8
3,000 LPS)
Main duct large system (above 3,000 LPS) 8 0.8
Maximum Friction
Maximum Velocity
HVAC Duct System Rate
(m/s)
(Pa/m)
Transfer duct 4 0.5
Branch duct 4 0.8
Free Flow through ceiling plenum 2 -
Through slots of ceiling plenum 2 -
Exhaust Air Duct 4 0.6
Fresh Air Duct 4 0.5
Duct work shall be constructed of galvanized sheet metal and all works shall be in
accordance with the current SMACNA standards.
Ductwork routings shall avoid going through noise sensitive areas or shall be
treated to avoid the transmission of noise to that area.
The friction rate of branch and sub-branch duct shall not exceed the friction rate of
its main and branch duct.
8.6.7 Water Velocity in Chilled Water System
The limitation of water velocity and pressure drop (or water friction loss) in chilled
water pipes shall be provided as below:
▪ Minimum pipe size for chilled water application shall be not be less than
Ø 25 mm;
▪ For pipe size Ø 50 mm and less:
» Maximum velocity shall be limited to 1.2 m/s.
▪ For pipe size above Ø 50 mm:
» The water velocity shall be limited so that the pressure drop in pipe shall
not exceed 400 Pa/m;
» The average pressure drop shall be 250 Pa/m or less;
» Velocity in excess of 1.2 m/s is acceptable for pipe size above Ø 50 mm.
8.6.8 Heat Transmission Data
Unless otherwise indicated, the heat transmission coefficient for the cooling load
calculation shall be re-checked by the designer.
Construction material shall be selected in such a way that the U-values will not
exceed the following:
▪ Roof u = 0.30 (W/m2/K);
▪ Outside walls u = 0.45 (W/m2/K);
▪ Windows u = 1.50 (W/m2/K);
▪ Steel Doors u = 2.00 (W/m2/K) (for single glass);
▪ Aluminium Glass Doors u = 5.60 (W/m2/K) (insulated).
Data such as U-valves, thermal resistances or thermal conductivities shall be taken
only from the following sources:
9.4 Voltage
Standard voltages and applications anticipated for the pumping stations and
related stuffs. It is assumed to be 13.8 kV, 3 phase, 60 Hz for medium voltage
system and 400 V, 3 phase, 5 wires, 60 Hz for low voltage system as per
requirements for LV loads.
The voltage available at the motor terminals during start-up will in any case be
adequate to ensure the start-up or re-acceleration of the motor (even at full load
where required) without damage of the motor.
However, at connection point to SEC distribution network, for non-repetitive
voltage variation, or voltage dips with motor-starting or power system switching,
the voltage variation shall not exceed 7% of the fundamental nominal voltage under
normal circumstances, as per The Saudi Arabia Distribution Code.
The maximum start-up voltage drop of 15% or 7% (at connection point to SEC
distribution network) is the sum of voltage drop in the cables, the bus bars and
transformers for motor feeding.
9.19 Cables
The MV & LV cables must be armored and made of high conductive electrolyte
copper conductors and XPLE insulated with a PVC outside cover in accordance
with BS 5468 or equivalent and extruded PVC sheathed cables manufactured to
BS 5467 for external cables.
All cabling and wiring shall comply with BS 7671, requirements for electrical
installations. IET wiring regulations.
Power and Control cables shall be segregated from instrument, signal, and
communication cables. All cables and conduits shall be provided with a tag
reference numbers.
All power, control and grounding cables shall be installed as per cable
manufacturer recommendation.
The proper sizing of cables is important to ensure that the cable can:
▪ Operate continuously under full load without being damaged;
▪ Provide the load with a suitable voltage (and avoid excessive voltage drops);
▪ Withstand the worst short circuits currents flowing through the cable.
LV cables laid outdoor shall be mainly installed in buried conduits. Installation in
ground without conduits may be allowed for some cases where consumers are
located out of main cable routes (i.e. outdoor lighting poles)
MV cables to VSDs should be installed in walkable cable ducts.
9.20 Lighting
The luminaire selection shall comply with BS EN 60598. Lighting levels will
generally be in accordance with the recommendations of the NWC code for the
interior lighting, Society of Light and Lighting guide, and relevant local standards.
The illumination levels are as follows:
Table 41: Illumination Level
Locations Lux Levels
Motors & Pump Halls 300
Offices 500
Distribution Board Room 500
Control Panel Room 500
Warehouses 150
Corridors 150
Workshop 300
Standard Power Generators Warehouse 200
Bathrooms 150
All lighting shall be provided with LED luminaries, only. This applies to indoor and
outdoor illumination, both. No mercury or HPS Lamps illumination shall be allowed.
The outdoor lighting required for each station contains the following subsystems:
▪ Road lighting (10 lx minimum illumination level);
▪ Area lighting including structures, valve and flow meter shafts, platforms and
other working places or areas outside of buildings (30 lx minimum illumination
level);
▪ Fence lighting (15 lx minimum illumination level);
▪ Entrance lighting (50 lx minimum illumination level).
The new installations for outdoor and fence lighting within existing stations shall
meet the used types (poles and lighting fixtures), as far as still available on the
market. The respective coordination and if necessary, extension and relocation of
existing lighting systems are part of the scope.
The EMG’s shall be placed together with all auxiliary facilities in a separate
generator room of the Emergency generator / Firefighting Building (if applicable)
or in own container outdoor installed.
Automatic start and switch-over is foreseen in case of total power failure at the
MDB level, with synchronization and switch back to normal without any interruption
if the power returns back. The EMG shall be designed to supply the full load of the
consumers connected to the ASB or essential bus bar, the final sizing of the EMG
is subject to detailed consumer load calculations, which is part of the final design.
A day fuel tank should be suitable for operation of 24 hours.
9.23 Earthing
For the entire station areas an equipotential meshed grounding network is to be
provided. For stations, which are to be extended, the existing earthing network
shall be considered. The new and the existing earthing network is to interconnect
at least at two (2) locations.
The system shall be designed and installed to provide a safe and effective earthing
system in accordance with BS 7430, NEC, and applicable local regulations.
The earth resistance of the overall interconnected station grounding network shall
not exceed 1 . For minor stations without high and medium installations a
maximum earth resistance of 2 will be accepted.
For installations in new stations, UPS, SCADA and telecommunication systems
shall not be grounded separately.
Each new building and high structure within the stations shall be provided with
lightning protection facilities. The lightning system consists of 0.3 m long collector
rods (air terminals), collector lines and down conductors from hot dip galvanised
round iron (St/tZn 10 mm) and the necessary fixing, connection and termination
elements.
Buildings shall be provided with mesh-type collector lines. The collectors have to
be configured in a way such that no point of the roof is at a distance of more than
5 m from a collector.
The maximum permitted mesh size is as follows:
▪ Buildings with telecommunication or control rooms 10 x 10 m
▪ Other buildings 10 x 20 m
Protruding roof superstructures, such as ladders, chimney stacks, pipes, antenna
mounting brackets, etc. and other metallic parts of buildings which are located near
the roof (e.g. louvers of ventilation openings) must be directly connected to the
collector lines.
The number of down conductors and the minimum distance between the
conductors is given as follows:
Buildings containing telecommunication and control systems
All field run cabling shall be armored with served steel wire or interlocked steel
armor under an extruded PVC outer jacket. Steel armor shall be galvanized.
All cables shall be routed segregated according to their voltage levels.
10.1.11 Power Supply
All systems and Instrumentation shall be supplied via the respective Uninterruptible
Power Supplies (UPS) system. Typically, redundant 220 VAC, 60 Hz, single phase
with 4 hour battery back-up for all control system equipment.
10.1.12 Grounding Systems
The grounding of measurement, control, and computer systems shall be arranged
to prevent electrical interference. Particular attention shall be given to the
arrangement of grounding circuits to prevent unwanted circulating currents in
grounding, signal and measurement conductors and screens.
Two grounding systems shall be required for Instrument systems to prevent start-
up and circulating currents of large motors and other electrical equipment from
interfering with the sensitive low current/power Instrumentation equipment:
▪ Safety earth grounding for personnel safety;
▪ Instrumentation D.C. and shield ground.
Both the safety ground and instrumentation D.C. and shield round must conform
to NEC
The Instrument ground and safety earth grounds shall be joined electrically at a
single point near a high-quality earth ground mat to prevent earth loops between
the two grounding systems.
The Instrument ground wiring shall be installed to provide a stable voltage
reference for all Instruments and PLC.
*) Typically the Command Authority between SCS and MCC shall not be
interlocked. That means e.g. a MOV can be closed or open either by SCS or MCC.
SCS and MCC-Operators shall align each other via Telephone. Normally the
process is fully controlled via MCC, only in case of system errors or requested by
MCC, SCC shall operate the process. In case the design consultants identify a
requirement of an interlock due to safety reasons (e.g. to ensure correct
implementation of a flow path direction) an interlock can be provided for special
cases.
**) The Quality of the water shall be constantly supervised and reported. The
SCADA system shall generate daily reports, showing received and dispatched
water combined with the online measured and sampled water quality. Online
monitoring and water sampling shall be provided accordingly. The status of
available samples shall also be reported. For water quality monitoring systems
reference is made to 10.3.17 TSE Quality Monitoring.
***) To be considered for future extensions are:
» The operation of decentralised systems with package units, if such a
system is to be implemented for further treatment of TSE (reduction of
TDS value, see MP);
» Operation of the neighbouring tanks and water distribution downstream of
the neighbouring tanks.
MCC
Redundant
communication
HVAC
Instrument
Air
CMS/ Vibration and
Condition monitoring
VMS
Chemical
injection
In some cases in the network the flow direction may change, this shall be indicated
properly.
10.3.4 Water Demand Forecasts
To distribute the available water according to the pre-determined distribution
schedule is the main task of the Operators at MCC. The Operators needs to see
in one glance how much water is available and for how long the reserves will last
according to supply targets.
In case that the water delivery schedule cannot be met, the system shall warn the
Operators. The system shall make suggestion for new supply targets.
Water demand shall be forecasted on daily, weekly and monthly basis, Basis for
the forecast shall be based on the previous consumptions of the past 5 years and
the number of consumers.
Supply targets shall be suggested by the system, based on forecasted demand
and available water resources. Available water resources shall be calculated
based on available water levels and expected supply.
Once the targets are fixed, the system shall automatically suggests flow paths and
flow set points, which will, once confirmed by the Operators, automatically
implemented.
The MCC software shall provide an HMI for configuration, which makes it simple
for Operators to configure changes in the network and new customers, etc. The
software shall also consider that any distribution beyond pre-approved daily or
weekly quantities as well as distribution to new costumers shall require manager
approval (this requirement is to remain in place as long as demand exceeds
supply).
10.3.5 Online Mass Balances (Leak Detection) and Quality Tracking
The principle shall be that the water coming in / leaving the system and the water
which is contained in the system shall always be balanced. An online Leak
detection system shall be provided which alarms water losses beyond certain
thresholds. The sensitivity of the leak detection shall be evaluated by the SCADA
Consultant. This is important especially for the pipelines, but also the flow to the
neighbourhood tanks shall be supervised online by the Leak detection system.
Mass Balances shall be reported on daily, weekly and monthly basis.
The water quality in the system shall always be monitored and tracked as far as
possible. Also quality deviations beyond certain thresholds shall be alarmed.
It shall be possible for the operators to configure the thresholds for the leak
detection system and the quality monitoring. Every change shall be logged by the
SCADA system.
10.3.6 Flow and Pressure Control
The required set points for flow- or pressure shall be suggested by the SCADA
system. Implementation of flow- and pressure control shall be carried out on SCS
level. For pump stations with N+1 Pumps the required number of pumps shall be
▪ TSS
▪ BOD
▪ Ammonia Nitrogen (NH3-N)
▪ Nitrate (NO3-N)
▪ Residual Chlorine
A feasible instrumentation able to obtain online measurements shall be considered
and in case of non-compliance of these parameters with the unrestricted TSE
reuse regulation, a notification system shall be provided in order to impose an
automatic shutdown, avoiding the contamination of the Strategic Tanks and of the
TSE network.
In addition to the online measurements, daily samples shall be taken at the first
monitoring point in the immediate vicinity of the WWTP, as well as within the
Strategic Tanks, prior to the distribution to the Secondary Mains and to the
Neighbourhood Tanks.
It is understood that TSE originating from different WWTPs, may be collected and
mixed in common Strategic Tanks. The mixing of different TSE sources within the
Strategic Tanks could be beneficial to promote further dilution of eventual TSE
streams, which may be characterized by higher concentration of certain
parameters.
The daily sample shall be analyzed in a laboratory and the sampling strategy shall
be performed accordingly to the one described in the following table:
Table 46: TSE Sampling Strategy
Parameter Sample Frequency, Type Compliance requirement
No more than two (2) samples
Biochemical Oxygen
Daily,24-hour composite per month may exceed the
Demand, 5-day (BOD5)
standard
No more than two (2) samples
Total Suspended Solids
Daily,24-hour composite per month may exceed the
(TSS)
standard
No more than two (2) samples
Total Dissolved Solids
Daily,24-hour composite per month may exceed the
(TDS)
standard
Average of daily samples
Ammonia Nitrogen (NH3-
Daily,24-hour composite during a month may not
N)
exceed the standard
Average of daily samples
Nitrate Nitrogen (NO3-N) Daily, 24-hour composite during a month may not
exceed the standard
Average of daily samples
Total Nitrogen (TN) Daily, 24-hour composite during a month may not
exceed the standard
No more than two (2) samples
Total Phosphorous (TP) Daily, 24-hour composite per month may exceed the
standard
rooms and battery rooms. Dedicated bottle rooms for the clean agent shall be
provided. NOVEC is the preferred extinguishing agent. In the extinguishing
zone negative pressure occurs briefly when flooding begins. During the
flooding process the pressure increases – excess pressure occurs. For the
proper function of the fire suppression system and to avoid structural damage
in the protected enclosure, negative pressure and excess pressure must be
dissipated from the extinguishing zone via a pressure relief device.
12 UTILITY CONNECTIONS
Drinking water for those facilities that require it, will be supplied in through the
existing water distribution network if possible. The designer must verify that the
water network has the capacity to supply the service to the facility. If this is not
possible, it will be supplied through tanker trucks to tanks located in the vicinity of
the facility. Storage tanks should have a minimum capacity of 1 week, estimated
on the base of the water requirements. In both cases the designer must complete
the designs to supply the facility.
Electricity will be supplied in the first instance from the electrical power line closest
to the facility. The designer will validate that the existing network has sufficient
capacity to supply the service. The electrical wiring from the nearest network must
be carried out by the designer. For temporary works, the use of power plants can
be considered, which can later serve as back-up to the facilities.
If wastewater is generated, the designer should consider the connection of the
facility to the wastewater network of the area. In the event that the area does not
have wastewater network, the designer should design the collection, transport and
treatment for the wastewater.
Lead Pb 0.1
Lithium Li 2.5
Manganese Mn 0.2
Mercury 0.001
Molybdenum Mo 0.01
Nickel Ni 0.2
Selenium Se 0.02
Vanadium V 0.1
Zinc Zn 4.0
Notes:
(A-1) The monthly average for each TSS, BOD5 shall not exceed 10 mg/liter.
(A-2) The weekly average for each TSS, BOD5 shall not exceed 15 mg/liter.
(B) The treated sewage water is considered sanitized to a non-contagious
degree and sufficient for use in unrestricted irrigation if the maximum possible
number (MPN) of the fecal coliform does not exceed 2.2 for each 100 mm (or
its equivalent in other measurement methods) in accordance with bacteria test
findings within a week. In addition, it shall not exceed 23 for each 100 mm in
any sample (or its equivalent in other measurement methods).
(+) Not less than 0.2 mg/liter in the case of chlorine used in sanitization.
14.5 Waste
The “General Environmental Regulations and Rules for Implementation” stipulates
the environmental requirements regarding waste and hazardous waste, as well as
related issues which are set forth in Articles 13 and 14 of the regulation. Some
relevant requirements include:
▪ Prevent direct or indirect contamination of surface, ground and coastal waters
that may be caused by solid or liquid residues.
▪ Prevent the discharge, in any quantity, of any type of solid or liquid wastes,
substance, element, organic or inorganic compound that may be classified as
hazardous into surface, ground or coastal waters
▪ All agencies and persons shall comply with local regulations, standards,
guidelines, and instructions concerning the production, exchange, storage,
treatment, recycling and transportation of hazardous, toxic or radioactive
wastes.
▪ No persons or agencies may dispose of chemical, toxic, hazardous, or
radioactive materials without a license from the PME.
▪ The disposal or discharge of any harmful pollutants, poisonous, hazardous, or
radioactive wastes are prohibited in the territorial waters or the free economic
zone.
In addition, the rules, and procedures to control hazardous wastes are specified in
Appendix 4 of the “General Environmental Regulations and Rules for
Implementation”.
The detail design shall identify the project components which may responsible to
produce substantial waste both non-hazardous and hazardous, during construction
and operation, and include provisions, such as temporary storage areas, to enable
the management of the waste according to the requirements above.
APPENDICES
Appendix 1: TSE System Schematic
02-PM01-PSV400 01-PS16
Phase 2
Bi-directional Flow
02-PS07 02-PS10 01-PM04-PSV100
01-PM02-PSV100
1
02-PM02 CON PZ 2
CON PZ 3
02-PM02-PSV300 01-PM05
1
1
1 01-WT09
01-PS09
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
1
02-PS05
1
CON PZ 4
02-WT12 Wadi
01-PS02 01-PM02 Tagging of Locations and Primary Pipelines
02-PM01-PSV200 1-Tag Master Plan 2-Tag 3-Description
1
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
01-PS01 01-PM01
NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
01-PS13
1
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
1 PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
1 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
1
1
02-PM01 Primary Main from WT13 to WT12
02-PM02 Primary Main from 02-WT12 to 02-WT10
03-PM01 02-PM03 Primary Main from 02-PM02 to 02-WT15
PS-RCRC-04 02-PS04 PS from 02-WT12 to PZ4
PS-RCRC-xx 02-PS05 PS from 02-WT12 to 02-WT10
PS-RCRC-07 02-PS07 PS to WT_RCRC_07(Zone 3)
PS-RCRC-08 02-PS08 PS to WT_RCTC_15 (Zone 3)
PS-RCRC-10 02-PS10 PS to Zone 2
03-PS02
03-PM01-PSV002 1a WT-RCRC-10 02-WT10 Strategic Storage - Al Arubah Park
WT-RCRC-12 02-WT12 Water Tower 12
WT-RCRC-15 02-WT15 Zone 2 Reservoir (King Salman Park)
03-PM04-PSV001
BPT-RCRC-05 03-BPT-05 Break Pressure Tank in Zone 1
03-BPT-05 1a 03-WT02
03-PM01 Primary Main from 03-WT01 to 01-WT13
03-PM04 03-PM03 03-PS03
Twin Pipline 03-PM02 Primary Main from 03-WT02 to 01-WT09
1b 1b 03-PM03 Primary Main from 03-WT02 to 01-BPT05
03-PM04 Primary Main from 01-BPT05 to 03-PM01
1b PS-RCRC-01 03-PS01 PS from 03-WT01 to 03PM01 and 03PM04
PS-RCRC-02 03-PS02 PS at Heet WWTP
03-PS01 PS-RCRC-03 03-PS03 PS at Heet WWTP
WT-RCRC-01 03-WT01 Pump Sump Al Hair WWTP
WT-RCRC-02 03-WT02 Heet WWTP
03-WT01 PS-RCRC-11 0X-PS11 PS North WWTP
PS-RCRC-12 0X-PS12 PS East WWTP
Client: Project: Consultant: Document Name:
Green Riyadh TSE Network Schematic – Primary
TSE Supply for Green Riyadh System
01 Updated for Review 28.11.2021 MI MH DC Programme
Royal Commission for Riyadh Document No.:
00 Issued for Review 29.10.2021 MH MI DC City PMC and Design Coordination ILF Consulting Engineers TSE-G-GN-00-ILF-G-EN-PLN-00002
Rev. Issue or Revision Date Prep. Check Appr.
Notes Legend
01-PS17
2 01-WT04
To Sodous Not in Scope: 0X-PS11
01-PS06 WWTP, Wastewater Treatment Plant
0X-PS12
01-PM06
2 01-WT17 PSV, Pressure Sustaining Valve
CON PZ 3
01-PS15 Optional Expansion – to be discussed
02-PM01-PSV400 01-PS16
Phase 2
Bi-directional Flow
02-PS07 02-PS10 01-PM04-PSV100
2 Operational Mode 2
01-PM02-PSV100
2
02-PM02 CON PZ 2
2
CON PZ 3
2
02-PM02-PSV300 01-PM05
2 01-WT09
01-PS09
2
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
2
02-PS05
2
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
2 NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PS01 01-PM01
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
01-PS13
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
2 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
2
2
02-PM01 Primary Main from WT13 to WT12
02-PM02 Primary Main from 02-WT12 to 02-WT10
03-PM01 02-PM03 Primary Main from 02-PM02 to 02-WT15
PS-RCRC-04 02-PS04 PS from 02-WT12 to PZ4
PS-RCRC-xx 02-PS05 PS from 02-WT12 to 02-WT10
PS-RCRC-07 02-PS07 PS to WT_RCRC_07(Zone 3)
PS-RCRC-08 02-PS08 PS to WT_RCTC_15 (Zone 3)
PS-RCRC-10 02-PS10 PS to Zone 2
03-PS02
03-PM01-PSV002 2a WT-RCRC-10 02-WT10 Strategic Storage - Al Arubah Park
WT-RCRC-12 02-WT12 Water Tower 12
2a WT-RCRC-15 02-WT15 Zone 2 Reservoir (King Salman Park)
03-PM04-PSV001
BPT-RCRC-05 03-BPT-05 Break Pressure Tank in Zone 1
2b 03-BPT-05 2b 03-WT02
03-PM01 Primary Main from 03-WT01 to 01-WT13
03-PM04 03-PM03 03-PS03
Twin Pipline 03-PM02 Primary Main from 03-WT02 to 01-WT09
03-PM03 Primary Main from 03-WT02 to 01-BPT05
2b 03-PM04 Primary Main from 01-BPT05 to 03-PM01
PS-RCRC-01 03-PS01 PS from 03-WT01 to 03PM01 and 03PM04
PS-RCRC-02 03-PS02 PS at Heet WWTP
03-PS01 PS-RCRC-03 03-PS03 PS at Heet WWTP
WT-RCRC-01 03-WT01 Pump Sump Al Hair WWTP
WT-RCRC-02 03-WT02 Heet WWTP
03-WT01 PS-RCRC-11 0X-PS11 PS North WWTP
PS-RCRC-12 0X-PS12 PS East WWTP
Client: Project: Consultant: Document Name:
Green Riyadh TSE Network Schematic – Primary
TSE Supply for Green Riyadh System
01 Updated for Review 28.11.2021 MI MH DC Programme
Royal Commission for Riyadh Document No.:
00 Issued for Review 29.10.2021 MH MI DC City PMC and Design Coordination ILF Consulting Engineers TSE-G-GN-00-ILF-G-EN-PLN-00002
Rev. Issue or Revision Date Prep. Check Appr.
Notes Legend
01-PS17
3 01-WT04
To Sodous Not in Scope: 0X-PS11
01-PS06 WWTP, Wastewater Treatment Plant
0X-PS12
01-PM06
3 01-WT17 PSV, Pressure Sustaining Valve
CON PZ 3
01-PS15 Optional Expansion – to be discussed
02-PM01-PSV400 01-PS16
Phase 2
Bi-directional Flow
02-PS07 02-PS10 01-PM04-PSV100
3 Operational Mode 3
01-PM02-PSV100
3
02-PM02 CON PZ 2
3
CON PZ 3
02-PM02-PSV300 01-PM05
3
01-WT09
01-PS09
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
02-PS05
CON PZ 4
02-WT12 Wadi
01-PS02 01-PM02 Tagging of Locations and Primary Pipelines
02-PM01-PSV200 1-Tag Master Plan 2-Tag 3-Description
3
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
01-PS01 01-PM01
NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
01-PS13
3
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
3 PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
3 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
3b
3
02-PM01 Primary Main from WT13 to WT12
02-PM02 Primary Main from 02-WT12 to 02-WT10
03-PM01 02-PM03 Primary Main from 02-PM02 to 02-WT15
PS-RCRC-04 02-PS04 PS from 02-WT12 to PZ4
PS-RCRC-xx 02-PS05 PS from 02-WT12 to 02-WT10
PS-RCRC-07 02-PS07 PS to WT_RCRC_07(Zone 3)
PS-RCRC-08 02-PS08 PS to WT_RCTC_15 (Zone 3)
PS-RCRC-10 02-PS10 PS to Zone 2
03-PS02
03-PM01-PSV002 3 WT-RCRC-10 02-WT10 Strategic Storage - Al Arubah Park
WT-RCRC-12 02-WT12 Water Tower 12
3a WT-RCRC-15 02-WT15 Zone 2 Reservoir (King Salman Park)
03-PM04-PSV001
BPT-RCRC-05 03-BPT-05 Break Pressure Tank in Zone 1
03-WT02
03-BPT-05 03-PM01 Primary Main from 03-WT01 to 01-WT13
03-PM04 03-PM03 03-PS03
Twin Pipline 03-PM02 Primary Main from 03-WT02 to 01-WT09
03-PM03 Primary Main from 03-WT02 to 01-BPT05
03-PM04 Primary Main from 01-BPT05 to 03-PM01
PS-RCRC-01 03-PS01 PS from 03-WT01 to 03PM01 and 03PM04
PS-RCRC-02 03-PS02 PS at Heet WWTP
03-PS01 PS-RCRC-03 03-PS03 PS at Heet WWTP
WT-RCRC-01 03-WT01 Pump Sump Al Hair WWTP
WT-RCRC-02 03-WT02 Heet WWTP
03-WT01 PS-RCRC-11 0X-PS11 PS North WWTP
PS-RCRC-12 0X-PS12 PS East WWTP
Client: Project: Consultant: Document Name:
Green Riyadh TSE Network Schematic – Primary
TSE Supply for Green Riyadh System
01 Updated for Review 28.11.2021 MI MH DC Programme
Royal Commission for Riyadh Document No.:
00 Issued for Review 29.10.2021 MH MI DC City PMC and Design Coordination ILF Consulting Engineers TSE-G-GN-00-ILF-G-EN-PLN-00002
Rev. Issue or Revision Date Prep. Check Appr.
Notes Legend
01-PS17
4 01-WT04
To Sodous Not in Scope: 0X-PS11
01-PS06 WWTP, Wastewater Treatment Plant
0X-PS12
01-PM06
4 01-WT17 PSV, Pressure Sustaining Valve
CON PZ 3
01-PS15 Optional Expansion – to be discussed
02-PM01-PSV400 01-PS16
Phase 2
4 Operational Mode 4
01-PM02-PSV100
02-PM02 CON PZ 2
4
CON PZ 3
02-PM02-PSV300 01-PM05
4
4 01-WT09
01-PS09
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
4
02-PS05
4
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
4 NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PS01 01-PM01
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
01-PS13
4
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
4 PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
4 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
4
4
02-PM01 Primary Main from WT13 to WT12
02-PM02 Primary Main from 02-WT12 to 02-WT10
03-PM01 02-PM03 Primary Main from 02-PM02 to 02-WT15
PS-RCRC-04 02-PS04 PS from 02-WT12 to PZ4
PS-RCRC-xx 02-PS05 PS from 02-WT12 to 02-WT10
PS-RCRC-07 02-PS07 PS to WT_RCRC_07(Zone 3)
PS-RCRC-08 02-PS08 PS to WT_RCTC_15 (Zone 3)
PS-RCRC-10 02-PS10 PS to Zone 2
03-PM01-PSV002 03-PS02 WT-RCRC-10 02-WT10 Strategic Storage - Al Arubah Park
WT-RCRC-12 02-WT12 Water Tower 12
WT-RCRC-15 02-WT15 Zone 2 Reservoir (King Salman Park)
03-PM04-PSV001
BPT-RCRC-05 03-BPT-05 Break Pressure Tank in Zone 1
4 03-BPT-05 4 03-WT02
03-PM01 Primary Main from 03-WT01 to 01-WT13
03-PM04 03-PM03 03-PS03
Twin Pipline 03-PM02 Primary Main from 03-WT02 to 01-WT09
03-PM03 Primary Main from 03-WT02 to 01-BPT05
4 03-PM04 Primary Main from 01-BPT05 to 03-PM01
PS-RCRC-01 03-PS01 PS from 03-WT01 to 03PM01 and 03PM04
PS-RCRC-02 03-PS02 PS at Heet WWTP
03-PS01 PS-RCRC-03 03-PS03 PS at Heet WWTP
WT-RCRC-01 03-WT01 Pump Sump Al Hair WWTP
WT-RCRC-02 03-WT02 Heet WWTP
03-WT01 PS-RCRC-11 0X-PS11 PS North WWTP
PS-RCRC-12 0X-PS12 PS East WWTP
Client: Project: Consultant: Document Name:
Green Riyadh TSE Network Schematic – Primary
TSE Supply for Green Riyadh System
01 Updated for Review 28.11.2021 MI MH DC Programme
Royal Commission for Riyadh Document No.:
00 Issued for Review 29.10.2021 MH MI DC City PMC and Design Coordination ILF Consulting Engineers TSE-G-GN-00-ILF-G-EN-PLN-00002
Rev. Issue or Revision Date Prep. Check Appr.
Notes Legend
01-PS17
5 01-WT04
To Sodous Not in Scope: 0X-PS11
01-PS06 WWTP, Wastewater Treatment Plant
0X-PS12
01-PM06
5 01-WT17 PSV, Pressure Sustaining Valve
CON PZ 3
01-PS15 Optional Expansion – to be discussed
02-PM01-PSV400 01-PS16
Phase 2
Bi-directional Flow
02-PS07 02-PS10 01-PM04-PSV100
5 Operational Mode 5
01-PM02-PSV100
5
02-PM02 CON PZ 2
5
CON PZ 3
02-PM02-PSV300 01-PM05
5
5 01-WT09
01-PS09
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
5
02-PS05
5
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
5 NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PS01 01-PM01
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
01-PS13
5
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
5 PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
5 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
5
5
02-PM01 Primary Main from WT13 to WT12
02-PM02 Primary Main from 02-WT12 to 02-WT10
03-PM01 02-PM03 Primary Main from 02-PM02 to 02-WT15
PS-RCRC-04 02-PS04 PS from 02-WT12 to PZ4
PS-RCRC-xx 02-PS05 PS from 02-WT12 to 02-WT10
PS-RCRC-07 02-PS07 PS to WT_RCRC_07(Zone 3)
PS-RCRC-08 02-PS08 PS to WT_RCTC_15 (Zone 3)
PS-RCRC-10 02-PS10 PS to Zone 2
03-PS02
03-PM01-PSV002 5a WT-RCRC-10 02-WT10 Strategic Storage - Al Arubah Park
WT-RCRC-12 02-WT12 Water Tower 12
5a WT-RCRC-15 02-WT15 Zone 2 Reservoir (King Salman Park)
03-PM04-PSV001
BPT-RCRC-05 03-BPT-05 Break Pressure Tank in Zone 1
5b 03-BPT-05 5b 03-WT02
03-PM01 Primary Main from 03-WT01 to 01-WT13
03-PM04 03-PM03 03-PS03
Twin Pipline 03-PM02 Primary Main from 03-WT02 to 01-WT09
03-PM03 Primary Main from 03-WT02 to 01-BPT05
5b 03-PM04 Primary Main from 01-BPT05 to 03-PM01
PS-RCRC-01 03-PS01 PS from 03-WT01 to 03PM01 and 03PM04
PS-RCRC-02 03-PS02 PS at Heet WWTP
03-PS01 PS-RCRC-03 03-PS03 PS at Heet WWTP
WT-RCRC-01 03-WT01 Pump Sump Al Hair WWTP
WT-RCRC-02 03-WT02 Heet WWTP
03-WT01 PS-RCRC-11 0X-PS11 PS North WWTP
PS-RCRC-12 0X-PS12 PS East WWTP
Client: Project: Consultant: Document Name:
Green Riyadh TSE Network Schematic – Primary
TSE Supply for Green Riyadh System
01 Updated for Review 28.11.2021 MI MH DC Programme
Royal Commission for Riyadh Document No.:
00 Issued for Review 29.10.2021 MH MI DC City PMC and Design Coordination ILF Consulting Engineers TSE-G-GN-00-ILF-G-EN-PLN-00002
Rev. Issue or Revision Date Prep. Check Appr.
Notes Legend
01-PS17
6 01-WT04
To Sodous Not in Scope: 0X-PS11
01-PS06 WWTP, Wastewater Treatment Plant
0X-PS12
01-PM06
6 01-WT17 PSV, Pressure Sustaining Valve
CON PZ 3
01-PS15 Optional Expansion – to be discussed
02-PM01-PSV400 01-PS16
Phase 2
Bi-directional Flow
02-PS07 02-PS10 01-PM04-PSV100
6 Operational Mode 6
01-PM02-PSV100
6
02-PM02 CON PZ 2
CON PZ 3
02-PM02-PSV300 01-PM05
6 01-WT09
01-PS09
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
6
02-PS05
6
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
6 NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PS01 01-PM01
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
01-PS13
6
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
6 PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
6 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
6
6
02-PM01 Primary Main from WT13 to WT12
02-PM02 Primary Main from 02-WT12 to 02-WT10
03-PM01 02-PM03 Primary Main from 02-PM02 to 02-WT15
PS-RCRC-04 02-PS04 PS from 02-WT12 to PZ4
PS-RCRC-xx 02-PS05 PS from 02-WT12 to 02-WT10
PS-RCRC-07 02-PS07 PS to WT_RCRC_07(Zone 3)
PS-RCRC-08 02-PS08 PS to WT_RCTC_15 (Zone 3)
PS-RCRC-10 02-PS10 PS to Zone 2
03-PS02
03-PM01-PSV002 6a WT-RCRC-10 02-WT10 Strategic Storage - Al Arubah Park
WT-RCRC-12 02-WT12 Water Tower 12
6a WT-RCRC-15 02-WT15 Zone 2 Reservoir (King Salman Park)
03-PM04-PSV001
BPT-RCRC-05 03-BPT-05 Break Pressure Tank in Zone 1
6b 03-BPT-05 6b 03-WT02
03-PM01 Primary Main from 03-WT01 to 01-WT13
03-PM04 03-PM03 03-PS03
Twin Pipline 03-PM02 Primary Main from 03-WT02 to 01-WT09
03-PM03 Primary Main from 03-WT02 to 01-BPT05
6b 03-PM04 Primary Main from 01-BPT05 to 03-PM01
PS-RCRC-01 03-PS01 PS from 03-WT01 to 03PM01 and 03PM04
PS-RCRC-02 03-PS02 PS at Heet WWTP
03-PS01 PS-RCRC-03 03-PS03 PS at Heet WWTP
WT-RCRC-01 03-WT01 Pump Sump Al Hair WWTP
WT-RCRC-02 03-WT02 Heet WWTP
03-WT01 PS-RCRC-11 0X-PS11 PS North WWTP
PS-RCRC-12 0X-PS12 PS East WWTP
Client: Project: Consultant: Document Name:
Green Riyadh TSE Network Schematic – Primary
TSE Supply for Green Riyadh System
01 Updated for Review 28.11.2021 MI MH DC Programme
Royal Commission for Riyadh Document No.:
00 Issued for Review 29.10.2021 MH MI DC City PMC and Design Coordination ILF Consulting Engineers TSE-G-GN-00-ILF-G-EN-PLN-00002
Rev. Issue or Revision Date Prep. Check Appr.
Notes Legend
01-PS17
7 01-WT04
To Sodous Not in Scope: 0X-PS11
01-PS06 WWTP, Wastewater Treatment Plant
0X-PS12
01-PM06
7 01-WT17 PSV, Pressure Sustaining Valve
CON PZ 3
01-PS15 Optional Expansion – to be discussed
02-PM01-PSV400 01-PS16
Phase 2
Bi-directional Flow
02-PS07 02-PS10 01-PM04-PSV100
7 Operational Mode 7
01-PM02-PSV100
7
02-PM02 CON PZ 2
CON PZ 3
02-PM02-PSV300 01-PM05
7
7 01-WT09
01-PS09
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
7
02-PS05
CON PZ 4
02-WT12 Wadi
01-PS02 01-PM02 Tagging of Locations and Primary Pipelines
02-PM01-PSV200 1-Tag Master Plan 2-Tag 3-Description
7
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
7 NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PS01 01-PM01
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
01-PS13
7
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
7 PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
7 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
7
7
02-PM01 Primary Main from WT13 to WT12
02-PM02 Primary Main from 02-WT12 to 02-WT10
03-PM01 02-PM03 Primary Main from 02-PM02 to 02-WT15
PS-RCRC-04 02-PS04 PS from 02-WT12 to PZ4
PS-RCRC-xx 02-PS05 PS from 02-WT12 to 02-WT10
PS-RCRC-07 02-PS07 PS to WT_RCRC_07(Zone 3)
PS-RCRC-08 02-PS08 PS to WT_RCTC_15 (Zone 3)
PS-RCRC-10 02-PS10 PS to Zone 2
03-PS02
03-PM01-PSV002 7a WT-RCRC-10 02-WT10 Strategic Storage - Al Arubah Park
WT-RCRC-12 02-WT12 Water Tower 12
7a WT-RCRC-15 02-WT15 Zone 2 Reservoir (King Salman Park)
03-PM04-PSV001
BPT-RCRC-05 03-BPT-05 Break Pressure Tank in Zone 1
7b 03-BPT-05 7b 03-WT02
03-PM01 Primary Main from 03-WT01 to 01-WT13
03-PM04 03-PM03 03-PS03
Twin Pipline 03-PM02 Primary Main from 03-WT02 to 01-WT09
03-PM03 Primary Main from 03-WT02 to 01-BPT05
7b 03-PM04 Primary Main from 01-BPT05 to 03-PM01
PS-RCRC-01 03-PS01 PS from 03-WT01 to 03PM01 and 03PM04
PS-RCRC-02 03-PS02 PS at Heet WWTP
03-PS01 PS-RCRC-03 03-PS03 PS at Heet WWTP
WT-RCRC-01 03-WT01 Pump Sump Al Hair WWTP
WT-RCRC-02 03-WT02 Heet WWTP
03-WT01 PS-RCRC-11 0X-PS11 PS North WWTP
PS-RCRC-12 0X-PS12 PS East WWTP
Client: Project: Consultant: Document Name:
Green Riyadh TSE Network Schematic – Primary
TSE Supply for Green Riyadh System
01 Updated for Review 28.11.2021 MI MH DC Programme
Royal Commission for Riyadh Document No.:
00 Issued for Review 29.10.2021 MH MI DC City PMC and Design Coordination ILF Consulting Engineers TSE-G-GN-00-ILF-G-EN-PLN-00002
Rev. Issue or Revision Date Prep. Check Appr.
Notes Legend
01-PS17
8 01-WT04
To Sodous Not in Scope: 0X-PS11
01-PS06 WWTP, Wastewater Treatment Plant
0X-PS12
01-PM06
8 01-WT17 PSV, Pressure Sustaining Valve
CON PZ 3
01-PS15 Optional Expansion – to be discussed
02-PM01-PSV400 01-PS16
Phase 2
Bi-directional Flow
02-PS07 02-PS10 01-PM04-PSV100
8 Operational Mode 8
01-PM02-PSV100
8
02-PM02 CON PZ 2
CON PZ 3
02-PM02-PSV300 01-PM05
8
8 01-WT09
01-PS09
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
8
02-PS05
8
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
8 NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PS01 01-PM01
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
01-PS13
8
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
8 PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
8 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
8
8
02-PM01 Primary Main from WT13 to WT12
02-PM02 Primary Main from 02-WT12 to 02-WT10
03-PM01 02-PM03 Primary Main from 02-PM02 to 02-WT15
PS-RCRC-04 02-PS04 PS from 02-WT12 to PZ4
PS-RCRC-xx 02-PS05 PS from 02-WT12 to 02-WT10
PS-RCRC-07 02-PS07 PS to WT_RCRC_07(Zone 3)
PS-RCRC-08 02-PS08 PS to WT_RCTC_15 (Zone 3)
PS-RCRC-10 02-PS10 PS to Zone 2
03-PS02
03-PM01-PSV002 8a WT-RCRC-10 02-WT10 Strategic Storage - Al Arubah Park
WT-RCRC-12 02-WT12 Water Tower 12
8a WT-RCRC-15 02-WT15 Zone 2 Reservoir (King Salman Park)
03-PM04-PSV001
BPT-RCRC-05 03-BPT-05 Break Pressure Tank in Zone 1
8b 03-BPT-05 8b 03-WT02
03-PM01 Primary Main from 03-WT01 to 01-WT13
03-PM04 03-PM03 03-PS03
Twin Pipline 03-PM02 Primary Main from 03-WT02 to 01-WT09
03-PM03 Primary Main from 03-WT02 to 01-BPT05
8b 03-PM04 Primary Main from 01-BPT05 to 03-PM01
PS-RCRC-01 03-PS01 PS from 03-WT01 to 03PM01 and 03PM04
PS-RCRC-02 03-PS02 PS at Heet WWTP
03-PS01 PS-RCRC-03 03-PS03 PS at Heet WWTP
WT-RCRC-01 03-WT01 Pump Sump Al Hair WWTP
WT-RCRC-02 03-WT02 Heet WWTP
03-WT01 PS-RCRC-11 0X-PS11 PS North WWTP
PS-RCRC-12 0X-PS12 PS East WWTP
Client: Project: Consultant: Document Name:
Green Riyadh TSE Network Schematic – Primary
TSE Supply for Green Riyadh System
01 Updated for Review 28.11.2021 MI MH DC Programme
Royal Commission for Riyadh Document No.:
00 Issued for Review 29.10.2021 MH MI DC City PMC and Design Coordination ILF Consulting Engineers TSE-G-GN-00-ILF-G-EN-PLN-00002
Rev. Issue or Revision Date Prep. Check Appr.
Notes Legend
01-PS17
9 01-WT04
To Sodous Not in Scope: 0X-PS11
01-PS06 WWTP, Wastewater Treatment Plant
0X-PS12
01-PM06
01-WT17 PSV, Pressure Sustaining Valve
CON PZ 3
01-PS15 Optional Expansion – to be discussed
02-PM01-PSV400 01-PS16
Phase 2
Bi-directional Flow
02-PS07 02-PS10 01-PM04-PSV100
9 Operational Mode 9
01-PM02-PSV100
9
02-PM02 CON PZ 2
9
CON PZ 3
02-PM02-PSV300 01-PM05
9
9 01-WT09
01-PS09
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
9
02-PS05
9
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
9 NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PS01 01-PM01
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
01-PS13
9
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
9 PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
9 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
9
9
02-PM01 Primary Main from WT13 to WT12
02-PM02 Primary Main from 02-WT12 to 02-WT10
03-PM01 02-PM03 Primary Main from 02-PM02 to 02-WT15
PS-RCRC-04 02-PS04 PS from 02-WT12 to PZ4
PS-RCRC-xx 02-PS05 PS from 02-WT12 to 02-WT10
PS-RCRC-07 02-PS07 PS to WT_RCRC_07(Zone 3)
PS-RCRC-08 02-PS08 PS to WT_RCTC_15 (Zone 3)
PS-RCRC-10 02-PS10 PS to Zone 2
03-PS02
03-PM01-PSV002 9a WT-RCRC-10 02-WT10 Strategic Storage - Al Arubah Park
WT-RCRC-12 02-WT12 Water Tower 12
9a WT-RCRC-15 02-WT15 Zone 2 Reservoir (King Salman Park)
03-PM04-PSV001
BPT-RCRC-05 03-BPT-05 Break Pressure Tank in Zone 1
9b 03-BPT-05 9b 03-WT02
03-PM01 Primary Main from 03-WT01 to 01-WT13
03-PM04 03-PM03 03-PS03
Twin Pipline 03-PM02 Primary Main from 03-WT02 to 01-WT09
03-PM03 Primary Main from 03-WT02 to 01-BPT05
9b 03-PM04 Primary Main from 01-BPT05 to 03-PM01
PS-RCRC-01 03-PS01 PS from 03-WT01 to 03PM01 and 03PM04
PS-RCRC-02 03-PS02 PS at Heet WWTP
03-PS01 PS-RCRC-03 03-PS03 PS at Heet WWTP
WT-RCRC-01 03-WT01 Pump Sump Al Hair WWTP
WT-RCRC-02 03-WT02 Heet WWTP
03-WT01 PS-RCRC-11 0X-PS11 PS North WWTP
PS-RCRC-12 0X-PS12 PS East WWTP
Client: Project: Consultant: Document Name:
Green Riyadh TSE Network Schematic – Primary
TSE Supply for Green Riyadh System
01 Updated for Review 28.11.2021 MI MH DC Programme
Royal Commission for Riyadh Document No.:
00 Issued for Review 29.10.2021 MH MI DC City PMC and Design Coordination ILF Consulting Engineers TSE-G-GN-00-ILF-G-EN-PLN-00002
Rev. Issue or Revision Date Prep. Check Appr.
Notes Legend
01-PS17
10 01-WT04
To Sodous Not in Scope: 0X-PS11
01-PS06 WWTP, Wastewater Treatment Plant
0X-PS12
01-PM06
10 01-WT17 PSV, Pressure Sustaining Valve
CON PZ 3
01-PS15 Optional Expansion – to be discussed
02-PM01-PSV400 01-PS16
Phase 2
Bi-directional Flow
02-PS07 02-PS10 01-PM04-PSV100
10 Operational Mode 10
01-PM02-PSV100
10
02-PM02
10
CON PZ 2
CON PZ 3
02-PM02-PSV300 01-PM05
10
10 01-WT09
01-PS09
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
10
02-PS05
10
02-PM01-PSV200
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
10 NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PS01 01-PM01
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
10
01-PS13
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
10 PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
10 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
10
02-PM01 Primary Main from WT13 to WT12
02-PM02 Primary Main from 02-WT12 to 02-WT10
03-PM01 02-PM03 Primary Main from 02-PM02 to 02-WT15
PS-RCRC-04 02-PS04 PS from 02-WT12 to PZ4
PS-RCRC-xx 02-PS05 PS from 02-WT12 to 02-WT10
PS-RCRC-07 02-PS07 PS to WT_RCRC_07(Zone 3)
PS-RCRC-08 02-PS08 PS to WT_RCTC_15 (Zone 3)
PS-RCRC-10 02-PS10 PS to Zone 2
03-PS02
03-PM01-PSV002 10 WT-RCRC-10 02-WT10 Strategic Storage - Al Arubah Park
WT-RCRC-12 02-WT12 Water Tower 12
WT-RCRC-15 02-WT15 Zone 2 Reservoir (King Salman Park)
03-PM04-PSV001
BPT-RCRC-05 03-BPT-05 Break Pressure Tank in Zone 1
10 03-BPT-05 10 03-WT02
03-PM01 Primary Main from 03-WT01 to 01-WT13
03-PM04 03-PM03 03-PS03
Twin Pipline 03-PM02 Primary Main from 03-WT02 to 01-WT09
03-PM03 Primary Main from 03-WT02 to 01-BPT05
10 03-PM04 Primary Main from 01-BPT05 to 03-PM01
PS-RCRC-01 03-PS01 PS from 03-WT01 to 03PM01 and 03PM04
PS-RCRC-02 03-PS02 PS at Heet WWTP
03-PS01 PS-RCRC-03 03-PS03 PS at Heet WWTP
WT-RCRC-01 03-WT01 Pump Sump Al Hair WWTP
WT-RCRC-02 03-WT02 Heet WWTP
03-WT01 PS-RCRC-11 0X-PS11 PS North WWTP
PS-RCRC-12 0X-PS12 PS East WWTP
Client: Project: Consultant: Document Name:
Green Riyadh TSE Network Schematic – Primary
TSE Supply for Green Riyadh System
01 Updated for Review 28.11.2021 MI MH DC Programme
Royal Commission for Riyadh Document No.:
00 Issued for Review 29.10.2021 MH MI DC City PMC and Design Coordination ILF Consulting Engineers TSE-G-GN-00-ILF-G-EN-PLN-00002
Rev. Issue or Revision Date Prep. Check Appr.
Notes Legend
01-PS17
11 01-WT04
To Sodous Not in Scope: 0X-PS11
01-PS06 WWTP, Wastewater Treatment Plant
0X-PS12
01-PM06
11 01-WT17 PSV, Pressure Sustaining Valve
CON PZ 3
01-PS15 Optional Expansion – to be discussed
02-PM01-PSV400 01-PS16
Phase 2
Bi-directional Flow
02-PS07 02-PS10 01-PM04-PSV100
11 Operational Mode 11
01-PM02-PSV100
11
02-PM02
11
CON PZ 2
CON PZ 3
02-PM02-PSV300 01-PM05
11
11 01-WT09
01-PS09
03-PM02-PSV001
01-PM03 01-PS03
01-PM07
01-WT03
11
02-PS05
11
02-PM01-PSV200
02-PS04
NWC S2-1200 01-PM01 Primary Main from PS-NWC-01
11 NWC S2-1200 01-PM02 Primary Main from PS-NWC-02
01-PS01 01-PM01
01-PM03 Primary Main from WT13 to WT09
01-PM04 Primary Main from 01-WT09 to 02-WT15
11
01-PS13
CON PZ 4 to be discussed NWC S2-1200 01-PM05 Primary Main from 01-WT03 to 01-WT17
to be discussed 01-PM06 Primary Main from 02-WT15 to 01-WT17
02-PM01-PSV100 PS-NWC-01 01-PS01 NWC PS (Manfouha) to Sodous
01-WT13 PS-NWC-02 01-PS02 NWC PS (Manfouha) to 01-WT17
01-PS14 to be dicussed 01-PS03 PS from 01-WT03 to 01-WT17
11 PS-RCRC-09 01-PS09 PS at Strategic Reservoir
02-PM01 01-PS13 PS at Manfouha WWTP to 01-WT09
PS-RCRC-14 01-PS14 PS at Manfouha WWTP
11 CON PZ 1 to be discussed 01-PS15 PS to 02-WT15
to be discussed 01-PS16 PS to 01-WT17
03-PM02-PSV100
to be discussed 01-PS17 PS to Sodus
to be discussed 01-WT03 Strategic Tank for PZ 7
WT-RCRC-09 at Cement Factory 01-WT09 Strategic Reservoir Ministry of Health
WT-RCRC-13 01-WT13 Pump Sump Manfouha WWTP
03-PM02 WT-RCRC-17 01-WT17 Zone 6 Reservoir (Airport Park)
11