You are on page 1of 2

PT.

Great Giant Pineapple


Department Power Plant

Rencana Kerja Instrument Libur Lebaran 2022

Tanggal
No Deskripsi Pekerjaan Personil Sparepart
27 28 29 30 1 2 3 4
1 Setting controller untuk capasity of 2nd generator Sydiq, Riki
Bambang, Sydiq, thermocouple type K; transmitter
2 Instalasi thermocouple dan Pressure Transitter PTRS
Riki STG 700; kabel NYY 2x1,5mm
3 Cleaning Computer DCS Suroyo
4 Back up data Server dan PC DCS Suroyo
thermis 1x6A; box thermis; rel
5 Pasang thermis untuk PC DCS L Suroyo, Riki thermis; terminal isi 3; wire deck
I 45x45mm; kabel NYY 2x1,5mm
B
6 Ganti thermowell boiler 01 Bambang, Sydiq thermowell wear
U
7 Pindah controller desuperheater ekstraksi turbin R All personil
8 Pasang inverter pompa demin Bambang, Sydiq, inverter ACS580; controller SWP-
Riki ND825-020-04/12 HL
9 Ganti terminal block R2-MB6 DO PLC HC900 Bambang, Sydiq
10 Connect kabel 505 start turbin R2- MB6 DO PLC HC900 Bambang, Sydiq
11 Ganti kabel jumper R2- MB2 DI PLC HC900 Bambang, Sydiq
12 Persiapan start boiler dan turbin All personil

Dibuat Oleh, Disetujui Oleh, Mengetahui,

Feni Fitriani Supriyono Erwin Rahardianto,


Ka. Sie Instrument Ka. Bag Instrument Ast. Manager PP
Keterangan Sparepart

No Sparepart Jumlah Status Sparepart


1 Thermocouple type K 1 pcs Ready
2 Transmitter STG 700 1 pcs Ready
3 Kabel NYY 2x1,5mm 100 m Ready
4 Thermis 1x6A 10 pcs Ready
5 Box thermis 1 phase 10 pcs Not Yet
6 Rel thermis 10 btg Not Yet
7 Terminal isi 3 10 pcs Not Yet
8 Wire deck 45x45mm; 10 btg Not Yet
9 Thermowell wear 6 pcs Ready
10 Inverter ACS580 1 pcs Ready
11 controller SWP-ND825-020-04/12 HL 1 pcs Ready