2022.02.28 - Informe Semanal N°1 - REV.01
2022.02.28 - Informe Semanal N°1 - REV.01
Julio C e sa r C o lq ue G om e z
Re side nte de Obra
TAC Ge re nc ia y Co nstruc c ión S.A.C
RUC: 20601237840
Informe Semanal N° 06
Ca lle Ma rtir Jo se O la ya Nº129 O fic 503 Mira flo re s
Te lf. (51-1) 368 9753, 990 110 904
www .ta c g yc .c om
Indice
2 Sectorización
3 Programación de 3 Semanas
4 Analisis de Restricciones
5 Plan Semanal
7 Temas Relevantes
8 Panel Fotográfico
9 Anexos
Supervisor : ING. EDGAR ALCA 22-Feb 27-Feb-22 06-Mar-22 13-Mar-22 20-Mar-22 27-Mar-22 03-Apr-22 10-Apr-22 17-Apr-22 24-Apr-22 01-May-22 08-May-22 15-May-22 22-May-22 29-May-22 05-Jun-22 12-Jun-22 19-Jun-22 27-Feb-22 06-Mar-22 13-Mar-22 20-Mar-22 27-Mar-22 03-Apr-22 10-Apr-22 17-Apr-22 24-Apr-22 01-May-22 08-May-22 15-May-22 22-May-22 29-May-22 05-Jun-22 12-Jun-22 18-Jun-22
PRESUPUESTO
ITEM DESCRIPCION DE PARTIDA FEBRERO MARZO ABRIL MAYO JUNIO FEBRERO MARZO ABRIL MAYO JUNIO
UNIDA Monto
METRADO PRECIO UNITARIO PARCIAL Sem1 Sem2 Sem3 Sem4 Sem5 Sem6 Sem7 Sem8 Sem9 Sem10 Sem11 Sem12 Sem13 Sem14 Sem15 Sem16 Sem17 Sem1 Sem 2 Sem 3 Sem 4 Sem 5 Sem 6 Sem 7 Sem 8 Sem 9 Sem 10 Sem 11 Sem 12 Sem 13 Sem 14 Sem 15 Sem 16 Sem 17 Monto Acumulado
D Acumulado
2
CURVA "S"
Del 05 de agosto al 05 de Febrero del 2020
Supervisor : ING. EDGAR ALCA 22-Feb 27-Feb-22 06-Mar-22 13-Mar-22 20-Mar-22 27-Mar-22 03-Apr-22 10-Apr-22 17-Apr-22 24-Apr-22 01-May-22 08-May-22 15-May-22 22-May-22 29-May-22 05-Jun-22 12-Jun-22 19-Jun-22 27-Feb-22 06-Mar-22 13-Mar-22 20-Mar-22 27-Mar-22 03-Apr-22 10-Apr-22 17-Apr-22 24-Apr-22 01-May-22 08-May-22 15-May-22 22-May-22 29-May-22 05-Jun-22 12-Jun-22 18-Jun-22
PRESUPUESTO
ITEM DESCRIPCION DE PARTIDA FEBRERO MARZO ABRIL MAYO JUNIO FEBRERO MARZO ABRIL MAYO JUNIO
UNIDA Monto
METRADO PRECIO UNITARIO PARCIAL Sem1 Sem2 Sem3 Sem4 Sem5 Sem6 Sem7 Sem8 Sem9 Sem10 Sem11 Sem12 Sem13 Sem14 Sem15 Sem16 Sem17 Sem1 Sem 2 Sem 3 Sem 4 Sem 5 Sem 6 Sem 7 Sem 8 Sem 9 Sem 10 Sem 11 Sem 12 Sem 13 Sem 14 Sem 15 Sem 16 Sem 17 Monto Acumulado
D Acumulado
03.04.04.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 29.54 84.02 2,481.95 100.00% 100.00% 0.00%
03.04.04.01.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 427.80 6.35 2,716.53 100.00% 100.00% 0.00%
03.04.04.02 VIGAS
03.04.04.02.01 CONCRETO F'C= 210 KG/CM2 m3 0.82 364.68 299.04 100.00% 100.00% 0.00%
03.04.04.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 8.18 129.72 1,061.11 100.00% 100.00% 0.00%
03.04.04.02.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 87.14 6.35 553.34 100.00% 100.00% 0.00%
03.04.04.03 ALBAÑILERIA
03.04.04.03.01 ASENTAMIENTO DE MUROS DE ALBAÑILERIA m2 31.69 157.86 5,002.58 100.00% 100.00% 0.00%
03.05 TERCER PISO (NIVEL +10.45 A +15.50)
03.05.01 COLUMNAS
03.05.01.01 CONCRETO F'C= 350 KG/CM2 m3 38.20 388.96 14,858.27 100.00% 100.00% 0.00%
03.05.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 158.57 84.02 13,323.05 25.00% 75.00% 100.00% 0.00%
03.05.01.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 9,024.86 6.35 57,307.86 50.00% 50.00% 100.00% 0.00%
03.05.02 VIGAS
03.05.02.01 CONCRETO F'C= 350 KG/CM2 m3 54.54 380.39 20,746.47 50.00% 50.00% 100.00% 0.00%
03.05.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 288.60 129.72 37,437.19 100.00% 100.00% 0.00%
03.05.02.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 9,438.14 6.35 59,932.19 100.00% 100.00% 0.00%
03.05.02.04 INSTALACIÓN DE INSERTOS METÁLICOS kg 15.29 13.06 199.69 100.00% 100.00% 0.00%
03.05.03 LOSAS DE TECHO
03.05.03.01 CONCRETO F'C= 350 KG/CM2 m3 16.73 380.39 6,363.92 50.00% 50.00% 100.00% 0.00%
03.05.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 98.41 109.95 10,820.18 100.00% 100.00% 0.00%
03.05.03.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 1,529.70 6.35 9,713.60 100.00% 100.00% 0.00%
03.05.04 MURO DE CERRAMIENTO DE ALBAÑILERIA
03.05.04.01 COLUMNAS
03.05.04.01.01 CONCRETO F'C= 210 KG/CM2 m3 3.28 364.68 1,196.15 100.00% 100.00% 0.00%
03.05.04.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 39.02 84.02 3,278.46 100.00% 100.00% 0.00%
03.05.04.01.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 541.41 6.35 3,437.95 100.00% 100.00% 0.00%
03.05.04.02 VIGAS
03.05.04.02.01 CONCRETO F'C= 210 KG/CM2 m3 0.92 364.68 335.51 100.00% 100.00% 0.00%
03.05.04.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 9.16 129.72 1,188.24 100.00% 100.00% 0.00%
03.05.04.02.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 97.07 6.35 616.39 100.00% 100.00% 0.00%
03.05.04.03 ALBAÑILERIA
03.05.04.03.01 ASENTAMIENTO DE MUROS DE ALBAÑILERIA m2 59.54 157.86 9,398.98 100.00% 100.00% 0.00%
03.06 CUARTO PISO (NIVEL 15.50 A +22.55)
03.06.01 COLUMNAS
03.06.01.01 CONCRETO F'C= 350 KG/CM2 m3 44.00 388.96 17,114.24 100.00% 100.00% 0.00%
03.06.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 174.00 84.02 14,619.48 100.00% 100.00% 0.00%
03.06.01.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 10,580.00 6.35 67,183.00 100.00% 100.00% 0.00%
03.07.02 VIGAS
03.07.02.01 CONCRETO F'C= 350 KG/CM2 m3 41.68 380.39 15,854.66 100.00% 100.00% 0.00%
03.07.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 213.77 129.72 27,730.24 50.00% 50.00% 100.00% 0.00%
03.07.02.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 5,542.19 6.35 35,192.91 50.00% 50.00% 100.00% 0.00%
03.07.02.04 INSTALACIÓN DE INSERTOS METÁLICOS kg 132.49 13.06 1,730.32 100.00% 100.00% 0.00%
03.07.03 LOSAS DE TECHO
03.07.03.01 CONCRETO F'C= 350 KG/CM2 m3 14.62 380.39 5,561.30 100.00% 100.00% 0.00%
03.07.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 86.45 109.95 9,505.18 100.00% 100.00% 0.00%
03.07.03.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 1,288.86 6.35 8,184.26 100.00% 100.00% 0.00%
03.06.02 PEDESTALES
03.06.02.01 CONCRETO F'C= 280 KG/CM2 m3 0.15 351.06 52.66 100.00% 100.00% 0.00%
03.06.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 1.73 84.02 145.35 25.00% 75.00% 100.00% 0.00%
03.06.02.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 50.00 6.35 317.50 25.00% 75.00% 100.00% 0.00%
03.06.03 BASE DE VENTILADOR
03.06.03.01 CONCRETO F'C= 280 KG/CM2 m3 0.59 351.06 207.13 100.00% 100.00% 0.00%
03.06.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 1.40 84.02 117.63 25.00% 75.00% 100.00% 0.00%
03.06.03.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 135.74 6.35 861.95 25.00% 75.00% 100.00% 0.00%
03.06.06 MURO DE CERRAMIENTO DE ALBAÑILERIA
03.06.06.01 COLUMNAS
03.06.06.01.01 CONCRETO F'C= 210 KG/CM2 m3 5.71 364.68 2,082.32 100.00% 100.00% 0.00%
03.06.06.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 71.36 84.02 5,995.67 100.00% 100.00% 0.00%
03.06.06.01.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 852.90 6.35 5,415.92 100.00% 100.00% 0.00%
03.06.06.02 VIGAS
03.06.06.02.01 CONCRETO F'C= 210 KG/CM2 m3 1.14 364.68 415.74 100.00% 100.00% 0.00%
03.06.06.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 11.60 129.72 1,504.75 100.00% 100.00% 0.00%
03.06.06.02.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 114.35 6.35 726.12 100.00% 100.00% 0.00%
03.06.06.03 ALBAÑILERIA
03.06.06.03.01 ASENTAMIENTO DE MUROS DE ALBAÑILERIA m2 98.55 157.86 15,557.10 100.00% 100.00% 0.00%
03.06.07 ESTRUCTURAS METALICAS
03.06.07.01 BARANDAS kg 356.75 18.08 6,450.04 100.00% 100.00% 0.00%
03.06.08 SARDINEL PERIMETRAL
03.06.08.01 CONCRETO F'C= 210 KG/CM2 m3 1.47 364.68 536.08 100.00% 100.00% 0.00%
03.06.08.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 18.71 72.18 1,350.49 100.00% 100.00% 0.00%
03.06.08.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 121.80 6.35 773.43 100.00% 100.00% 0.00%
03.06.09 SISTEMA DE DRENAJE
03.06.09.01 BAJADA DE TUBERÍA 4" PVC SAP, NIVEL +29.80 A +0.00 ml 68.65 80.55 5,529.76 100.00% 100.00% 0.00%
03.06.09.02 GRAPAS PARA TUBERIA DE DRENAJE DE 4" und 25.00 78.29 1,957.25 100.00% 100.00% 0.00%
03.08 QUINTO (NIVEL +22.55 A +29.00)
03.08.01 COLUMNAS
03.08.01.01 CONCRETO F'C= 350 KG/CM2 m3 27.96 388.96 10,875.32 100.00% 100.00% 0.00%
03.08.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 131.58 84.02 11,055.35 50.00% 50.00% 100.00% 0.00%
03.08.01.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 6,531.60 6.35 41,475.66 75.00% 25.00% 100.00% 0.00%
03.08.02 VIGAS
03.08.02.01 CONCRETO F'C= 350 KG/CM2 m3 31.85 380.39 12,115.42 100.00% 100.00% 0.00%
03.08.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 183.27 129.72 23,773.78 100.00% 100.00% 0.00%
03.08.02.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 4,240.80 6.35 26,929.08 100.00% 100.00% 0.00%
03.08.02.04 INSTALACIÓN DE INSERTOS METÁLICOS kg 120.00 13.06 1,567.20 100.00% 100.00% 0.00%
03.08.03 LOSA DE TECHO
03.08.03.01 CONCRETO F'C= 350 KG/CM2 m3 21.42 380.39 8,147.95 100.00% 100.00% 0.00%
03.08.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 126.02 109.95 13,855.90 100.00% 100.00% 0.00%
03.08.03.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 1,582.28 6.35 10,047.48 100.00% 100.00% 0.00%
03.08.04 MURO DE CERRAMIENTO DE ALBAÑILERIA
03.08.04.01 COLUMNAS
03.08.04.01.01 CONCRETO F'C= 210 KG/CM2 m3 4.82 364.68 1,757.76 100.00% 100.00% 0.00%
03.08.04.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 60.15 84.02 5,053.80 100.00% 100.00% 0.00%
03.08.04.01.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 763.81 6.35 4,850.19 100.00% 100.00% 0.00%
03.08.04.02 VIGAS
03.08.04.02.01 CONCRETO F'C= 210 KG/CM2 m3 1.10 364.68 401.15 100.00% 100.00% 0.00%
03.08.04.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 10.96 129.72 1,421.73 100.00% 100.00% 0.00%
03.08.04.02.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 113.69 6.35 721.93 100.00% 100.00% 0.00%
03.08.04.03 ALBAÑILERIA Y VENTANAS
03.08.04.03.01 ASENTAMIENTO DE MUROS DE ALBAÑILERIA m2 86.32 157.86 13,626.48 100.00% 100.00% 0.00%
03.08.03 ESTRUCTURAS METALICAS
03.08.03.01 BARANDAS kg 250.50 18.08 4,529.04 100.00% 100.00% 0.00%
3
CURVA "S"
Del 05 de agosto al 05 de Febrero del 2020
Supervisor : ING. EDGAR ALCA 22-Feb 27-Feb-22 06-Mar-22 13-Mar-22 20-Mar-22 27-Mar-22 03-Apr-22 10-Apr-22 17-Apr-22 24-Apr-22 01-May-22 08-May-22 15-May-22 22-May-22 29-May-22 05-Jun-22 12-Jun-22 19-Jun-22 27-Feb-22 06-Mar-22 13-Mar-22 20-Mar-22 27-Mar-22 03-Apr-22 10-Apr-22 17-Apr-22 24-Apr-22 01-May-22 08-May-22 15-May-22 22-May-22 29-May-22 05-Jun-22 12-Jun-22 18-Jun-22
PRESUPUESTO
ITEM DESCRIPCION DE PARTIDA FEBRERO MARZO ABRIL MAYO JUNIO FEBRERO MARZO ABRIL MAYO JUNIO
UNIDA Monto
METRADO PRECIO UNITARIO PARCIAL Sem1 Sem2 Sem3 Sem4 Sem5 Sem6 Sem7 Sem8 Sem9 Sem10 Sem11 Sem12 Sem13 Sem14 Sem15 Sem16 Sem17 Sem1 Sem 2 Sem 3 Sem 4 Sem 5 Sem 6 Sem 7 Sem 8 Sem 9 Sem 10 Sem 11 Sem 12 Sem 13 Sem 14 Sem 15 Sem 16 Sem 17 Monto Acumulado
D Acumulado
03.09 AZOTEA (NIVEL +29.00)
03.09.01 SARDINEL PERIMETRAL
03.09.01.01 CONCRETO F'C= 210 KG/CM2 m3 1.47 364.68 536.08 100.00% 100.00% 0.00%
03.09.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 18.71 72.18 1,350.49 100.00% 100.00% 0.00%
03.09.01.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 121.80 6.35 773.43 100.00% 100.00% 0.00%
03.09.02 ESTRUCTURAS METALICAS
03.09.02.01 BARANDAS kg 893.00 18.08 16,145.44 100.00% 100.00% 0.00%
03.09.03 SISTEMA DE DRENAJE
03.09.03.01 BAJADA DE TUBERÍA 4" PVC SAP, NIVEL +29.80 A +0.00 ml 68.65 80.55 5,529.76 100.00% 100.00% 0.00%
03.09.03.02 GRAPAS PARA TUBERIA DE DRENAJE DE 4" und 25.00 78.29 1,957.25 100.00% 100.00% 0.00%
04 HANGAR N°01
04.01 MOVIMIENTO DE TIERRAS
04.01.01 EXCAVACION PARA CIMENTACIÓN CON EQUIPO m3 1,695.08 22.09 37,444.32 20.00% 30.00% 30.00% 20.00% 100.00% 0.00%
04.01.02 RELLENO Y COMPACTACIÓN CON MATERIAL PROPIO m3 640.64 43.55 27,899.87 50.00% 33.33% 16.67% 100.00% 0.00%
04.01.03 ELIMINACION DE EXCEDENTES m3 1,370.77 19.17 26,277.66 25.00% 25.00% 50.00% 100.00% 0.00%
04.02 CIMENTACION
04.02.01 FALSO CIMIENTO (CONCRETO F'C= 100 KG/CM2) m3 640.22 320.31 205,068.87 20.00% 20.00% 30.00% 30.00% 100.00% 0.00%
04.02.02 ZAPATA
04.02.02.01 CONCRETO F'C= 210 KG/CM2 m3 350.71 329.90 115,699.23 15.00% 30.00% 30.00% 25.00% 100.00% 0.00%
04.02.02.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 283.68 69.18 19,624.98 20.00% 35.00% 35.00% 10.00% 100.00% 0.00%
04.02.02.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 15,334.73 6.35 97,375.54 25.00% 35.00% 35.00% 5.00% 100.00% 0.00%
04.02.03 CALIZ
04.02.03.01 CONCRETO F'C= 210 KG/CM2 m3 69.53 329.90 22,937.95 20.00% 50.00% 30.00% 100.00% 0.00%
04.02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 312.00 72.18 22,520.16 30.00% 30.00% 20.00% 20.00% 100.00% 0.00%
04.02.03.03 ACERO ESTRUCTURAL FY= 4,210 KG/CM2 kg 10,074.55 6.35 63,973.39 35.72% 42.86% 21.43% 100.00% 0.00%
04.03 LOSA DE PISO, NIVEL +0.00
04.03.01 MOVIMIENTO DE TIERRAS
04.03.01.01 CORTE DE TERRENO m3 0.00 16.71 0.00 0.00% 0.00%
04.03.01.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 0.00 43.55 0.00 0.00% 0.00%
04.03.01.03 RELLENO COMPACTADO CON MATERIAL DE PRÉSTAMO m3 1,056.72 106.55 112,593.52 100.00% 100.00% 0.00%
04.03.01.04 ELIMINACIÓN DE MATERIAL EXCEDENTE m3 0.00 19.17 0.00 0.00% 0.00%
04.03.02 LOSA DE PISO, NIVEL +0.00
04.03.02.01 CONCRETO F'C= 280 KG/CM2 m3 1,053.19 332.09 349,753.87 20.00% 40.00% 40.00% 100.00% 0.00%
04.03.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 154.19 93.15 14,362.80 20.00% 40.00% 40.00% 100.00% 0.00%
04.03.02.03 JUNTA JC (JUNTA DE CONTRACCIÓN) ml 4,816.95 10.12 48,747.53 18.75% 43.75% 37.50% 100.00% 0.00%
04.03.02.04 JUNTA JD (JUNTA DE DILATACIÓN) ml 356.85 63.02 22,488.69 18.75% 43.75% 37.50% 100.00% 0.00%
04.03.02.05 JUNTA JE (JUNTA DE EXTREMO) ml 407.60 25.74 10,491.62 18.75% 43.75% 37.50% 100.00% 0.00%
COSTO DIRECTO TOTAL 3,328,494.70 50,015.14 57,584.88 102,460.81 177,877.05 287,497.35 299,753.58 314,187.92 248,149.85 183,413.00 229,401.55 185,075.55 203,472.96 350,930.46 209,531.60 256,855.41 84,291.70 87,995.90 3,328,494.70 57,400.06 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 57,400.06
1.50% 0.23% 1.35% 2.27% 3.29% 0.37% 0.43% -1.98% -1.94% 1.38% -1.33% 0.60% 4.43% 0.73% 1.42% -8.01% 0.11%
0.00% 1.50% 1.73% 3.08% 5.34% 8.64% 9.01% 9.44% 7.46% 5.51% 6.89% 5.56% 6.11% 10.54% 6.30% 7.72% 2.53% 2.64%
% AVANCE PROG. 0.00% 1.50% 3.23% 6.31% 11.66% 20.29% 29.30% 38.74% 46.19% 51.70% 58.60% 64.16% 70.27% 80.81% 87.11% 94.82% 97.36% 100.00%
0.00% 1.72% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.72%
% AVANCE REAL 0.00% 1.72%
4
Ing . Julio Ce sa r C o lq u e G o m e z
Re side nte de Obra
TAC Ge re nc ia y Co nstruc c ió n S.A.C
RUC : 20601237840
Resumen Semanal Nº 01
Ca lle Ma rtir Jo se Ola ya Nº129 O fic 503 Mira flore s
Te lf. (51-1) 368 9753, 990 110 904
www.ta c g yc .c o m
Nombre de la Obra: CONSTRUCCIÓN DE EDIFICIO EMBOLSADO Nº6 Y CIMENTACIÓN DEL HANGAR Nº1
Centro de Costo: Nº 1108 Fin de Semana: 28-Feb-22
Contratista: TAC GERENCIA Y CONSTRUCCION S.A.C. Informe de la Semana: Nº 01
97.36% 100.00%
100.00% 94.82%
90.00% 87.11%
80.81%
80.00% Prog. 1.50%
70.27%
70.00% 64.16%
Actual: 1.72% 58.60%
60.00% 51.70%
∆= 0.22% 46.19%
50.00%
38.74%
40.00% SPI: 1.15
29.30%
30.00%
20.29%
20.00%
11.66%
10.00% 6.31%
1.50% 3.23%
0.00%
0.00%
80
70
60
50
40
30
20
10
5 de 23
Ing . Julio Ce sa r C o lq u e G o m e z
Re side nte de Obra
TAC Ge re nc ia y Co nstruc c ió n S.A.C
RUC : 20601237840
Resumen Semanal Nº 01
Ca lle Ma rtir Jo se Ola ya Nº129 O fic 503 Mira flore s
Te lf. (51-1) 368 9753, 990 110 904
www.ta c g yc .c o m
Nombre de la Obra: CONSTRUCCIÓN DE EDIFICIO EMBOLSADO Nº6 Y CIMENTACIÓN DEL HANGAR Nº1
Centro de Costo: Nº 1108 Fin de Semana: 28-Feb-22
Contratista: TAC GERENCIA Y CONSTRUCCION S.A.C. Informe de la Semana: Nº 01
CURVAS ESPECIALES
6 de 23
Ing . Julio Ce sa r C o lq u e G o m e z
Re side nte de Obra
TAC Ge re nc ia y Co nstruc c ió n S.A.C
RUC : 20601237840
Resumen Semanal Nº 01
Ca lle Ma rtir Jo se Ola ya Nº129 O fic 503 Mira flore s
Te lf. (51-1) 368 9753, 990 110 904
www.ta c g yc .c o m
Nombre de la Obra: CONSTRUCCIÓN DE EDIFICIO EMBOLSADO Nº6 Y CIMENTACIÓN DEL HANGAR Nº1
Centro de Costo: Nº 1108 Fin de Semana: 28-Feb-22
Contratista: TAC GERENCIA Y CONSTRUCCION S.A.C. Informe de la Semana: Nº 01
100.0 500
80.0 400
60.0 300
40.0 200
20.0 100
0.0 0
27-Feb 6-Mar 13-Mar 20-Mar 27-Mar 3-Apr 10-Apr 17-Apr 24-Apr 1-May 8-May 15-May 22-May 29-May 5-Jun 12-Jun 19-Jun
7 de 23
Contract: COSAPI S.A. N° Contract: 2171-0530
WEEK PAST WEEK CURRENT WEEK NEXT WEEK NEXT WEEK NEXT WEEK
DATE 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10
T Engineering by Ausenco 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 29 30 31 1 2 3 4 5 6 7 8 9 10 11
Sched
3220 Grinding-Operating floor susp slab glb X
Actual
Sched
3220 Grinding-Ramp footings glb X
Actual
Sched
3220 Grinding-Cyclone feed pumps footings glb X
Actual
Sched
3440 Flocculants (Tailings)-3440 Flocculants (Tailings) glb X
Actual
Sched X
3110 Crusher - Concrete and Cure-Complete glb
Actual
Sched On Hold
3213 SAG Mills Feed Conveyors-3213 SAG Mills Feed Conveyors glb On Hold
Actual
Sched On Hold
4100 Pounds-4100 Pounds glb On Hold
Actual
Sched
3270 Concretrate Thickening-3270 Concretrate Thickening glb X
Actual
Sched
3430 Flocculant (Concentrate)-3430 Flocculant (Concentrate) glb X
Actual
T Preliminary Works 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 29 30 31 1 2 3 4 5 6 7 8 9 10 11
Sched X X X X X X X 1.00
Mobilization of temporal facilities and equipment . glb 100% X X X X X X X X X X X X X X X X X X X X X X X X X X X X
Actual X X X X X X X 1.00
Sched X X X X X 1.00
Foundation and aprobation of BM glb 0% X
Actual
T 3220 - Grinding 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 29 30 31 1 2 3 4 5 6 7 8 9 10 11
N° Planned Activities 5
N° Completed Activities 3
PAC 60%
Week Ending: 5-Dec-12
3220 GRINDING ADICIONAL SUBFOUNDATION MILLS 20 - CONCRETE 20 MPA m3 2.59 14,350.0 37,166.0 0.00 0.0%
ADICIONAL SUBFOUNDATION MILLS 21 - FORMWORK m3 3.51 680.0 2,388.0 0.00 0.0%
Week No. 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
CONSTRUCCION 7,742,910 100.0% 1.59% 1.02% 1.0% Plan 0.0% 0.2% 1.6% 4.0% 8.0% 12.8% 18.4% 24.0% 29.8% 33.7% 38.9% 42.8% 49.8% 55.7% 63.1% 69.0% 77.4% 83.7% 92.4% 96.6% 99.9% 100.0%
Actual 0.0% 0.2% 1.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
0 TRABAJOS PARALELOS 941,849 12.2% 6.8% 6.8% 0.8% Plan 0.0% 1.7% 6.8% 12.0% 17.1% 22.3% 27.5% 32.6% 37.8% 43.0% 48.1% 53.3% 58.5% 63.6% 68.8% 74.0% 79.1% 84.3% 89.5% 94.6% 99.8% 100.0%
Actual 0.0% 1.70% 6.80%
1 COSTA AZUL (1.3 km) 679,436 8.8% 8.6% 2.2% 0.2% Plan 0.0% 0.3% 8.6% 25.3% 47.5% 70.6% 82.1% 98.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Actual 0.0% 0.3% 2.2%
2 JAZMINES - A (1.3 km) 771,687 10.0% 0.0% 0.0% 0.0% Plan 0.0% 0.0% 0.0% 2.9% 17.8% 36.7% 66.0% 79.8% 99.1% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Actual 0.0%
3 LOMAS - A (1.3 km) 579,278 7.5% 0.0% 0.0% 0.0% Plan 0.0% 0.0% 0.0% 0.0% 0.0% 2.5% 17.5% 43.8% 69.8% 82.1% 99.2% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Actual 0.0%
4 LOMAS - B (1.3 km) 612,501 7.9% 0.0% 0.0% 0.0% Plan 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 2.4% 16.5% 42.5% 70.7% 83.0% 99.2% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Actual 0.0%
5 LOMAS - C (1.3 km) 579,278 7.5% 0.0% 0.0% 0.0% Plan 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 2.5% 17.5% 43.8% 69.8% 82.1% 99.2% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%
Actual 0.0%
6 LOMAS - D (1.3 km) 579,278 7.5% 0.0% 0.0% 0.0% Plan 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 2.5% 17.5% 43.8% 69.8% 82.1% 99.2% 100.0% 100.0% 100.0% 100.0% 100.0%
Actual 0.0%
7 JAZMINES - B (1.3 km) 771,687 10.0% 0.0% 0.0% 0.0% Plan 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 2.9% 17.8% 36.7% 66.0% 79.8% 99.1% 100.0% 100.0% 100.0%
Actual 0.0%
8 JAZMINES - C (1.3 km) 879,975 11.4% 0.0% 0.0% 0.0% Plan 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 2.5% 15.6% 34.1% 70.1% 82.3% 99.2% 100.0%
Actual 0.0%
9 PAVIMENTACION 1,347,941 17.4% 0.0% 0.0% 0.0% Plan 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.3% 11.8% 23.8% 35.8% 47.8% 59.8% 71.8% 83.8% 95.8% 100.0% 100.0%
Actual 0.0%
1.02% 0.00%
SECTORIZACIÓN DE EDIFICIO EMBOLSADO N°06
2
SECTORIZACIÓN CIMENTACIÓN
SECTOR 1
SECTOR 2
Confidential
Ing . Ju lio Ce sa r C o lq u e G o m e z
Re side nte de Ob ra
TAC G e re nc ia y C onstru c c ió n S.A.C 3 WEEK SCHEDULE
RUC : 20601237840
C a lle Ma rtir Jo se O la ya Nº129 O fic 503 Mira flo re s
Te lf. (51-1) 368 9753, 990 110 904 REQUERIMIENTO DE CONCRETO
ww w.ta c g yc .c o m
Requerimientos Semana ESTA SEMANA PROXIMA SEMANA SEMANA SIGUIENTE SEMANA SIGUIENTE
Método de
Contratista Frente / Ubicación Especiales del Tipo Dia L M M J V S L M M J V S L M M J V S L M M J V S
Colocación
concreto Fecha 29 30 1 2 3 4 6 7 8 9 10 11 13 14 15 16 17 18 20 21 22 23 24 25
H20
Resistencia Final Hora Inicio 6:00 AM 262.5 262.5 525 525 525 262.5 262.5 262.5 262.5 525 525 525 525 525
280kg/cm2.
TAC Muros Anclados Bombeado H32
Resistencia a los
3 días 210kg/cm2 Hora Inicio
H40
Hora Inicio
Volumen Concreto 0 0 0 0 0 0 0 262.5 0 262.5 0 525 525 525 262.5 262.5 262.5 262.5 525 525 525 525 525
REPORTE DE AVANCE AL 07.NOV.2012
Variación detallada
Area 220 Area 400
Area 210 Remolienda Err:508 Area 260 MC 220/255 Err:508
Edif Molienda Err:508 BL003 Err:508 Planta de cal Err:508 Ducto de conex Err:508
Ciclones Err:508 BL007 Err:508 Total Err:508 PB051 - 053, 021 Err:508
Losa de Lubric Err:508 ER-015 Err:508 PB009 Err:508
CV001, 005 Err:508 BL009 Err:508 Total Err:508
ER012,013 y
Torres de Err:508 BL006 Err:508
enfriam.
5
6 80% 80%
7 67%
67% 67%
8 67%
60% 57%
9
10
11
40%
12
13
14 20%
Calificacion Comparativo % PAC
Excelente mas de 85%
Bueno mas de 80% 0%
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Regular Entre 65% - 80%
Semanas
Malo menos de 60% PAC Semanal PAC Semanal Acumulado
21-Feb
22-Feb
23-Feb
24-Feb
25-Feb
26-Feb
28-Feb
10-Mar
11-Mar
12-Mar
13-Mar
14-Mar
15-Mar
16-Mar
17-Mar
18-Mar
19-Mar
1-Mar
2-Mar
3-Mar
4-Mar
5-Mar
6-Mar
7-Mar
8-Mar
9-Mar
###
Metrado
Ítem EDIFICIO DE EMBOLSADO N°06 1.00
Prog
### ### ###
1.00 OBRAS PROVISIONALES
1.01 CERCO DE OBRA, SEÑALIZACION Y CERRAMIENTO glb 1.00 1 ###
1.02 TRAZO Y REPLANTO INICIAL glb 1.00 2
1.03 INSTALACION DE TOLDO PARA LLUVIA glb 1.00 3
1.02 INST. DE TRANSFORMADOR Y TABLEROS glb 1.00 4
2.00 MOVIMIENTO DE TIERRAS
2.01 ACOPIO DE AGREGADOS m3 864.00 1 1 1 1 1 1
2.02 DEMOLICION DE ESTRUCTURAS EXISTENTES - PEDESTALES m3 14.00 2 2 2
2.03 EXCAVACIÓN CON EQUIPO m3 580.00 3 3 3
2.04 DEMOLICION DE ESTRUCTURAS EXISTENTES - LOSA m3 24.00 4 4 4 4 4
2.05 ANCLAJE DE DOWELLS EN VIGAS DE CIMENTACION und 16.00 5 5
3.00 CIMENTACION
3.01 SOLADO m3 14.00 1
3.02 PLATEA DE CIMENTACION
3.02.01 ACERO EN PLATEA DE CIMENTACION kg 11,143.75 2 2 2 2 2 2
3.02.02 ENCOFRADO EN PLATEA DE CIMENTACION m2 25.77 3 3 3 3
3.02.03 CONCRETO f´c= 280 kc/cm2 EN PLATEA DE CIMENTACION m3 133.66 4 4
3.03 VIGAS DE CIMENTACION
3.03.01 ACERO EN VIGAS DE CIMENTACION kg 11,089.26 5 5 5 5 5 5
3.03.02 ENCOFRADO EN VIGAS DE CIMENTACION m2 113.42 6 6 6 6
3.03.03 CONCRETO f´c= 280 kc/cm2 EN VIGAS DE CIMENTACION m3 69.31 7 7
4.00 ESTRUCTURA
4.01 PISO 1 2 3 4 5
4.01.01 COLUMNAS
4.01.01.01 INST. DE CONECTOR MECANICO DE 1" und 112.00 C1 C1 C1
4.01.01.02 ACERO EN COLUMNAS kg 48,800.00 A1 A1 A1 B1 B1 B1
4.01.01.03 ENCOFRADO EN COLUMNAS m2 809.00 A1 A1 B1 B1
4.01.01.04 CONCRETO f´c= 350 kc/cm2 EN COLUMNAS m3 191.21 A1 B1
4.01.01.05 DESENCOFRADO A1 B1
4.01.02 VIGAS
4.01.02.01 ENCOFRADO FONDO DE VIGAS m2 1,317.00 A1 A1 A1
4.01.02.02 ACERO EN VIGAS kg 37,300.00 A1 A1 ###
4.01.02.03 INST. DE INSERTOS METALICOS kg 468.30 A1 A1
4.01.02.04 CONCRETO f´c= 350 kc/cm2 EN VIGAS m3 253.13
4.01.03 LOSA DE TECHO
4.01.03.01 ENCOFRADO EN TECHO m2 592.00 A1 A1 A1
4.01.03.02 ACERO EN TECHO kg 9,000.00 A1 A1
4.01.03.03 CONCRETO f´c= 350 kc/cm2 EN TECHO m3 100.32
#REF! CIMENTACION DE HANGAR N°01 1.00 #REF!
1.00 OBRAS PROVISIONALES
1.01 TRAZO Y REPLANTO INICIAL glb 1.00 1 1 1 1 1 1 ###
2.00 SECTOR 1 - EJE H1
2.01 DEMOLICION DE LOSA EXISTENTE m3 8.00 2 2 2 2 2 2
2.02 RETIRO DE ADOQUINES m2 28.00 3 3
1.01 MOVIMIENTO DE TIERRAS
1.01.01 EXCAVACION LOCALIZADA CON MAQUINA m3 140.00 5 5 5 5 5 5 5
1.02 ZAPATAS
1.02.01 FALSA ZAPATA f´c=100kg/cm2 m3 54.00 6 6 6 6 6 6 6
1.02.02 PERFILADO CON MAQUINA und 12.00 7 7 7 7 7 7 7
1.02.03 ACERO EN ZAPATAS und 6,000.00 8 8 8 8 8 8 8
1.02.04 ENCOFRADO EN ZAPATAS m2 142.00 9 9 9 9 9 9 9
1.02.05 CONCRETO f´c=210kg/cm2 EN ZAPATAS m3 176.00 10 10 10 10 10 10 10
1.03 CALIZ
1.03.01 ACERO EN CALIZ kg 5,000.00 11 11 11 11 11 11 11
1.03.02 ENCOFRADO EN CALIZ m2 156.00 12 12 12 12 12 12 12
1.03.03 CONCRETO f´c=210kg/cm2 EN CALIZ m3 35.00 13 13 13 13 13 13 13
2.00 MURO DE CONTENCION
2.02 MOVIMIENTO DE TIERRAS
2.02.01 EXCAVACION PARA CIMENTACION m3 180.00 3 3
2.03 CIMENTACION ARMADA
2.03.01 SOLADO Y FALSO CIMIENTO f´c=100kg/cm2 m3 6.00 4 4
2.03.02 ACERO EN CIMENTACION kg 750.00 4 4
2.03.03 ENCOFRADO EN CIMENTACION m2 30.00 4 4
2.03.04 CONCRETO f´c=210kg/cm2 EN CIMENTACION m3 15.00 4 4
2.04 MURO DE CONTENCION
2.04.01 ACERO EN MURO kg 1,552.00 6 6
2.04.02 ENCOFRADO EN MURO m2 220.00 6 6
2.04.03 CONCRETO f´c=210kg/cm2 EN MURO m3 22.00 6
2.05 ZAPATAS DE PEDESTALES (10 und)
2.05.01 ACERO EN ZAPATAS kg 1,040.00 5 5
2.05.02 ENCOFRADO EN ZAPATAS m2 62.00 5 5
2.05.03 CONCRETO f´c=210kg/cm2 EN ZAPATAS m3 25.00 5 5
2.06 PEDESTALES (10 und)
2.06.01 ACERO EN PEDESTALES kg 1,366.00 7
2.06.02 ENCOFRADO EN PEDESTALES m2 60.00
2.06.03 CONCRETO f´c=210kg/cm2 EN PEDESTALES m3 7.00
3.00 SECTOR 2 - EJE H2
3.01 MOVIMIENTO DE TIERRAS
3.01.01 EXCAVACION LOCALIZADA CON MAQUINA m3 850.00 1 1 1 1 1 1 1
3.02 ZAPATAS
3.02.01 FALSA ZAPATA f´c=100kg/cm2 m3 320.00 2 2 2 2 2 2 2
3.02.02 ACERO EN ZAPATAS kg 7,700.00 3 3 3 3 3 3 3
3.02.03 ENCOFRADO EN ZAPATAS m2 142.00 4 4 4 4 4 4
3.02.04 CONCRETO f´c=210kg/cm2 EN ZAPATAS m3 176.00 5 5 5 5 5 5
REGISTRO
GESTION DE PROYECTOS
ANÁLISIS DE RESTRICCIONES
PROYECTO : SEMANA 01 SEMANA 02 SEMANA 03 SEMANA 04 SEMANA 05 SEMANA 06 SEMANA 07 TOTAL RESTRICCIONES
UBICACIÓN: 1 4 0 0 0 0 0 5
20% 80% 0% 0% 0% 0% 0% 100.00%
RESTRICCIONES L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D
FECHA
22/02/22
23/02/22
24/02/22
25/02/22
26/02/22
27/02/22
28/02/22
01/03/22
02/03/22
03/03/22
04/03/22
05/03/22
06/03/22
07/03/22
08/03/22
09/03/22
10/03/22
11/03/22
12/03/22
13/03/22
14/03/22
15/03/22
16/03/22
17/03/22
18/03/22
19/03/22
20/03/22
21/03/22
22/03/22
23/03/22
24/03/22
25/03/22
26/03/22
27/03/22
28/03/22
29/03/22
30/03/22
31/03/22
01/04/22
02/04/22
03/04/22
04/04/22
05/04/22
06/04/22
07/04/22
08/04/22
09/04/22
10/04/22
11/04/22
RESP.
N° ACTIVIDAD DESCRIPCIÓN DE LA RESTRICCIÓN TAREA REQUERIDA STATUS OBSERVACIONES
MAT MO EQ. INFO. CAL. SSOMA SUP. LEVANT.
PREVIA (PROD)
SEMANA 1
Rendimiento bajo por la falta de equipo, y el espesor de la losa X
1.00 DEMOLICION DE LOSAS HANGAR N°1 a demoler
X 3/1/2022 LOG EN PROCESO
DESCARAGA DE ACERO /HABILITACION DE Hasta la fecha no se tiene programada la fecha de llegada del X
3.00
material
X 3/1/2022 LOG. EN PROCESO
ACERO
4.00 EXCAVACION DE ZAPATAS EN HANGAR N°1 EXCAVADORA MALOGRADA X 3/1/2022 LOG. EN PROCESO X
EN PROCESO 4.00
LEVANTADA 1.00
TOTAL 5.00
PLAN SEMANAL
PROYECTO : FECHA: 27-Feb-22 ACTIVIDAD N°01
UBICACIÓN:
SECUENCIA DE SECTORIZACIÓN
SEMANA 1 PPC
L M X J V S 57%
Metrado
Ítem Descripción de la Actividad Und Start Finish TIPO Causas de Incumplimiento Acción Correctiva
Prog
21-Feb
22-Feb
23-Feb
24-Feb
25-Feb
26-Feb
SI NO
Metrado
Ítem EDIFICIO DE EMBOLSADO N°06 1.00
Prog
Start Finish
1.00 OBRAS PROVISIONALES
1.01 CERCO DE OBRA, SEÑALIZACION Y CERRAMIENTO glb 1.00 P X
concreto 1.02 TRAZO Y REPLANTO INICIAL glb 1.00 P X
Los viajes de los 2 volquetes al dia son 3 como maximo, debido a la lejania de la cantera, y ahora que se empearon las excavaciones en
encofrado 2.01 ACOPIO DE AGREGADOS m3 864.00 P P P P P P X LOG
la cimentacion de Edificio de embolsado no estan dedicados unicamente a a traer agregados
No se culminaron las excavaciones de la cimetacion para el edificio de embolsado N°1, y por temas de seguirdad , no se pudieron iniciar
concreto 2.02 DEMOLICION DE ESTRUCTURAS EXISTENTES - PEDESTALES m3 14.00 P P P X PP
los trabajos ya que estan demtro del radio de accion de la maquinaria.
2.03 EXCAVACIÓN CON EQUIPO m3 580.00 P P P X
No se culminaron las excavaciones de la cimetacion para el edificio de embolsado N°1, y por temas de seguirdad , no se pudieron iniciar
2.04 DEMOLICION DE ESTRUCTURAS EXISTENTES - LOSA m3 24.00 P X PP
los trabajos ya que estan demtro del radio de accion de la maquinaria.
#REF! CIMENTACION DE HANGAR N°01 1.00 #REF!
1.00 OBRAS PROVISIONALES
1.01 TRAZO Y REPLANTO INICIAL glb 1.00 P X
2.00 SECTOR 1 - EJE H1
concreto 2.01 DEMOLICION DE LOSA EXISTENTE m3 8.00 P P P P X
2.02 RETIRO DE ADOQUINES m2 28.00 P P X
PROG PROGRAMACION 0 0% Error en la programación, cambios en programación o mala utilización de las herramientas de programación
acero LOG LOGISTICA 1 17% Falta de recursos en obra (equipos mayores y menores, herramientas, subcontratos y materiales.
encofrado QA/AC CONTROL DE CALIDAD 0 0% Area control de calidad, liberación de partidas durante la ejecucón
concreto PP PARTIDA PREDECESORA 3 50% Retraso en actividades previas
EXT EXTERNOS 0 0% Retraso por clima o por eventos extraodinarios (marchas, huelgas) y por falta de entrega de permisos o licencias
SUP/CLI SUPERVISION / CLIENTES 0 0% Causas que competen al cliente
EJEC ERRORES DE EJECUCION 0 0% Error en la ejecución
SC SUBCONTRATOS 0 0% Falas con Subcontratistas
EQ EQUIPOS 1 17% Averias o fallas en equipos
ADM ADMINISTRATIVOS 1 17% No ingreso de personal especializado, otros tramites, etc
6 100%
RESUMEN PPC
PROYECTO : CONSTRUCCIÓN DE EDIFICIO DE EMBOLSADO N°06 Y CIMENTACIÓN DE FECHA: 27-Feb-22
HANGAR N°01
UBICACIÓN: LOCALIDAD DE CONDORCOCHA, DISTRITO UNION DE LETICIA, PROVINCIA DE SEMANA : 1
Control de calidad 0% 0%
Externos 0% 0%
Supervisión 0% 0%
Subcontratos 0% 0% 50%
TEMAS RELEVANTES
PRODUCCION
1. Se esta haciendo el control del avance según CRONOGRAMA
2. El acero dimensionado hasta la fecha no llega a obra, eso tiene un impacto negativo en lo que concierne a planificacion y la utilizacion
de horas hombre.
3. La maquinaria excavadora se malogro el dia sabado 26.02.2022 , no permitiendo cumplir con las tareas planificadas.
4. El agua que nos estra proveyendo, para la elaboracion de concreto en obra no es completamente potable ya que tiene color medio
amarillento, y la supervison solo nos autorizo preparar concreto para solados y falza zapata.
5. No se pudo realizar la demolicion de la losa en edificio de embolsado ya que , no se finalizo las exvaciones al 100% , y por medidas de
seguridad y por el radio de accion del brazo de la excavadora, nos era imposible atacar ese frente.
6. El abastecimiento de agreagdos es de 3 viajes por dia por cada volquete, debido a que la cantera se encuentran lejanas.
7. La excavadora nos esta retrasando en los trabajos de excavacion , debidoa que sufre constantemente desperfectos mecanicos.
ADMINISTRATIVO
1. El acero dimensionado, hasta la fecha no llega a obra , debido que en varias oportunidades se nos indico que estaba en camino ,
esto puede implicar mucho en el avance de las siguientes semanas, si no se toman acciones inmediatas.
2. Para el caso de la maquinaria pesada o linea amarilla que se encuentra en obra, al proveedor no se le solcito documentacion sobre el
estado de operatividad, teniendo en cuenta que el rendiemiento de la maquinaria disminuye en altura como es el caso de la ubicación de
obra, esto nos esta causando retrasos en las actividades planificadas y puede tener un gran impacto ya que las partidas de excavaciones
para los dos frentes se estan iniciando
OFICINA TECNICA
1. Verificar lasinterferencias, según los planos brindados por la supervision a manera de informacion ya que , hay un buzon que esta muy
cercano a la zapta del HANGAR N°1
ANEXO - INFORME N° 1
ITEM # DESCRIPCIÓN PANEL FOTOGRAFICO
Charla diaria de 10 minutos antes de jornada Excavación de cimentacion de Edificio embolsado -2.20 Eliminación de material hacia acopio asignado
Demolicion de Losas para Zapatas en Hnagar N°1 Demolicion de Losas para Zapatas en Hnagar N°1 Retiro de adoquines paraz zapatas en Hangar N°1