Professional Documents
Culture Documents
FETTERS
Project Engineer
847-736-9367
wffa845a@westpost.net
Project Manager: Plan tunnel re-entry and rehabilitation of test chamber. Work
progressed under confined space permit required rules. The chamber was contamin
ated with white phosphorous which can produce phosphine gas (PH3) when in contac
t with water. Initial work was performed wearing the proper PPE and using full-
face respirators with phosphine gas (PH3) filter canisters. The tunnel was bolt
ed with epoxy encapsulated Williams bolts on a 5a x 5a pattern and sealed with 5
000 psi fiber-reinforced shotcrete using a robot and pump. The test chamber was
washed down, bolted with 10a bolts, mine mats were cut off and shotcrete applie
d. After rehabbing the tunnel the site was set up for testing an aerial shot us
ing a skip bomb. Test support and installing the ventilation fan and fence acro
ss the portal after the test were also required.
Frontier\Kemper (3/03 to 1/05):
Chief Field Engineer: Co-ordinate field engineering staff and survey crews in c
omplex underground expansion of existing freight tunnel. This was a self direct
ed position on a technically difficult job encompassing a wide range of work. P
osition required hiring and training field engineers to assist tunnel superinten
dents and walkers in understanding specifications, qa/qc, and ground support req
uirements in a challenging tunnel rehab. An existing 4200a freight tunnel with
brick lined sections in unstable ground was widened with mechanical equipment.
The tunnel was widened to 65a wide and 40a high for 1200a to build an undergrou
nd train station using drill and blast techniques. As the tunnel was widened th
ree separate faces advancing at different rates were excavated, shotcreted, and
bolted with grouted rock dowels. On one end of the station a 41adiameter shaft
was being excavated using drill and blast techniques after an 8a 3a diameter rai
se bore was accomplished from the existing tunnel. The station, shaft, and bric
k sections of the tunnel were all being excavated at the same time once the work
force, walkers, and engineering staff were trained. The Portals on either end of
the tunnel were completely rebuilt and stabilized. The West portal was dug bac
k and the ground was stabilized using soil nails, shotcrete and wire. The form
traveler was poured beyond the tunnel limits and backfilled. On the surface a b
us transfer station with 3 high speed elevators was constructed to access the lo
wer station. The shaft centerline, the tunnel centerline, and the train station
centerline were all offset from each other making survey control complicated an
d difficult.
BU Corp (9/02 to 2/03):
Survey Superintendent: Co-ordinate complex geometry surveying at the Exchange P
lace Subway Station that feeds the World Trade Center from New Jersey. The stat
ion platform was enlarged with roadheaders to use a 10 car train from an 8 car t
rain. Work with Dibit survey crew and generate final Vehicle Dynamic Outline (V
DO.) The geometry of the cuts and crossovers were an increasing or decreasing s
ize. Once it was determined the survey crews were accurate, the accuracy of the
cuts were transferred to the operators and foreman. The roadheader foremen wer
e taught to use offsets and survey marks improving the accuracy of the roadheade
r work. Document and record construction of Exchange Place subway station with
power point presentation showing the various stages of construction.
Superintendent: Remove 3.5 miles of track, clean the invert, stabilize bad grou
nd areas, and re-install high speed rail back into the Stillwater East Boulder P
latinum Mine. I had a major roll in planning and scheduling the work, training
an unskilled workforce, and supervising all phases of this job. The ground supp
ort and rehabilitation included relieving the baskets in the wire mesh, bolting
with splitsets, and shotcreting. In squeezing ground 20a grouted cable bolts we
re installed in the invert to hold the invert in place and inhibit heaving. MSH
A 40 hour underground training was received.
Reference:
Defense Threat Reduction Agency (DTRA)
Dave Hoag a" Engineer (505) 507-3866
Carl Jorgensen a" Engineer (435) 831-7260