Professional Documents
Culture Documents
Ogl 421 Risk Management Plan
Ogl 421 Risk Management Plan
11 February 2022
Risks
Given the timeline that Eldon Tyrell has given me, I believe that the initial anticipated
project risks I listed in the Risk Management Project Roles and Responsibilities assignment are
still valid. As a reminder, the initial identified risks that I mentioned were the stakeholders not
being satisfied with the completed project, there being miscommunication within the team, and
there being miscommunication between the team and the executives. The reason why I believe
these identified risks are still valid is because miscommunication will always be a relevant risk
importance regardless of the timeline given. If anything, the three month deadline that the project
team has been given to complete this web rebuild project accentuates the significance of those
identified risks. With that being said, I do foresee some additional risks based on the new
information gathered that I did not have before such as the deadline. The shortened time frame
allotted to the project team forbids room for mistakes even further, so it is important to include as
many risks as possible into the risk management plan. These new risks include potential factors
that are out of the team’s control such as technical issues, decreased deadline, and reduced
budget. All of these factors are risks that cannot necessarily be prevented but can be better
managed if included in the risk management plan, in case these events were to take place.
Caceres Melendez 2
Solutions
Risk Solution
Decreased Deadline Use the allotted buffer time period set for
necessary by stakeholders.
Action Plan
assuring that frequent and effective communication between project team and
stakeholders.
any changes, updates, or notifications done by the team. Reinforcing transparency and
monthly team meetings is also part of the preventative action plan. Also as importantly, it
is crucial to include making an active effort to be certain that what each member says is
changes, updates, or notifications done by the team. Reinforcing transparency and weekly
Caceres Melendez 4
team meetings is also part of the preventative action plan. Also as importantly, it is
crucial to include making an active effort to be certain that what each member says is
- Decreased Deadline: The contingency action plan is to have a detailed ranked list of
components that we would like to include but are not required, in case we must uninclude
them due to a time restriction. The preventative action plan is to make the target deadline
a week or two before the official deadline given by Eldon Tyrell. This will give us some
buffer time in case there is a delay we cannot avoid. Furthermore, if the deadline is
decreased then there is a possibility it might not affect the project at all.
- Reduced Budget: The contingency action plan is to have a detailed ranked list of
components that we would like to include but are not required, in case we must uninclude
them due to a budget restriction. The preventative action plan is to set aside 10% of the
allotted budget and have it be an emergency fund. This will allow us some additional
budget is reduced then there is a possibility that it might not affect our project at all if it
only takes away from unused emergency funds that were set aside.