Arrangement Check List for dynamic load test

Sl CHECK LIST YES/NO


no.
1. Pile has to be chipped up to cut off level or sound concrete level and

The pile has to be built up with higher grade of concrete (higher than
2.
the concrete used for pile) up to 1.5 time of pile dia.

3. Pile top surface should be uniform and leveled

4. Cube test for built up concrete to assess the strength

5. Extra Helical ring for built up pile head

6. It is batter to put liner or cashing in the built up pile.


300 mm X 300 mm at 500 mm from pile top has to be smooth enough,
7. bentonite free to fix the gauges

Round circular plywood of 25 mm should be kept on t he top surface of


8. the pile for cushioning.

Steel helmet of 40 mm should be provided at the pile top.


9.
Excavation of 1 meter depth from pile top is required. Surrounding 2
10. mtrs. For accessibility to fix the gauges.

Contractor Name Consultant Name Client Name and


and signature and signature signature