OPERATING MANUAL DOC . No.

BR: PN: ACU:OM :6


IOCL
OF ADDITIONAL ISSUE No. ISSUE DATE VOL. No. VOL DATE
BARAUNI
COKING UNIT
REFINERY 3 01.08.01
(COKER -B)

SECTION –9
FIRE FIGHTING FACILITY IN ACU

A 8” dia fire water header forming ring serves the additional Coking unit. It has an isolation
valve at B/L and also at various other location within unit in underground pit to facilitate
maint. work. There are twelve nos. long range monitor both in ACU & LRU , within unit 2
Nos. hydrants are provided.

There are 95 nos. fire post in ACU/LRU area out of which 63 are located / existing in ACU
and thirty two (32) in LRU.

In order to serve emergency call two nos each fire alarm points are provided in ACU &
LRU.

Pump house in ACU and LRU are separately provided with water sprinkler system. In the
year 1996. 7- P- 09C/D were exclusively provided with water sprinker system facilitating
enclosed water spray during fire etc.

Prepared by Approved by Issued by Page No.

A.K. Roy,PNM G.S. Singh, SPNM (I/C) L.S.Kharkongor,SPNM 161 of 204