VENDOR DATA REVIEW

V-101946-0508-0181
Doc. No._____________________________ 2
Rev._______
Equipment No.____________________________________
Discipline By Date
Civil / Struct ______________________ ___________
Mech / Piping ______________________ ___________
Elec / Instr ______________________ ___________
Drafting ______________________ ___________
Process ______________________ ___________
Quality ______________________
FERNANDO VILLAVERDE ___________
29-03-2019
Procurement ______________________ ___________
X 1 Accepted to Proceed.----------------------------------------------------
SUBMIT FINAL CERTIFIED COPY completed
2 Accepted to Proceed except as noted. Revise & Resubmit
3 Not Accepted to Proceed. Revised & Resubmit
4 Information ONLY
Review of this document has been completed to determine if
the intent of the Contract Documents has generally been
complied with. Such review does not relieve the Contractor /
Supplier of contractual obligations.

Responsible Engineer Signature Date