Contractor: Makeway Construction Sdn Bhd

Summary Outstanding Work at Majunaka Sdn Bhd

Item Building Element List of Outstanding Work Outstanding % Finish % Description


1 1. Skim coat stringer staircase 40% 60% Both Staircase
Staircases
2. Undercoat and 2 layers Panting 100% 0% Both Staircase
1. Window at: 1. Only bilik latihan and
(Ground Floor) bilik mensyuarat at
- 3 nos type W2 at Ruang ground floor has been
Pejabat installed complete
- 1 nos type W2 at Bilik Pengurus window
- 4 nos type W1 at Surau
Perempuan & Lelaki 2. Other than that it is
- 2 nos type W5 at Lobi still not installed

(1st Floor)
Window 100% 0%
- 4 nos type W1, 2 nos type W3
and 1 no type W1 at Bilik Latihan
- 4 nos type W1 at Pejabat 3
- 3 nos type W1 at ruang pejabat
- 2 nos type W4 at Tandas
Perempuan & Lelaki
- 2 nos type W1 at Bilik
Mensyuarat
1 no type W9, W8 & W4 at Bilik
Pengurus
1. All door except bilik MDF and 2 1. Only one complete
door frame at bilik mensyuarat door has been installed
and bilik latihan ground floor at bilik MDF.

Pejabat (2 Tingkat) Door Including 99% 1% 2. Only 2 complete door


Ironmongery
frame has been installed
at bilik mensyuarat and
bilik latihan ground floor

1. Tiles at ground floor 80% 20%


2. Tiles at First floor 100% 0%
3. 25mm thick render at 1st floor All three bilik pengurus
Floor Finishes
are still not render due
10% 90%
to the roof at that time
still incomplete
1. Tiles to wall at ground floor 30% 70%
2. Undercoat and 2 finishing coat 1. Only bilik latihan and
(Internal) bilik mensyuarat at
ground floor has been
paint undercoat and 2
layer finishing coat
80% 20%
Wall Finishes 2. Area in ground floor
other than bilik latihan
and bilik mensyuarat has
been paint undercoat.
The another 2 layer still
not paint
3. Undercoat and 2 finishing coat
100% 0%
(External)
Ceiling Finishes 1. Skim coat concrete slab 100% 0%
Item Building Element List of Outstanding Work Outstanding % Finish % Description
1 2. 1200mm X 600mm X 3.2mm The room has been
thick ceiling at ground floor covered with ceiling:
- Bilik MDF (GF)-
- Bilik IT (GF)
Ceiling Finishes 70% 30%
- Bilik Mensyuarat (GF)
- Bilik Latihan (GF)

3. 1200mm X 600mm X 3.2mm


100% 0%
thick ceiling at first floor
4. Ceiling lining 100% 0%
1. Padestal water closet 90% 10% Total padestal water
closet is 8 and only 1 has
been installed in the
tandas perempuan
2. Padestal water closet for OKU
100% 0%
toilet
Squating Water Closet Only tandas perempuan
3. 90% 10% has been installed

Pejabat (2 Tingkat) 4. Wash hand basin Only tandas perempuan


70% 30% has been installed
Sanitary
Appliances 5. Wall hang hadicap basin 100% 0%
6. Hand spray bidet 100% 0%
7. Tissue holder 100% 0%
8. Stainless steel grab 100% 0%
9. Mirror 100% 0%
10. Stooling water closet Only tandas perempuan
90% 10% has been installed
11. stooling for ablution foot plinth 100% 0%
12. Scupper drain 100% 0%
13. Solid phenolic resin toilet cubicle
100% 0%
L shape
Handrails and 1. Handrail for staircase and step
100% 0%
Balustrades
1. Mild steel grillwork at staircase -
100% 0%
Type W09
Miscellaneous 2. Precast concrete drain 20% 80%
3. Ligh duty mild steel grating to
100% 0%
cover drain
2 1. Ligh duty mild steel grating to
Biomass Store Miscellaneous 100% 0%
cover drain
3 1. Ligh duty mild steel grating to
Plant Store Miscellaneous 100% 0%
cover drain
4 1. Fixed glass louvres window 100% 0%
2. Fixed glass panel window 100% 0%
Window
3. Fixed glass panel window, L-
100% 0%
shape
1. Single leaf door 100% 0%
2. Stainless steel butt hinges 100% 0%
Door Including 3. Cylindrical lockset 100% 0%
Guard House Ironmongery 4. Toilet lockset with toilet
100% 0%
indicator
5. Door Stopper 100% 0%
1. Tissue holder 100% 0%
Sanitary
2. Mirror 100% 0%
Appliances
3. Floor drainer 100% 0%
1. Light duty mild steel grating to
Miscellaneous 100% 0%
cover drain